Discusses Closeout of GL 97-06, Degradation of Steam Generator Internals. Purpose of GL Was to Obtain Info That Would Enable NRC to Verify That Condition of Licensee SG Internals Comply with Current Licensing Bases
ML20212L289
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 10/01/1999
From: Jaffe D
NRC (Affiliation Not Assigned)
To: Terry C
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
References
GL-97-06, TAC-MA0906, TAC-MA0907, NUDOCS 9910080003
Download: ML20212L289 (3)


Text

.. . .

Mr. C. Lancs Terry - Octobsr 1, 1999 I TXU El:ctric - l Senior Vics Prasid:nt

& Princioal Nuclear Officer -

~

l 1

Attn: Regulatory Affairs Department P. O. Box 1002 Glen Rose, TX 76043

SUBJECT:

COMANCHE PEAK STEAM ELECTRIC STATION (CPSES) UNIT NOS.1

~ AND 2 - CLOSEOUT OF GENERIC LETTER 97-06, " DEGRADATION OF STEAM GENERATOR WTERNALS"(TAC NOS. MA0906 AND MA0907) l

Dear Mr. Terry:

l On December 30,1997, the NRC staff issued Generic Letter (GL) 97-06, " Degradation of Steam Generator internals." The purpose of GL 97-06 was to obtain information that would enable the NRC staff to verify that the condition of licensees' steam generator internals comply  ;

with, and conform to, the current licensing bases for their respective facilities. By letter dated i March 30,1998, you responded to GL 97-06. , l The NRC staff's review of your response to the GL 97-06 is complete and did not identify any

' new concerns with the condition of the steam generator internals. In addition, the NRC staff did  !

not identify any concerns with the inspection practices employed at your facility to detect degradation of steam generator internals. The NRC staff, therefore, concludes that your '

response to GL 97-06 provides reasonable assurance that the condition of your steam generator internals is in compliance with the current licensing basis for CPSES, Units 1 and 2.

The detailed technical basis that supports the staff's determination for all facilities will be published in a NUREG report. The expected publication date is December 1999. This ,

completes the NRC staff's effort on TAC Nos. MA0906 and MA0907. l Sincerely,  !

ORIGINAL SIGNED BY: Thomas Alexion for David H. Jaffe, Senior Project Manager, Section 1 l Project Directorate IV & Decommissioning Division of Licensing Project Management i Office of Nuclear Reactor Regulation Docket Nos. 50-445 and 50-446 cc: See next page DISTRIBUTION SRichards (cover ltr only) 0 y- , O l S eelset h OGC #

PUBLIC ACRS. l PDIV-1 Reading G.Wunder  !

K.Brockman,RIV Rscholl(SE only) . [O g To receive a copy of Inis document, indicate c in the box OFFICE PDIV5/PMJ ,

C PDIV-1/LA , N PDI-1/PM: PDIV-1/SC C NAME D.Jaffe :kg L. Berry [ G M er R.Gramm DATE [O/ / /9N /0 / o8 /99 //#/// /99 \o / l /99  !

DOCUMENT' NAM %: G:\PDIV-1\ComanchePeak\gl9706close.WPD i f OFFICIAL RECORD COPY l 9910080003 991001 PDR ADOCK 05000445 P PDR U'_  :

I

S..

k-f%,,4

[* UNITED STATES s* j NUCLEAR REGULATORY COMMISSION WASHINGTON. D.C. 2055!R001

%, . . . . . ,o 1 October 1, 1999 Mr. C. Lance Terry TXU Electric Senior Vice President

& Principal Nuclear Officer Attn: Regulatory Affairs Department P. O. Box 1002 Glen Rose, TX 76043

SUBJECT:

COMANCHE PEAK STEAM ELECTRIC STATION (CPSES) UNIT NOS.1 AND 2 - CLOSEOUT OF GENERIC LETTER 97-06, " DEGRADATION OF STEAM GENERATOR INTERNALS" (TAC NOS. MA0906 AND MA0907)

Dear Mr. Terry:

On December 30,1997, the NRC staff issued Generic Letter (GL) 97-06, " Degradation of Steam Generator Internals." The purpose of GL 97-06 was to obtain information that would enable the NRC staff to verify that the condition of licensees' steam generator internals comply with, and conform to, the current licensing bases for their respective facilities. By letter dated March 30,1998, you responded to GL 97-06.

The NRC staff's review of your response to the GL 97-06 is complete and did not identify any new concerns with the condition of the steam generator internals. In addition, the NRC staff did not identify any concerns with the inspection practices employed at your facility to detect degradation of steam generator internals. The NRC staff, therefore, concludes that your response to GL 97-06 provides reasonable assurance that the condition of your steam generator internals is in compliance with the current licensing basis for CPSES, Units 1 and 2.

The detailed technical basis that supports the staff's determination for all facilities will be published in a NUREG report. The expected publication date is December 1999. This completes the NRC staff's effort on TAC Nos. MA0906 and MA0907.

Sincereg ,

6 l .

&l0d/}VY-f4Y - x {

David H. Jaffe, Senior Project Mana r, Section 1 1 Project Directorate IV & Decommissioning I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-445 and 50-446 cc: See next page

'v * ,.

]

I j

Comanche Peak Steam Electric Station l cc:

Senior Resident inspector Office of the Governor U.S. Nuclear Regulatory Commission ATTN: John Howard, Director P. O. Box 2159 Environmental and Natural Glen Rose, TX 76403-2159 Resources Policy P. O. Box 12428 Regional Administrator, Region IV Austin, TX 78711 U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 Arthur C. Tate, Director Arlington, TX 76011 Division of Compliance & Inspection Bureau of Radiation Control Mrs. Juanita Ellis, President Texas Department of Health Citizens Association for Sound Energy 1100 West 49th Street 1426 South Polk Austin, TX 78756-3189 Dallas, TX 75224 Jim Calloway Mr. Roger D. Walker Public Utility Commission of Texas Regulatory Affairs Manager Electric industry Analysis TU Electric P. O. Box 13326 P. O. Box 1002 Austin, TX 78711-3326 Glen Rose, TX 76043 George L. Edgar, Esq.

Morgan, Lewis & Bockius 1800 M Street, N.W.

Washington, DC 20036-5869 Honorable Dale McPherson County Judge P. O. Box 851 Glen Rose, TX 76043 l