March 27, 2007 MEMORANDUM TO: Robert Schaaf, Acting Chief License Renewal Branch A Division of License Renewal Office of Nuclear Reactor Regulation Rani Franovich, Chief Environmental Branch B Division of License Renewal Office of Nuclear Reactor Regulation FROM:
Maurice Heath, Project Manager /RA/
License Renewal Branch A Division of License Renewal Office of Nuclear Reactor Regulation Samuel Hernandez, Environmental Project Manager /RA/
Environmental Branch B Division of License Renewal Office of Nuclear Reactor Regulation
SUBJECT:
FORTHCOMING MEETING TO DISCUSS THE LICENSE RENEWAL PROCESS AND ENVIRONMENTAL SCOPING FOR SHEARON HARRIS NUCLEAR POWER PLANT, UNIT 1, LICENSE RENEWAL APPLICATION REVIEW DATE AND TIME:
Wednesday, April 18, 2007 (Two Identical Meetings)
First Meeting: 1:30 - 4:30 p.m.
Second Meeting: 7:00 - 10:00 p.m.
LOCATION:
New Horizons Fellowship 820 E. Williams Street Apex, NC 27502 CATEGORY 3:*
This is a Category 3 Meeting. The public is invited to participate in this meeting by providing comments and asking questions throughout the meeting.
CONTACT:
Maurice Heath, NRR 301-415-3137 MLH5@nrc.gov Samuel Hernandez, NRR 301-415-4049 SHQ@nrc.gov
- Commission's Policy Statement on Enhancing Public Participation in NRC Meetings, 67 Federal Register 36920, May 28, 2002.
PURPOSE:
The U.S. Nuclear Regulatory Commission (NRC) received a license renewal application (LRA) from Carolina Power & Light Company, doing business as Progress Energy Carolinas, Inc., dated November 14, 2006, for the renewal of the operating license for the Shearon Harris Nuclear Power Plant, Unit 1. The purpose of these meetings is to discuss the license renewal and environmental scoping process for the LRA review.
These meetings are being conducted as part of the scoping process outlined in Title 10 of the Code of Federal Regulations Part 51 (10 CFR Part 51) to support the development of an environmental impact statement. These meetings will provide members of the public with the opportunity to provide comments regarding environmental issues that the NRC should consider during its review.
Both meetings will be preceded by an informal ?open house beginning one hour prior to each meeting. The open house will provide members of the public with an opportunity to talk informally with NRC staff. Members of the public may register to present oral comments at the meetings by contacting Samuel Hernandez at 1-800-368-5642, extension 4049, or via e-mail at SHQ@nrc.gov by April 11, 2007. Those who wish to make comments may also register within 15 minutes of the start of each meeting. Individual oral comments may be limited by the time available, depending on the number of persons who register.
The agenda for the meeting and the Federal Register notice are enclosed. The LRA and information on the license renewal process are available on the NRC web site at http://www.nrc.gov/reactors/operating/licensing/renewal.html.
PARTICIPANTS:
Participants from the NRC include members of the Office of Nuclear Reactor Regulation (NRR) and members who register to speak.
NRC / NRR Maurice Heath Samuel Hernandez Rani Franovich Robert Schaaf et al.
Docket No. 50-400
Enclosures:
- 1. Agenda
- 2. Federal Register Notice cc w/encls: See next page
ML070790149 (meeting notice), ML070790177 (FRN), and ML070790093 (Pkg)
DOCUMENT NAME: C:\\FileNet\\ML070790149.wpd OFFICE LA:DLR PM:RLRA:DLR PM:REBB:DLR BC:RLRA:DLR BC:REBB:DLR NAME SFigueroa MHeath SHernandez Llund R. Schaaf for RFranovich J. Davis for DATE 3/21/07 3/22/07 3/27/07 3/21/07 3/27/07 NUCLEAR REGULATORY COMMISSION LICENSE RENEWAL AND ENVIRONMENTAL SCOPING PROCESS SHEARON HARRIS NUCLEAR POWER PLANT, UNIT 1 LICENSE RENEWAL APPLICATION NEW HORIZONS FELLOWSHIP APEX, NC AGENDA April 18, 2007 Two Identical Meetings*
(1:30 - 4:30 p.m. and 7:00 - 10:00 p.m.)
I.
Welcome and Purpose of Meeting 10 minutes **
II. Overview of License Renewal Process 15 minutes III. Overview of the Environmental Review Process 15 minutes IV. Public Comments As Needed V. Closing/Availability of Transcript 5 minutes The NRC staff will host informal discussions one hour prior to each meeting session. No formal comments on the proposed scope of the environmental impact statement will be accepted during the informal discussions. To be considered, comments must be provided either at the transcribed public meetings or in writing, as described in the enclosed Federal Register notice.
- Times in this agenda are approximates.
Memo to R. Schaaf and R. Franovich, from M. Heath and S. Hernandez, dated March 27, 2007
SUBJECT:
FORTHCOMING MEETING TO DISCUSS THE LICENSE RENEWAL PROCESS AND ENVIRONMENTAL SCOPING FOR SHEARON HARRIS NUCLEAR POWER PLANT, UNIT 1, LICENSE RENEWAL APPLICATION REVIEW DISTRIBUTION:
HARD COPY DLR RF E-MAIL:
PUBLIC PMNS JFair RWeisman AMurphy RPettis GGalletti DShum GBagchi SSmith (srs3)
SDuraiswamy YL (Renee) Li RidsNrrDlr RidsNrrDlrRlr RidsNrrDlrRlrb RidsNrrDlrRlrc RidsNrrDlrReba RidsNrrDlrRebb RidsNrrDe RidsNrrDci RidsNrreEemb RidsNrrDeEeeb RidsNrrDeEqva RidsNrrDss RidsNrrDnrl RidsOgcMailCenter RidsNrrAdes MHeath SHernandez CPatel CColleli RKWild JStorch RidsOpaMail RidsOcaMailCenter
Shearon Harris Nuclear Power Plant cc:
David T. Conley Associate General Counsel II -
Legal Department Progress Energy Service Company, LLC P.O. Box 1551 Raleigh, NC 27602-1551 Resident Inspector/ Harris NPS c/o U. S. Nuclear Regulatory Commission 5421 Shearon Harris Road New Hill, NC 27562-9998 Ms. Margaret A. Force Assistant Attorney General State of North Carolina P.O. Box 629 Raleigh, NC 27602 Public Service Commission State of South Carolina Post Office Drawer 11649 Columbia, SC 29211 Ms. Beverly Hall, Section Chief Division of Radiation Protection N.C. Department of Environment and Natural Resources 3825 Barrett Drive Raleigh, NC 27609-7721 Mr. Chris L. Burton Manager Performance Evaluation and Regulatory Affairs PEB 7 Progress Energy P.O. Box 1551 Raleigh, NC 27602-1551 Mr. Eric McCartney Plant General Manager Shearon Harris Nuclear Power Plant Carolina Power & Light Company P. O. Box 165, Mail Zone 3 New Hill, NC 27562-0165 Mr. Robert J. Duncan II Director of Site Operations Shearon Harris Nuclear Power Plant Carolina Power & Light Company P.O. Box 165, Mail Zone 1 New Hill, NC 27562-0165 Mr. Robert P. Gruber Executive Director Public Staff NCUC 4326 Mail Service Center Raleigh, NC 27699-4326 Chairman of the North Carolina Utilities Commission P.O. Box 29510 Raleigh, NC 27626-0510 Mr. Herb Council, Chair Board of County Commissioners of Wake County P. O. Box 550 Raleigh, NC 27602 Mr. Tommy Emerson, Chair Board of County Commissioners of Chatham County P. O. Box 87 Pittsboro, NC 27312 Mr. Christos Kamilaris, Manager Support Services Shearon Harris Nuclear Power Plant Carolina Power & Light Company P. O. Box 165, Mail Zone 1 New Hill, NC 27562-0165 Mr. David H. Corlett, Supervisor Licensing/Regulatory Programs Shearon Harris Nuclear Power Plant Carolina Power & Light Company P. O. Box 165, Mail Zone 1 New Hill, NC 27562-0165 Mr. John H. ONeill, Jr.
Shearon Harris Nuclear Power Plant cc: Shaw, Pittman, Potts & Trowbridge 2300 N. Street, NW Washington, DC 20037-1128