TXX-9924, Forwards Responses to Questions by NRC Re Application for Amends to Licenses NPF-87 & NPF-89,by Incorporating Changes Increasing RWST low-level Setpoint from Greater than But Equal to 40% to Greater than But Equal to 45% of Span | 22 October 1999 | Forwards Responses to Questions by NRC Re Application for Amends to Licenses NPF-87 & NPF-89,by Incorporating Changes Increasing RWST low-level Setpoint from Greater than But Equal to 40% to Greater than But Equal to 45% of Span | Stroke time |
TXX-9923, Forwards Monthly Operating Repts for Sept 1999 for CPSES, Units 1 & 2,per Plant TS 5.6.4.No Failures of Challenges to PORVs of SV for Units Occurred | 15 October 1999 | Forwards Monthly Operating Repts for Sept 1999 for CPSES, Units 1 & 2,per Plant TS 5.6.4.No Failures of Challenges to PORVs of SV for Units Occurred | |
ML20217E795 | 12 October 1999 | Forwards COLR for Unit 1,Cycle 8,per TS 5.6.5 | |
ML20216J557 | 1 October 1999 | Provides Final Response to GL 98-01,suppl 1, Y2K Readiness of Computer Sys at Npps | |
TXX-9922, Forwards Revised COLR, for Cycle 5 for Unit 2 | 1 October 1999 | Forwards Revised COLR, for Cycle 5 for Unit 2 | |
ML20212G072 | 24 September 1999 | Forwards Rev 4 to Augmented Inservice Insp Plan for CPSES, Unit 1. Future Changes & Revs to Unit 1 Augmented Inservice Insp Plan Will Be Available on Site | |
ML20212H046 | 24 September 1999 | Forwards Rev 6 to CPSES Glen Rose,Tx ASME Section XI ISI Program Plan for 1st Interval on 990820 | |
TXX-9921, Suppls 981221 LAR 98-010 to Licenses NPF-87 & NPF-89, Clarfying Conditions of Use Re Analytical Methods Used to Determine Core Operating Limits,Per Telcon with NRC | 10 September 1999 | Suppls 981221 LAR 98-010 to Licenses NPF-87 & NPF-89, Clarfying Conditions of Use Re Analytical Methods Used to Determine Core Operating Limits,Per Telcon with NRC | |
ML20211L987 | 3 September 1999 | Forwards Rev 31 to Technical Requirements Manual. All Changes Applicable to Plants Have Been Reviewed Under Util 10CFR50.59 Process & Found Not to Include Any USQs | |
TXX-9915, Responds to 990701 & 0825 RAI Telcons Re Spent Fuel Pool Temp,Per LAR 98-008,which Requested Increase in Spent Fuel Storage capacity.Marked-up Page 4-1 of CPSES Fuel Storage Licensing Rept, Encl | 3 September 1999 | Responds to 990701 & 0825 RAI Telcons Re Spent Fuel Pool Temp,Per LAR 98-008,which Requested Increase in Spent Fuel Storage capacity.Marked-up Page 4-1 of CPSES Fuel Storage Licensing Rept, Encl | |
ML20211K223 | 31 August 1999 | Forwards Txu Electric Comments of Rvid,Version 2 | |
ML20211G108 | 26 August 1999 | Responds to NRR Staff RAI Re Util Mar 1999 Submittal for NRC Review & Approval of Changes to CPSES Emergency Classification Procedure | |
ML20211G730 | 26 August 1999 | Forwards Revs 29 & 30 to CPSES Technical Requirements Manual (Trm). Attachments 1 & 2 Contain Description of Changes for Revs 29 & 30 Respectively | Safe Shutdown Shutdown Margin Ultimate heat sink |
ML20211G344 | 25 August 1999 | Forwards Response to NRC RAI on LAR 98-010 for Cpses,Units 1 & 2.Communication Contains No New Licensing Commitments Re Cpses,Units 1 & 2 | |
ML20210U398 | 17 August 1999 | Forwards Monthly Operating Repts for July 1999 for CPSES, Units 1 & 2,per TS 6.9.1.5.No Failures or Challenges to PORVs or SVs for Plant Occurred | |
ML20211C099 | 17 August 1999 | Forwards Rev 3 to ASME Section XI ISI Program Plan,Unit 2 - 1st Interval, Replacing Rev 2 in Entirety | |
TXX-9919, Forwards Relief Request A-3,Rev 1 to Unit 1 ISI Program,Per Conversations Between NRC & Txu Electric on 990802 | 16 August 1999 | Forwards Relief Request A-3,Rev 1 to Unit 1 ISI Program,Per Conversations Between NRC & Txu Electric on 990802 | |
ML20210R656 | 13 August 1999 | Forwards Response to NRR 990805 Telcon RAI Re License Amend Request 98-010,to Increase Power for Operation of CPSES Unit 2 to 3445 Mwth & Incorporating Addl Changes Into Units 1 & 2 TS | Shutdown Margin |
ML20210S641 | 12 August 1999 | Informs That Wg Guldemond,License SOP-43780,is No Longer Performing Licensed Duties.Discontinuation of License Is Requested | |
ML20210N110 | 4 August 1999 | Provides Supplemental Info to Util 990623 License Amend Request 99-005 Re Bypassing DG Trips.Info Replaces Info Contained in Subject Submittal in Attachment 2,Section II, Description of TS Change Request | |
TXX-9918, Forwards CPSES 10CFR50.59 Evaluation Summary Rept 0008,for 970802-990201 & CPSES Commitment Matl Change Evaluation Rept 0003,for 970802-990630 | 2 August 1999 | Forwards CPSES 10CFR50.59 Evaluation Summary Rept 0008,for 970802-990201 & CPSES Commitment Matl Change Evaluation Rept 0003,for 970802-990630 | |
ML20210J230 | 2 August 1999 | Forwards Amend 96 to CPSES Ufsar.Replacement of FSAR Figures with Plant Process Flow Diagrams Meets Intent & Requirements of NRC Reg Guide 1.70,Rev 2 | |
ML20210J607 | 2 August 1999 | Forwards line-by-line Descriptions of Changes in Amend 96 to CPSES UFSAR Transmitted by Util Ltr TXX-99166,dtd 990802. Replacment of FSAR Figures with Plant Process Flow Diagrams Meets Intent & Requirements of NRC Reg Guide 1.70,rev 2 | Safe Shutdown Boric Acid Loop seal Tornado Missile Hydrostatic Earthquake Pressure Boundary Leakage |
TXX-9916, Notifies NRC That CPSES Units 1 & 2,improved TS Implemented on 990727 | 2 August 1999 | Notifies NRC That CPSES Units 1 & 2,improved TS Implemented on 990727 | |
ML20210G586 | 29 July 1999 | Forwards fitness-for-duty Program Performance Data for Six Month Period of Jan-June 1999 | Fitness for Duty |
ML20210J012 | 27 July 1999 | Forwards Summary of Methodology for Determination of NDE Measurement Uncertainty,In Response to Recent Discussions with NRC Re LAR 98-006 Concerning Rev to SG Tube Plugging Criteria | |
TXX-9917, Provides Info Re Augmented Inservice Insp Plan,Which Requires Periodic Insp of Rv Head & Internals Lifting Devices at CPSES | 26 July 1999 | Provides Info Re Augmented Inservice Insp Plan,Which Requires Periodic Insp of Rv Head & Internals Lifting Devices at CPSES | Safe Shutdown Nondestructive Examination Control of Heavy Loads Liquid penetrant |
ML20210F312 | 26 July 1999 | Responds to GL 99-02, Laboratory Testing of Nuclear-Grade Activated Charcoal, | |
ML20210C293 | 21 July 1999 | Supplements 880323 Response to NRC Bulletin 88-02, Rapidly Propagating...Sg Tubes, Non-proprietary WCAP-15010 & Proprietary Rev 0 to WCAP-15009, CP Unit 1 Evaluation for Tube Vibration... Encl.Proprietary Rept Withheld | |
ML20210D321 | 21 July 1999 | Provides List of Estimates of Licensing Actions,In Response to Administrative Ltr 99-02,dtd 990603 | |
ML20209H255 | 16 July 1999 | Forwards ISI Summary Rept for Fourth Refueling Outage of CPSES Unit 2 & Containment ISI Summary Rept for Fourth Refueling Outage of CPSES Unit 2,per ASME Boiler & Pressure Vessel Code,Section Xi,Paragraph IWA-6230 | |
ML20209H011 | 16 July 1999 | Forwards Relief Request C-4 to CPSES Unit 2 ISI Program for Approval | |
ML20209G072 | 13 July 1999 | Forwards Monthly Operating Repts for June 1999 for CPSES, Units 1 & 2,per TS 6.9.1.5.No Failures or Challenges to PORVs of SV Occurred During Reporting Period | |
ML20209F068 | 9 July 1999 | Informs That Effective 990514,TU Electric Formally Changed Name to Txu Electric.Change All Refs of TU Electric to Txu Electric on Correspondence Distribution Lists | |
ML20209E042 | 9 July 1999 | Forwards Response to NRC Request for Addl Info on LAR 98-010.Attachment 1 Is Affidavit for Info Supporting LAR 98-010 | Flow Induced Vibration |
ML20209B602 | 30 June 1999 | Submits Second Response to NRC GL 98-01,Suppl 1, Y2K Readiness of Computer Sys at Npps. Readiness Disclosure for Reporting Status of Facility Y2K Readiness Encl | |
ML20195J698 | 15 June 1999 | Provides Addl Info Related to Open Issue,Discussed in 990610 Conference Call with D Jaffe Re ISI Program Relief Request L-1 Submitted by Util on 980220 | |
ML20196A492 | 15 June 1999 | Forwards Rev 30 to Physical Security Plan.Rev Withheld,Per 10CFR73.21 | |
ML20195J049 | 14 June 1999 | Submits Response to RAI Re Implementation of 1.0 Volt Repair Criteria | Grab sample |
ML20195J065 | 14 June 1999 | Submits Response to RAI Re GL 95-07, Pressure Locking & Thermal Binding of Safety Related Power Operated Gate Valves | |
05000445/LER-1999-001, Forwards LER 99-001-00, Some Electrical Contacts for RCS Pressure Relief Valves Were Not Included in Surveillance Testing Procedures. New Licensing Commitments Identified in Attachment 1 | 8 June 1999 | Forwards LER 99-001-00, Some Electrical Contacts for RCS Pressure Relief Valves Were Not Included in Surveillance Testing Procedures. New Licensing Commitments Identified in Attachment 1 | |
ML20195F009 | 8 June 1999 | Forwards Response to RAI Re Units 1 & 2 ISI Program for Relief Requests E-1 & L-1.Communication Contains No New Licensing Basis Commitments Re Cpses,Units 1 & 2 | Coatings |
ML20207E192 | 28 May 1999 | Submits Updated Request for NRC Staff to Review & Approve Certain Changes to CPSES Emergency Plan Submitted in 981015 & s Prior to Changes Being Implemented at CPSES | |
ML20207E171 | 28 May 1999 | Supplements 990526 LAR 99-004 as TU Electric Believes Extingency Exists in That Proposed Amend Was Result of NOED Granted to Prevent Shudown of CPSES Unit 1 | Enforcement Discretion |
ML20207D984 | 26 May 1999 | Requests That NRC Exercise Enforcement Discretion to Allow Cpses,Unit 1 to Remain in Mode 1,power Operation,Without Having Performed Svc Test,Per SR 4.8.2.1d on Unit 1 Battery BT1ED2 | Enforcement Discretion Probabilistic Risk Assessment Missed surveillance |
ML20195B635 | 25 May 1999 | Submits Response to RAI Re GL 95-07, Pressure Locking & Thermal Binding of Safety Related Power Operated Gate Valves | |
TXX-9912, Forwards Txu Electric (Formerly TU Electric) CPSES Emergency Preparedness Exercise Scenario Manual for 990721-22,Graded Exercise | 21 May 1999 | Forwards Txu Electric (Formerly TU Electric) CPSES Emergency Preparedness Exercise Scenario Manual for 990721-22,Graded Exercise | |
ML20206U198 | 20 May 1999 | Forwards Form 10K Annual Rept,Per 10CFR50.71(b). Communication Contains No New Licensing Basis Commitments Re Cpses,Units 1 & 2 | Incorporated by reference |
ML20196L193 | 20 May 1999 | Forwards MOR for Apr 1999 for Cpses,Units 1 & 2.During Reporting Period There Have Been No Failures or Challenges to Power Operated Relief Valves or Safety Valves | |
TXX-9911, Forwards non-proprietary & Proprietary Responses to RAI Re LAR 98-010 by Incorporating Attached Changes Into CPSES Unit 2 OL NPF-89 & CPSES Units 1,OL NPF-87 & 2 TS to Increase Licensed Power.W & Caldon Proprietary Responses Withheld | 14 May 1999 | Forwards non-proprietary & Proprietary Responses to RAI Re LAR 98-010 by Incorporating Attached Changes Into CPSES Unit 2 OL NPF-89 & CPSES Units 1,OL NPF-87 & 2 TS to Increase Licensed Power.W & Caldon Proprietary Responses Withheld | Safe Shutdown Ultimate heat sink Flow Induced Vibration |