July 2003 Monthly Operating Report for Kewaunee
ML032310410
Person / Time
Site: Kewaunee Dominion icon.png
Issue date: 08/11/2003
From: Coutu T
Nuclear Management Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NRC-03-087
Download: ML032310410 (3)


Text

-'-4 NMCP Committed to Nuclear Eccellen" Kewaunee Nuclear Power Plant Operated by Nuclear Management Company, LLC NRC-03-087 10 CFR 50.36 August 11, 2003 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555 KEWAUNEE NUCLEAR POWER PLANT DOCKET 50-305 LICENSE No. DPR-43 MONTHLY OPERATING REPORT The monthly operating report for the Kewaunee Nuclear Power Plant for July 2003 is enclosed in accordance with Technical Specification 6.9.a.3.

Thomas Coutu Site Vice-President, Kewaunee Plant MLA cc US NRC, Region IlIl US NRC, Senior Resident Inspector INPO Records Center PSCW - Sharon Henning Attachment r

N490 Highway 42

  • Kewaunee, Wisconsin 54216-9510 Telephone: 920.388.2560

$6 (:t-I4

OPERATING DATA REPORT DOCKET NO. 50-305 Notes: Rx power was raised from 1650 UNIT NAME Kewaunee MWt to new licensed level of 1673 MWt on July 28. As a result, new DATE August 11, 2003 generation ratings will not be updated until August report.

COMPLETED BY Mary Anderson TELEPHONE (920) 388-8453 REPORTING PERIO D July, 2003

1. DESIGN ELECTRICAL RATING (MWE-NET) 536
2. MAXIMUM DEPENDABLE CAPACITY (MWE-NET) 516 MONTH YEAR-TO-DATE CUMULATIVE
3. NUMBER OF HOURS REACTOR WAS CRITICAL 744.0 4252.0 217746.7
4. NUMBER OF HOURS GENERATOR WAS ON LINE 744.0 4220.8 215514.1
5. UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 10.0
6. NET ELECTRICAL ENERGY (MWH) 395677 2182026 107824256

-.4 UNIT SHUTDOWNS DOCKET NO. 50-305 UNIT NAME Kewaunee DATE August 11, 2003 COMPLETED BY Mary Anderson TELEPHONE (920) 388-8453 REPORTING PERIOD July, 2003 (1) (2) (3)

F: Forced Reason: Method:

S: Scheduled A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2 - Manual Trip/Scram C - Refueling 3 - Automatic Trip/Scram D - Regulatory Restriction 4 - Other (Explain)

E - Operator Training & License Examination Continuation F - Administrative 5 - Load Reductions G - Operational Error (Explain) 9 - Other H - Other (Explain)

SUMMARY

The unit continues to operate at 100% steady state power.