|
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARTXX-9924, Forwards Responses to Questions by NRC Re Application for Amends to Licenses NPF-87 & NPF-89,by Incorporating Changes Increasing RWST low-level Setpoint from Greater than But Equal to 40% to Greater than But Equal to 45% of Span1999-10-22022 October 1999 Forwards Responses to Questions by NRC Re Application for Amends to Licenses NPF-87 & NPF-89,by Incorporating Changes Increasing RWST low-level Setpoint from Greater than But Equal to 40% to Greater than But Equal to 45% of Span ML20217M5711999-10-20020 October 1999 Forwards Insp Repts 50-445/99-15 & 50-446/99-15 on 990822- 1002.Two Severity Level IV Violations of NRC Requirements Identified & Being Treated as non-cited Violations Consistent with App C of Enforcement Policy TXX-9923, Forwards Monthly Operating Repts for Sept 1999 for CPSES, Units 1 & 2,per Plant TS 5.6.4.No Failures of Challenges to PORVs of SV for Units Occurred1999-10-15015 October 1999 Forwards Monthly Operating Repts for Sept 1999 for CPSES, Units 1 & 2,per Plant TS 5.6.4.No Failures of Challenges to PORVs of SV for Units Occurred ML20217E7951999-10-12012 October 1999 Forwards COLR for Unit 1,Cycle 8,per TS 5.6.5 ML20212L2891999-10-0101 October 1999 Discusses Closeout of GL 97-06, Degradation of Steam Generator Internals. Purpose of GL Was to Obtain Info That Would Enable NRC to Verify That Condition of Licensee SG Internals Comply with Current Licensing Bases TXX-9922, Forwards Revised COLR, for Cycle 5 for Unit 21999-10-0101 October 1999 Forwards Revised COLR, for Cycle 5 for Unit 2 ML20216J5571999-10-0101 October 1999 Provides Final Response to GL 98-01,suppl 1, Y2K Readiness of Computer Sys at Npps ML20212G0721999-09-24024 September 1999 Forwards Rev 4 to Augmented Inservice Insp Plan for CPSES, Unit 1. Future Changes & Revs to Unit 1 Augmented Inservice Insp Plan Will Be Available on Site ML20212H0461999-09-24024 September 1999 Forwards Rev 6 to CPSES Glen Rose,Tx ASME Section XI ISI Program Plan for 1st Interval on 990820 ML20212F7481999-09-24024 September 1999 Forwards SER Authorizing Relief from Exam Requirement of 1986 Edition ASME Code,Section XI Pursuant to 10CFR50.55a(a)(3)(ii) for Relief Request A-3 & 10CFR50.55a(g)(6)(i) for Relief Requests B15,16,17 & C-4 ML20212F1041999-09-23023 September 1999 Requests That NRC Be Informed of Any Changes in Scope of Y2K System Deficiencies Listed or Util Projected Completion Schedule for Comanche Peak Steam Electric Station,Units 1 & 2 ML20212E6661999-09-21021 September 1999 Advises That Info Contained in Application & Affidavit, (CAW-99-1342) Re WCAP-15009,Rev 0, Comache Peak Unit 1 Evaluation for Tube Vibration Induced Fatigue, Will Be Withheld from Public Disclosure ML20212D9111999-09-16016 September 1999 Informs That on 990818,NRC Completed Midcycle PPR of CPSES & Did Not Identify Any Areas in Which Performance Warranted Insp Beyond Core Insp Program.Core Insp Plan at Facility Over Next 7 Months.Insp Plan Through March 2000 Encl ML20212A7601999-09-14014 September 1999 Forwards Insp Repts 50-445/99-14 & 50-446/99-14 on 990707-0821.Four Violations Occurred & Being Treated as Ncvs.Conduct of Activities Was Generally Characterized by safety-conscious Operations & Sound Radiological Controls TXX-9921, Suppls 981221 LAR 98-010 to Licenses NPF-87 & NPF-89, Clarfying Conditions of Use Re Analytical Methods Used to Determine Core Operating Limits,Per Telcon with NRC1999-09-10010 September 1999 Suppls 981221 LAR 98-010 to Licenses NPF-87 & NPF-89, Clarfying Conditions of Use Re Analytical Methods Used to Determine Core Operating Limits,Per Telcon with NRC ML20211P3761999-09-0707 September 1999 Ack Receipt of Ltr Dtd 990615,transmitting Rev 30 to Physical Security Plan,Per 10CFR50.54(p).No NRC Approval Is Required ML20211L9871999-09-0303 September 1999 Forwards Rev 31 to Technical Requirements Manual. All Changes Applicable to Plants Have Been Reviewed Under Util 10CFR50.59 Process & Found Not to Include Any USQs TXX-9915, Responds to 990701 & 0825 RAI Telcons Re Spent Fuel Pool Temp,Per LAR 98-008,which Requested Increase in Spent Fuel Storage capacity.Marked-up Page 4-1 of CPSES Fuel Storage Licensing Rept, Encl1999-09-0303 September 1999 Responds to 990701 & 0825 RAI Telcons Re Spent Fuel Pool Temp,Per LAR 98-008,which Requested Increase in Spent Fuel Storage capacity.Marked-up Page 4-1 of CPSES Fuel Storage Licensing Rept, Encl ML20211K2231999-08-31031 August 1999 Forwards Txu Electric Comments of Rvid,Version 2 ML20211J3801999-08-27027 August 1999 Forwards Corrected TS Page 3.8-26 to Amend 66 to Licenses NPF-87 & NPF-89,respectively.Footnote on TS Page 3.8-26 Incorrectly Deleted ML20211G7301999-08-26026 August 1999 Forwards Revs 29 & 30 to CPSES Technical Requirements Manual (Trm). Attachments 1 & 2 Contain Description of Changes for Revs 29 & 30 Respectively ML20211G1081999-08-26026 August 1999 Responds to NRR Staff RAI Re Util Mar 1999 Submittal for NRC Review & Approval of Changes to CPSES Emergency Classification Procedure ML20211G3441999-08-25025 August 1999 Forwards Response to NRC RAI on LAR 98-010 for Cpses,Units 1 & 2.Communication Contains No New Licensing Commitments Re Cpses,Units 1 & 2 ML20211B2861999-08-18018 August 1999 Forwards Insp Repts 50-445/99-13 & 50-446/99-13 on 990720- 23.No Violations Noted.Insp Included Implementation of Licensee Emergency Plan & Procedures During Util Biennial Emergency Preparedness Exercise ML20211C4661999-08-18018 August 1999 Discusses Proprietary Info Re Thermo-Lag.NRC Treated Bisco Test Rept 748-105 as Proprietary & Withheld It from Public Disclosure,Iaw 10CFR2.790 ML20210U3981999-08-17017 August 1999 Forwards Monthly Operating Repts for July 1999 for CPSES, Units 1 & 2,per TS 6.9.1.5.No Failures or Challenges to PORVs or SVs for Plant Occurred ML20211C0991999-08-17017 August 1999 Forwards Rev 3 to ASME Section XI ISI Program Plan,Unit 2 - 1st Interval, Replacing Rev 2 in Entirety ML20211C4571999-08-16016 August 1999 Forwards Omitted Subj Page of Contractor TER TXX-9919, Forwards Relief Request A-3,Rev 1 to Unit 1 ISI Program,Per Conversations Between NRC & Txu Electric on 9908021999-08-16016 August 1999 Forwards Relief Request A-3,Rev 1 to Unit 1 ISI Program,Per Conversations Between NRC & Txu Electric on 990802 ML20210R6561999-08-13013 August 1999 Forwards Response to NRR 990805 Telcon RAI Re License Amend Request 98-010,to Increase Power for Operation of CPSES Unit 2 to 3445 Mwth & Incorporating Addl Changes Into Units 1 & 2 TS ML20211A9501999-08-12012 August 1999 Discusses 990720-21 Workshop Conducted in Region IV Ofc,Re Exchange of Info in Area of Use of Risk Insights in Regulatory Activities.List of Attendees,Summary of Topic & Issues,Agenda & Copies of Handouts Encl ML20210S6411999-08-12012 August 1999 Informs That Wg Guldemond,License SOP-43780,is No Longer Performing Licensed Duties.Discontinuation of License Is Requested ML20210R2221999-08-12012 August 1999 Forwards Insp Repts 50-445/99-10 & 50-446/99-10 on 990510-0628.Violations Noted & Being Treated as Ncvs, Consistent with App C of Enforcement Policy ML20210N1101999-08-0404 August 1999 Provides Supplemental Info to Util 990623 License Amend Request 99-005 Re Bypassing DG Trips.Info Replaces Info Contained in Subject Submittal in Attachment 2,Section II, Description of TS Change Request ML20210L1461999-08-0303 August 1999 Informs That NRC Plans to Administer Gfes of Written Operator Licensing Exam on 991006.Requests Submittal of Ltr Identifying Individuals Taking Exam,Personnel Allowed Access to Exams & Mailing Address for Exams ML20210J2301999-08-0202 August 1999 Forwards Amend 96 to CPSES Ufsar.Replacement of FSAR Figures with Plant Process Flow Diagrams Meets Intent & Requirements of NRC Reg Guide 1.70,Rev 2 ML20210J6071999-08-0202 August 1999 Forwards line-by-line Descriptions of Changes in Amend 96 to CPSES UFSAR Transmitted by Util Ltr TXX-99166,dtd 990802. Replacment of FSAR Figures with Plant Process Flow Diagrams Meets Intent & Requirements of NRC Reg Guide 1.70,rev 2 TXX-9916, Notifies NRC That CPSES Units 1 & 2,improved TS Implemented on 9907271999-08-0202 August 1999 Notifies NRC That CPSES Units 1 & 2,improved TS Implemented on 990727 TXX-9918, Forwards CPSES 10CFR50.59 Evaluation Summary Rept 0008,for 970802-990201 & CPSES Commitment Matl Change Evaluation Rept 0003,for 970802-9906301999-08-0202 August 1999 Forwards CPSES 10CFR50.59 Evaluation Summary Rept 0008,for 970802-990201 & CPSES Commitment Matl Change Evaluation Rept 0003,for 970802-990630 ML20210K2321999-07-29029 July 1999 Forwards Insp Repts 50-445/99-12 & 50-446/99-12 on 990530-0710.No Violations Noted ML20210G5861999-07-29029 July 1999 Forwards fitness-for-duty Program Performance Data for Six Month Period of Jan-June 1999 ML20210J0121999-07-27027 July 1999 Forwards Summary of Methodology for Determination of NDE Measurement Uncertainty,In Response to Recent Discussions with NRC Re LAR 98-006 Concerning Rev to SG Tube Plugging Criteria TXX-9917, Provides Info Re Augmented Inservice Insp Plan,Which Requires Periodic Insp of Rv Head & Internals Lifting Devices at CPSES1999-07-26026 July 1999 Provides Info Re Augmented Inservice Insp Plan,Which Requires Periodic Insp of Rv Head & Internals Lifting Devices at CPSES ML20210F3121999-07-26026 July 1999 Responds to GL 99-02, Laboratory Testing of Nuclear-Grade Activated Charcoal, ML20210D8231999-07-23023 July 1999 Forwards Safety Evaluation of Relief Requests Re Use of 1998 Edition of Subsections IWE & Iwl of ASME Code for Containment Insp ML20210D3211999-07-21021 July 1999 Provides List of Estimates of Licensing Actions,In Response to Administrative Ltr 99-02,dtd 990603 ML20210C2931999-07-21021 July 1999 Supplements 880323 Response to NRC Bulletin 88-02, Rapidly Propagating...Sg Tubes, Non-proprietary WCAP-15010 & Proprietary Rev 0 to WCAP-15009, CP Unit 1 Evaluation for Tube Vibration... Encl.Proprietary Rept Withheld ML20209H0111999-07-16016 July 1999 Forwards Relief Request C-4 to CPSES Unit 2 ISI Program for Approval ML20210C3331999-07-16016 July 1999 Forwards Exam Repts 50-445/99-301 & 50-446/99-301 on 990618- 24.Exam Included Evaluation of Six Applicants for Senior Operator Licenses ML20209H2551999-07-16016 July 1999 Forwards ISI Summary Rept for Fourth Refueling Outage of CPSES Unit 2 & Containment ISI Summary Rept for Fourth Refueling Outage of CPSES Unit 2,per ASME Boiler & Pressure Vessel Code,Section Xi,Paragraph IWA-6230 1999-09-07
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEARTXX-9924, Forwards Responses to Questions by NRC Re Application for Amends to Licenses NPF-87 & NPF-89,by Incorporating Changes Increasing RWST low-level Setpoint from Greater than But Equal to 40% to Greater than But Equal to 45% of Span1999-10-22022 October 1999 Forwards Responses to Questions by NRC Re Application for Amends to Licenses NPF-87 & NPF-89,by Incorporating Changes Increasing RWST low-level Setpoint from Greater than But Equal to 40% to Greater than But Equal to 45% of Span TXX-9923, Forwards Monthly Operating Repts for Sept 1999 for CPSES, Units 1 & 2,per Plant TS 5.6.4.No Failures of Challenges to PORVs of SV for Units Occurred1999-10-15015 October 1999 Forwards Monthly Operating Repts for Sept 1999 for CPSES, Units 1 & 2,per Plant TS 5.6.4.No Failures of Challenges to PORVs of SV for Units Occurred ML20217E7951999-10-12012 October 1999 Forwards COLR for Unit 1,Cycle 8,per TS 5.6.5 ML20216J5571999-10-0101 October 1999 Provides Final Response to GL 98-01,suppl 1, Y2K Readiness of Computer Sys at Npps TXX-9922, Forwards Revised COLR, for Cycle 5 for Unit 21999-10-0101 October 1999 Forwards Revised COLR, for Cycle 5 for Unit 2 ML20212G0721999-09-24024 September 1999 Forwards Rev 4 to Augmented Inservice Insp Plan for CPSES, Unit 1. Future Changes & Revs to Unit 1 Augmented Inservice Insp Plan Will Be Available on Site ML20212H0461999-09-24024 September 1999 Forwards Rev 6 to CPSES Glen Rose,Tx ASME Section XI ISI Program Plan for 1st Interval on 990820 TXX-9921, Suppls 981221 LAR 98-010 to Licenses NPF-87 & NPF-89, Clarfying Conditions of Use Re Analytical Methods Used to Determine Core Operating Limits,Per Telcon with NRC1999-09-10010 September 1999 Suppls 981221 LAR 98-010 to Licenses NPF-87 & NPF-89, Clarfying Conditions of Use Re Analytical Methods Used to Determine Core Operating Limits,Per Telcon with NRC ML20211L9871999-09-0303 September 1999 Forwards Rev 31 to Technical Requirements Manual. All Changes Applicable to Plants Have Been Reviewed Under Util 10CFR50.59 Process & Found Not to Include Any USQs TXX-9915, Responds to 990701 & 0825 RAI Telcons Re Spent Fuel Pool Temp,Per LAR 98-008,which Requested Increase in Spent Fuel Storage capacity.Marked-up Page 4-1 of CPSES Fuel Storage Licensing Rept, Encl1999-09-0303 September 1999 Responds to 990701 & 0825 RAI Telcons Re Spent Fuel Pool Temp,Per LAR 98-008,which Requested Increase in Spent Fuel Storage capacity.Marked-up Page 4-1 of CPSES Fuel Storage Licensing Rept, Encl ML20211K2231999-08-31031 August 1999 Forwards Txu Electric Comments of Rvid,Version 2 ML20211G1081999-08-26026 August 1999 Responds to NRR Staff RAI Re Util Mar 1999 Submittal for NRC Review & Approval of Changes to CPSES Emergency Classification Procedure ML20211G7301999-08-26026 August 1999 Forwards Revs 29 & 30 to CPSES Technical Requirements Manual (Trm). Attachments 1 & 2 Contain Description of Changes for Revs 29 & 30 Respectively ML20211G3441999-08-25025 August 1999 Forwards Response to NRC RAI on LAR 98-010 for Cpses,Units 1 & 2.Communication Contains No New Licensing Commitments Re Cpses,Units 1 & 2 ML20210U3981999-08-17017 August 1999 Forwards Monthly Operating Repts for July 1999 for CPSES, Units 1 & 2,per TS 6.9.1.5.No Failures or Challenges to PORVs or SVs for Plant Occurred ML20211C0991999-08-17017 August 1999 Forwards Rev 3 to ASME Section XI ISI Program Plan,Unit 2 - 1st Interval, Replacing Rev 2 in Entirety TXX-9919, Forwards Relief Request A-3,Rev 1 to Unit 1 ISI Program,Per Conversations Between NRC & Txu Electric on 9908021999-08-16016 August 1999 Forwards Relief Request A-3,Rev 1 to Unit 1 ISI Program,Per Conversations Between NRC & Txu Electric on 990802 ML20210R6561999-08-13013 August 1999 Forwards Response to NRR 990805 Telcon RAI Re License Amend Request 98-010,to Increase Power for Operation of CPSES Unit 2 to 3445 Mwth & Incorporating Addl Changes Into Units 1 & 2 TS ML20210S6411999-08-12012 August 1999 Informs That Wg Guldemond,License SOP-43780,is No Longer Performing Licensed Duties.Discontinuation of License Is Requested ML20210N1101999-08-0404 August 1999 Provides Supplemental Info to Util 990623 License Amend Request 99-005 Re Bypassing DG Trips.Info Replaces Info Contained in Subject Submittal in Attachment 2,Section II, Description of TS Change Request TXX-9918, Forwards CPSES 10CFR50.59 Evaluation Summary Rept 0008,for 970802-990201 & CPSES Commitment Matl Change Evaluation Rept 0003,for 970802-9906301999-08-0202 August 1999 Forwards CPSES 10CFR50.59 Evaluation Summary Rept 0008,for 970802-990201 & CPSES Commitment Matl Change Evaluation Rept 0003,for 970802-990630 ML20210J2301999-08-0202 August 1999 Forwards Amend 96 to CPSES Ufsar.Replacement of FSAR Figures with Plant Process Flow Diagrams Meets Intent & Requirements of NRC Reg Guide 1.70,Rev 2 ML20210J6071999-08-0202 August 1999 Forwards line-by-line Descriptions of Changes in Amend 96 to CPSES UFSAR Transmitted by Util Ltr TXX-99166,dtd 990802. Replacment of FSAR Figures with Plant Process Flow Diagrams Meets Intent & Requirements of NRC Reg Guide 1.70,rev 2 TXX-9916, Notifies NRC That CPSES Units 1 & 2,improved TS Implemented on 9907271999-08-0202 August 1999 Notifies NRC That CPSES Units 1 & 2,improved TS Implemented on 990727 ML20210G5861999-07-29029 July 1999 Forwards fitness-for-duty Program Performance Data for Six Month Period of Jan-June 1999 ML20210J0121999-07-27027 July 1999 Forwards Summary of Methodology for Determination of NDE Measurement Uncertainty,In Response to Recent Discussions with NRC Re LAR 98-006 Concerning Rev to SG Tube Plugging Criteria TXX-9917, Provides Info Re Augmented Inservice Insp Plan,Which Requires Periodic Insp of Rv Head & Internals Lifting Devices at CPSES1999-07-26026 July 1999 Provides Info Re Augmented Inservice Insp Plan,Which Requires Periodic Insp of Rv Head & Internals Lifting Devices at CPSES ML20210F3121999-07-26026 July 1999 Responds to GL 99-02, Laboratory Testing of Nuclear-Grade Activated Charcoal, ML20210C2931999-07-21021 July 1999 Supplements 880323 Response to NRC Bulletin 88-02, Rapidly Propagating...Sg Tubes, Non-proprietary WCAP-15010 & Proprietary Rev 0 to WCAP-15009, CP Unit 1 Evaluation for Tube Vibration... Encl.Proprietary Rept Withheld ML20210D3211999-07-21021 July 1999 Provides List of Estimates of Licensing Actions,In Response to Administrative Ltr 99-02,dtd 990603 ML20209H2551999-07-16016 July 1999 Forwards ISI Summary Rept for Fourth Refueling Outage of CPSES Unit 2 & Containment ISI Summary Rept for Fourth Refueling Outage of CPSES Unit 2,per ASME Boiler & Pressure Vessel Code,Section Xi,Paragraph IWA-6230 ML20209H0111999-07-16016 July 1999 Forwards Relief Request C-4 to CPSES Unit 2 ISI Program for Approval ML20209G0721999-07-13013 July 1999 Forwards Monthly Operating Repts for June 1999 for CPSES, Units 1 & 2,per TS 6.9.1.5.No Failures or Challenges to PORVs of SV Occurred During Reporting Period ML20209F0681999-07-0909 July 1999 Informs That Effective 990514,TU Electric Formally Changed Name to Txu Electric.Change All Refs of TU Electric to Txu Electric on Correspondence Distribution Lists ML20209E0421999-07-0909 July 1999 Forwards Response to NRC Request for Addl Info on LAR 98-010.Attachment 1 Is Affidavit for Info Supporting LAR 98-010 ML20209B6021999-06-30030 June 1999 Submits Second Response to NRC GL 98-01,Suppl 1, Y2K Readiness of Computer Sys at Npps. Readiness Disclosure for Reporting Status of Facility Y2K Readiness Encl ML20195J6981999-06-15015 June 1999 Provides Addl Info Related to Open Issue,Discussed in 990610 Conference Call with D Jaffe Re ISI Program Relief Request L-1 Submitted by Util on 980220 ML20196A4921999-06-15015 June 1999 Forwards Rev 30 to Physical Security Plan.Rev Withheld,Per 10CFR73.21 ML20195J0491999-06-14014 June 1999 Submits Response to RAI Re Implementation of 1.0 Volt Repair Criteria ML20195J0651999-06-14014 June 1999 Submits Response to RAI Re GL 95-07, Pressure Locking & Thermal Binding of Safety Related Power Operated Gate Valves 05000445/LER-1999-001, Forwards LER 99-001-00, Some Electrical Contacts for RCS Pressure Relief Valves Were Not Included in Surveillance Testing Procedures. New Licensing Commitments Identified in Attachment 11999-06-0808 June 1999 Forwards LER 99-001-00, Some Electrical Contacts for RCS Pressure Relief Valves Were Not Included in Surveillance Testing Procedures. New Licensing Commitments Identified in Attachment 1 ML20195F0091999-06-0808 June 1999 Forwards Response to RAI Re Units 1 & 2 ISI Program for Relief Requests E-1 & L-1.Communication Contains No New Licensing Basis Commitments Re Cpses,Units 1 & 2 ML20207E1921999-05-28028 May 1999 Submits Updated Request for NRC Staff to Review & Approve Certain Changes to CPSES Emergency Plan Submitted in 981015 & s Prior to Changes Being Implemented at CPSES ML20207E1711999-05-28028 May 1999 Supplements 990526 LAR 99-004 as TU Electric Believes Extingency Exists in That Proposed Amend Was Result of NOED Granted to Prevent Shudown of CPSES Unit 1 ML20207D9841999-05-26026 May 1999 Requests That NRC Exercise Enforcement Discretion to Allow Cpses,Unit 1 to Remain in Mode 1,power Operation,Without Having Performed Svc Test,Per SR 4.8.2.1d on Unit 1 Battery BT1ED2 ML20195B6351999-05-25025 May 1999 Submits Response to RAI Re GL 95-07, Pressure Locking & Thermal Binding of Safety Related Power Operated Gate Valves TXX-9912, Forwards Txu Electric (Formerly TU Electric) CPSES Emergency Preparedness Exercise Scenario Manual for 990721-22,Graded Exercise1999-05-21021 May 1999 Forwards Txu Electric (Formerly TU Electric) CPSES Emergency Preparedness Exercise Scenario Manual for 990721-22,Graded Exercise ML20206U1981999-05-20020 May 1999 Forwards Form 10K Annual Rept,Per 10CFR50.71(b). Communication Contains No New Licensing Basis Commitments Re Cpses,Units 1 & 2 ML20196L1931999-05-20020 May 1999 Forwards MOR for Apr 1999 for Cpses,Units 1 & 2.During Reporting Period There Have Been No Failures or Challenges to Power Operated Relief Valves or Safety Valves TXX-9911, Forwards non-proprietary & Proprietary Responses to RAI Re LAR 98-010 by Incorporating Attached Changes Into CPSES Unit 2 OL NPF-89 & CPSES Units 1,OL NPF-87 & 2 TS to Increase Licensed Power.W & Caldon Proprietary Responses Withheld1999-05-14014 May 1999 Forwards non-proprietary & Proprietary Responses to RAI Re LAR 98-010 by Incorporating Attached Changes Into CPSES Unit 2 OL NPF-89 & CPSES Units 1,OL NPF-87 & 2 TS to Increase Licensed Power.W & Caldon Proprietary Responses Withheld 1999-09-03
[Table view] Category:UTILITY TO NRC
MONTHYEARML20059K6141990-09-17017 September 1990 Submits Documentation of 900906 Telcon Re Addl Util Candidate for Licensed Operator Generic Fundamentals Exam Section ML20059G8761990-09-10010 September 1990 Forwards Rev 8 to Physical Security Plan.Rev Withheld (Ref 10CFR73.21) ML20059F8461990-09-0404 September 1990 Responds to NRC Re Violations Noted in Insp Repts 50-445/90-22 & 50-446/90-22 on 900606-0705.Corrective action:OPT-467A Changed to Provide Addl Prerequisite Info Re Solid State Protection Sys Switch Lineup During Testing ML20059E4981990-08-31031 August 1990 Forwards Revised Radial Peaking Factor Limit Rept for Cycle 1 Per Tech Specs Through Amend 1 & ML20059E4201990-08-30030 August 1990 Forwards Objectives & Guidelines for 1990 Emergency Preparedness Exercise Scheduled for 901113 ML20028G8281990-08-29029 August 1990 Forwards Comanche Peak Unit 1 Semiannual Radioactive Effluent Release Rept,900403-0630 & ODCM TXX-9030, Forwards Endorsements 40 & 4 to Nelia Policy NF-274 & Maelu Policy M-90,respectively & Endorsements 10,11,12,13,14 & 15 to Maelu Policy MF-1311990-08-27027 August 1990 Forwards Endorsements 40 & 4 to Nelia Policy NF-274 & Maelu Policy M-90,respectively & Endorsements 10,11,12,13,14 & 15 to Maelu Policy MF-131 ML20059F4381990-08-23023 August 1990 Forwards Public Version of Revised Emergency Plan & Corporate Emergency Response Procedures,Consisting of Rev 1 to EPP-313,Rev 7 to CERP-101,Rev 7 to CERP-102 & Revised Forms.W/Dh Grimsley 900906 Release Memo TXX-9029, Responds to NRC Re Violations Noted in Insp Repts 50-445/89-57 & 50-446/89-57.Corrective Actions:Storage Facilities for Instrumentation & Control Work Packages Improved to Provide Acceptable Protection for Documents1990-08-20020 August 1990 Responds to NRC Re Violations Noted in Insp Repts 50-445/89-57 & 50-446/89-57.Corrective Actions:Storage Facilities for Instrumentation & Control Work Packages Improved to Provide Acceptable Protection for Documents ML20058P0571990-08-13013 August 1990 Forwards, Comanche Peak Steam Electric Station Unit 1 Control Room Simulator 10CFR55 Certification Initial Rept ML20058N2311990-08-0909 August 1990 Forwards First Half 1990 fitness-for-duty Program Performance Data,Per 10CFR26.71(d).Point of Contact for Personnel,Random Testing Program Results & Confirmed Positive Tests Summary & Mgt Summary Included in Data ML20059A5831990-08-0404 August 1990 Responds to Info Request Made During 900802 Meeting Re Inadvertent Safety Injections on 900726 & 30 & Results of 100% Power Plateau Testing TXX-9024, Provides Status of Exam Activity & Revised Completion Schedule for Portion of Exam.Util Deferred Preoperational Testing of Facility Spent Fuel Pool Cooling & Cleanup Sys Until Prior to First Off Loading of Spent Fuel1990-08-0303 August 1990 Provides Status of Exam Activity & Revised Completion Schedule for Portion of Exam.Util Deferred Preoperational Testing of Facility Spent Fuel Pool Cooling & Cleanup Sys Until Prior to First Off Loading of Spent Fuel TXX-9022, Forwards Detailed Descriptions of Changes in Amend 79 to FSAR for Comanche Peak Steam Electric Station1990-07-31031 July 1990 Forwards Detailed Descriptions of Changes in Amend 79 to FSAR for Comanche Peak Steam Electric Station TXX-9027, Responds to NRC Re Violations Noted in Insp Repts 50-445/90-19 & 50-446/90-19.Corrective Action:Specific Activity within Tech Spec Limits.No Further Corrective Action Required1990-07-30030 July 1990 Responds to NRC Re Violations Noted in Insp Repts 50-445/90-19 & 50-446/90-19.Corrective Action:Specific Activity within Tech Spec Limits.No Further Corrective Action Required ML20055J1571990-07-27027 July 1990 Submits Info Re Replacement of Borg-Warner/Intl Pump,Inc Check Valve Swing Arms,Per .Swing Arms in ASME Code Class 2 Check Valves Will Be Replaced During First Refueling Outage ML20056A0461990-07-24024 July 1990 Requests Regional Waiver of Compliance for Containment Pressure Transmitter 1-PT-934 During Coming Outage TXX-9023, Responds to NRC Bulletin 90-001, Loss of Fill-Oil in Transmitters Mfg by Rosemount. No Subj Transmitters in Existence at Facility1990-07-18018 July 1990 Responds to NRC Bulletin 90-001, Loss of Fill-Oil in Transmitters Mfg by Rosemount. No Subj Transmitters in Existence at Facility ML20055G6351990-07-17017 July 1990 Submits Results of Remote Shutdown Panel Environ Survey ML20055F9391990-07-13013 July 1990 Advises That Operators Have Gained Significant Experience in Operating Plant Under Wide Range of Conditions & Have Demonstrated Necessary Proficiency to Safely Operate Unit ML20055F9371990-07-13013 July 1990 Submits Info Re Revised Acceptance Criteria for THERMO-LAG Fire Barrier,Per 900705 Telcon.On Exposure to Heat Flux at Surface of Barrier,Listed Mechanisms Activated.Fire Testing Demonstrates That Panels Qualified W/Variation in Thickness ML20044A7001990-06-26026 June 1990 Responds to Generic Ltr 90-04, Request for Info on Status of Licensee Implementation of Generic Safety Issues Resolved W/Imposition of Requirements or Corrective Actions. Util Will Implement for Unit 2 Activities Performed for Unit 1 ML20044A1411990-06-20020 June 1990 Forwards Endorsements 4 & 5 to Nelia Certificate N-90, Endorsements 5 & 6 to Maelu Certificate M-90 & Endorsements 34,35,36,37,38 & 39 to Nelia Policy NF-274 ML20043H7031990-06-18018 June 1990 Discusses Mod/Rework to Auxiliary Feedwater Sys Check Valves Mfg by Bw/Ip Intl,Inc.All But One Affected Check Valve modified.Motor-driven Auxiliary Feedwater Pump Discharge Valve Check Valve Body Replaced ML20043H2181990-06-15015 June 1990 Forwards Response to 900515 Request for Addl Info on Emergency Preparedness.Ongoing Emergency Preparedness Programs Address Concerns Raised by Citizens for Fair Util Regulation ML20043G3131990-06-15015 June 1990 Forwards Addl Info Re Pressurizer Surge Line Thermal Stratification & leak-before-break Evaluation & Nonproprietary Suppl 3 to WCAP-12247, Supplementary Assessment... & Proprietary Suppl 3 to WCAP-12248 ML20043C5671990-06-0101 June 1990 Discusses Identification of Slave Relays Tested Using Alternative Methodology,Per 900402 Commitment.Encl Tabulation Identifies Test Type,Applicable Procedures & Equipment & Impact of Improper Documentation ML20043E7131990-06-0101 June 1990 Responds to NRC 900517 Notice of Violation & Imposition of Civil Penalty in Amount of $25,000.Corrective Action:Qc Mgt Counseled Level III Inspector & QC Supervisor on Importance of Good Communications W/Receipt Inspectors ML20043C4501990-05-31031 May 1990 Advises That Util Revised FSAR Section 15.1.2 & Question/ Response 32.108,per 10CFR50.59 ML20043B5471990-05-25025 May 1990 Provides Status of Facility Design & Const Activities,Per Request.Detailed Design Work Will Resume in June 1990.Const Activities Expected to Increase Signficantly by Jan 1991 ML20043B5481990-05-23023 May 1990 Provides Clarification of 890710 Commitment Re Power Ascension Program.Cooldown Portion of Remote Shutdown Test Performed During Preoperational Testing,Per FSAR & Reg Guide 1.68.2 ML20043D1711990-05-21021 May 1990 Forwards Public Version of Revised Emergency Plan Procedures,Including Rev 8 to EPP-109,Rev 7 to EPP-112,Rev 4 to EPP-116 & Rev 6 to EPP-121.W/DH Grimsley 900604 Release Memo TXX-9018, Advises of Completion of Implementation of Requirements of Generic Ltr 89-13, Svc Water Sys Problems Affecting Safety- Related Equipment1990-05-21021 May 1990 Advises of Completion of Implementation of Requirements of Generic Ltr 89-13, Svc Water Sys Problems Affecting Safety- Related Equipment ML20043B0981990-05-15015 May 1990 Forwards Radial Peaking Factor Limit Rept for Cycle 1, Containing F(Xy) Limits for All Core Planes Containing Bank D Control Rods & All Unrodded Core Planes ML20042F2851990-05-0303 May 1990 Supplemental Response to Generic Ltr 90-01, Request for Voluntary Participation in NRC Regulatory Impact Survey. ML20042F3861990-05-0303 May 1990 Responds to NRC 900410 Ltr Re Violations Noted in Insp Repts 50-445/90-10 & 50-446/90-10 on 900206-07 & 0226-0302. Corrective Action:Memo Issued Emphasizing That Discrepancies Should Be Brought to Attention of Site Organizations ML20042F3021990-05-0202 May 1990 Responds to NRC 900402 Ltr Re Violations Noted in Insp Repts 50-445/89-23 & 50-446/89-23.Util Does Not Believe That Circumstances Described in 900402 Ltr Constitutes Violation of 10CFR50.9(a) ML20042F3051990-05-0202 May 1990 Provides Revised Response to Generic Ltr 88-17 Re Loss of DHR ML20042E4581990-04-12012 April 1990 Responds to Inconsistencies in Terminology & Labelling Identified During NRC 890118 & 19 Audit of Facility Dcrdr. Util Believes Control Room Inventory Requirement of Suppl 1 to NUREG-0737,satisfied ML20042E0701990-04-10010 April 1990 Discusses 900305 Meeting W/Nrc in Rockville,Md Re Offsite Power Availability for Automatic Switch Co Solenoids for MSIV in Event of Nonmechanistic Main Steam Line Crack in Superpipe Region ML20012F5011990-04-0303 April 1990 Forwards Corrections to 891016 Response to Emergency Diesel Generator Engine Requirements.Lengths of Two Pairs of Bolts Above Crankpin Shall Be Measured Ultrasonically Before Detensioning & Disassembly of Bolts ML20012F3221990-04-0202 April 1990 Discusses ESF Sys Slave Relay Alternate Test Methodology. Implementation Schedule for Design Mods to Relay Will Be Submitted by 900601 ML20042D8081990-03-29029 March 1990 Forwards Proposed Change to FSAR Section 13.4 Re Station Operations Review Committee.Similar Change Submitted in 900328 Ltr for Chapter 6 of Facility Tech Specs ML20012F0411990-03-28028 March 1990 Forwards marked-up Pages of Facility Draft Tech Specs & Bases (NUREG-1381) Provided W/Low Power OL ML20012E6051990-03-27027 March 1990 Forwards Endorsements 1-4 to Maelu Certificate M-90, Endorsements 1-9 to Maelu Policy MF-131,Endorsements 29-33 to Nelia Policy NF-274 & Endorsements 1-3 to Nelia Certificate N-90 ML20012E6531990-03-27027 March 1990 Provides Final Response to Reporting Requirement 2 of NRC Bulletin 88-008, Thermal Stresses in Piping Connected to RCS, for Unit.Nde Requirements of Action 2 Not Considered Applicable to Unit ML20012E1911990-03-23023 March 1990 Forwards Comanche Peak Steam Electric Station Unit 1 Cycle 1 Startup Physics Tests Control Rod Worth Predictions Utilizing TU Electric Control Rod Swap Methodology. ML20012E1581990-03-23023 March 1990 Clarifies 880624 Response to NRC Generic Ltr 88-05, Boric Acid Corrosion of Carbon Steel Reactor Pressure Boundary Components in PWR Plants. ML20012D0201990-03-19019 March 1990 Advises That Allegations Provided to NRC by Former Util Employee Unsubstantiated,Based on Investigation by Util Safeteam Organization ML20012E2181990-03-19019 March 1990 Responds to Generic Ltr 89-19 Re USI A-47, Safety Implication of Control Sys in LWR Nuclear Power Plants. Util Determined That Loss of safety-related Inverters 1 or 2 Would Involve Coincidental Opening of Main Feedwater Valves 1990-09-04
[Table view] |
Text
-. _ . . _ _ _ _ _
EE5"EEE
~
Log # TXX-89243
..__ File # 10014 r C 916 7UELECTRlC Ref. # 10CFR50.36 May 15, 1989 W. J. Cahm becutive Vice Prendent U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D. C. 20555 5UBJECT: LOMANCHE PEAK STEAM ELECTRIC STATION (CPSES)
DOCKET NO. 50-445 TECHNICAL SPECIFICATION CERTIFICATION REF: 1) TV Electric letter (TXX-89169) from W. J. Cahill, Jr. to the NRC dated April 14, 1989.
- 2) TV Electric letter (TXX-89225) from W. J. Cahill, Jr. to the NRC dated May 2, 1989.
Gentlemen:
Reference 1 provided TV Electric's affirmation and certification regarding the adequacy and accuracy of the CPSES Unit 1 Technical Specifications with the following exceptions:
Plant Systems (Auxiliary Feedwater flow requirements / Condensate Storage Tank volume),
Accident Monitoring Instrumentation, Area Temperature Monitoring Our review of the above Technical Specifications is complete. Attached are additional corrections to the Final Draft Technical Specifications transmitted by your letter, dated March 17, 1989, which are required for the above specifications to adequately and accurately reflect the CPSES as-bui't design.
These corrections are in addition to the corrections transmitted by reference 1.
This letter affirms and certifies that to the best of my knowledge, with the corrections noted, the above listed Technical Specifications accurately reflect the as-built plant (as it will be upon completion of design modifications in progress) and the FSAR.
8905310052 890515 ADOCK 05000445 ofl PDR g PDC i l 400 North Olive Street LB81 Dallas, Texas 75201 !
\,
TXX-89243 May 15, 1989 Page 2 of 3 Should you require additional information or desire further discussions on the CPSES Unit 1 Technical Specifications, do not hesitate to contact me.
Si nc.erely ,
/
/$
William J. Cahill, Jr.
'* /4 JDS/vid Attachment c - Mr. R. D. Martin, Region IV Resident inspectors, CPSES (3)
____________J
?. 3; .
~
'l
+: '
.H TXX-89243-
-May 15,' 1989~
Page 3 of.3-STATE-OF TEXAS )- ,
.S.~ r . \\) .SS.
COUNTY OF BAL4A&)
I, W. J. Cahill, Jr.,'being duly sworn, subscribe to and say that I im'the Executive Vice President, Nuclear of TV Electric Company; that I have full authority to execute this oath; that I have read the foregoing Technical S>ecifications Certification Letter logged TXX-89243 and know the contents t1ereof; and that.to the best of my knowledge, information, and belief.the statements made-in it are true.
I A
.J.Cahill,pr.'
SUBSCRIBED AND SWORN to before me, a Notary Public, in and for the County and State above named, this ID% day of A ,, , 1989.
~
M N6t a i Public bs X Pa W, l#. Ile u M hy Cwm'.s C,m e q'da S)
~
LAttachment.td TXX-89243
. .May;15,-1989: <
Page 1 of 11-
.J Page: Descript:on
~: .
3/4' 3-43 The Accident M aitori..g' Instrumentation.
Specification. ;- modified to reflect the addition - u of Reactor Ve el Water Level instruments and-changes to a' cady existi g required channels.
The ACTION 5.atements are organized in a tabular _
form >' ' .iuman factor concerns.
3/4 3-45 Table 3.3-6 has been corrected-to include all type.
. .A, category 1 accident monitoring instrumentation-plus the additional instrumentation' identified by the NRC in.the Final Draft Technical Specifications, except as corrected below.
Item #'s 2 & 3 --Increased the Minimum Channels Fiierable requirement to include insta' led Wide Range T (hot) and T (cold) Instrumentation. the 1/ loop requirement ensures single-failure criterion is met, per CPSES design. Redundancy for T(hot) and.T(cold) is met using diverse instrumentation-(i.e., Core Exit Temperature for T(hot) and Steam Generator Pressure for T(cold)). ,
The associated ACTION Statement considered the I availability cf the diverse instrumentation _in i establishing the time' required to restore '
OPERABILITY of the instrumentation. 1 Item #6 - This instrumentation has been modified i to meet the requirements of SER Section II.E.1.2, j Part 2, Clarification 2a, Page :'2-48. o
.i Item #7 - The Steam Generator Water Level (Narrow ;
Range) Required Number of Channels has been )
increased to encompass redundancy for this instrumentation.
Item #9 - The Required Number of Channels for Core liTt Temperature has been modified to clarify the requirement to ensure single-failure criterion is q satisfied for Required Number of Channels.
Item #10 - The Containmen' .trea Radiation (High Range) instrumentation hN 'Jeen modified-to j clarify that the ACTION S .tement only applies to d o the Minimum Channels Operable requirement as written in the Standard Technical Specifications. 'l l
' a
? Attach'mentLto> TXX-89243
- , . .May'15, 1989
. Page 2 of 11' !
I Item #11 - The Reactor Vessel Water level (RVWL) has been' modified to define OPERABILITY for the U number of sentors required i'n a probe for the
! system to.be 0PERABLE. The ACTION Statement has been changed to the industry accepted ACTION 4 Statement for RVWL Systems identical to the CPSES RVWL System. This ACTION Statement allows the determination for the feasibility of performing the repair and if determined not feasible informing the NRC per Specification 6.9.2, Special-Report, outlining the event and actions to be taken.
Old Item #16 - The Containment Isolation Valve -
Position Instrumentation is being deleted based on two reasons. The first reasua is that this-rec uirement is covered by. Specification 3/4.6.3 anc, the definition of OPERABILITY. For the valve to be OPERABLE it must satisfy the requirements of ASME Section IX, i.e., Specification 4.0.5, which incluries the requirement that position indication be tested periodically per Section XI. .The testing .
methodology for stroke testing these valves is to time these valves using the position indication.
This'will identify problems with the position .
. indication so that they can be rectified. .The second reason for deletion is based on.the fact 4 that at CPSES the Containment Isolation Valve Status is a type C, category 2. variable. This.
designation is based on the fact that it is the ,
preferred backup monitoring indication for Containment Boundary Integrity. .The CIV Status is not one of the KEY variables used to determine Containment Integrity as described in FSAR, Section 7.5.
3/4 7-4 The required head for the auxiliary feedwater B 3/4 7-2 pump has been correlated, by calculation, to a testable configuration due to test line' !
limitations. The resultant flow and differential I pressure are provided in the attached corrections.
3/4 7-5 ValidationoftheCondensateStorageTank(CST) l-B 3/4 '7-2 required volume has resulted in a revision to the; usable volume. The minimum required CST volume is that volume required to remove heat at hot standby-for four hours followed by a five hour cooldown to 3500 F as stated in the BASES. This usable volume is provided in the attached correction.
L l t-l t
L.. _- - _ _ _ _ , . , _ . . _ ' - _ o._ _ _ ___..2 __.-.-_._.______.__._______..____m_._____.___a _______-.______m__ - - . _ _ _ _ _ _ _ _ _ _ _ . _ _ _ _ _ . _ _ _
Attachment to TXX-8.9243 a e 3 of ten
.. INSTRUMENTATION ACCIDENT MONITORING INSTRUMENTATION LIMITING CONDITION FOR OPERATION 3.3.3.3 The accident monitoring instrumentation channels shown in Table 3.3-6 shall be OPERABLE.
APPLICABILITY: MODES 1, 2, and 3.
, ACTION: g, g gu (n Ta to l e., S . 3 - 4:,
. With the number of OP RABLE accident monitoring instrumentation channels less than the Required Number of Channels shown in Table 3.3-6, restore the inoperable channel (s) to DPERABLE status within 7 days, or be in at least HOT SHUTDOWN within the
- next 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />,
- b. With the number of OPERABLE accident monitoring instrumentation channels less than the Minimum Channels OPERABLE requirements of Table 3.3-6, restore the inoperable channel (s) to OPERABLL status within 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> or be in HOT SHUTDOWN within the following 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.
( c. With the number of OPERABLE channels for the containrr,st atmosphere-high range radiation monitor less than required by the .'nimum j Channels OPERABLE requirements, initiate an alternate met..od of monitoring the appropriate parameter, within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />, and either restore the inoperable channel to OPERABLE status witnin 7 days or prepare and submit a Special Report to the Commission, pursuant to Specification 6.9.2, within 14 days that provides actions taken, l cause of the inoperability, and the plans and schedule for restoring the channe status.
- b. E The provisions of Specification 3.0.4 are not applicable.
l l
~
l 1
COMANCHE PEAK - UNIT 1 3/4 3-43
- Attackment to VXX-e)M3 ~R e of INSTRUMENTATION o
l ('
gs z s ACCIDENT MONITORING INSTRUMENTATION gfG m 1 -_
/ SURVEILLANCE REQUIREMENTS \
4.3.3.3 Each accident monitoring instrumentation channel shall be demonstrated OPERABLE:
- a. At least once per 31 days by performance of a CHANNEL CHECK, and I k
- b. At least once per 18 months by performance of a CHANNEL CALIBRATION *
.i
( 4
\
- Containment Arc.? Radiation (High Range) CHANNEL CALIBRATION may consist of an electronic calit) ration of the channel, not including the detector, for range decades above 10 R/h and a one point calibration check of the detector below 10 R/h with an installed or portable gamma source.
N _
COMANCHE PEAL'. - UNIT 1 3/4 3-44
.___m_.-.-. __ - - . _ _ - - - _ - _ - . _ _ _ _ . - _ _ _ _ _ _
t o ao rt t a car n r "- e a
- e r e n en d n e ye a i g g u l SE q MLL UEB MNA p
p o
m a
e "ae e
m p
e m a
e I NR NAE I HP
/
/ [/
s
/
t s
Y/Hts /
s e
'l /
t s
MCO 1 1 1 1 1 1 1 1 2 1 1 1 1 1 r n t
r o
a r
c 4 r ao rta h n a
e n mr e
e ne d r e n
e a i g f u q
l N m nm m aa e O D S a a A
/A I EFL e e e e A e T
A ROE I N N
/N t s is t
e / t s
T U .N /s N *2 N
E M
QGA ENl R
l 2 X% 2 2 2 X X 2
/
2 2 2 C g 2 6
3 U
R T
S N
I g/s
. ) )
3 G e a y E
N I
g n
o n rr a
)
L R a a i o e B O R R l r A
T T
I e e ixW,' u s
N d d uy s O i i At e M W
(
W
( 'r '
i r
P T
N E
T 0
D L
a%i ea b
e g
n r
o l D l i O gl a ) t e I T C ni R e a v C T e aa - ) g r e C - - g R v ew ) s n e L A c ) - n A o e e a n kg e e r e R a
dt a1r e
r g
n l
p R
G e r e
a na u r u e inRN a a u h t UR t W21 R o g hr a c a t d c i a W e +
n :- p r
e a
r e
i W
l we a l C w-c ol i d
e o m
r l
I
(
l e
v t
S e
k n
s' r m e
p m
e e
e F v yF v er l e e
(
W h
e n o
l e
v L
e (
e T
a
+d n
(
T t
e l
t r
u s
l e < L t rL v ern e r l
e v
(
T e
i i
t a L e k n
a r
u s
e g
a Te r l
t e s e L t t e
L e r u
d a
r e
T s e
r o s e +aee elW+n tr l
u u n r a R e r r s
s O I P rwWS el ( a e t
a r a t
W a g a
P S t
t o
e r
t n
t n
t n
t er a aow e or t a
e p
e r l r
o e
n r
e i
n P a a a W et o Fe a t W m e
A e t i t a M o
3 4
2 t
n l
o o
l o
o l
o o
rFrF e
al e
t n
T t n
s s
e S
e L
m W g 9
8 e
m C C C z r e ae h.r e m
t e m
V t a
a e
g n
n
$.Gt i i i
- n r r r r a hG n x n r s t i l X i o o o a i E i o n S l o X
T T
N t a t c
t c
t c uh s i m w :x m s ad a t a
e a t c
e n
e u
o c
E n o
a a e
a e
e x ee oe n r t
n o
a d
n i f b o
t31 M
U C R e
R R r ut e At C o
C o
C R e o M
a R
e S
u R P A S. F .S C t9 .
n1f 81 T
S . . . .
.a b e
m ,o -
N I
1 2 3 4 5 . lok 7 8 9 0 1
1 1
2 1
3 1
4 1
5 1
h55 c1 a e t yg t aa n Mxm u9n ' E { lu i AMP
-q
' Attachment to TXX-89243 L May 15, 1989
- .Page 6 of 11' ;
I l
l Table 3.3-6 (continued) l ACTTQ'N Statements .
l 1
l
- ACTION 29 - a. With the number of OPERABLE channels less than the l- Required Number of Channels, restore the inoperable channel (s) to OPERABLE status within 7 days, or be in at least HOT SHUTDOWN within the next 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.
- b. With the number of OPERABLE channels less than the Minimum Channels OPERABLE requirements, restore the inoperable channel (s) to OPERABLE status within 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br />, or be in at least HOT SHUTDOWN ,
within the next 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />. !
ACTION 30 - With the number of OPERABLE channels less than the Minimum '
Channels OPERABLE requirement, ooerations may proceed provided one of the following conditions is satisfied:
- a. For Th ot, the Core Exit Temperature !
(Thermocouple) Required Number of Channels requirement is met and the inoperable channel is restored to OPERABLE status within 90 days, or be in at least HOT SHUTDOWN within the next 12 aours, or
- b. For Tcold, the Main Steam Line Pressure (Steam Generator Pressure) Required Number of Channels requirement (for the steam generator associated with the loop of concern) is met and the inoperable channel is restored to OPERABLE status within 90 days, or be in at least HOT SHUIDOWN within the next 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />, or
- c. The inoperable channel is restored to OPERABLE 3tatus within 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br />, or be in at least HOT S'IUTDOWN within the next 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.
ACTION 31 - With the number of OPERABLE channels less than the Minimum Channels OPERABLE requirement, initiate an alternate method of monitoring the appropriate )arameter within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />, and either restore the inoperaale channel to OPERABLE status within 7 days or prepare and submit a Special Report, pursuant to Specification 6.9.2, within 14 days that provides actions taken, cause of the inoperability, and the plans and schedule for restoring the channels to OPERABLE status.
Y _ _ - - _ . _ - _ _ _
JAttachment to TXX-89243 <
l 1
May 15e 19891 g
.Page' 7 of 11-1 Table 3.3-6 (continued)
ACTION Statements l l
1 l
ACTION 32 - a- With the number of OPERABLE channels one less than l the Required Number of Channels requirement, i either restore the system to OPERABLE status within 7 days if repairs are feasible without shutting down or prepare and submit a Special Report to the Commission pursuant to Specification 6.9.2 within 30 days following the event outlinirg the action taken, and the cause of the inoperability and the plans and schedule for restoring the system to OPERABLE status.
.b With the number of OPERABLE Channels less than the Minimum Channels OPERABLE requirement, either rastore the inoperable channel (s) to OPERABLE status within 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br />, if the repairs are teasible without shutting down, or:
- 1. Initiate an alternate method of monitoring the reactor vessel inventory; ;
'1
- 2. Prepare and submit a Special Report to the Commission pursuant to Specification 6.9.2 within 30 days following the event outlining the action taken, the cause of the inoperability and the plans and schedule for restoring the system to OPERABLE status; and
- 3. Restore the system to OPERABLE status at the next scheduled refueling, i
1 l
i l
( ._
LAttachmentto.TXX-8'9243 g May 15,'1989 Page 8_of 11 k PLANT SYSTEMS SURVEILLANCE REQUIREMENTS (Continued) _m
" ^
TS I442- 89-019
- 2) Verihingthatthesteamturbine-dr e pump develo pressure of greater than or equal t psid at a ow of greater than or equal to 860 gpm whe hed ec e da y steam supply pressure is greater than 532 psig. The provisions of i
- f. Specification 4.0.4 are not applicable for entry into MODE 3;
- 3) Verifying that each non-automatic valve in the flow path that is not locked, sealed, or otherwise secured in position is in its correct position; and
- 4) Verifying that each automatic valve in the flow path is in the fully open position whenever the Auxiliary Feedwater System is i in standby fo'r auxiliary feedwater automatic i.nitiation or when '
above 10% RATED THERMAL POWER. . .
- b. At least once per 18 months during shutdown by:
- 1) Verifying that each automatic valve in the fl9w path actuates to its correct position upon receipt of an Auxiliary Feedwater Actuation test signal, and
- 2) Verifying that each auxiliary .feedwater pump starts as designed automatically upon receipt of an Auxiliary Feedwater Actuation test sirjnal. The provisions of Specification 4.0.4 are not applicable to the turbine driven auxiliary feedwater pump for entry into Mode 3.
l k
i 1
9 COMANCHE PEAK - UNIT 1 3/4 7-4
a men o TXX-89243
> Page 9 of 11 l l
- 1 PLANT SYSTEMS '
CONDENSATE STORAGE TANK U l
LIMITING CONDITION.iOR OPERATION 1
T5 j 3.7.1.3 The condensate tofa yrtank_. ST) shall be OPERABLE with an indicated 1 water level of at leas M-0?i APPLICABILITY: MODES 1, , .
ACTION:
With the CST inoparable, within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> either:
- a. Restore the CST to OPERABLE status or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in HOT SHUTDOWN within i the following 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />, or b.
Demonstrate the OPERABILITY of the Station Service Water (SSW) system as a backup supply to the auxiliary feedwater pumps and restore the CST to OPERABLE status within 7 days or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in HOT SHUTDOWN within the following 6' hours.
SURVEILLANCE RE0UIREMENTS 4.7.1.3.1 The CST shall be demonstrated OPERABLE at least once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> by verifying the indicated water volume is within its limits when the tank is the supply source for the auxiliary feedwater pumps.
4.7.1.3.2 The SSW system shall be demonstrated DPERABLE at least once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> whenever the SSW system is being used as an alternate supply source to the auxiliary feedwater pumps by verifying the SSW system operable and each motor operated valve between the SSW system and each operable auxiliary feed-water pump is operable.
s COMANCHE PEAK - UNIT 1 3/4 7-5
~ ~
" ~ ~~~
"~- "
NaTi5,~ 989 Page 10 of 11 h PLANT SYSTEMS BASES 3/4.7.1.2 AUXILIARY FEEDWATER SYSTEM The OPERABILITY of the Auxiliary Feedwater System ensures that the Reactor Coolant System can be cooled down to less than 350'F from normal operating conditions in the event of a total loss-of-offsite power.
Each electric motor-driven auxiliary feedwater pump is capable of deliver-ing a total feedwater flow of 430 gpm to two steam generators at a presture of 1221 psig to the entrance of the steam generators. The steam-driven auxiliary feedwater pump is . capable of delivering a total feedwater flow of 860 gpm to four steam generators at a pressure of 1221 psig to the entrance of the steam generators. This capacity is sufficient to ensure that adequate feedwater flow is available to remove decay heat and reduce the Reactor Coolant System temp-erature to less than 350 F when the Residual Heat Removal System may be placed s into operation. -
The Auxiliary Feedwater System is capable of delivering a total feedwater flow of 430 gpm at a pressure of 1221 psig to the entrance of at least two steam generators while allowing for: (1) any possible spillage through the design worst case break of the main feedwater line; (2) the design worst case single failure; and (3) recirculation flow. This. capacity is sufficient to ensure that adequate feedwater flow is available to remove decay heat and - ,T5 reduce Reactor Coolant System temperature to less than 350 F oint g_ g ,
the Residual Heat Removal System may be placed in operation. INSN The auxiliary feedwater flow path is a passive flow path based on the fact that valva actuation is not required in order to supply flow to the steam 1 generators. The automatic valves tested in the flow path are the Feedwater
[ Split Flow Bypass which are required to be shut upon initiation of the Auxiliary Feedwater System to meet the requirements of the accident aralysis.
Both steam supplies for the turbine-driven auxiliary feedwater pump must be OPERABLE in order to meet the design bases for the complete range of accident analyses. The allowed outage time for one inoperable steam source in consistent with the lower probability of the worst case steam or feedwater line break accident.
3/4.7.1.3 CONDENSATE STORAGE TANK The OPERABILITY of the condensate storage tank with the minimum water volume ensures that sufficient water is available to maintain the RCS at HOT STANDBY conditions for 18 hours2.083333e-4 days <br />0.005 hours <br />2.97619e-5 weeks <br />6.849e-6 months <br /> with steam discharge to the atmosphere concurrent with total loss-of-offsite power or 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> at HOT STANDBY followed by a cooldown to.350 F at a rate of 50 F/HR for 5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />. The contained water volume limit includes an allowance for water not usable because of tank disc rge line loca-tion or other physical characteristics. The required indicAt includes U M ere nt meas esenta n ertainty, an unusable volume o it,-WJ ga Yons and a 89 - O d L
a ble require 4 v lume "4 o15ac~co271,3 5 g 11ons. apooJ
- UR_G-0737,NI. tem _M. . 1 requires a backup source to the4STAhich is the tBE5StationServiceWaterSystem,whichcanbemanuallyaligned,ifrequired in lieu of CST minimum water volume.
COMANCHE PEAK - UNIT 1 B 3/4 7-2 i
-Attachment to TXX-89243 May 15, 1989
..Page '11 of 11.
a .
i l
Insert p. B 3/4 7-2 i The test flow for the steam-driven auxiliary feedwater pump at a pressure of greater than or equal to 1442 psid ensures this capability.
I 3
)
1
.- _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ - - _ _ _