November 2002 Monthly Operating Report for Kewaunee
ML023520029
Person / Time
Site: Kewaunee Dominion icon.png
Issue date: 12/06/2002
From: Coutu T
Nuclear Management Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NRC-02-106
Download: ML023520029 (3)


Text

Kewaunee Nuclear Power Plant Point Beach Nuclear Plant N490 Highway 42 6610 Nuclear Road Kewaunee, WI 54216-9511 Two Rivers, WI 54241 920 388 2560 920 755.2321 NMC CommItted to NuclearExcellene~ Kewaunee / Point Beach Nuclear Operated by Nuclear Management Company, LLC NRC-02-106 December 6, 2002 10 CFR 50.36 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555 Ladies/Gentlemen:

Docket 50-305 Operating License DPR-43 Kewaunee Nuclear Power Plant Monthly Operating Report The monthly operating report for the Kewaunee Nuclear Power Plant forNovember 2002 is enclosed in accordance with Technical Specification 6.9.a.3.

Sincerely, Thomas Coutu 6Z Site Vice President MLA Enclosure cc - US NRC - Region III NRC Senior Resident Inspector INPO Records Center PSCW - Sharon Henning

OPERATING DATA REPORT DOCKET NO. 50-305 Notes: Unit continues to operate at 100%

UNIT NAME KEWAUNEE power.

DATE DECEMBER 4,2002 COMPLETED BY MARY ANDERSON TELEPHONE (920) 388-8453 REPORTING PERIOD NOVEMBER, 2002

1. DESIGN ELECTRICAL RATING (MWE-NET) 535
2. MAXIMUM DEPENDABLE CAPACITY (MWE-NET) 511 MONTH! YEAR-TO-DATE CUMULATIVE
3. NUMBER OF HOURS REACTOR WAS CRITICAL 720.0 7784.8 212750.7
4. NUMBER OF HOURS GENERATOR WAS ON LINE 720.0 7770.7 210549.3
5. UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 10.0
6. NET ELECTRICAL ENERGY (MWVH) 380890 4077891 105251388

UNIT SHUTDOWNS DOCKET NO. 50-305 UNIT NAME Kewaunee DATE December 4, 2002 COMPLETED BY Mary Anderson TELEPHONE (920) 388-8453 REPORTING PERIOD November, 2002 METHOD OF NO. DATE Type DURATION REASON 2 SHUTTING CAUSE/CORRECTIVE ACTIONS (Hours) DOWN REACTOR 3

No shutdowns or power reductions in November (1) (2) (3)

F: Forced Reason: Method:

S: Scheduled A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2 - Manual Trip/Scram C - Refueling 3 - Automatic Trip/Scram D - Regulatory Restriction 4 - Other (Explain)

E - Operator Training & License Examination Continuation F - Administrative G - Operational Error (Explain)

H - Other (Explain)

SUMMARY

The unit continues to operate at 100% steady state power