June 2002 Monthly Operating Report for Kewaunee Nuclear Power Plant
ML022000063
Person / Time
Site: Kewaunee Dominion icon.png
Issue date: 07/11/2002
From: Coutu T
Nuclear Management Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NRC-02-062
Download: ML022000063 (3)


Text

Kewaunee Nuclear Power Plant N490 Highway 42 Kewaunee, WI 54216-9511 920.388.2560 Point Beach Nuclear Plant 6610 Nuclear Road Two Rivers, WI 54241 920.755.2321 Kewaunee / Point Beach Nuclear Operated by Nuclear Management Company, LLC NRC-02-062 July 11, 2002 10 CFR 50.36 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555 Ladies/Gentlemen:

Docket 50-305 Operating License DPR-43 Kewaunee Nuclear Power Plant Monthly Operating Report The monthly operating report for the Kewaunee Nuclear Power Plant for June 2002 is enclosed in accordance with Technical Specification 6.9.a.3.

Sincerely, Thomas Coutu Manager-Kewaunee Plant MLA Enclosure cc -

US NRC - Region III NRC Senior Resident Inspector INPO Records Center PSCW - Sharon Henning NMe eln Committed to Nuclear Excellence

UNIT SHUTDOWNS DOCKET NO.

UNIT NAME DATE COMPLETED BY TELEPHONE REPORTING PERIOD

1.

2.

50-305 KEWAUNEE July 8, 2002 MARY ANDERSON (920) 388-8453 JUNE, 2002 DESIGN ELECTRICAL RATING (MWE-NET)

MAXIMUM DEPENDABLE CAPACITY (MWE-NET) 535 511 MONTH YEAR-TO-DATE NUMBER OF HOURS REACTOR WAS CRITICAL NUMBER OF HOURS GENERATOR WAS ON LINE UNIT RESERVE SHUTDOWN HOURS NET ELECTRICAL ENERGY (MWH) 720.0 720.0 0.0 380201 4111.8 4097.7 0.0 2147739 CUMULATIVE 209077.7 206876.3 10.0 103321235 Notes: Unit continues to operate at 100%

power.

3.
4.
5.

6.

UNIT SHUTDOWNS DOCKET NO.

UNIT NAME DATE COMPLETED BY TELEPHONE REPORTING PERIOD (1)

F: Forced S: Scheduled 50-305 KEWAUNEE July 1, 2002 MARY ANDERSON (920) 388-8453 JUNE, 2002 Reason:

Method:

A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2 - Manual Trip/Scram C - Refueling 3 - Automatic Trip/Scram D - Regulatory Restriction 4 - Other (Explain)

E - Operator Training & License Examination Continuation F - Administrative G - Operational Error (Explain)

H - Other (Explain)

SUMMARY

The unit continues to operate at 100% steady state power METHOD OF NO.

DATE Type' DURATION REASON SHUTTING CAUSE/CORRECTIVE ACTIONS (Hours)

DOWN REACTOR3 No Shutdowns or power reductions in the month of June (2)

(3)