© 2003 Dominion Keys to Surry Power Stations NRC Exam
© 2003 Dominion 2
Communication - Written and Verbal z Early and Clear Communications and Expectations shared z Frequent communications (about twice a week) z Use of a project plan to track completion of key deliverables z Timely submittals of material
- Delay the exam, if needed
© 2003 Dominion 4
VALIDATION z Simulator Exams Validated - 2 Crews z Admin JPMs Validated - 4 Individuals z In-plant/simulator JPMs Validated - 3 Individuals z Written Exam - 12 individuals
- Above average, below average, and average individuals selected
- Scores predicted prior to validation
© 2003 Dominion 4
Reaching a Consensus on Changes z Came with alternative questions
- Came with alternatives to alternative z Came with a desire to have a fair and discriminating exam z Communications were never heated, even when disagreement could not be resolved z If unable to resolve an issue, it was put aside to discuss at a later time
© 2003 Dominion 5
Exam Implementation z Prep Week
- In-processing completed prior to arrival
- Material ready and plans set to accomplish the goals
- Accepting change when change was needed
- Accepting change when change was desired z NRC Exam Week
- Organized, but flexible (i.e., back-up plans)
- Significant support (i.e., people and rooms to sequester candidates)
- Continuous oversight of the process/plan
© 2003 Dominion 6
Contacts For more information contact:
David H Wilson 757-365-2811 David.H.Wilson@dom.dom Bill Marshall 757-365-2647 Bill.Marshall@dom.com