December 2002 Monthly Operating Report for Kewaunee Nuclear Power Plant
ML030150573
Person / Time
Site: Kewaunee Dominion icon.png
Issue date: 01/09/2003
From: Coutu T
Nuclear Management Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NRC-03-002
Download: ML030150573 (3)


Text

Kewaunee Nuclear Power Plant Point Beach Nuclear Plant N490 Highway 42 6610 Nuclear Road Kewaunee, Wl 54216-9511 Two Rivers, Wl 54241 920.388.2560 920.755.2321 NMCe Committed to NuclearExcellenc Kewaunee / Point Beach Nuclear Operated by Nuclear Management Company, LLC NRC-03-002 January 9, 2003 10 CFR 50.36 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555 Ladies/Gentlemen:

Docket 50-305 Operating License DPR-43 Kewaunee Nuclear Power Plant Monthly Operating Report The monthly operating report for the Kewaunee Nuclear Power Plant for December 2002 is enclosed in accordance with Technical Specification 6.9.a.3.

Sincerely, ThomaCut Thomas Coutu Site Vice President MLA Enclosure cc - US NRC - Region llI NRC Senior Resident Inspector INPO Records Center PSCW - Sharon Henning 2x

OPERATING DATA REPORT DOCKET NO. 50-305 Notes: Unit continues to operate at 100%

UNIT NAME Kewaunee power.

DATE January 9, 2003 COMPLETED BY Mary Anderson TELEPHONE (920) 388-8453 REPORTING PERIOD December, 2002

1. DESIGN ELECTRICAL RATING (MWE-NET) 535
2. MAXIMUM DEPENDABLE CAPACITY (MWE-NET) 511 MONTH YEAR-TO-DATE CUMULATIVE
3. NUMBER OF HOURS REACTOR WAS CRITICAL 744.0 8528.8 213494.7
4. NUMBER OF HOURS GENERATOR WAS ON LINE 744.0 8514.7 211293.3
5. UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 10.0
6. NET ELECTRICAL ENERGY (MWH) 390843 4468734 105642231

UNIT SHUTDOWNS DOCKET NO. 50-305 UNIT NAME Kewaunee DATE January 9, 2003 COMPLETED BY Mary Anderson TELEPHONE (920) 388-8453 REPORTING PERIOD December, 2002 METHOD OF NO. DATE Type' DURATION REASON, SHUTTING CAUSEICORRECTIVE ACTIONS (Hours) DOWN REACTOR' Performance of SP54-086, Turbine Stop and 5 12/07/02 S 22.55 B 5 Governor Valve Operability Test, and other reduced power procedures (2) (3)

(1)

F: Forced Reason: Method:

A - Equipment Failure (Explain) 1 - Manual S: Scheduled B - Maintenance or Test 2 - Manual Trip/Scram C - Refueling 3 - Automatic Trip/Scram D - Regulatory Restriction 4 - Other (Explain)

E - Operator Training & License Examination Continuation F - Administrative 5 - Load Reductions G - Operational Error (Explain) 9 - Other H - Other (Explain)

SUMMARY

The unit continues to operate at 100% steady state power