{{#Wiki_filter:'-4 '. t 4W4 Committed to NuciearExcellence                                                Kewaunee Nuclear Power Plant Operated by Nuclear Management Company, LLC December 13, 2004                                                                          NRC-04-143 TS 6.9.a.3 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555 KEWAUNEE NUCLEAR POWER PLANT DOCKET 50-305 LICENSE No. DPR-43 Monthly Operating Report In accordance with Technical Specification 6.9.a.3., enclosed is the Monthly Operating Report for November 2004 for the Kewaunee Nuclear Power Plant.
Thomas Coutu Site Vice President, Kewaunee Nuclear Power Plant Nuclear Management Company, LLC Enclosure cc:      Administrator, Region Ill, USNRC Senior Resident Inspector, Kewaunee, USNRC Project Manager, Kewaunee, USNRC Public Service Commission of Wisconsin INPO Records Center 0)-
N490 Highway 42 . Kewaunee, Wisconsin 54216-9511 Telephone: 920.388.2560
 
OPERATING DATA REPORT DOCKET NO. 50-305                            Notes:
UNIT NAME    Kewaunee                            Unit shutdown for refueling outage.
DATE          December 13, 2004 COMPLETED    Mary Anderson BY TELEPHONE      (920) 388-8453 REPORTING PERIOD    November, 2004
: 1. DESIGN ELECTRICAL RATING (MWE-NET)    574
: 2. MAXIMUM DEPENDABLE CAPACITY (MWE-      556 NET)
YEAR-TO-MONTH            DATE            CUMULATIVE
: 3. NUMBER OF HOURS REACTOR WAS CRITICAL        0              6412.5            227832.2
: 4. NUMBER OF HOURS GENERATOR WAS ON LINE        0              6386.1            225573.2
: 5. UNIT RESERVE SHUTDOWN HOURS                0.0              0.0                10.0
: 6. NET ELECTRICAL ENERGY (MWH)                  0            3546920            113348279
 
_ I V, e                                                    UNIT SHUTDOWNS DOCKET NO.                50-305 UNIT NAME                Kewaunee DATE                      December 13,2004 COMPLETED BY              Mary Anderson TELEPHONE                (920) 388-8453 REPORTING PERIOD                    November, 2004 METHOD NO AE          Type      DURATION          REASON          OF NO.        DATE        I          (Hours)          2      SHUTTING          CAUSE/ORRECTIVE ACTIONS DOWN
                                                    ._          REACTOR3 5      11/01/04      S            720.0          C            4      Cycle XXVI-XXVII Refueling Outage
                                            .0                              continued throughout the reporting period (1)                        (2)                                                    (3)
F: Forced                    Reason:                                              . Method:
S: Scheduled                A - Equipment Failure (Explain)                        1 - Manual B - Maintenance or Test                                2 - Manual Trip/Scram C - Refueling                                          3 - Automatic Trip/Scram D - Regulatory Restriction                            4 - Other (Explain)
E - Operator Training & License Examination                Continuation F - Administrative                                    5 - Load Reductions G - Operational Error (Explain)                        9- Other H - Other (Explain)
 
==SUMMARY==
Mechanical Maintenance completed a full core reload sequence in support of Westinghouse Spilt Pin, 10 Year ISI, and Head Replacement Projects. Mechanical Maintenance completed retests on RHR Pump B, and Turbine Driven Auxiliary Feedwater Pump, and Main Feedwater Pump Speed Increaser Gear Sets. The Heater Drain Pump A Motor, Mag Drive, and Thrust Stand was replaced with the spare set. Various valves and flanges were inspected and rebuilt based on the boric acid leakage reduction program and operational leak checks. The Main Condensers were leak checked under vacuum and plugged as required. Supported Operations with returning the Plant to power. Completed overhaul of the Demin Water System Pre-treatment Flocculator.
Electrical Maintenance key activities in November included preventive maintenance work on 11 Motor Operated Valves, calibration of power relays, Main Auxiliary Transformer bus insulation replacement and replacement of 160 Polar Crane bus insulators.
I&C continued the performance of outage related preventative and corrective maintenance on the primary and secondary systems. I&C supported the major scheduled projects including the Reactor Head replacement, Reactor Protection Relay replacements and the New Analog Rod Position Indication system (NARPI) installation. I&C also performed many Air Operated Valve (AOV) diagnostic tests which will result in improved AOV performance.}}

Latest revision as of 06:25, 24 March 2020

November 2004 Monthly Operating Report for Kewaunee Nuclear Power Plant
ML043630339
Person / Time
Site: Kewaunee Dominion icon.png
Issue date: 12/13/2004
From: Coutu T
Nuclear Management Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NRC-04-143
Download: ML043630339 (3)


Text

'-4 '. t 4W4 Committed to NuciearExcellence Kewaunee Nuclear Power Plant Operated by Nuclear Management Company, LLC December 13, 2004 NRC-04-143 TS 6.9.a.3 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555 KEWAUNEE NUCLEAR POWER PLANT DOCKET 50-305 LICENSE No. DPR-43 Monthly Operating Report In accordance with Technical Specification 6.9.a.3., enclosed is the Monthly Operating Report for November 2004 for the Kewaunee Nuclear Power Plant.

Thomas Coutu Site Vice President, Kewaunee Nuclear Power Plant Nuclear Management Company, LLC Enclosure cc: Administrator, Region Ill, USNRC Senior Resident Inspector, Kewaunee, USNRC Project Manager, Kewaunee, USNRC Public Service Commission of Wisconsin INPO Records Center 0)-

N490 Highway 42 . Kewaunee, Wisconsin 54216-9511 Telephone: 920.388.2560

OPERATING DATA REPORT DOCKET NO. 50-305 Notes:

UNIT NAME Kewaunee Unit shutdown for refueling outage.

DATE December 13, 2004 COMPLETED Mary Anderson BY TELEPHONE (920) 388-8453 REPORTING PERIOD November, 2004

1. DESIGN ELECTRICAL RATING (MWE-NET) 574
2. MAXIMUM DEPENDABLE CAPACITY (MWE- 556 NET)

YEAR-TO-MONTH DATE CUMULATIVE

3. NUMBER OF HOURS REACTOR WAS CRITICAL 0 6412.5 227832.2
4. NUMBER OF HOURS GENERATOR WAS ON LINE 0 6386.1 225573.2
5. UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 10.0
6. NET ELECTRICAL ENERGY (MWH) 0 3546920 113348279

_ I V, e UNIT SHUTDOWNS DOCKET NO. 50-305 UNIT NAME Kewaunee DATE December 13,2004 COMPLETED BY Mary Anderson TELEPHONE (920) 388-8453 REPORTING PERIOD November, 2004 METHOD NO AE Type DURATION REASON OF NO. DATE I (Hours) 2 SHUTTING CAUSE/ORRECTIVE ACTIONS DOWN

._ REACTOR3 5 11/01/04 S 720.0 C 4 Cycle XXVI-XXVII Refueling Outage

.0 continued throughout the reporting period (1) (2) (3)

F: Forced Reason: . Method:

S: Scheduled A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2 - Manual Trip/Scram C - Refueling 3 - Automatic Trip/Scram D - Regulatory Restriction 4 - Other (Explain)

E - Operator Training & License Examination Continuation F - Administrative 5 - Load Reductions G - Operational Error (Explain) 9- Other H - Other (Explain)

SUMMARY

Mechanical Maintenance completed a full core reload sequence in support of Westinghouse Spilt Pin, 10 Year ISI, and Head Replacement Projects. Mechanical Maintenance completed retests on RHR Pump B, and Turbine Driven Auxiliary Feedwater Pump, and Main Feedwater Pump Speed Increaser Gear Sets. The Heater Drain Pump A Motor, Mag Drive, and Thrust Stand was replaced with the spare set. Various valves and flanges were inspected and rebuilt based on the boric acid leakage reduction program and operational leak checks. The Main Condensers were leak checked under vacuum and plugged as required. Supported Operations with returning the Plant to power. Completed overhaul of the Demin Water System Pre-treatment Flocculator.

Electrical Maintenance key activities in November included preventive maintenance work on 11 Motor Operated Valves, calibration of power relays, Main Auxiliary Transformer bus insulation replacement and replacement of 160 Polar Crane bus insulators.

I&C continued the performance of outage related preventative and corrective maintenance on the primary and secondary systems. I&C supported the major scheduled projects including the Reactor Head replacement, Reactor Protection Relay replacements and the New Analog Rod Position Indication system (NARPI) installation. I&C also performed many Air Operated Valve (AOV) diagnostic tests which will result in improved AOV performance.