TXX-9024, Provides Status of Exam Activity & Revised Completion Schedule for Portion of Exam.Util Deferred Preoperational Testing of Facility Spent Fuel Pool Cooling & Cleanup Sys Until Prior to First Off Loading of Spent Fuel

From kanterella
Jump to navigation Jump to search
Provides Status of Exam Activity & Revised Completion Schedule for Portion of Exam.Util Deferred Preoperational Testing of Facility Spent Fuel Pool Cooling & Cleanup Sys Until Prior to First Off Loading of Spent Fuel
ML20058L069
Person / Time
Site: Comanche Peak Luminant icon.png
Issue date: 08/03/1990
From: William Cahill
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
TXX-90248, NUDOCS 9008060156
Download: ML20058L069 (2)


Text

o * ,

.o 1

EEEEFEEEE '

EEEEII3 Log # TXX 90248

. .:- File # 10010 1 905.2 nlELECTRIC i l

l ylh"jg{*y"lf; August 3, 1990  ;

l U. 5. Nuclear Regulatory Commission j Attn Document Control Desk Washington, D.C. 20555 '

i SUBJECT - COMANCHE PEAK STEAM ELECTRIC STATION (CPSES)

DOCKET NO. 50 445 ASME SECTION XI VT 2 EXAMINATIONS DURING CPSES UNIT 1 HEATUP -

t REF: 1) TV Electric Letter TXX 88709 dated September 28, 1988, from l W. G. Counsil to the NRC

2) TU Electric Letter TXX 89007 dated January 11, 1989, from William J. Cahill to the NRC
3) TU Electric Letter TXX 89824 dated December 6,1989, from William J. Cahill to the NRC i
4) TV Electric Letter TXX 90112 dated March 16, 1990, from William J. Cahill to the NRC ,

Gentlemen: ,

References 1 and.2 discussed the performance of additional examinations of CPSES Unit 1 ASHE Code C14ss piping. These examinations included ASME Code i Class 1, 2 or 3 piping greatcr then 1" nominal pipe diameter. Examinations were to be conducted during system functional testing /heatup (or the additional ASME Section XI system Hydrostatic Test conducted prior to fuel load). utilizing VT 2 visual examinations in accordance with the provisions of ASME Section XI (1983 Edition through Summer 1983 Addenda). The purpose of this letter is to provide the status of the examination activity and a revised ,

completion schedule for a portion of these examinations.

As previously discussed in the correspondence of References 3 and 4, TU Electric has deferred Preoperational Testing of the Unit 1 Spent Fuel Pool -

Cooling and Cleanup System (Spent Fuel) until prior to the first off loading l; of spent fuel. VT 2 visual examinations of the Spent Fuel System will be y _ completed concurrently with this deferred testing, c

400 North Olive Street LB. 81 Dallas. Texas 75201

.D O M

co i -

l a

TXX 9024B August 3, 1990 Page 2 of 2 ,

i For the remaining 19 systems subject. to VT 2 examinations, the examinations have been completed for 18 systems.

The single remaining system subject to the additional examination is Containment Spray. Full flow testing of the Containment Spray System has been performed and the system thoroughly examined for leakage by performance and test personnel. As a result the full functional capability of this system has been established. However, visual examinations for leakage meeting the specific requirements of a VT-2 examination were not met at that time.

Completion of the remaining additional examinations for Containment Spray will be accomplished during the next full flow test required by the CPSES Unit 1 Technical Specifications.

Performance of these remaining additional examinations will complete all additional examinations described by the referenced documents.

Sincerely.

NI n1 '[ [).

William J. Cahill, Jr.

Bys &k "

Roger'D. Walker Manager, Nuclear Licensing JAA/bm c Mr. R. D. Martin, Region IV Resident Inspectors, CPSES (3)