|
---|
Category:Inspection Plan
MONTHYEARIR 05000277/20240052024-08-29029 August 2024 Updated Inspection Plan for Peach Bottom Atomic Power Station, Units 2 and 3 (Report 05000277/2024005 and 05000278/2024005) IR 05000482/20240052024-08-14014 August 2024 Updated Inspection Plan for Wolf Creek Generating Station (Report 05000482/2024005) ML24060A1192024-02-29029 February 2024 Notification of Conduct of a Fire Protection Team Inspection IR 05000277/20230062024-02-28028 February 2024 Annual Assessment Letter for Peach Bottom Atomic Power Station, Units 2 and 3 (Reports 05000277/2023006 and 05000278/2023006) IR 05000277/20230052023-08-31031 August 2023 Updated Inspection Plan for Peach Bottom Atomic Power Station, Units 2 and 3 (Report 05000277/2023005 and 05000278/2023005) IR 05000277/20220062023-03-0101 March 2023 Annual Assessment Letter for Peach Bottom Atomic Power Station, Units 2 and 3 (Reports 05000277/2022006 and 05000278/2022006) ML23019A0752023-01-19019 January 2023 Information Request for Quadrennial Baseline Comprehensive Engineering Team Inspection; Notification to Perform Inspection 05000277/2023011 and 05000278/2023011 IR 05000277/20220052022-08-31031 August 2022 Updated Inspection Plan for Peach Bottom Atomic Power Station, Units 2 and 3 (Report 05000277/2022005 and 05000278/2022005) IR 05000277/20210062022-03-0202 March 2022 Annual Assessment Letter for Peach Bottom Atomic Power Station, Units 2 and 3 (Reports 05000277/2021006 and 05000278/2021006) IR 05000277/20210052021-09-0101 September 2021 Updated Inspection Plan for the Peach Bottom Atomic Power Station, Units 2 and 3 (Report 05000277/2021005 and 05000278/2021005) IR 05000277/20200062021-03-0303 March 2021 Annual Assessment Letter for Peach Bottom Atomic Power Station, Units 2 and 3 (Reports 05000277/2020006 and 05000278/2020006) ML21091A1782021-02-0202 February 2021 Ti 2515/194 Inspection Documentation Request ML20296A3342020-10-21021 October 2020 ISI Remote Inspection - Supplemental Request for Information IR 05000277/20200052020-08-31031 August 2020 Updated Inspection Plan (Inspection Reports 05000277/2020005 and 05000278/2020005) ML20119A8852020-04-28028 April 2020 Stations, Unit 3, Long-Term Steam Dryer Inspection Plan at EPU Conditions IR 05000277/20190062020-03-0303 March 2020 Annual Assessment Letter for Peach Bottom Atomic Power Station, Units 2 and 3 (Report 05000277/2019006 and 05000278/2019006) IR 05000277/20190052019-08-28028 August 2019 Updated Inspection Plan (Inspection Reports 05000277/2019005 and 05000278/2019005) ML19119A1202019-04-29029 April 2019 Long-Term Steam Dryer Inspection Plan at EPU Conditions IR 05000277/20180062019-03-0404 March 2019 Annual Assessment Letter for Peach Bottom Atomic Power Station, Units 2 and 3 (Reports 05000277/2018006 and 05000278/2018006) ML18330A0532018-11-21021 November 2018 Information Request for the Cyber-Security Inspection, Notification to Perform Inspection 05000277/2019403 and 05000278/2019403 IR 05000277/20180052018-08-28028 August 2018 Updated Inspection Plan (Inspection Report 05000277/2018005 and 05000278/2018005) IR 05000277/20170062018-02-28028 February 2018 Annual Assessment Letter for Peach Bottom Atomic Power Station Units 2 and 3 -(Report 05000277-2017006 and 05000278-2017006 Report 05000277-2017402 and 05000278-2017402 Report 05000277-2017501 and 05000278-2017501) ML17340A4112017-12-0505 December 2017 Notification of Conduct of a Triennial Fire Protection Baseline Inspection IR 05000277/20170052017-08-28028 August 2017 Updated Inspection Plan Letter 05000277/2017005 and 05000278/2017005 with Rpt. 22 IR 05000277/20160062017-03-0101 March 2017 Annual Assessment Letter Units 2 and 3 - Report Nos. 05000277/2016006 and 05000278/2016006 with Report 22 IR 05000277/20150062016-03-0202 March 2016 ROP 16 Annual Assessment Letter for Peach Bottom Atomic Power Station, Units 2 & 3 (Report 05000277/2015006 & 05000278/2015006) IR 05000277/20150052015-09-0101 September 2015 ROP-16 Mid-Cycle Assessment Letter for Peach Bottom Atomic Power Station, Units 2 and 3 (Report 05000277/2015005 and 05000278/2015005) IR 05000277/20140012015-03-0404 March 2015 ROP 15 Annual Assessment Letter for Peach Bottom Atomic Power Station (Report 05000277/2014001 and 05000278/2014001) IR 05000277/20140062014-09-0202 September 2014 ROP-15 Mid-Cycle Performance Review and Inspection Plan Report 05000277/2014006 and 05000278/2014006 IR 05000277/20130012014-03-0404 March 2014 ROP-14 2013 Peach Bottom Atomic Power Station Annual Assessment Letter, Report 05000277/2013001 and 05000278/2013001, and Inspection Plan IR 05000277/20130062013-09-0303 September 2013 ROP-14 Mid-Cycle Performance Review and Inspection Plan Report 05000277/2013006 and 05000278/2013006 IR 05000277/20120012013-03-0404 March 2013 Annual Assessment Letter for Peach Bottom Atomic Power Station Units 2 and 3 (Report 05000277/2012001 and 05000278/2012001) ML12318A0022012-11-0909 November 2012 Notification to Perform an Inspection of Temporary Instruction 2201/004, Inspection of Implementation of Interim Cyber Security Milestones 1 - 7 and Request for Information IR 05000277/20120062012-09-0404 September 2012 Mid-Cycle Performance Review and Inspection Plan 2012 - Peach Bottom Atomic Power Station (Report 05000277/2012006 and 05000278/2012006) IR 05000277/20110012012-03-0505 March 2012 Annual Assessment Letter for Peach Bottom Atomic Power Station (Report 05000277-11-001 and 05000278-11-001) ML1124113452011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plan 2011 - Peach Bottom Atomic Power Station IR 05000277/20100012011-03-0404 March 2011 Annual Assessment Letter for Peach Bottom Atomic Power Station, EOC-11 (05000277/2010001 and 05000278/2010001) ML1024404132010-09-0101 September 2010 Mid-Cycle Assessment Letter 2010 - Peach Bottom Atomic Power Station, Units 2 and 3 ML1006210092010-03-0303 March 2010 Annual Assessment Letter - Peach Bottom Atomic Power Station (05000277-10-001 and 05000278-10-001) and Report 22 ML0924402532009-09-0101 September 2009 Mid-Cycle Performance Assessment Letter - Peach Bottom Atomic Power Station IR 05000277/20090012009-03-0404 March 2009 Annual Assessment Letter - Peach Bottom Atomic Power Station (05000277/2009001 and 05000278/2009001) ML0824704542008-09-0202 September 2008 2008 Mid-Cycle Performance Assessment Letter - Peach Bottom ML0734705752007-12-13013 December 2007 ROP - Peach Bottom - Change to Inspection Plan, 12/13/07 ML0724306242007-08-31031 August 2007 Mid-Cycle Performance Review and Inspection Plan, for 07/01/2007 - 12/31/2008 ML0706106152007-03-0202 March 2007 Annual Assessment Letter EOC 2006 - Peach Bottom Station (05-277-07-001 and 05-278-07-001) ML0624305232006-08-31031 August 2006 Mid-Cycle Performance Review and Inspection Plan - Peach Bottom Atomic Power Station IR 05000277/20060012006-03-0202 March 2006 2006-001 - Annual Assessment Letter - Peach Bottom Atomic Power Station (Report 05000277/2006001 and 05000278/2006001) ML0524207012005-08-30030 August 2005 Mid-Cycle Performance Review and Inspection Plan - Peach Bottom Atomic Power Station ML0506107082005-03-0202 March 2005 Annual Assessment Letter 2005001-Peach Bottom ML0424404642004-08-30030 August 2004 2004 Peach Bottom Mid-Cycle Performance Review and Inspection Plan 2024-08-29
[Table view] Category:Letter
MONTHYEARML24313A1012024-11-13013 November 2024 SLRA Supplemental Environmental Audit Plan ML24310A2832024-11-0404 November 2024 Issuance of the Core Operating Limits Report for Reload 25, Cycle 26 IR 05000277/20240032024-11-0404 November 2024 Integrated Inspection Report 05000277/2024003 and 05000278/2024003 ML24317A1432024-11-0404 November 2024 Constellation Energy Generation, LLC, 2024 Annual Report - Guarantees of Payment of Deferred Premiums IR 05000277/20244012024-10-17017 October 2024 Security Baseline Inspection Report 05000277/2024401 and 05000278/2024401 (Cover Letter Only) RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24284A2842024-10-10010 October 2024 (Wcgs), Revision of One Form That Implements the Radiological Emergency Response Plan (RERP) ML24281A1012024-10-0707 October 2024 Senior Reactor and Reactor Operator Initial License Examinations ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24221A2582024-09-0606 September 2024 Response to Request for Re-Engagement Regarding the Subsequent License Renewal Environmental Review for Peach Bottom Atomic Power Station, Units 2 and 3 ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification 05000277/LER-2024-003, Automatic Reactor Scram Following Main Turbine Trip Due to Degraded Condenser Vacuum2024-09-0505 September 2024 Automatic Reactor Scram Following Main Turbine Trip Due to Degraded Condenser Vacuum IR 05000277/20240022024-09-0404 September 2024 Reissued Integrated Inspection Report 05000277/2024002 and 05000278/2024002 IR 05000277/20240052024-08-29029 August 2024 Updated Inspection Plan for Peach Bottom Atomic Power Station, Units 2 and 3 (Report 05000277/2024005 and 05000278/2024005) IR 05000277/20240102024-08-23023 August 2024 Fire Protection Team Inspection Report 05000277/2024010 and 05000278/2024010 ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 ML24235A0342024-08-23023 August 2024 U.S. Nuclear Regulatory Commission’S Analysis of Constellation Energy Generation’S Decommissioning Funding Status Report IR 05000482/20240052024-08-14014 August 2024 Updated Inspection Plan for Wolf Creek Generating Station (Report 05000482/2024005) ML24227A5492024-08-14014 August 2024 Integrated Inspection Report 05000277/2024002 and 05000278/2024002 ML24225A1692024-08-12012 August 2024 10 CFR 50.46 Annual Report ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition ML24214A3232024-08-0101 August 2024 Response to Request for Additional Information - Request for Alternative Schedule to Complete Decommissioning Beyond 60 Years of Permanent Cessation of Operations ML24208A0962024-07-25025 July 2024 57243-EN 57243 - Rssc Wire & Cable LLC, Dba Marmon - Part 21 Notification ML24206A1252024-07-24024 July 2024 Revision of Three Procedures and Two Forms That Implement the Radiological Emergency Response Plan (RERP) ML24191A0612024-07-0606 July 2024 Independent Spent Fuel Storage Installation (ISFSI) - Annual Radioactive Effluent Release Report ML24178A3672024-06-26026 June 2024 Correction to 2023 Annual Radioactive Effluent Release Report – Report 47 ML24178A4142024-06-26026 June 2024 Revision of One Procedure and One Form That Implement the Radiological Emergency Response Plan (RERP) ML24177A1512024-06-24024 June 2024 Post Accident Monitoring Instrumentation Report ML24166A1172024-06-20020 June 2024 Regulatory Audit Summary Regarding Proposed Alternative Schedule to Complete Decommissioning Beyond 60 Years RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000277/20243012024-06-13013 June 2024 Initial Operator Licensing Examination Report 05000277/2024301 and 05000278/2024301 RS-24-058, Regarding Subsequent License Renewal Environmental Review2024-06-0505 June 2024 Regarding Subsequent License Renewal Environmental Review ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities ML24150A2722024-05-29029 May 2024 Annual Radiological Environmental Operating Report 81, January 1, 2023 Through December 31, 2023 ML24150A0032024-05-28028 May 2024 Request for Exemptions from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv) and Proposed Amendment to the Decommissioning Trust Agreement ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report IR 05000277/20240012024-05-13013 May 2024 Integrated Inspection Report 05000277/2024001 and 05000278/2024001 ML24134A1792024-05-13013 May 2024 Supplemental Information in Support of Request for Alternative Schedule to Complete Decommissioning Beyond 60 Years of Permanent Cessation of Operations IR 05000277/20245012024-05-0808 May 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000277/2024501 and 05000278/2024501 ML24121A1832024-04-30030 April 2024 Pre-Submittal Meeting Presentation Material Peach Bottom ECCS Compensated Level System Replacement Project RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24118A0032024-04-27027 April 2024 2023 Annual Radioactive Effluent Release Report - Report 47 ML24120A2762024-04-23023 April 2024 Independent Spent Fuel Storage Installation (ISFSI) Facility - Annual Radioactive Effluent Release Report 66 January 1, 2023 Through December 31, 2023 CNL-24-033, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-04-17017 April 2024 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML24107A2462024-04-15015 April 2024 Submittal of Changes to Technical Specifications Bases ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition ML24102A0472024-04-11011 April 2024 Operator Licensing Examination Approval 05000277/LER-2024-002, Uncoordinated DC Circuits Cause Unanalyzed Condition2024-04-0808 April 2024 Uncoordinated DC Circuits Cause Unanalyzed Condition 2024-09-06
[Table view] |
Text
March 3, 2021
SUBJECT:
ANNUAL ASSESSMENT LETTER FOR PEACH BOTTOM ATOMIC POWER STATION, UNITS 2 AND 3 (REPORTS 05000277/2020006 AND 05000278/2020006)
Dear Mr. Rhoades:
The U.S. Nuclear Regulatory Commission (NRC) has completed its end-of-cycle performance assessment of Peach Bottom Atomic Power Station, Units 2 and 3, reviewing performance indicators (PIs), inspection results, and enforcement actions from January 1, 2020 through December 31, 2020. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. The NRC concluded that overall performance at your facility preserved public health and safety. The baseline inspection program was completed at your facility as defined in Inspection Manual Chapter 2515, Light-Water Reactor Inspection Program - Operations Phase.
The NRC determined the performance at Peach Bottom Atomic Power Station, Units 2 and 3 during the most recent quarter was within the Licensee Response Column (Column 1) of the NRCs Reactor Oversight Process (ROP) Action Matrix in Inspection Manual Chapter 0305, Operating Reactor Assessment Program, because all inspection findings had very low safety significance (i.e., Green), and all PIs were within the expected range (i.e., Green). Therefore, the NRC plans to conduct ROP baseline inspections at Peach Bottom Atomic Power Station, Units 2 and 3.
The enclosed inspection plan lists the inspections scheduled through December 31, 2022.
The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
In response to the COVID-19 public health emergency (PHE), the NRC is adjusting inspection plans and schedules in order to safeguard the health and safety of both NRC and licensee staff while still effectively implementing the ROP. Each planned inspection is being carefully reviewed in order to determine if any portions of the inspection can be performed remotely, how best to perform on-site portions to minimize personnel health risks and adjust inspection schedules if needed. This is done in accordance with guidance contained in the February 1, 2021 memo, Calendar Year 2021 Inspection Guidance During COVID-19 Telework Restrictions (ML21027A274). For inspections requiring extensive coordination with offsite organizations, such as evaluated emergency preparedness exercises, NRC guidance and frequently asked questions for security and emergency preparedness can be found here:
https://www.nrc.gov/about-nrc/covid-19/security-ep/. Similarly, the NRC has developed guidance if force-on-force inspections cannot be completed as scheduled due to an emergency, such as the COVID-19 PHE. These changes help ensure the health and safety of both NRC and licensee staff while maintaining the NRCs important safety and security mission during the COVID-19 PHE. The attached inspection plan is accurate on the date of issuance but remains subject to change based on approval of potential exemption requests or other changes needed due to changing conditions in the COVID-19 PHE. NRC staff will contact your appropriate regulatory affairs staff in order to coordinate inspection planning and scheduling.
Additionally, during this period the NRC will perform inspections per Temporary Instruction 2515/194, Inspection of the Licensees Implementation of Industry Initiative Associated with the Open Phase Condition Design Vulnerability in Electrical Power Systems (NRC Bulletin 2012-01).
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRCs Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at (610) 337-5124 with any questions you have regarding this letter.
Sincerely, X /RA/
Signed by: Christopher Lally Chris M. Lally, Acting Chief Reactor Projects Branch 4 Division of Reactor Projects Docket Nos. 05000277 and 05000278 License Nos. DPR-44 and DPR-56 Enclosure:
As stated cc w/ encl: Distribution via LISTSERV
ML21060B509 Non-Sensitive Publicly Available SUNSI Review Sensitive Non-Publicly Available OFFICE RI/DRP RI/DRP NAME LCasey CLally DATE 2/26/21 3/3/21
IP 22 Inspection Activity Plan Report Peach Bottom 01/01/2021 - 12/31/2022 Unit Start End Activity CAC Title Staff Count EP PROGRAM INSPECTION - PEACH BOTTOM 1 2, 3 02/08/2021 02/12/2021 IP 71114.02 000717 Alert and Notification System Testing 2, 3 02/08/2021 02/12/2021 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 2, 3 02/08/2021 02/12/2021 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 2, 3 02/08/2021 02/12/2021 IP 71114.05 000720 Maintenance of Emergency Preparedness 2, 3 02/08/2021 02/12/2021 IP 71151 001397 Performance Indicator Verification TI-194 Open Phase Condition Inspection - Peach Bottom 2 2, 3 03/22/2021 03/26/2021 TI 2515/194 000512 Inspection of the Licensees Implementation of Industry Initiative Associated With the Open Phase Condition Design Vulnerabilities In Electric Power Systems (NRC Bulletin 2012-01)
PB Requal Inspection with P/F Results 2 2 03/29/2021 04/02/2021 IP 71111.11A 000703 Licensed Operator Requalification Program and Licensed Operator Performance 2 03/29/2021 04/02/2021 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance Access Control, Equipment Testing and Maintenance, Training, SPR 3 2, 3 04/05/2021 04/09/2021 IP 71130.02 000734 Access Control 2, 3 04/05/2021 04/09/2021 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance 2, 3 04/05/2021 04/09/2021 IP 71130.07 000739 Security Training 2, 3 04/05/2021 04/09/2021 IP 71130.09 001656 Security Plan Changes 2, 3 04/05/2021 04/09/2021 IP 71151 001338 Performance Indicator Verification FY2021 Peach Bottom Initial Examination 4 2, 3 05/02/2021 05/07/2021 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)
2, 3 05/30/2021 06/11/2021 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)
Fire Protection - Peach Bottom 3 2, 3 06/07/2021 06/11/2021 IP 71111.21N.05 001646 Fire Protection Team Inspection (FPTI)
2, 3 06/21/2021 06/25/2021 IP 71111.21N.05 001646 Fire Protection Team Inspection (FPTI)
Radwaste (71124.08) 1 2, 3 07/26/2021 07/30/2021 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, &
Transportation This report does not include INPO and OUTAGE activities. Page 1 of 3 This report shows only on-site and announced inspection procedures.
2/10/2021 6:41:10 AM
IP 22 Inspection Activity Plan Report Peach Bottom 01/01/2021 - 12/31/2022 Unit Start End Activity CAC Title Staff Count PI&R BIENNIAL - PB 4 2, 3 07/26/2021 07/30/2021 IP 71152B 000747 Problem Identification and Resolution 2, 3 08/09/2021 08/13/2021 IP 71152B 000747 Problem Identification and Resolution HP Instrumentation (71124.05) 1 2, 3 09/13/2021 09/17/2021 IP 71124.05 000729 Radiation Monitoring Instrumentation INSERVICE INSPECTION - UNIT 3 1 3 10/31/2021 11/06/2021 IP 71111.08G 000701 Inservice Inspection Activities (BWR)
Rad Hazards (71124.01) and PIs (71151) 1 2, 3 11/01/2021 11/05/2021 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 2, 3 11/01/2021 11/05/2021 IP 71151 000746 Performance Indicator Verification ALARA (71124.02) 1 2, 3 11/29/2021 12/03/2021 IP 71124.02 000726 Occupational ALARA Planning and Controls Design Basis Assurance Inspection - Power Operated Valves - Peach Bottom Units 2 and 3 3 2, 3 03/21/2022 04/08/2022 IP 71111.21N.02 001645 Design-Basis Capability of Power-Operated Valves Under 10 CFR 50.55a Requirements Resp Protection & Dose Assessment (71124.03/71124.04) 1 2, 3 04/18/2022 04/22/2022 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 2, 3 04/18/2022 04/22/2022 IP 71124.04 000728 Occupational Dose Assessment FY22 Peach Bottom Initial License Examination 4 2, 3 04/24/2022 04/29/2022 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)
2, 3 05/15/2022 05/27/2022 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)
EP EXERCISE INSPECTION - PEACH BOTTOM 4 2, 3 04/25/2022 04/29/2022 IP 71114.07 000722 Exercise Evaluation - Hostile Action (HA) Event 2, 3 04/25/2022 04/29/2022 IP 71151 001397 Performance Indicator Verification Access Control, Protective Strat, TSR, SPR, PI-PB 4 2, 3 05/16/2022 05/20/2022 IP 71130.02 000734 Access Control 2, 3 05/16/2022 05/20/2022 IP 71130.05 000737 Protective Strategy Evaluation 2, 3 05/16/2022 05/20/2022 IP 71130.09 001656 Security Plan Changes 2, 3 05/16/2022 05/20/2022 IP 71130.14 000743 Review of Power Reactor Target Sets This report does not include INPO and OUTAGE activities. Page 2 of 3 This report shows only on-site and announced inspection procedures.
2/10/2021 6:41:10 AM
IP 22 Inspection Activity Plan Report Peach Bottom 01/01/2021 - 12/31/2022 Unit Start End Activity CAC Title Staff Count Access Control, Protective Strat, TSR, SPR, PI-PB 4 2, 3 05/16/2022 05/20/2022 IP 71151 001338 Performance Indicator Verification 59.59 Inspection - Peach Bottom Units 2 and 3 3 2, 3 06/13/2022 06/17/2022 IP 71111.17T 000709 Evaluations of Changes, Tests, and Experiments RETS (71124.06) 1 2, 3 07/18/2022 07/22/2022 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment Material Control and Accountability - Peach Bottom Units 2 and 3 1 2, 3 08/22/2022 08/26/2022 IP 71130.11 000742 Material Control and Accounting (MC&A)
Triennial Heat Sink - Peach Bottom Units 2 and 3 1 2, 3 09/19/2022 09/23/2022 IP 71111.07T 000700 Heat Sink Performance Inservice Inspection - Peach Bottom Unit 2 1 2 10/24/2022 10/28/2022 IP 71111.08G 000701 Inservice Inspection Activities (BWR)
Rad Hazards (71124.01) and PIs (71151) 1 2, 3 10/24/2022 10/28/2022 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 2, 3 10/24/2022 10/28/2022 IP 71151 000746 Performance Indicator Verification This report does not include INPO and OUTAGE activities. Page 3 of 3 This report shows only on-site and announced inspection procedures.
2/10/2021 6:41:10 AM