Surry Annual Assessment Meeting Slides - Reactor Oversight Program - Cy 2007
ML081130167
Person / Time
Site: Surry  Dominion icon.png
Issue date: 04/15/2008
From:
NRC/RGN-II
To:
References
IR-08-002
Download: ML081130167 (18)


Text

Surry Power Station Surry Power Station Annual Assessment Meeting Annual Assessment Meeting Reactor Oversight Program Reactor Oversight Program

--CY 2007 CY 2007 U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission

--Region IIRegion II Surry, Virginia Surry, Virginia April 15, 2008 April 15, 2008 Purpose of Today's MeetingTo provide To provide NRC's NRC'sannual assessment of licensee annual assessment of licensee performance at Surry for CY 2007performance at Surry for CY 2007To discuss performance issues identified during the To discuss performance issues identified during the annual assessmentannual assessmentTo provide the Licensee an opportunity to respond to To provide the Licensee an opportunity to respond to the annual assessment and to inform the NRC of new the annual assessment and to inform the NRC of new or existing initiatives to maintain or improve or existing initiatives to maintain or improve performance performance Agenda Introductions Review Reactor Oversight ProcessNational Summary of Plant PerformanceSurry's Plant Performance ResultsLicensee Response NRC Closing Remarks BreakNRC available to address public questions Region II OrganizationVictor McCreeActing Regional AdministratorCharles CastoActing Deputy Regional AdministratorJoseph SheaActing Director Division of Reactor ProjectsHarold ChristensenDeputy DirectorKrissKennedyDirector Division of Reactor SafetyDavid AyresDeputy DirectorEugene F. GuthrieBranch ChiefRegional SpecialistsChris WelchSr. Resident Inspector VacantResident InspectorJim DodsonSr. Project EngineerDan ArnettProject Engineer NRC Strategic Goals Safety: Ensure adequate protection of public health and safety and the environment Security: Ensure adequate protection in the secure use and manage ment of radioactive materials Reactor Oversight ProcessSafetyCornerstonesBaseline Inspection ResultsSignificance ThresholdAction MatrixSignificance ThresholdPerformance IndicatorResultsRegulatory ResponseStrategicPerformance AreasSafetyCornerstonesBaseline Inspection ResultsSignificance ThresholdAction MatrixSignificance ThresholdPerformance IndicatorResultsRegulatory ResponseStrategicPerformance Areas Significance ThresholdPerformance Indicators Green: Only Baseline Inspection White:May increase NRC oversightYellow:Requires more NRC oversight Red:Requires more NRC oversight Inspection Findings Green:Very Low safety issue White:Low to moderate safety issueYellow:Substantial safety issue Red:High safety issue Action Matrix ConceptLicenseeResponseRegulatoryResponseDegradedCornerstoneMultiple/Rep.DegradedCornerstoneUnacceptablePerformance Increasing Safety Significance Increasing NRC Inspection Efforts Increasing NRC/Licensee Management Involvement Increasing Regulatory Actions Examples of Baseline InspectionsEquipment Alignment ~80 hrs/yr Triennial Fire Protection ~200 hrs every 3 yrsOperator Response ~125 hrs/yrEmergency Preparedness ~80 hrs/yrRad Release Controls ~110 hrs every 2 yrsWorker Radiation Protection ~90 hrs/yrCorrective Action Program ~250 hrs every 2 yrsCorrective Action Case Reviews ~60 hrs/yr National Summary of Plant Performance Status at End of CY 2007Licensee Response 87Regulatory Response 8Degraded Cornerstone 8Multiple/Repetitive Degraded Cornerstone1Unacceptable 0Total104 National Summary Performance Indicator Resu lts (at end of CY 2007)Green 1942White 8Yellow 2Red 0 Total Inspection Findings (CY 2007)Green 759White9Yellow 5Red 0 Surry Power Station Inspection Activities (Jan 1 (Jan 1 --Dec 31, 2007)Dec 31, 2007) 7,810 hours0.00938 days <br />0.225 hours <br />0.00134 weeks <br />3.08205e-4 months <br /> of inspection related activities

  • Operator Licensing Requalification Inspection
  • Independent Spent Fuel Storage Installation Inspections
  • Emergency Preparedness Inspections
  • Radiation Protection Inspections
  • Problem Identification a nd Resolution Inspection
  • Unit 1 In-Service Inspections
  • Resident Inspector daily Inspections Surry Power Station Assessment Results(Jan 1-Dec 31, 2007)
  • Surry's performance was within the Licensee Response Column of the Action Matrix for all four quarters.
    • No safety significant findi ngs or PIs were identified No safety significant findi ngs or PIs were identified
  • All inspection findings were classified as very low safety significance (Green). *During the assessment period there were fourteen violations of regulatory requirements.
  • All performance indicators were Green.

Surry Power Station Annual Assessment Summary

  • Virginia Electric and Power Company operated the Surry Power Station in a manner that preserved public health and safety.
  • All cornerstone objectives were met.
  • NRC plans baseline inspections at North Anna

for the remainder of CY 2008. (Jan 1-Dec 31, 2007)

Licensee Response and Remarks Questions?

Contacting the NRC Report an emergency(301) 816-5100 (call collect) Report a safety concern: (800) 695-7403 Allegation@nrc.gov General information or questionswww.nrc.govSelect "What We Do" for Public Affairs NRC Representatives NRC RepresentativesChris Welch, Senior Resident Inspector-(757) 357-2101Jim Dodson, Senior Project Engineer-(404) 562-4655 Gene Guthrie, Branch Chief-(404) 562-4662 Reference SourcesReactor Oversight Processhttp://www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.htmlPublic Electronic Reading Roomhttp://www.nrc.gov/reading-rm.html Public Document Room1-800-397-4209 (Toll Free)