September 2003 Monthly Operating Report for Kewaunee Nuclear Power Plant
ML032880415
Person / Time
Site: Kewaunee Dominion icon.png
Issue date: 10/06/2003
From: Coutu T
Nuclear Management Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NRC-03-104
Download: ML032880415 (3)


Text

Committed to Nuclear Excellen Kewaunee Nuclear Power Plant Operated by Nuclear Management Company, LLC NRC-03-1 04 10 CFR 50.36 October 6, 2003 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555 KEWAUNEE NUCLEAR POWER PLANT DOCKET 50-305 LICENSE No. DPR-43 MONTHLY OPERATING REPORT The monthly operating report for the Kewaunee Nuclear Power Plant for September 2003 is enclosed in accordance with Technical Specification 6.9.a.3.

Thomas Coutu Site Vice President, Kewaunee Nuclear Power Plant Nuclear Management Company, LLC MLA Enclosure cc:

Administrator, Region Ill, USNRC Senior Resident Inspector, Kewaunee, USNRC Project Manager, Kewaunee, USNRC Public Service Commission of Wisconsin INPO Records Center j''e N490 Highway 42

  • Kewaunee, Wisconsin 54216-9510 Telephone: 920.388.2560

OPERATING DATA REPORT DOCKET NO.

5(

UNIT NAME K

DATE 0

COMPLETED BY IM TELEPHONE (9

REPORTING PERIOD

)-305 ewaunee ctober 6, 2003

[ary Anderson 120) 388-8453 September, 2003 Notes:

Unit continues to operate at 100% power.

1.

DESIGN ELECTRICAL RATING (MWE-NET)

2.

MAXIMUM DEPENDABLE CAPACITY (MWE-NET) 544 526

3.

NUMBER OF HOURS REACTOR WAS CRITICAL

4.

NUMBER OF HOURS GENERATOR WAS ON LINE

5.

UNIT RESERVE SHUTDOWN HOURS

6.

NET ELECTRICAL ENERGY (MWH)

MONTH 720.0 720.0 0.0 388429 YEAR-TO-DATE 5716.0 5684.8 0.0 2968801 CUMULATIVE 219210.7 216978.1 10.0 108611031

UNIT SHUTDOWNS DOCKET NO.

UNIT NAME DATE COMPLETED BY TELEPHONE 50-305 Kewaunee October 2, 2003 Mary Anderson (920) 388-8453 REPORTING PERIOD September, 2003 METHOD OF NO.

DATE Type DURATION REASON2 SHUTTING CAUSECORRECTIVE ACTIONS ye (Hours)

DOWVNN REACTOR3 No shutdowns or power reductions in September (1)

F: Forced S: Scheduled (2)

Reason:

A - Equipment Failure (Explain)

B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training & License Examination F - Administrative G - Operational Error (Explain)

H - Other (Explain)

(3)

Method:

1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Other (Explain)

Continuation 5 - Load Reductions 9 - Other

SUMMARY

The unit continues to operate at 100% steady state power