Line 1: |
Line 1: |
| {{Adams | | {{Adams |
| | number = ML13255A296 | | | number = ML13025A295 |
| | issue date = 09/12/2013 | | | issue date = 01/25/2013 |
| | title = Er 05000482-13-301; June 17, 2013 - August 8, 2013; Wolf Creek Generating Station; Initial Operator Licensing Examination Report; Examination Development | | | title = IR 05000482-13-301, Wolf Creek Nuclear Operating Company - Notification of NRC Initial Operator Licensing Examination |
| | author name = Gaddy V | | | author name = Gaddy V |
| | author affiliation = NRC/RGN-IV/DRS/OB | | | author affiliation = NRC/RGN-IV/DRS/OB |
Line 10: |
Line 10: |
| | license number = NPF-042 | | | license number = NPF-042 |
| | contact person = | | | contact person = |
| | document report number = 50-482/13-301 | | | document report number = IR-13-301 |
| | document type = Letter, License-Operator Examination Report | | | document type = Letter, License-Operator Examination Report, Inspection Report |
| | page count = 17 | | | page count = 3 |
| }} | | }} |
|
| |
|
Line 18: |
Line 18: |
|
| |
|
| =Text= | | =Text= |
| {{#Wiki_filter:ber 12, 2013 | | {{#Wiki_filter:UNITE D S TATE S NUC LEAR RE GULATOR Y C OMMI S SI ON ary 25, 2013 |
|
| |
|
| ==SUBJECT:== | | ==SUBJECT:== |
| WOLF CREEK GENERATING STATION - NRC EXAMINATION REPORT 05000482/2013301 | | WOLF CREEK NUCLEAR OPERATING COMPANY - NOTIFICATION OF NRC INITIAL OPERATOR LICENSING EXAMINATION 05000482/2013301 |
|
| |
|
| ==Dear Mr. Sunseri:== | | ==Dear Mr. Sunseri:== |
| On July 26, 2013, the U.S. Nuclear Regulatory Commission (NRC) completed an initial operator license examination at Wolf Creek Generating Station. The enclosed report documents the examination results and licensing decisions. The preliminary examination results were discussed on July 25, 2013, with yourself and other members of your staff. A telephonic exit meeting was conducted on August 8, 2013, with Mr. James Knapp, who was provided the NRC licensing decisions.
| | In a telephone conversation on January 9, 2013 between Ms. Jane Hartley and Duane Strickland, Chief Examiner, arrangements were made for the administration of licensing examinations at Wolf Creek during the week of July 22, 2013. |
|
| |
|
| The examination included the evaluation of six applicants for reactor operator licenses and one applicant for an instant senior reactor operator license. The license examiners determined that all seven applicants satisfied the requirements of 10 CFR Part 55 and the appropriate licenses have been issued. There were ten post examination comments submitted by your staff.
| | As agreed during the telephone conversation, your staff will prepare the examinations based on the guidelines in NUREG-1021, Operator Licensing Examination Standards for Power Reactors, Revision 9, Supplement 1, and NUREG-1122, Knowledge and Abilities Catalog for Nuclear Power Plant Operators, Revision 2, Supplement 1. The NRCs regional office will discuss with your staff any changes that might be necessary before the examinations are administered, To meet the above schedule, it will be necessary for your staff to furnish the examination outlines by May 3, 2013. The written examinations, operating tests, and supporting reference materials identified in Attachment 3 to ES-201 will be due by May 31, 2013. Pursuant to Title 10, Section 55.40(b)(3), of the Code of Federal Regulations, an authorized representative of the facility licensee shall approve the outlines, examinations, and tests before they are submitted to the NRC for review and approval. All materials shall be complete and ready-to-use. We request that any personal, proprietary, sensitive unclassified, or safeguards information in your response be contained in a separate enclosure and appropriately marked. Any delay in receiving the required examinations and reference materials, or the submittal of inadequate or incomplete materials, may cause the examinations to be rescheduled. In addition, your support for on-site validation of the examinations is required during the week of June 17, 2013. |
|
| |
|
| Enclosure 1 contains details of this report and Enclosure 2 summarizes post examination comment resolution.
| | In order to conduct the requested written examinations and operating tests, it will be necessary for your staff to provide adequate space and accommodations in accordance with ES-402, and to make the simulation facility available on the dates noted above. In accordance with ES-302, your staff should retain the original simulator performance data (e.g., system pressures, temperatures, and levels) generated during the dynamic operating tests until the examination results are final. Appendix E to NUREG-1021 contains a number of NRC policies and guidelines that will be in effect while the written examinations and operating tests are being administered. |
|
| |
|
| No findings were identified during this examination.
| | To permit timely NRC review and evaluation, your staff should submit preliminary operator and senior operator license applications (Office of Management and Budget (OMB) approval number 3150-0090), medical certifications (OMB approval number 3150-0024), and waiver requests (if any) (OMB approval number 3150-0090) at least 30 days before the first examination date. If the applications are not received at least 30 days before the examination date, a postponement may be necessary. Signed applications certifying that all training has been completed should be submitted at least 14 days before the first examination date. |
|
| |
|
| In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
| | This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by OMB, under approval number 3150-0018, which expires on February 28, 2013. The public reporting burden for this collection of information is estimated to average 50 hours per response, including the time for reviewing instructions, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of these information collections, including suggestions for reducing the burden, to the Records and FOIA/Privacy Services Branch (T-5 F52), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by Internet electronic mail to INFOCOLLECTS@NRC.GOV. |
|
| |
|
| Sincerely,
| | The NRC may neither conduct nor sponsor, and a person is not required to respond to, an information collection, unless it displays a currently valid OMB control number. |
| /RA/
| |
| Vince Gaddy, Chief Operations Branch Division of Reactor Safety Docket: 50-482 License: NPF-42
| |
|
| |
|
| ===Enclosure:===
| | In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of the NRCs Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the electronic Reading Room page of the NRCs public Web site at http://www.nrc.gov/reading-rm/adams.html. |
| 1. NRC Examination Report 05000482/2013301 w/Attachment: Supplemental Information 2. NRC Post Examination Comment Resolution
| |
|
| |
|
| REGION IV==
| | Thank you for your cooperation in this matter. Ms. Hartley has been advised of the policies and guidelines referenced in this letter. If you have any questions regarding the NRCs examination procedures and guidelines, please contact Mr. Strickland at 817-200-1570 or myself at 817-200-1159. |
| Docket: 50-482 License: NPF-42 Report: 05000482/2013301 Licensee: Wolf Creek Nuclear Operating Corporation Facility Wolf Creek Generating Station Location: 1550 Oxen Lane NE Burlington, Kansas Dates: June 17, 2013 - August 8, 2013 Inspectors: D. Strickland, Senior Operations Engineer K. Clayton, Senior Operations Engineer S. Hedger, Operations Engineer Approved By: Vince Gaddy, Chief Operations Branch Division of Reactor Safety-1- Enclosure
| |
| | |
| =SUMMARY OF FINDINGS=
| |
| ER05000482/2013301; June 17, 2013 - August 8, 2013; Wolf Creek Generating Station; Initial
| |
| | |
| Operator Licensing Examination Report; Examination Development NRC examiners evaluated the competency of six applicants for reactor operator licenses and one applicant for an instant senior reactor operator license at Wolf Creek Generating Station.
| |
| | |
| The licensee developed the examinations using NUREG-1021, "Operator Licensing Examination Standards for Power Reactors," Revision 9, Supplement 1. The written examination was administered by the licensee on July 19, 2013. NRC examiners administered the operating tests on the week of July 22, 2013.
| |
| | |
| The examiners determined that all seven of the applicants satisfied the requirements of 10 CFR Part 55, and the appropriate licenses have been issued.
| |
| | |
| ===NRC-Identified and Self-Revealing Findings===
| |
| | |
| None
| |
| | |
| ===Licensee-Identified Violations===
| |
| | |
| None
| |
| | |
| =REPORT DETAILS=
| |
| | |
| ==OTHER ACTIVITIES (OA)==
| |
| {{a|4OA5}}
| |
| ==4OA5 Other Activities (Initial Operator License Examination)==
| |
| | |
| ===.1 License Applications===
| |
| | |
| ====a. Scope====
| |
| NRC examiners reviewed all license applications submitted to ensure each applicant satisfied relevant license eligibility requirements. The examiners also audited three of the license applications in detail to confirm that they accurately reflected the subject applicants qualifications. This audit focused on the applicants experience and on-the-job training, including control manipulations that provided significant reactivity changes.
| |
| | |
| ====b. Findings====
| |
| No findings were identified.
| |
| | |
| ===.2 Examination Development===
| |
| | |
| ====a. Scope====
| |
| NRC examiners reviewed integrated examination outlines and draft examinations submitted by the licensee against the requirements of NUREG-1021. The NRC examination team conducted an onsite validation of the operating tests.
| |
| | |
| ====b. Findings====
| |
| No findings were identified.
| |
| | |
| NRC examiners provided outline, draft examination and post-validation comments to the licensee. The licensee satisfactorily completed comment resolution prior to examination administration.
| |
| | |
| NRC examiners determined that the written examination initially submitted by the licensee was not within the range of acceptability expected for a proposed examination.
| |
| | |
| There were 38 questions categorized as unsatisfactory per NUREG-1021 requirements, with the two most common issues being knowledge/ability mismatch or two or more distracters that were not credible. Additionally, there were 36 questions that needed editorial changes, and 26 questions that were satisfactory as originally submitted.
| |
| | |
| Consistent with the corporate notification letter sent to licensees at the start of examination development for each examination, future unsatisfactory examination submittals may cause the examinations to be rescheduled or cancelled. The licensee wrote Condition Report 00073742 to address these exam development issues.
| |
| | |
| ===.3 Operator Knowledge and Performance===
| |
| | |
| ====a. Scope====
| |
| On July 19, 2013, the licensee proctored the administration of the written examinations to all seven applicants. The licensee staff graded the written examinations, analyzed the results, and presented their analysis and post examination comments to the NRC on August 2, 2013.
| |
| | |
| The NRC examination team administered the various portions of the operating tests to all ten applicants on the week of July 22, 2013.
| |
| | |
| ====b. Findings====
| |
| No findings were identified.
| |
| | |
| All seven applicants passed all portions of the operating test. All of the applicants passed the written examination. The final written examinations and post-examination analysis and comments may be accessed in the ADAMS system under the accession numbers noted in the attachment. Post examination comments formally submitted by the licensee are included in the Enclosure 2 of this report.
| |
| | |
| The examination team noted a generic weakness during the administration of the Job Performance Measure associated with the ability to complete a Containment Purge Isolation. Three out of seven applicants initially closed two incorrect dampers, prior to closing the correct dampers. There was also a generic weakness noted in the completion of the Job Performance Measure associated with a task on the Radiation Monitoring Panel. Two of seven operators had problems with the operation of the RM11R panel. The licensee wrote Condition Report 00072089 to address the Radiation Monitoring Panel issue.
| |
| | |
| ===.4 Simulation Facility Performance===
| |
| | |
| ====a. Scope====
| |
| The NRC examiners observed simulator performance with regard to plant fidelity during examination validation and administration.
| |
| | |
| ====b. Findings====
| |
| No findings were identified.
| |
| | |
| ===.5 Examination Security===
| |
| | |
| ====a. Scope====
| |
| The NRC examiners reviewed examination security during both the onsite preparation week and examination administration week for compliance with 10 CFR 55.49 and NUREG-1021. Plans for simulator security and applicant control were reviewed and discussed with licensee personnel.
| |
| | |
| ====b. Findings====
| |
| No findings were identified.
| |
| | |
| ===.6 Facility Post Examination Comments===
| |
| | |
| The facility provided the NRC chief examiner with ten post administration comments on the written examination. These comments are included in Enclosure 2 to this report and in ADAMS under as Accession Number ML13248A545.
| |
| | |
| {{a|4OA6}}
| |
| ==4OA6 Meetings, Including Exit==
| |
| | |
| The chief examiner presented the preliminary examination results to Mr. Al Camp, Plant Manager, and other members of the staff on July 25, 2013. A telephonic exit was conducted on August 8, 2013, between Mr. Duane Strickland, Chief Examiner, and Mr. James Knapp, Supervisor, Operations Training.
| |
| | |
| All proprietary information and materials used during the examination were returned to the licensee.
| |
| | |
| ATTACHMENT:
| |
| | |
| =SUPPLEMENTAL INFORMATION=
| |
| | |
| ==KEY POINTS OF CONTACT==
| |
| | |
| ===Licensee Personnel===
| |
| Al Camp, Plant Manager
| |
| Steve Henry, Operations Manager
| |
| Shane Battenfield, Operations Instructor
| |
| Kenneth Fredrickson, Licensing
| |
| James Knapp, Supervisor, Operations Training
| |
| Edward Ray, Manager Training
| |
| Terry Damashek, Supervisor Operations Support Training
| |
| Brendan Ryan, Initial Licensing Supervising Instructor
| |
| Robert Acree, Simulator Fidelity Coordinator
| |
| George Smith, Initial Licensing Supervising Instructor
| |
| ===NRC Personnel===
| |
| Charles Peabody, Senior Resident Inspector
| |
| | |
| ==ADAMS DOCUMENTS REFERENCED==
| |
|
| |
|
| | Sincerely, |
| | /RA/ |
| | Vince Gaddy, Chief Operations Branch Division of Reactor Safety Docket: 50-482 License: NPF-42 Electronic Distribution to Wolf Creek Nuclear Operating Company Electronic distribution by RIV: |
| | Regional Administrator (Elmo.Collins@nrc.gov) |
| | Deputy Regional Administrator (Steven.Reynolds@nrc.gov) |
| | DRP Director (Kriss.Kennedy@nrc.gov) |
| | Acting DRP Deputy Director (Barry.Westreich@nrc.gov) |
| | Acting DRS Director (Tom.Blount@nrc.gov) |
| | Acting DRS Deputy Director (Jeff.Clark@nrc.gov) |
| | Senior Resident Inspector (Chris.Long@nrc.gov) |
| | Resident Inspector (Charles.Peabody@nrc.gov) |
| | WC Administrative Assistant - Vacant Branch Chief, DRP/B (Neil.OKeefe@nrc.gov) |
| | Senior Project Engineer, DRP/B (Leonard.Willoughby@nrc.gov) |
| | Project Engineer, DRP/B (David.You@nrc.gov) |
| | Public Affairs Officer (Victor.Dricks@nrc.gov) |
| | Public Affairs Officer (Lara.Uselding@nrc.gov) |
| | Project Manager (Randy.Hall@nrc.gov) |
| | Branch Chief, DRS/TSB (Ray.Kellar@nrc.gov) |
| | RITS Coordinator (Marisa.Herrera@nrc.gov) |
| | Regional Counsel (Karla.Fuller@nrc.gov) |
| | Technical Support Assistant (Loretta.Williams@nrc.gov) |
| | Congressional Affairs Officer (Jenny.Weil@nrc.gov) |
| | OEMail Resource R:\_REACTORS\_WC\2013\WC 2013301 exam notify-DGS.docx ML13025A295 ADAMS: No Yes SUNSI Review Complete Reviewer Initials: DGS Publicly Available Non-Sensitive Non-publicly Available Sensitive RIV: SOE C: |
| | DStrickland VGaddy |
| | /RA/ /RA/ |
| | 1/25/13 1/25/13 OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax |
| }} | | }} |
|
---|
Category:Letter
MONTHYEARIR 05000482/20244202024-10-31031 October 2024 Security Baseline Inspection Report 05000482/2024420 ML24296B1902024-10-22022 October 2024 10 CFR 50.55a Requests for the Fifth Ten-Year Interval Inservice Testing Program 05000482/LER-2024-001-01, Mode 3 Entry with One Auxiliary Feedwater Pump Train Inoperable Due to Missed Post-Maintenance Testing2024-10-22022 October 2024 Mode 3 Entry with One Auxiliary Feedwater Pump Train Inoperable Due to Missed Post-Maintenance Testing 05000482/LER-2024-002, Technical Specification Required Shutdown Due to Inoperable Auxiliary Feedwater Discharge Valve2024-10-21021 October 2024 Technical Specification Required Shutdown Due to Inoperable Auxiliary Feedwater Discharge Valve ML24284A2842024-10-10010 October 2024 (Wcgs), Revision of One Form That Implements the Radiological Emergency Response Plan (RERP) ML24283A0752024-10-0909 October 2024 Notification of Commercial Grade Dedication Inspection (05000482/2025012) and Request for Information ML24199A1712024-09-17017 September 2024 Issuance of Amendment No. 241 Revise Ventilation Filter Testing Program Criteria and Administrative Correction of Absorber in Technical Specification 5.5.11 ML24260A0712024-09-12012 September 2024 License Amendment Request for a Risk-Informed Resolution to GSI-191 IR 05000482/20240102024-09-10010 September 2024 Biennial Problem Identification and Resolution Inspection Report 05000482/2024010 (Public) ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification ML24248A0762024-09-0404 September 2024 Containment Inservice Inspection Program Third Interval, Second Period, Refueling Outage 26 Owner’S Activity Report ML24248A2492024-09-0404 September 2024 Inservice Inspection Program Fourth Interval, Third Period, Refueling Outage 26 Owner’S Activity Report ML24241A2212024-08-29029 August 2024 Notice of Enforcement Discretion for Wolf Creek Generating Station ML24240A2642024-08-27027 August 2024 Corporation - Request for Notice of Enforcement Discretion Regarding Technical Specification 3.7.5, Auxiliary Feedwater (AFW) System ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 IR 05000482/20240052024-08-14014 August 2024 Updated Inspection Plan for Wolf Creek Generating Station (Report 05000482/2024005) ML24227A5562024-08-14014 August 2024 Application to Revise Technical Specifications to Adopt TSTF-569-A, Revision 2, Revision of Response Time Testing Definitions ML24213A3352024-07-31031 July 2024 License Amendment Request to Revise Technical Specification 3.2.1, Heat Flux Hot Channel Factor (Fq(Z)) (Fq Methodology), to Implement the Methodology from WCAP-17661-P-A, Revision 1. ML24206A1252024-07-24024 July 2024 Revision of Three Procedures and Two Forms That Implement the Radiological Emergency Response Plan (RERP) IR 05000482/20240022024-07-18018 July 2024 Integrated Inspection Report 05000482/2024002 05000482/LER-2024-001, Mode 3 Entry with One Auxiliary Feedwater Pump Train Inoperable Due to Missed Post-Maintenance Testing2024-07-0202 July 2024 Mode 3 Entry with One Auxiliary Feedwater Pump Train Inoperable Due to Missed Post-Maintenance Testing IR 05000482/20244012024-07-0202 July 2024 Security Baseline Inspection Report 05000482/2024401 ML24178A3672024-06-26026 June 2024 Correction to 2023 Annual Radioactive Effluent Release Report – Report 47 ML24178A4142024-06-26026 June 2024 Revision of One Procedure and One Form That Implement the Radiological Emergency Response Plan (RERP) ML24162A1632024-06-11011 June 2024 Operating Corporation – Notification of Biennial Problem Identification and Resolution Inspection and Request for Information (05000482/2024010) ML24150A0562024-05-29029 May 2024 Foreign Ownership, Control or Influence (FOCI) Information – Change to Lists of Owners, Officers, Directors and Executive Personnel - Form 405F Amendment ML23345A1602024-05-0909 May 2024 Revision of Safety Evaluation for Amendment No. 237 Request for Deviation from Fire Protection Requirements ML24089A2622024-04-29029 April 2024 Financial Protection Levels ML24118A0022024-04-27027 April 2024 Wolf Generating Nuclear Station - 2023 Annual Radiological Environmental Operating Report ML24118A0032024-04-27027 April 2024 2023 Annual Radioactive Effluent Release Report - Report 47 ML24113A1882024-04-19019 April 2024 Foreign Ownership, Control or Influence Information - Change to Lists of Owners, Officers, Directors and Executive Personnel - Form 405F Amendment ML24109A1842024-04-18018 April 2024 Cycle 27 Core Operating Limits Report ML24109A1212024-04-18018 April 2024 (WCGS) Form 5 Exposure Report for Calendar Year 2023 IR 05000482/20240012024-04-17017 April 2024 Integrated Inspection Report 05000482/2024001 ML24114A1442024-04-15015 April 2024 Redacted Updated Safety Analysis Report (WCGS Usar), Revision 37 ML24106A1482024-04-15015 April 2024 Notification of Inspection (NRC Inspection Report 05000482/2024003) and Request for Information ML24098A0052024-04-0707 April 2024 2023 Annual Environmental Operating Report ML24089A0972024-03-29029 March 2024 Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24089A1352024-03-29029 March 2024 10 CFR 50.46 Annual Report of Emergency Core Cooling System (ECCS) Evaluation Model Changes ML24074A3312024-03-14014 March 2024 Missed Quarterly Inspection Per 40 CFR 266 Subpart N IR 05000482/20240122024-03-11011 March 2024 Fire Protection Team Inspection Report 05000482/2024012 ML24080A3452024-03-11011 March 2024 7 of the Wolf Creek Generating Station Updated Safety Analysis Report ML24016A0702024-03-0808 March 2024 Issuance of Amendment No. 240 Removal of the Power Range Neutron Flux Rate - High Negative Rate Trip Function from Technical Specifications ML24068A1992024-03-0707 March 2024 Changes to Technical Specification Bases - Revisions 93 and 94 ML24066A0672024-03-0505 March 2024 4-2022-024 Letter - OI Closure to Licensee ML24061A2642024-03-0101 March 2024 Revision of Two Procedures That Implement the Radiological Emergency Response Plan (RERP) for Wolf Creek Generating Station (WCGS) Commissioners IR 05000482/20230062024-02-28028 February 2024 Annual Assessment Letter for Wolf Creek Generating Station Report 05000482/2023006 ML24059A1702024-02-28028 February 2024 Annual Fitness for Duty Program Performance Report, and Annual Fatigue Report for 2023 ML24026A0212024-02-27027 February 2024 Issuance of Amendment No. 239 Modified Implementation Date of License Amendment No. 238 ML24050A0012024-02-19019 February 2024 (Wcgs), Revision of One Form That Implements the Radiological Emergency Response Plan (RERP) 2024-09-06
[Table view] Category:License-Operator Examination Report
MONTHYEARML24089A0972024-03-29029 March 2024 Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000482/20213012022-01-19019 January 2022 NRC Examination Report 05000482/2021301 IR 05000482/20173012018-01-11011 January 2018 NRC Examination Report 05000482/2017301 IR 05000482/20153012016-01-28028 January 2016 Er 05000482/2015301; 11/13/2015 - 12/29/2015; Wolf Creek Generating Station; Initial Operator Licensing Examination Report IR 05000482/20133012013-09-12012 September 2013 Er 05000482-13-301; June 17, 2013 - August 8, 2013; Wolf Creek Generating Station; Initial Operator Licensing Examination Report; Examination Development ML13025A2952013-01-25025 January 2013 IR 05000482-13-301, Wolf Creek Nuclear Operating Company - Notification of NRC Initial Operator Licensing Examination IR 05000482/20123012012-02-23023 February 2012 Er 05000482-12-301, on January 18, 2012 - February 15, 2012, Wolf Creek Generating Station, Retake Operator Licensing Examination Report IR 05000482/20110012011-10-18018 October 2011 Er 05000482-11-001; August 26, 2011 - September 22, 2011; Wolf Creek Generating Station; Initial Operator Licensing Examination Report; Examination Development IR 05000482/20093022010-02-11011 February 2010 Er 05000482-09-302; December 14, 2009 - January 6, 2010; Wolf Creek Generating Station; Initial Operator Licensing Examination Report; Identification and Resolution of Problems IR 05000482/20093012009-10-20020 October 2009 Er 05000482-09-301; August 31 - October 2, 2009; Wolf Creek Generating Station; Initial Operator Licensing Examination Report IR 05000482/20063012006-04-0303 April 2006 Er 05000482-06-301; 03/03-09/2006; Wolf Creek Nuclear Generating Station; Initial Operator Licensing Examination Report ML0409200332004-03-30030 March 2004 Generic Fundamentals Section of the Written Operator Licensing Examination WO 02-0037, Preparation and Scheduling of Operator Licensing Examinations2002-07-11011 July 2002 Preparation and Scheduling of Operator Licensing Examinations 2024-03-29
[Table view] Category:Inspection Report
MONTHYEARIR 05000482/20244202024-10-31031 October 2024 Security Baseline Inspection Report 05000482/2024420 IR 05000482/20240102024-09-10010 September 2024 Biennial Problem Identification and Resolution Inspection Report 05000482/2024010 (Public) IR 05000482/20240052024-08-14014 August 2024 Updated Inspection Plan for Wolf Creek Generating Station (Report 05000482/2024005) IR 05000482/20240022024-07-18018 July 2024 Integrated Inspection Report 05000482/2024002 IR 05000482/20244012024-07-0202 July 2024 Security Baseline Inspection Report 05000482/2024401 IR 05000482/20240012024-04-17017 April 2024 Integrated Inspection Report 05000482/2024001 IR 05000482/20240122024-03-11011 March 2024 Fire Protection Team Inspection Report 05000482/2024012 IR 05000482/20230062024-02-28028 February 2024 Annual Assessment Letter for Wolf Creek Generating Station Report 05000482/2023006 IR 05000482/20230042024-01-11011 January 2024 Integrated Inspection Report 05000482/2023004 IR 05000482/20233012023-12-19019 December 2023 NRC Examination Report 05000482/2023301 IR 05000482/20230052023-08-23023 August 2023 Updated Inspection Plan for Wolf Creek Nuclear Operating Corporation, Unit 1 (Report 05000482/2023005) - Mid-Cycle Letter 2023 IR 05000482/20234202023-07-12012 July 2023 Security Baseline Inspection Report 05000482/2023420 - Cover Letter IR 05000482/20230022023-07-11011 July 2023 Integrated Inspection Report 05000482/2023002 IR 05000482/20234012023-06-21021 June 2023 Security Baseline Inspection Report 05000482/2023401 ML23111A0662023-04-20020 April 2023 (Cover Letter Only) Wolf Creek Generating Station – Special Inspection Reactive Report 05000482-20220502 IR 05000482/20230012023-04-19019 April 2023 Integrated Inspection Report 05000482/2023001 IR 05000482/20220062023-03-0101 March 2023 Annual Assessment Letter for Wolf Creek Generating Station (Report 05000482/2022006) IR 05000482/20234022023-02-0606 February 2023 Security Baseline Inspection Report 050004822023402 ML23017A2092023-01-18018 January 2023 Emergency Preparedness Biennial Exercise Inspection URI Closure Report IR 05000482/20220042023-01-17017 January 2023 Integrated Inspection Report 05000482/2022004 ML22333A7132022-12-0202 December 2022 License Renewal Phase 1 Report IR 05000482/20220032022-10-25025 October 2022 Integrated Inspection Report 05000482/2022003 IR 05000482/20224032022-08-31031 August 2022 NRC Security Baseline Inspection Report 05000482/2022403 IR 05000482/20220052022-08-23023 August 2022 Updated Inspection Plan for Wolf Creek Generating Station (Report 05000482/2022005) IR 07200079/20224042022-08-0404 August 2022 NRC Security Inspection Report 07200079/2022404 (Cover Letter) IR 05000482/20220022022-07-25025 July 2022 Integrated Inspection Report 05000482/2022002 IR 05000482/20224022022-06-29029 June 2022 Security Baseline Inspection Report 05000482/2022402 - Public IR 05000482/20220102022-05-0505 May 2022 Biennial Problem Identification and Resolution Inspection Report 05000482/2022010 IR 05000482/20224012022-05-0303 May 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000482/2022401 IR 05000482/20220012022-04-25025 April 2022 Integrated Inspection Report 05000482/2022001 and Independent Spent Fuel Storage Installation Inspection Report 07200079/2022001 IR 05000482/20210062022-03-0202 March 2022 Annual Assessment Letter (Report 05000482/2021006) IR 05000482/20210042022-01-19019 January 2022 Integrated Inspection Report 05000482/2021004 and Independent Spent Fuel Storage Installation Inspection Report 07200079/2021002 IR 05000482/20213012022-01-19019 January 2022 NRC Examination Report 05000482/2021301 IR 05000482/20210112021-12-0101 December 2021 Temporary Instruction 2515/194 Report 05000482/2021011 IR 05000482/20214202021-11-15015 November 2021 Inspection Report Cover Letter FOF 05000482/2021420 IR 05000482/20210032021-11-0505 November 2021 Integrated Inspection Report 05000482/2021003 and Independent Spent Fuel Storage Installation Inspection Report 07200079/2021001, WC2021003 IR Ch IR 05000482/20210102021-09-0909 September 2021 Design Basis Assurance Inspection (Teams) Inspection Report 05000482/2021010 IR 05000482/20210022021-08-0909 August 2021 Integrated Inspection Report 05000482/2021002 IR 05000482/20214022021-07-27027 July 2021 NRC Security Baseline Inspection Report 05000482/2021402 (Cover Letter Without Enclosure) IR 05000482/20210012021-05-0505 May 2021 Integrated Inspection Report 05000482/2021001 IR 05000482/20190062021-03-0303 March 2021 Annual Assessment Letter (Report 05000482/2019006) IR 05000482/20214012021-02-26026 February 2021 NRC Security Inspection Report 05000482/2021401 IR 05000482/20200042021-02-0909 February 2021 Integrated Inspection Report 05000482/2020004 IR 05000482/20200132020-12-0303 December 2020 Traditional Enforcement Follow-Up Inspection Report 05000482/2020013 IR 05000482/20200122020-11-19019 November 2020 Triennial Fire Protection Inspection Report 05000482/2020012 IR 05000482/20200032020-11-12012 November 2020 Integrated Inspection Report 05000482/2020003 IR 05000482/20204102020-09-29029 September 2020 Security Baseline Inspection Report 05000482/2020410 IR 05000482/20200022020-08-12012 August 2020 Integrated Inspection Report 05000482/2020002 and Independent Spent Fuel Storage Installation Inspection Report 07200079/2020001 IR 05000482/20200102020-08-0303 August 2020 Biennial Problem Identification and Resolution Inspection Report 05000482/2020010 IR 05000482/20200112020-05-21021 May 2020 Design Basis Assurance Inspection (Programs) Inspection Report 05000482/2020011 2024-09-10
[Table view] |
Text
UNITE D S TATE S NUC LEAR RE GULATOR Y C OMMI S SI ON ary 25, 2013
SUBJECT:
WOLF CREEK NUCLEAR OPERATING COMPANY - NOTIFICATION OF NRC INITIAL OPERATOR LICENSING EXAMINATION 05000482/2013301
Dear Mr. Sunseri:
In a telephone conversation on January 9, 2013 between Ms. Jane Hartley and Duane Strickland, Chief Examiner, arrangements were made for the administration of licensing examinations at Wolf Creek during the week of July 22, 2013.
As agreed during the telephone conversation, your staff will prepare the examinations based on the guidelines in NUREG-1021, Operator Licensing Examination Standards for Power Reactors, Revision 9, Supplement 1, and NUREG-1122, Knowledge and Abilities Catalog for Nuclear Power Plant Operators, Revision 2, Supplement 1. The NRCs regional office will discuss with your staff any changes that might be necessary before the examinations are administered, To meet the above schedule, it will be necessary for your staff to furnish the examination outlines by May 3, 2013. The written examinations, operating tests, and supporting reference materials identified in Attachment 3 to ES-201 will be due by May 31, 2013. Pursuant to Title 10, Section 55.40(b)(3), of the Code of Federal Regulations, an authorized representative of the facility licensee shall approve the outlines, examinations, and tests before they are submitted to the NRC for review and approval. All materials shall be complete and ready-to-use. We request that any personal, proprietary, sensitive unclassified, or safeguards information in your response be contained in a separate enclosure and appropriately marked. Any delay in receiving the required examinations and reference materials, or the submittal of inadequate or incomplete materials, may cause the examinations to be rescheduled. In addition, your support for on-site validation of the examinations is required during the week of June 17, 2013.
In order to conduct the requested written examinations and operating tests, it will be necessary for your staff to provide adequate space and accommodations in accordance with ES-402, and to make the simulation facility available on the dates noted above. In accordance with ES-302, your staff should retain the original simulator performance data (e.g., system pressures, temperatures, and levels) generated during the dynamic operating tests until the examination results are final. Appendix E to NUREG-1021 contains a number of NRC policies and guidelines that will be in effect while the written examinations and operating tests are being administered.
To permit timely NRC review and evaluation, your staff should submit preliminary operator and senior operator license applications (Office of Management and Budget (OMB) approval number 3150-0090), medical certifications (OMB approval number 3150-0024), and waiver requests (if any) (OMB approval number 3150-0090) at least 30 days before the first examination date. If the applications are not received at least 30 days before the examination date, a postponement may be necessary. Signed applications certifying that all training has been completed should be submitted at least 14 days before the first examination date.
This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by OMB, under approval number 3150-0018, which expires on February 28, 2013. The public reporting burden for this collection of information is estimated to average 50 hours5.787037e-4 days <br />0.0139 hours <br />8.267196e-5 weeks <br />1.9025e-5 months <br /> per response, including the time for reviewing instructions, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of these information collections, including suggestions for reducing the burden, to the Records and FOIA/Privacy Services Branch (T-5 F52), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by Internet electronic mail to INFOCOLLECTS@NRC.GOV.
The NRC may neither conduct nor sponsor, and a person is not required to respond to, an information collection, unless it displays a currently valid OMB control number.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of the NRCs Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the electronic Reading Room page of the NRCs public Web site at http://www.nrc.gov/reading-rm/adams.html.
Thank you for your cooperation in this matter. Ms. Hartley has been advised of the policies and guidelines referenced in this letter. If you have any questions regarding the NRCs examination procedures and guidelines, please contact Mr. Strickland at 817-200-1570 or myself at 817-200-1159.
Sincerely,
/RA/
Vince Gaddy, Chief Operations Branch Division of Reactor Safety Docket: 50-482 License: NPF-42 Electronic Distribution to Wolf Creek Nuclear Operating Company Electronic distribution by RIV:
Regional Administrator (Elmo.Collins@nrc.gov)
Deputy Regional Administrator (Steven.Reynolds@nrc.gov)
DRP Director (Kriss.Kennedy@nrc.gov)
Acting DRP Deputy Director (Barry.Westreich@nrc.gov)
Acting DRS Director (Tom.Blount@nrc.gov)
Acting DRS Deputy Director (Jeff.Clark@nrc.gov)
Senior Resident Inspector (Chris.Long@nrc.gov)
Resident Inspector (Charles.Peabody@nrc.gov)
WC Administrative Assistant - Vacant Branch Chief, DRP/B (Neil.OKeefe@nrc.gov)
Senior Project Engineer, DRP/B (Leonard.Willoughby@nrc.gov)
Project Engineer, DRP/B (David.You@nrc.gov)
Public Affairs Officer (Victor.Dricks@nrc.gov)
Public Affairs Officer (Lara.Uselding@nrc.gov)
Project Manager (Randy.Hall@nrc.gov)
Branch Chief, DRS/TSB (Ray.Kellar@nrc.gov)
RITS Coordinator (Marisa.Herrera@nrc.gov)
Regional Counsel (Karla.Fuller@nrc.gov)
Technical Support Assistant (Loretta.Williams@nrc.gov)
Congressional Affairs Officer (Jenny.Weil@nrc.gov)
OEMail Resource R:\_REACTORS\_WC\2013\WC 2013301 exam notify-DGS.docx ML13025A295 ADAMS: No Yes SUNSI Review Complete Reviewer Initials: DGS Publicly Available Non-Sensitive Non-publicly Available Sensitive RIV: SOE C:
DStrickland VGaddy
/RA/ /RA/
1/25/13 1/25/13 OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax