A VT-2 is a visual examination for leakage during a pressure test. aka the Hydrostatic Test.
IWA-2212 VT-2 Examination
(a) VT-2 examination is conducted to detect evidence of leakage from pressure retaining components, as required 6.1 during the conduct of system pressure test.
(b) VT-2 examination shall be conducted in accordance with IWA-5000.
Topic |
---|
|
|
All by date | | Start date | Site | Title |
---|
IR 05000483/2023004 | 19 January 2024 | Callaway | Integrated Inspection Report 05000483/2023004 | RS-24-001, Response to Request for Additional Information Regarding Relief Request I5R-26, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval | 3 January 2024 | Quad Cities | Response to Request for Additional Information Regarding Relief Request I5R-26, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval | NMP1L3563, Submittal of Relief Request I5R-12, Revision 0, Concerning the Installation of a Full Structural Weld Overlay on Reactor Pressure Vessel Recirculation Inlet Nozzle N2E Safe End-to-Nozzle Dissimilar Metal Weld (32-WD-208) | 4 December 2023 | Nine Mile Point | Submittal of Relief Request I5R-12, Revision 0, Concerning the Installation of a Full Structural Weld Overlay on Reactor Pressure Vessel Recirculation Inlet Nozzle N2E Safe End-to-Nozzle Dissimilar Metal Weld (32-WD-208) | IR 05000454/2023003 | 13 November 2023 | Byron | Integrated Inspection Report 05000454/2023003 and 05000455/2023003 and Exercise of Enforcement Discretion | ML23279A067 | 9 November 2023 | Point Beach | Issuance of Relief Request I6 RR 02 - Examination of the Unit 2 Steam Generator Feedwater Nozzle Extension to Nozzle Weld Sixth 10 Year Inservice Inspection Program Interval | L-MT-23-046, Subsequent License Renewal Application Response to Request for Additional Information Round 2 - Set 1 | 9 November 2023 | Monticello | Subsequent License Renewal Application Response to Request for Additional Information Round 2 - Set 1 | RS-23-107, Relief Request I5R-22, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval | 8 November 2023 | Dresden | Relief Request I5R-22, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval | RS-23-114, Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds | 1 November 2023 | Byron Braidwood | Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds | ML23304A345 | 31 October 2023 | 05200050 | LLC, Revision 1 to Standard Design Approval Application, Part 2, Chapter 6, Engineered Safety Features | ML23353A157 | 31 October 2023 | Nine Mile Point | UFSAR Revision 28 (Redacted Version) |
|
---|