Letter Sequence RAI |
---|
|
Results
Other: 0CAN029802, Informs of Revised Commitment Re GL 87-02,Suppl 1.Util Will Complete Relay Resolution by 1R15 Which Is Currently Scheduled to Begin on 990925, 0CAN039602, Notifies That Addl Time Needed to Submit Ipeee/Usi A-46 Summary Repts.Unexpected Delays Occurred in Receiving Final Info Required to Complete,Compile & Review Repts for Plant. Util Intends to Extends Submittal Date to 960531, 0CAN049505, Discusses Individual Plant Exam of External Events for Severe Accident Vulnerabilities,Per GL 88-20,Suppl 4, 0CAN099201, Responds to GL 87-02,Suppl 1 Re Sser 2 on SQUG Generic Implementation Procedure,Rev 2 & GL 88-20,Suppl 4 Re IPEEE for Severe Accident Vulnerabilities,Consisting of Description of Licensing Basis to Resolve USI A-46, 0CAN109505, Informs That Util Will Like to Submit Ipeee/Usi A-46 Summary Repts by 960331 for Units 1 & 2,in Order to Allow Sufficient Time to Complete Review,Per GL 88-20, ML20056H356, ML20247B148
|
MONTHYEAR0CAN099201, Responds to GL 87-02,Suppl 1 Re Sser 2 on SQUG Generic Implementation Procedure,Rev 2 & GL 88-20,Suppl 4 Re IPEEE for Severe Accident Vulnerabilities,Consisting of Description of Licensing Basis to Resolve USI A-461992-09-18018 September 1992 Responds to GL 87-02,Suppl 1 Re Sser 2 on SQUG Generic Implementation Procedure,Rev 2 & GL 88-20,Suppl 4 Re IPEEE for Severe Accident Vulnerabilities,Consisting of Description of Licensing Basis to Resolve USI A-46 Project stage: Other 0CAN019307, Forwards Response to NRC 921116 Request for Addl Info Re in-structure Response Spectra,Per Suppl 1 to GL 87-02. Confirms That Util Used Generic Implementation Procedure 2 Guidance to Resolve USI A-461993-01-28028 January 1993 Forwards Response to NRC 921116 Request for Addl Info Re in-structure Response Spectra,Per Suppl 1 to GL 87-02. Confirms That Util Used Generic Implementation Procedure 2 Guidance to Resolve USI A-46 Project stage: Request ML20056G9981993-08-19019 August 1993 Forwards SE Accepting Licensee 920916 Response to GL 87-02, Suppl 1 Project stage: Approval ML20056H3561993-08-24024 August 1993 Informs That Proposed Schedule for Completion of IPEEE/A-46 Efforts for Both Units,Though Later than Staff Would Have Preferred,Acceptable Per Project stage: Other 2CAN079401, Informs That Util Intends to Complete Seismic IPEEE for ANO Unit 2 at Reduced Scope Level of Effort,As Requested by GL 88-20,Suppl 41994-07-20020 July 1994 Informs That Util Intends to Complete Seismic IPEEE for ANO Unit 2 at Reduced Scope Level of Effort,As Requested by GL 88-20,Suppl 4 Project stage: Other 0CAN049505, Discusses Individual Plant Exam of External Events for Severe Accident Vulnerabilities,Per GL 88-20,Suppl 41995-04-0404 April 1995 Discusses Individual Plant Exam of External Events for Severe Accident Vulnerabilities,Per GL 88-20,Suppl 4 Project stage: Other 0CAN109505, Informs That Util Will Like to Submit Ipeee/Usi A-46 Summary Repts by 960331 for Units 1 & 2,in Order to Allow Sufficient Time to Complete Review,Per GL 88-201995-10-16016 October 1995 Informs That Util Will Like to Submit Ipeee/Usi A-46 Summary Repts by 960331 for Units 1 & 2,in Order to Allow Sufficient Time to Complete Review,Per GL 88-20 Project stage: Other 0CAN039602, Notifies That Addl Time Needed to Submit Ipeee/Usi A-46 Summary Repts.Unexpected Delays Occurred in Receiving Final Info Required to Complete,Compile & Review Repts for Plant. Util Intends to Extends Submittal Date to 9605311996-03-14014 March 1996 Notifies That Addl Time Needed to Submit Ipeee/Usi A-46 Summary Repts.Unexpected Delays Occurred in Receiving Final Info Required to Complete,Compile & Review Repts for Plant. Util Intends to Extends Submittal Date to 960531 Project stage: Other 0CAN029802, Informs of Revised Commitment Re GL 87-02,Suppl 1.Util Will Complete Relay Resolution by 1R15 Which Is Currently Scheduled to Begin on 9909251998-02-25025 February 1998 Informs of Revised Commitment Re GL 87-02,Suppl 1.Util Will Complete Relay Resolution by 1R15 Which Is Currently Scheduled to Begin on 990925 Project stage: Other ML20217N1831998-04-0303 April 1998 Forwards Request for Addl Info Pertaining to Operator Actions Following Events Addressed by Arkansas Nuclear One, Unit 1 & 2,summary Rept on Verification of Seismic Adequacy of Mechanical & Electrical Equipment Project stage: RAI ML20217K9881998-04-0303 April 1998 Forwards RAI Re IPEEE for Plant,Units 1 & 2.Staff Questions on Subj Matter Encl Project stage: RAI ML20247B1481998-05-0101 May 1998 Submits Commitment Extension Re IPEEE & USI A-46 Project stage: Other ML20216B6931998-05-0707 May 1998 Forwards Request for Addl Info Pertaining to Summary Repts for IPEEE & USI A-46 Seismic Evaluations That Entergy Operations,Inc Submitted on 960531 for ANO-1 & ANO-2 Project stage: RAI 1995-10-16
[Table View] |
|
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEAR1CAN109906, Forwards Framatome Technologies,Inc non-proprietary TR BAW-10235P, Mgt Program for Volumetric Outer Diameter Intergranular Attack in Tubesheet of Once-Through Sgs, Rev 11999-10-19019 October 1999 Forwards Framatome Technologies,Inc non-proprietary TR BAW-10235P, Mgt Program for Volumetric Outer Diameter Intergranular Attack in Tubesheet of Once-Through Sgs, Rev 1 ML20217J4971999-10-18018 October 1999 Requests Addl Info Re Results of Util Most Recent Steam Generator Insp at ANO-2 & Util Methodology Used to Predict Future Performance of SG Tubes ML20217J3871999-10-15015 October 1999 Informs That Topical Rept BAW-10235P, Management Program for Volumetric Outer Diameter Intergranular Attack in Tubesheets of Once-Through SG, Rev 0 Marked as Proprietary Will Be Withheld from Public Disclosure 2CAN109902, Submits Withdrawal of Code Case N-593 for ANO-2 Replacement SGs1999-10-15015 October 1999 Submits Withdrawal of Code Case N-593 for ANO-2 Replacement SGs ML20217J3601999-10-15015 October 1999 Informs That Topical Rept BAW-10235P, Management Program for Volumetric Outer Diameter Integranular Attack in Tubesheets of Once-Through SG, Rev 1 Marked as Proprietary Will Be Withheld from Public Disclosure 2CAN109903, Forwards Response to RAI Re Proposed Tech Specs Change for Special SG Insp1999-10-14014 October 1999 Forwards Response to RAI Re Proposed Tech Specs Change for Special SG Insp ML20217D1721999-10-0808 October 1999 Forwards RAI Re 990729 Request for Amend to TSs Allowing Special SG Insp for Plant,Unit 2.Questions Re Proposed Insp Scope for Axial Cracking Degradation in Eggcrate Support Region Submitted.Response Requested by 991015 1CAN109905, Discusses Insp of Once Through SG Tubing Surveillance Performed During 1R15 Scheduled RFO on 990910.Category C-3 Results,Included1999-10-0404 October 1999 Discusses Insp of Once Through SG Tubing Surveillance Performed During 1R15 Scheduled RFO on 990910.Category C-3 Results,Included ML20212L0621999-10-0101 October 1999 Forwards Safety Evaluation & Exemption from Certain Requirements of 10CFR50,App R,Section III.G.2, Fire Protection of Safe Shutdown Capability 1CAN099908, Withdraws 990919 Exigent TS Change Request to Allow Continued Installation of re-rolls for One Cycle of Operation Through End of Cycle 16 in Conjunction with Addl Insp Criteria1999-09-30030 September 1999 Withdraws 990919 Exigent TS Change Request to Allow Continued Installation of re-rolls for One Cycle of Operation Through End of Cycle 16 in Conjunction with Addl Insp Criteria 2CAN099902, Requests That NRC Assign CENPD-132,Suppl 4-P, Calculative Methods for Abb Cenp Large Break LOCA Evaluation Model, Review Priority So That Approval Will Be Granted No Later than Oct 31,20001999-09-29029 September 1999 Requests That NRC Assign CENPD-132,Suppl 4-P, Calculative Methods for Abb Cenp Large Break LOCA Evaluation Model, Review Priority So That Approval Will Be Granted No Later than Oct 31,2000 1CAN099903, Forwards Rev 0 to COLR for ANO-1 Cycle 16, IAW TS 6.12.31999-09-27027 September 1999 Forwards Rev 0 to COLR for ANO-1 Cycle 16, IAW TS 6.12.3 1CAN099907, Requests That Alternative Be Allowed in Accordance with 10CFR50.55a(a)(3)(i) & (II) as Discussed in Encl 1.Encl 2 & 3 Stress Analysis & Flaw Evaluation Summaries Ref in Encl Alternative1999-09-26026 September 1999 Requests That Alternative Be Allowed in Accordance with 10CFR50.55a(a)(3)(i) & (II) as Discussed in Encl 1.Encl 2 & 3 Stress Analysis & Flaw Evaluation Summaries Ref in Encl Alternative 1CAN099906, Forwards 1R15 Growth Data Obtained & Analyzed Through 990922 & Includes Plus Point Voltages,Axial Extent & Circumferential Extent Patches,As Well as Preliminary Growth Conclusions Based on Analysis of Data1999-09-24024 September 1999 Forwards 1R15 Growth Data Obtained & Analyzed Through 990922 & Includes Plus Point Voltages,Axial Extent & Circumferential Extent Patches,As Well as Preliminary Growth Conclusions Based on Analysis of Data 2CAN099901, Informs That G Kendrick,License SOP-43658,no Longer Has Need to Maintain Operating License on Ano,Unit 2.Entergy Requests That License for Individual Be Withdrawn,Due to Resignation, Effective 9908271999-09-24024 September 1999 Informs That G Kendrick,License SOP-43658,no Longer Has Need to Maintain Operating License on Ano,Unit 2.Entergy Requests That License for Individual Be Withdrawn,Due to Resignation, Effective 990827 2CAN099904, Forwards Ano,Unit 2 10CFR50.59 Rept for Time Period Ending 990225.Rept Contains Brief Description of Changes in Procedures & in Facility as Described in Sar,Tests & Experiments Conducted & Other Changes to SAR1999-09-23023 September 1999 Forwards Ano,Unit 2 10CFR50.59 Rept for Time Period Ending 990225.Rept Contains Brief Description of Changes in Procedures & in Facility as Described in Sar,Tests & Experiments Conducted & Other Changes to SAR ML20212F5031999-09-22022 September 1999 Forwards SER Granting Relief Requests 1-98-001 & 1-98-002 Which Would Require Design Mods to Comply with Code Requirements,Which Would Impose Significant Burden Pursuant to 10CFR50.55a(g)(6)(i) 1CAN099905, Submits Supplemental Info in Support of SG Outer Diameter Intergranular Attack Alternate Repair Criteria.Proposed TS Rev & Info Related to Use of Alternate Repair Discussed in Attachments1999-09-17017 September 1999 Submits Supplemental Info in Support of SG Outer Diameter Intergranular Attack Alternate Repair Criteria.Proposed TS Rev & Info Related to Use of Alternate Repair Discussed in Attachments ML20212D9961999-09-16016 September 1999 Informs That on 990818,NRC Completed Midcycle PPR of Arkansas Nuclear One.Nrc Plan to Conduct Core Insps at Facility Over Next 7 Months.Details of Insp Plan Through March 2000 Encl 1CAN099902, Forwards Proprietary Rev 1 to Topical Rept BAW-10235P, Mgt Program for Volumetric Outer Diameter Intergranular Attack in Tubesheets of Once-Through Sgs, in Response to 990831 Rai.Proprietary Encl Withheld1999-09-15015 September 1999 Forwards Proprietary Rev 1 to Topical Rept BAW-10235P, Mgt Program for Volumetric Outer Diameter Intergranular Attack in Tubesheets of Once-Through Sgs, in Response to 990831 Rai.Proprietary Encl Withheld 2CAN099905, Informs That Jk Caery,License OP-42589 & as Bates,License OP-42506,no Longer Need to Maintain Operating License at Ano,Unit 2.Withdrawal of Licenses Is Requested1999-09-0909 September 1999 Informs That Jk Caery,License OP-42589 & as Bates,License OP-42506,no Longer Need to Maintain Operating License at Ano,Unit 2.Withdrawal of Licenses Is Requested 1CAN099901, Forwards Responses to 990831 RAI Containing follow-up Questions Discussed on 990823-26,in Support of SG Outer Diameter Intergranular Attack Alternate Repair Criteria. Revs to Proposed TSs Included in Attachments1999-09-0707 September 1999 Forwards Responses to 990831 RAI Containing follow-up Questions Discussed on 990823-26,in Support of SG Outer Diameter Intergranular Attack Alternate Repair Criteria. Revs to Proposed TSs Included in Attachments ML20211P4121999-09-0707 September 1999 Requests NRC Staff Review & Approval of Integrated Nuclear Security Plan (Insp) & Integrated Security Training & Qualification Plan (Ist&Q), for Use by All Entergy Operations,Inc.Encl Withheld,Per 10CFR2.790(d) 0CAN099906, Forwards Comments on Ano,Units 1 & 2 Specific Reactor Vessel Info Contained in Rvid,Version 2,in Response to NRC 990708 & 0715 Ltrs1999-09-0101 September 1999 Forwards Comments on Ano,Units 1 & 2 Specific Reactor Vessel Info Contained in Rvid,Version 2,in Response to NRC 990708 & 0715 Ltrs ML20211L4901999-09-0101 September 1999 Forwards Insp Repts 50-313/99-12 & 50-368/99-12 on 990711- 0821.No Violations Noted ML20211J2351999-08-31031 August 1999 Forwards Request for Addl Info Re SG Outer Diameter Intergranular Attack Alternate Repair Criteria for Plant, Unit 1 ML20211E6161999-08-25025 August 1999 Forwards Amend 15 to ANO Unit 2,USAR,per 10CFR50.71(e) & 10CFR50.4(b)(6).Summary of 10CFR50.59 Evaluations Associated with Amend 15 of ANO Unit 2 SAR Will Be Provided Under Separate Cover Ltr with 30 Days 0CAN089905, Forwards Arkansas Nuclear One Units 1 & 2 FFD Program Performance Data for Period Jan-June 19991999-08-25025 August 1999 Forwards Arkansas Nuclear One Units 1 & 2 FFD Program Performance Data for Period Jan-June 1999 ML20211F4181999-08-25025 August 1999 Forwards SE Accepting Licensee 980603 & 990517 Requests for Approval of risk-informed Alternative to 1992 Edition of ASME BPV Code Section Xi,Insp Requirements for Class 1, Category B-J Piping Welds ML20211G0731999-08-19019 August 1999 Forwards Applications for Renewal of Operating License for Kw Canitz & Aj South.Without Encls 1CAN089904, Forwards Addl Info in Support of SG Tube End Cracking Alternate Repair Criteria,In Response to NRC 990728 Rai. Proposed TS Changes Encl1999-08-19019 August 1999 Forwards Addl Info in Support of SG Tube End Cracking Alternate Repair Criteria,In Response to NRC 990728 Rai. Proposed TS Changes Encl ML20211C5101999-08-19019 August 1999 Forwards Certified Copies of Liability Insurance Policy Endorsements Issued in First Half of 1999 for Each Entergy Operations,Inc Nuclear Unit,Per 10CFR140.15 ML20211A9501999-08-12012 August 1999 Discusses 990720-21 Workshop Conducted in Region IV Ofc,Re Exchange of Info in Area of Use of Risk Insights in Regulatory Activities.List of Attendees,Summary of Topic & Issues,Agenda & Copies of Handouts Encl 0CAN089903, Submits Addl Response to NRC Second RAI Re GL 95-07, Pressure Locking & Thermal Binding of Gate Valves1999-08-12012 August 1999 Submits Addl Response to NRC Second RAI Re GL 95-07, Pressure Locking & Thermal Binding of Gate Valves IR 05000368/19990111999-08-12012 August 1999 Forwards Insp Repts 50-313//99-11 & 50-368/99-11 on 990719-23.No Violations Noted.Insp Focused on Review of Licensed Operator Requalification Program & Observation of Requalification Exam Activities at Unit 1 2CAN089901, Forwards Description of Planned Scope & Expansion Criteria for Special SG Tube Insp,In Support of Proposed ANO-2 TS Amend for 2P99 Special SG Insp Submitted on 9907291999-08-0606 August 1999 Forwards Description of Planned Scope & Expansion Criteria for Special SG Tube Insp,In Support of Proposed ANO-2 TS Amend for 2P99 Special SG Insp Submitted on 990729 1CAN089902, Requests NRC Input on Encl Proposed Draft Format for ANO-1 License Renewal Application,Which Will Provide Option to Continue Operating Plant for Addl Twenty Years Beyond End of Current Operating License1999-08-0505 August 1999 Requests NRC Input on Encl Proposed Draft Format for ANO-1 License Renewal Application,Which Will Provide Option to Continue Operating Plant for Addl Twenty Years Beyond End of Current Operating License 2CAN089902, Informs That Tl Russell,License SOP-43587-1 & Jk Fancher, License OP-42300-1,no Longer Have Need to Maintain Operating License at ANO-2.Withdrawal of Licenses Requested1999-08-0404 August 1999 Informs That Tl Russell,License SOP-43587-1 & Jk Fancher, License OP-42300-1,no Longer Have Need to Maintain Operating License at ANO-2.Withdrawal of Licenses Requested ML20210L1461999-08-0303 August 1999 Informs That NRC Plans to Administer Gfes of Written Operator Licensing Exam on 991006.Requests Submittal of Ltr Identifying Individuals Taking Exam,Personnel Allowed Access to Exams & Mailing Address for Exams 0CAN089902, Submits 60 Day Response to GL 99-02, Laboratory Testing of Nuclear Grade Activated Charcoal. Proposed Actions That Will Be Taken on ANO Unit 1 RB Purge Filtration Sys & Unit 2 Containment Purge & Exhaust Sys,Clarified1999-08-0202 August 1999 Submits 60 Day Response to GL 99-02, Laboratory Testing of Nuclear Grade Activated Charcoal. Proposed Actions That Will Be Taken on ANO Unit 1 RB Purge Filtration Sys & Unit 2 Containment Purge & Exhaust Sys,Clarified 0CAN089901, Forwards Info Re Estimate of licensee-originated Licensing Actions for ANO-1 & ANO-2,in Response to Administrative Ltr 99-02,dtd 9906031999-08-0202 August 1999 Forwards Info Re Estimate of licensee-originated Licensing Actions for ANO-1 & ANO-2,in Response to Administrative Ltr 99-02,dtd 990603 ML20210L3581999-07-29029 July 1999 Ltr Contract,Task Order 43, Arkansas Nuclear One Safety System Engineering Insp (Ssei), Under Contract NRC-03-98-021 1CAN079903, Forwards non-proprietary Addendum to Rev 0 of Topical Rept BAW-2346P,in Support of Proposed TS Changes Revising SG Tubing Surveillance Requirements to Provide Alternate Repair Criteria for Tube End Cracks1999-07-29029 July 1999 Forwards non-proprietary Addendum to Rev 0 of Topical Rept BAW-2346P,in Support of Proposed TS Changes Revising SG Tubing Surveillance Requirements to Provide Alternate Repair Criteria for Tube End Cracks ML20216D8131999-07-28028 July 1999 Forwards Request for Addl Info Re SG Tube End Cracking Alternate Repair Criteria for Plant,Unit 1 ML20216D3561999-07-23023 July 1999 Discusses non-cited Violation Identified in Insp Rept 50-313/98-21,involving Failure to Have Acceptable Alternative Shutdown Capability for ANO-1 ML20210C2191999-07-21021 July 1999 Forwards Insp Repts 50-313/99-08 & 50-368/99-08 on 990530-0710 at Arkansas Nuclear One,Units 1 & 2,reactor Facility.No Violations Noted.Conduct of Activities at Plant Generally Characterized by safety-conscious Operations ML20209H5251999-07-15015 July 1999 Informs That as Result of NRC Review of Licensee 980701 & 990311 Responses to GL 92-01,rev 1 & Suppl 1 & Suppl 1 RAI, Staff Revised Info in Reactor Vessel Integrity Database & Releasing Database as Rvid Version 2 1CAN079901, Forwards Proposed Changes to Current Util 990409 Submittal Re Rev to RB Structural Integrity Requirements Contained in Plant Ts.Proposed Revs Affect ACs & Applicable Bases Re ISI Reporting for Containment Structures,Tendons & Anchorages1999-07-14014 July 1999 Forwards Proposed Changes to Current Util 990409 Submittal Re Rev to RB Structural Integrity Requirements Contained in Plant Ts.Proposed Revs Affect ACs & Applicable Bases Re ISI Reporting for Containment Structures,Tendons & Anchorages 0CAN079902, Responds to NRC Telcon RAI Re Proposed Administrative Controls TS Changes.Revised TS Pages Which Replaces Pages Previously Provided in 981124 Submittal,Encl1999-07-14014 July 1999 Responds to NRC Telcon RAI Re Proposed Administrative Controls TS Changes.Revised TS Pages Which Replaces Pages Previously Provided in 981124 Submittal,Encl ML20209E5551999-07-0808 July 1999 Informs That as Result of NRC Review of Util Responses to GL 92-01,rev 1,suppl 1,staff Revised Info in Rv Integrity Database & Releasing Database as Rvid Version 2 1999-09-09
[Table view] Category:OUTGOING CORRESPONDENCE
MONTHYEARML20217J4971999-10-18018 October 1999 Requests Addl Info Re Results of Util Most Recent Steam Generator Insp at ANO-2 & Util Methodology Used to Predict Future Performance of SG Tubes ML20217J3871999-10-15015 October 1999 Informs That Topical Rept BAW-10235P, Management Program for Volumetric Outer Diameter Intergranular Attack in Tubesheets of Once-Through SG, Rev 0 Marked as Proprietary Will Be Withheld from Public Disclosure ML20217J3601999-10-15015 October 1999 Informs That Topical Rept BAW-10235P, Management Program for Volumetric Outer Diameter Integranular Attack in Tubesheets of Once-Through SG, Rev 1 Marked as Proprietary Will Be Withheld from Public Disclosure ML20217D1721999-10-0808 October 1999 Forwards RAI Re 990729 Request for Amend to TSs Allowing Special SG Insp for Plant,Unit 2.Questions Re Proposed Insp Scope for Axial Cracking Degradation in Eggcrate Support Region Submitted.Response Requested by 991015 ML20212L0621999-10-0101 October 1999 Forwards Safety Evaluation & Exemption from Certain Requirements of 10CFR50,App R,Section III.G.2, Fire Protection of Safe Shutdown Capability ML20212F5031999-09-22022 September 1999 Forwards SER Granting Relief Requests 1-98-001 & 1-98-002 Which Would Require Design Mods to Comply with Code Requirements,Which Would Impose Significant Burden Pursuant to 10CFR50.55a(g)(6)(i) ML20212D9961999-09-16016 September 1999 Informs That on 990818,NRC Completed Midcycle PPR of Arkansas Nuclear One.Nrc Plan to Conduct Core Insps at Facility Over Next 7 Months.Details of Insp Plan Through March 2000 Encl ML20211L4901999-09-0101 September 1999 Forwards Insp Repts 50-313/99-12 & 50-368/99-12 on 990711- 0821.No Violations Noted ML20211J2351999-08-31031 August 1999 Forwards Request for Addl Info Re SG Outer Diameter Intergranular Attack Alternate Repair Criteria for Plant, Unit 1 ML20211F4181999-08-25025 August 1999 Forwards SE Accepting Licensee 980603 & 990517 Requests for Approval of risk-informed Alternative to 1992 Edition of ASME BPV Code Section Xi,Insp Requirements for Class 1, Category B-J Piping Welds IR 05000368/19990111999-08-12012 August 1999 Forwards Insp Repts 50-313//99-11 & 50-368/99-11 on 990719-23.No Violations Noted.Insp Focused on Review of Licensed Operator Requalification Program & Observation of Requalification Exam Activities at Unit 1 ML20211A9501999-08-12012 August 1999 Discusses 990720-21 Workshop Conducted in Region IV Ofc,Re Exchange of Info in Area of Use of Risk Insights in Regulatory Activities.List of Attendees,Summary of Topic & Issues,Agenda & Copies of Handouts Encl ML20210L1461999-08-0303 August 1999 Informs That NRC Plans to Administer Gfes of Written Operator Licensing Exam on 991006.Requests Submittal of Ltr Identifying Individuals Taking Exam,Personnel Allowed Access to Exams & Mailing Address for Exams ML20210L3581999-07-29029 July 1999 Ltr Contract,Task Order 43, Arkansas Nuclear One Safety System Engineering Insp (Ssei), Under Contract NRC-03-98-021 ML20216D8131999-07-28028 July 1999 Forwards Request for Addl Info Re SG Tube End Cracking Alternate Repair Criteria for Plant,Unit 1 ML20210C2191999-07-21021 July 1999 Forwards Insp Repts 50-313/99-08 & 50-368/99-08 on 990530-0710 at Arkansas Nuclear One,Units 1 & 2,reactor Facility.No Violations Noted.Conduct of Activities at Plant Generally Characterized by safety-conscious Operations ML20209H5251999-07-15015 July 1999 Informs That as Result of NRC Review of Licensee 980701 & 990311 Responses to GL 92-01,rev 1 & Suppl 1 & Suppl 1 RAI, Staff Revised Info in Reactor Vessel Integrity Database & Releasing Database as Rvid Version 2 ML20209E5551999-07-0808 July 1999 Informs That as Result of NRC Review of Util Responses to GL 92-01,rev 1,suppl 1,staff Revised Info in Rv Integrity Database & Releasing Database as Rvid Version 2 ML20209D8521999-07-0707 July 1999 Responds to Util 990706 Request That NRC Exercise Discretion Not to Enforce Compliance with Actions Required by TS 3.7.2, Auxiliary Electrical Sys. NOED Warranted & Approval Granted for Extension of Allowed Outage Time to 14 Days ML20209A8561999-06-25025 June 1999 Refers to Investigation Rept A4-1998-042 Re Potential Falsification of Training Record by Senior Licensed Operator at Arkansas Nuclear One Facility.Nrc Concluded That Training Attendance Record Falsified IR 05000313/19990071999-06-21021 June 1999 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Repts 50-313/99-07 & 50-368/99-07 Issued on 990514.Adequacy of Min Staffing Levels May Be Reviewed During Future Insps ML20196D4241999-06-21021 June 1999 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp of License SOP-43716 Issued on 990325.Believes That NRC Concerns Have Been Adequately Addressed at Present ML20207H3551999-06-10010 June 1999 Forwards Insp Repts 50-313/99-05 & 50-368/99-05 on 990411-0529.No Violations Noted ML20195G3481999-06-0909 June 1999 Ack Receipt of ,Transmitting Changes to Facility Emergency Plan,Rev 25,under Provisions of 10CFR50,App E, Section V IR 05000313/19993011999-06-0909 June 1999 Discusses Arrangements for Administration of Licensing Exam During Wk of 991213,per Telcon of 990602.As Agreed,Exams Repts 50-313/99-301 & 50-368/99-301 Will Be Prepared Based on Guidelines in Rev 8 of NUREG-1021 ML20195F1631999-06-0808 June 1999 Forwards Insp Repts 50-313/99-06 & 50-368/99-06 on 990524-28.Violation Identified & Being Treated as Noncited Violation ML20207G3111999-06-0707 June 1999 Ack Receipt of Changes to ANO EP Implementing Prcoedure 1903.010,Emergency Action Level Classification,Rev 34 PC-2, Received on 981218,under 10CFR50,App E,Section V Provisions. No Violations Identified ML20207G7951999-06-0707 June 1999 Forwards Notice of Violation Re Investigation Rept A4-1998-042 Re Apparent Violation Involving Initialing Record to Indicate Attendance at Required Reactor Simulator Training Session Not Attended ML20207E7131999-06-0202 June 1999 Discusses EOI 990401 Request for Alternative to Requirements of Iwl for Arkansas Nuclear One,Pursuant to 10CFR50.55a(g)(6)(ii)(B) & ASME BPV Code Section XI & Forwards Safety Evaluation Accepting Proposed Alternative ML20207B9521999-05-26026 May 1999 Discusses GL 98-04, Potential for Degradation of ECCS & CSS After LOCA Because of Const & Protective Coating Deficiencies & Foreign Matl in Containment. Staff Will Conduct Limited Survey in to Identify Sampling ML20207B4171999-05-24024 May 1999 Forwards Corrected Cover Ltr to Insp Repts 50-313/99-07 & 50-368/99-07 Issued 990514 with Incorrect Insp Closing Date ML20207A7771999-05-24024 May 1999 Forwards Insp Repts 50-313/98-21 & 50-368/98-21 on 981116-990406.One Violation of NRC Requirements Occurred & Being Treated as Noncited Violation,Consistent with App C of Enforcement Policy ML20206U4541999-05-17017 May 1999 Discusses Util & Suppl Re Changes to License NPF-06,App a TSs Bases Section.Staff Offers No Objection to These Bases Changes.Affected Bases Pages,B 202, B 2-4,B 2-7,B 3/4 2-1,B 3/4 2-3 & B 3/4 6-4,encl ML20206S4721999-05-14014 May 1999 Forwards Insp Repts 50-313/99-07 & 50-368/99-07 on 990426- 30.No Violations Noted.However,Nrc Requests That Util Provide Evaluation of Licensee Provisions to Maintain Adequate Level of Response Force Personnel on-site ML20207B4271999-05-14014 May 1999 Corrected Ltr Forwarding Insp Repts 50-313/99-07 & 50-368/99-07 on 990426-30.No Violations Noted.Areas Examined During Insp Included Portions of Physical Security Program ML20206R4741999-05-13013 May 1999 Informs That Staff Reviewed Draft Operation Insp Rept for Farley Nuclear Station Cooling Water Pond Dam & Concurs with FERC Findings.Any Significant Changes Made Prior to Issuance of Final Rept Should Be Discussed with NRC ML20206N7011999-05-12012 May 1999 Informs That NRC Office of Nuclear Reactor Regulation Reorganized Effective 990328.As Part of Reorganization, Division of Licensing Project Management Created ML20206M7581999-05-11011 May 1999 Forwards SE Accepting Relief Request from ASME Code Section XI Requirements for Plant,Units 1 & 2 ML20206S1761999-05-11011 May 1999 Responds to Informing of Changes in Medical Condition & Recommending License Restriction for Senior Reactor Operator.No Change Was Determined in Current License Conditions for Individual ML20206N4161999-05-11011 May 1999 Discusses Completion of Licensing Action for GL 96-01, Testing of Safety-related Logic Circuits, for Plant,Units 1 & 2 ML20206S4211999-05-10010 May 1999 Forwards Insp Repts 50-313/99-04 & 50-368/99-04 on 990228- 0410.Four Violations of NRC Requirements Identified & Being Treated as Noncited Violations Consistent with App C of Enforcement Policy ML20206H1031999-05-0606 May 1999 Forwards Results of Gfes of Written Operator Licensing Exam, Administered on 990407,to Nominated Employees of Facility. Requests That Training Dept Forward Individual Answer Sheet & Results to Appropriate Individuals.Without Encl ML20206F0611999-04-29029 April 1999 Forwards SE Accepting Licensee Re ISI Plan for Third 10-year Interval & Associated Requests for Alternatives for Plant,Unit 1 ML20205R6331999-04-20020 April 1999 Ack Receipt of Which Transmitted Rev 39 to ANO Industrial Security Plan,Submitted Under Provisions of 10CFR50.54(p).No NRC Approval Is Required,Since Util Determined Changes Do Not Decrease Effectiveness of Plan ML20205P4641999-04-15015 April 1999 Forwards for Review & Comment Draft Info Notice That Describes Unanticipated Reactor Water Draindown at Quad Cities Nuclear Power Station Unit 2,Arkansas Nuclear One Unit 2 & Ja Fitzpatrick NPP ML20205N7251999-04-13013 April 1999 Forwards Summary of 990408 Meeting with EOI in Jackson, Mississippi Re EOI Annual Performance Assessment of Facilities & Other Issues of Mutual Interest.List of Meeting Attendees & Licensee Presentation Slides Encl ML20205M6881999-04-12012 April 1999 Forwards Safety Evaluation on Second 10-year Interval Inservice Insp Request Relief 96-005 ML20205L7711999-04-0909 April 1999 Forwards Insp Repts 50-313/99-03 & 50-368/99-03 on 990202- 17.No Violations Noted ML20205K7681999-04-0606 April 1999 Forwards RAI Re risk-informed Alternative to Certain Requirements of ASME Code 11,table IWB-2500-1 ML20205G8871999-04-0202 April 1999 Forwards RAI Re GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Movs, for Plant, Units 1 & 2.Response Requested within 60 Days of Date of Ltr 1999-09-22
[Table view] |
Text
.. ..
a Mr. C. R*ndy Hutchins:n April 3, 1998
., Vice. President, Operations ANO Entergy Operations, Inc.
1448 S. R. 333 Russellville, AR 72801 -
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION PERTAINING TO INDIVIDUAL PLANT EXAMINATION OF EXTERNAL EVENTS (IPEEE) FOR ARKANSAS NUCLEAR ONE, UNITS 1 AND 2 (TAC NOS. M83588 AND M83589)
Dear Mr. Hutchinson:
I This is a request for additional information pertaining to the Individual Plant Examination of (
Extemal Events (IPEEE) submitted for Arkansas Nuclear One, Units 1 and 2. The staff's 1 questions on this matter are enclosed. Please contact me if you have any questions regarding this request for information.
Sincerely, ORIGINAL SIGNED BY:
William Reckley, Project Manager Project Directorate IV-1 Division of Reactor Projects lil/IV Office of Nuclear Reactor Regulation Docket Nos. 50-313 and 50-368
Enclosure:
Request for AdditionalInformation cc w/encls: See next page DISTRIBUTION:
Docket File PUBLIC PD4-1 r/f WReckley CHawes OGC \
.ACRS TGwynn, RIV EAdensam (EGA1) \
Jhannon ARubin (RES)
Document Name: AR83588.RAI OFC PM/PD4-1 LA/PD4-1 PD/PDIV-1
,y !
NAME WReckle CHawedl)N JHannorOh DATE Y/ 3 /98 4/1/98 Y/)/h8b COPY YES/NO YES/NO YES/NO OFFICIAL RECORD COPY .
1 o.O gg [T] ((j'{} QT5y 9804070349 900403 PDR ADOCK 05000313 i P PDR i
ME vq
- c. #1 UNITED STATES y
'2
} NUCLEAR RECULATORY COMMISSION WASHINGTON, D.C. 20066-0001
'+, . . '. . . ,o! April 3, 1998 Mr. C. Randy Hutchinson Vice President, Operations ANO Entergy Operations, Inc.
1448 S. R. 333 Russellville, AR 72801
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION PERTAINING TO INDIVIDUAL PLANT EXAMINATION OF EXTERNAL EVENTS (IPEEE) FOR ARKANSAS NUCLEAR ONE, UNITS 1 AND 2 (TAC NOS. M83588 AND M83589)
Dear Mr. Hutchinson:
This is a request for additional information pertaining to the Individual Plant Examination of Extemal Events (IPEEE) submitted for Arkansas Nuclear One, Units 1 and 2. The staff's questions on this matter are enclosed. Please contact me if you have any questions regarding this request for information.
I Sincerely, l 4
W bc William Reckley, Project Man r Project Directorate IV-1 Division of Reactor Projects lil/IV Office of Nuclear Reactor Regulation Docket Nos. 50-313 and 50-368
Enclosure:
Request for AdditionalInformation cc w/encts: See next page i
e .
Mr. C. Rrndy Hutchinson
- Entergy Operations, Inc. Arkansas Nuclear One, Units 1 & 2 cc:
Executive Vice President Vice President, Operations Support
& Chief Operating ONicer Entergy Operations, Inc.
Entergy Operations, Inc. P. O. Box 31995 P. O. Box 31995- Jackson, MS 39286-1995 Jackson, MS 39286-1995 Wise, Carter, Child & Caraway Director, Division of Radiation P. O. Box 651 Control and Emergency Management Jackson, MS 39205 Arkansas Department of Health 4815 West Markham Street, Slot 30
' Little Rock, AR 72205-3867 '
Winston & Strawn 1400 L Street, N.W.
Washington, DC 20005-3502 Manager, Rockville Nuclear Licensing Framatone Technologies 1700 Rockville Pike, Suite 525 Rockville, MD 20852 Senior Resident inspector U.S. Nuclear Regulatory Commission P. O. Box 310 London, AR 72847 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-8064 County Judge of Pope County Pope County Courthouse Russellville, AR 72801
ARKANSAS NUCLEAR ONE Request For Additional Information on IPEEE Submittal Seismic ,
(RAls 1, 2 and 3 apply to both ANO IPEEE submittels for units 1 and 2 while RAI 4 applies only to the Unit 2 submittal. However, if the responses to RAls 1,2 or 3 differ for the two units, please explain these differences.)
- 1. Although a table is provided in the IPEEE submittals for the systems " selected for i controlling safe shutdown systems" (Table 3.9-1), the submittals do not provide any discussion of the selected systems and the various operating modes of these systems required for a successful shutcown of the plant after a review level earthquake (RLE).
Non-seismic failures and human action issues as described in NUREG-1407 are also not provided in sufficient detail. The discussions related to supporting systems are also very f
~ brief.
(a) Please provide, as described in EPRI NP-6041, two plant specific success path logic diagrams (SPLDs)- one for transients wherein the reactor coolant system pressure boundary is intact and the other for a seismically induced small LOCA.
Please discuss in some detail the systems and the operating modes of these systems used in the SPLDs. Please include in the discussion the requirement on the recirculation modes of operation of the ECCS and the ways these are met at ANO, and any requirements for feed-and-bleed cooling (or once through cooling) in the success paths. Please identify the needed human actions, including consideration of their failure probabilities, in the selection of the success paths.
I (b) Please address the non-seismic failure issue as described in NUREG-1407.
Please include in the discussion the reliance on the turbine-driven emergency feedwater (EFW) system for decay heat removal. The non-seismic failure issue is important if single train systems with recognized poor availability are used in a success path (e.g., the turbine-driven EFW pump is used in one of the selected success paths). l (c) For the Service Water System the submittals state that "The system takes suction from Lake Dardanelle." Please discuss the effects of an RLE on the availability of the service water system. Please include in the discussion the effects of the RLE on the availability of the lake water (e.g., the effect of the RLE on the dam).
According to the IPE submittal, the Service Water System can also take suction from the Emergency Cooling Pond. Please discuss whether this water source is considered in the IPEEEs, and if it is, then discuss the operator actions involved and, if the pond is shared by the both units at the site, the multi-unit effect on the capability of the pond (e.g., heat capacity of the pond).
1 ENCLOSURE
Ple:se describe cny diff;rences in the Service W;t:r Syst:ms of the two units
, which could impact the IPEEE analyses, such as their ability to take suction from Lake Dardanelle in case of dem failure.
(d) Please provide the dependency matrix for the systems used in the success paths and include a description of the support systems listed in the dependency matrix.
- 2. As stated in both submittals, some steps in the emergency operating procedures (EOPs) were credited if the task could be accomplished using remote or local manual operation. Please identify the EOP steps that involve local manual operation. Please identify and discuss the locations of and the timing allowed for these actions, and provide an assessment of the success rate of these actions (taking into consideration the RLE conditions).
- 3. As indicated in the ANO IPEEE submittals, a significant number of outliers were identified during the combined IPEEE/USI A-46 seismic walkdown and evaluation effort. t Tables 1-2 and 7-1 summarize the " Major Findings" and " Opportunities for Plant '
Improvements," respectively.
Table 3.5-1 lists the high confidence of low probability of failure (HCLPF) capacity of emergency diesel fuel tanks T-57A and T-57B (2T-57A and 2T47B for Unit 2) as 0.2g.
These tanks control the plant HCLPF capacity and are identified as " Opportunities for Plant Improvement" in Table 7-1.
Please provide an update on the status of the resolution of all outliers, including any plant modifications which have been implemented; any additional plant modifications which are currently scheduled (include implementation schedule); other outlier resolutions and their basis (e.g., structural analysis, systems analysis, etc.); and any currently unresolved outliers. For currently unresolved outliers, please identify the plan and schedule for resolution.
Please update the plant HCLPF capacity to reflect afforts to date to resolve the outliers, and also estimate the plant HCLPF capacity after completion of all planned outlier resolution activities. ,
l
- 4. Please clarify the following items related to the selection of components on the safe shutdown equipment list (SSEL) (Regarding Unit 2 only):
(a) According to the IPE submittal section entitled Success Criteria and Major Assumptions for the Emergency Feedwater (EFW) System, " Operation of the l solenoid bypass valve 2SV-0205 is assumed to be required for successful operation of the 2P7A turbine....... Room cooling is assumed to be required for successful operation of either EFW pump. The SW supply valves 2CV-1529-1 and 2CV-1532-1 must open and remain open and the fans 2VUC4A and 2VUC-6B must start and remain running." Although the fans, 2VUC 6A and 2VUC-68, are included in the SSEL, the valves mentioned above are not. Please discuss 2
the rers:ns for not including these v;lv;s in the SSEL. Also, discuss the effects of the much longer mission time for IPEEE (than for IPE) on the requirement of )
pump room cooling and thus the selection of the SSEL. l (b) The ECCS pumps take suction from the refueling water tank (RWT) in the injection mode. There are two RWT discharge valves for the two trains of the ECCS systems,2CV 5630-1 and 2CV-5631-2. Please discuss why the valve for l
Train B (2CV-5631-2) is not included in the SSEL while the valve for Train A (2CV-5630-1) is included in the SSEL.
(c) The injection valves for the two high pressure injection (HPI) trains are 2CV-5103-1 and 2CV-5104-2 (for Train A and Train B, respectively). Although the pumps for both trains (2P-89A and 2P-898) are included in the SSEL, only the injection valve for Train A (2CV-5013-1) is included in the SSEL. Please discuss the effect of the valve on the various operating modes of the system and the reason for not including the valve for Train B (2CV 5014-2) in the SSEL.
f 3
l Fire
- 1. It is important that human error probabilities (HEPs) associated with plant recovery actions used in the screening phase of the fire analysis properly reflect the potential effects of fire (e.g. smoke, heat, loss of lighting, etc.). HEPs that are appropriate with respect to intamal events may not be appropriate in the context of a given fire scenario.
For example, certain recovery actions credited in the interre! events analysis may not be possible or credible given certain fires if the action requires accs:. to or passage through the impacted fire area. Such actions should not be credited in the analysis. l Also, the likelihood of human error will increase under fire conditions due to increased stress levels, loss of visibility due to smoke, and/or degraded communications.
Please identify any areas that were screened out of the fire analysis for which the screening assessment included one or more HEPs. For each such area discuss how the effects of fire were considered in the development of the HEPs used in the screening analysis. If fire effects were not considered, then please reassess the corcioution of these areas to plant fire risk when the impact of fire on HEPs is included. ,
Given this reassessment, identify any plant areas that would have survived the screening process given modified HEPs and provide an assessment of the contribution of these areas to the plant CDF.
- 2. NUREG-1407., Section 4.2 and Appendix C, and GL 88-20, Supplement 4, request that documentation be submitted with the IPEEE submittal with regard to the Fire Risk Scoping Study (FRSS) issues, including the basis and assumptions used to address these issues,i sd a discussion of the findings and conclusions. NUREG-1407 also requests that .luation results and potential improvements be specifically highlighted.
Control systex .nteractions involving a combination of fire-induced failures and high )
probability random equipment failures were identified in the FRSS as potential contributors to fire risk.
The issue of control systems interactions is associated primarily with the potential that a l' fire in the plant (e.g., the main control room [MCR]) might lead to potential control systems vulnerabilities. Given a fire in the plant, the likely sources of control systems interactions could happen between the control room, the remote shutdown panel, and shutdown systems. Specific areas that have been identified as requiring attention in the resolution of this issue include:
(a) Electricalindependence of the remote shutdown control systems: The primary concern of control systems interactions occurs at plants that do not provide independent remote shutdown control systems. The electricalindependence of the remote shutdown panel and the evaluation of the level of indication and control of remote shutdown control and monitoring circuits need to be assessed.
(b) Loss of control equipment or power before transfer: The potential for loss of control power for certain control circuits as a result of hot shorts and/or blown fuses before transferring control from the MCR to remote shutdown locations I needs to be assessed.
4 I
_, (c) Spurious actuation of components leading to component damage, loss-of-coolant accident (LOCA), or interfacing systems LOCA: The spurious actuation of one or more safety-related to safe-shutdown-related components as a result of fire-induced cable faults, hot shorts, or component failures leading to component damage, LOCA, or interfacing systems LOCA, prior to taking control from the remote shutdown panel, needs to be assessed. This assessment also needs to include the spurious starting and running of pumps as well as the spurious repositioning of valves.
(d) Total loss of system function: The potential for total loss of system function as a result of fire-induced redundant component failures or electrical distribution system (power source) failure needs to be addressed.
Please describe your remote shutdown capability, including the nature and location of the shutdown station (s), as well as the types of control actions which can be taken
- from the remote panel (s). Describe how your procedures provide for transfer of g control to the remote station (s). Provide an evaluation of whether loss of control power due to hot shorts and/or blown fuses could occur prior to transfarring control to the remote shutdown location and identify the risk contribution of these types of failures (if these failures are screened, please provide the besis for the screening).
Finally, provide an evaluation of whether spurious actuation of components as a result of fire-induced cable faults, hot shorts, or component failures could lead to component damage, a LOCA, or an interfacing systems LOCA prior to taking control from the remote shutdown panel (considering both spurious starting and running of pumps as well as the spurious repositioning of valves).
- 3. In the EPRI Fire PRA Implementation Guide, test results for the control cabinet heat release rates have been misinterpreted and have been inappropriately extrapolated.
Cabinet heat release rates as low as 65 Btu /sec are used in the Guide. In contrast, experimental work has developed heat release rates ranging from 23 to 1171 Btu /sec.
Considering the range of heat release rates that could be applicable to different control cabinet fires, and to ensure that cabinet fire areas are not prematurely screened out of the analysis, a heat release rate in the mid-range of the currently available experimental data (e.g.,550 Btu /sec) should be used for the analysis.
Discuss the heat release rates used in your assessment of control cabinet fires.
Please provide a discussion of changes in the IPEEE fire assessment results if it is assumed that the heat release from a cabinet fire is increased to 550 Btu /sec.
- 4. Tiie heat loss factor is defined as the fraction of energy released by a fire that is transferred to the enclosure boundaries. This is a key parameter in the prediction of component damage, as it determines the amount of heat available to the hot gas layer.
In Fire-Induced Vulnerability Evaluation (FIVE), the heat loss factor is modeled as inversely related to the amount of heat required to cause a given temperature rise.
Thus, for example, a larger heat loss factor means that a larger amount of heat (due to 5
l
]
a m:ro sev2ra fira, e longer buming time, or both) is needed to cause o given temperature rise. It can be seen that if the value assumed for the heat loss fador is unrealistically high, fire scenarios can be improperly screened out. Figure A.1 provides a representative example of how hot gas layer temperature predictions can char.ge assuming differe.nt heat loss factors. Note that: 1) the curves are computed for a 1000 kW fire in a 10m x Sm x 4m compartment with a forced ventilation rate of 1130 cfm; 2) the FIVE-recommended damage temperature for qualified cable is 700'F for qualified cable and 450'F for unqualified cable; and, 3) the SFPE curve in the figure is generated from a correlation provided in the Society for Fire Protection Engineers Handbook [A.1].
Based on evidence provided by a 1982 paper by Cooper et al. [A.2], the EPRI Fire PRA Implementation Guide recommends a heat loss factor of 0.94 for fires with durations greater than five minutes and 0.85 for " exposure fires away from a wall and quickly developing hot gas layers." However, as a general statement, this appears to be a misinterpretation of the results. Reference [A.2], which documents the results of multi-compartment fire experiments, states that the higher heat loss factors are associated with the movement of the hot gas layer from the buming compartment to adjacent, f cooler compartments. Earlier in the experiments, where the hot gas layer is limited to the burning compartment, Reference [A.2] reports much lower heat loss factors (on the order of 0.51 to 0.74). These lower heat loss factors are more appropriate when analyzing a single compartment fire. In summary, (a) hot gas layer predictions are very sensitive to the assumed va!ae of the heat loss factor; and (b) large heat loss factors cannot be justified for single-room scenarios based on the information referenced in the EPRI Fire PRA Impiamentation Guide.
For each scenario where the hot gas layer temperature was calculated, please specify the heat loss factor used in the analysis. The EPRI FIVE methodology, which was accepted by the USNRC for use in the IPEEE assessments, recommended the use of 0.7 for the heat loss factor (see FIVE Section 10.4, page 10.4-21). For any fire scenario frequency estimates if the analysis is performed consistent with the FIVE methodology that used a heat loss factor larger than 0.7, please assess the impact on core damage frequency.
6
Tim 3 Tcmperature curves 800 , , ,
m .
p 8N "
800 . - 7 e --e M = 0.70 700 g ,
,7 ,} ' , $ + M = 0.85 E 000 - ', , . ..T . , ,' + M = 0.94 ,
soo . ,. I. .
p-x U " N -
. a- .
u%
u,,.
- * ~. -
300. ,
200 100 ym,x x xm.xax:x$*MM ****'#*
~
0$$$$$$$$!!!$$$ Time (e)
Figure A.1 Sensitivity of the hot gas layer temperature predictions to the assumed heat loss factor.
A.1 P.J. DiNenno, et al, eds.,'SFPE Handbook of Fire Protection Engineering,"
2nd Edition National Fire Protection Associction, p. 3-140,1995 A.2 L. Y. Cooper, M. Harkleroad, J. Quintiere, W. Rinkinen, "An Experimental Study of Upper Hot Layer Stratification in Full-Scale Multiroom Fire Scenarios," ASME Joumal of Heat Transfer, .1E,741-749, November 1982.
- 5. The submittal indicates that some fire areas contain elements of both units. For example, Fire Areas B and G appear to be shared by both units. For multi-unit sites, there are three issues of potentialinterest. Hence, please answer the following:
(a) A fire in a shared area might cause a simultaneous trip demand for more than one unit. This may considerably complicate the response of operators to the fire event, and may create conflicting demands on plant systems which are shared between units. Please provide the following information regarding this issue: (1) identify all fire areas that are shared between units and the potentially risk-important systems / components for each unit that are housed in each such area, (2) for each area identified in (1), provide an assessment of the associated multi-unit fire risk, (3) for the special case of control rooms sharing a common fire area, assess the likelihood of a fire or smoke-induced evacuation with 7
subsequent shutdown of both units from remot] shutdown panels, cnd (4) provide an assessment of the risk contribution of any such multi-unit scenario.
(b) At some sites, the safe shutdown path for a given unit may call for cross-connects to a sister unit in the event of certain fires. Hence, the fire analysis '
should include the unavailability of the cross-connected equipment due to outages at the sister unit (e.g., routine in-service maintenance outages and/or the potential that normally available equipment may be unavailable during extended or refueling outages at the sister unit). Please provide the following relevant information regarding this issue: (1) identify if any fire response safe shutdown procedures call for unit cross-connects, and (2) if any such cross-connects are called for, determine the impact on fire risk if the total unavailability of the sister unit equipment is included in the assessment.
(c) Propagation of fire, smoke, and suppressants between fire zones containing equipment for one unit to fire zones containing equipment for the other unit also can result in multi-unit scenarios. Hence, the fire assessment for each unit .
should include analyses of scenarios addressing propagation of smoke, fire and suppressants to and from fire zones containing equipment for the other unit.
From the information in the submittal, it is not clear if these types of scenarios are possible. Please provide an assessment of the risk contribution of any such multi-unit scenarios.
- 6. The submittal assumes that safety-related equipment would not be damaged at room or target temperatures below 700* F. Fire test data published by Sandia in NUREG/CR-4596 and NUREG/CR-4310 indicate that many components have a lower temperature threshold for damage than the 700* F used for qualified cable. Sandia reports failure of relays at temperatures as low as 320' F. Please provide a technical basis for the selection of the temperature threshold or revise the analysis using the temperature of 425' F as specified in FIVE for unqualified cables.
- 7. Please provide a discussion of how transient fires were assessed in the IPEEE. Include in this discussion the basis for the selection of the transient modeled in each fire area. If the selection is not based on the plant's administrative controls, please revise the analysis to reflect the actual administrative limit.
- 8. The analysis states that all possible hot shorts were assumed to fail the component. No discussion of hot shorts that could result in a spurious operation of equipment that could affect safe shutdown capability was provided. Please provide the analysis to address spurious actuation of equipment due to hot shorts and the corresponding effect on safe shutdown capability.
- 9. The analysis assumes that the fire brigade responds and suppresses the fire in 10 minutes for all plant areas. This time appears overly optimistic. The time to effect manual suppression is not based solely on response time. The time required to suppress a fire can involve delays associated with detection time, response time of the fire brigade, size-up and assessment of the fire, time to don protective clothing, and time 8
I for firo suppression. B: sed on industry historical perform:nce, for most fires th:t requira fira brigade interdiction, the time to provide effective suppression ranges from 30 minutes to several hours. Please revise the analysis for areas that credited manual suppression in 10 minutes to account for the distribution of possible suppression times, and provide a basis for this distribution.
- 10. Smoke can also cause misdirected manual suppression efforts and hamper the .
operator's ability to safely shut down the plant. This issue concems the hampering effects of the potential buildup of smoke on the efforts of the manual fire brigade to promptly and effectively suppress fires. Sensitivity studies in the FRSS showed that prolonged fire-fighting times can lead to a noticeable increase in fire risk.
Please describe your provisions for smoke control in the event of fires at y'our facility.
For any fire scenario in which manual fire suppression efforts are credited in calculating core damage freauency, please describe how your analysis accounted for smoke controlissues. Fcr scenarios in which manual fire suppression is not credited in the analysis, please describe how your analysis evaluated the potential that additional ,
component failures could be caused by misdirected manual fire suppression efforts.
- 11. The analysis credits a fire watch as a rnanual suppression system, and assumes it is as reliable as automatic suppression. However, no technical basis is provided for this assumption. The FIVE methodology specifies that the manual fire suppression unavailability ranges from 0.1 to 1.0, whereas the automatic suppression unavailability ranges from .02 to .05. Please revise the analysis using the appropriate values for manual suppression by the fire watch.
- 12. Several high hazard fire areas such as the clean and dirty tube oil storage tank room, turbine lube oil storage room, and diesel fuel oil storage rooms were screened based on ignition frequency and conditional core damage probability. These areas could present an exposure hazard to adjacent fire areas that contain safe shutdown equipment or cabling. Three-hour barriers may not be sufficient to ensure that fire does not propagate from these high hazard areas. Therefore, a detailed fire compartment interaction analysis is necessary to address these areas. Please provide a detailed fire compartment interaction analysis for the high fire hazard areas considering the potential for failure of active fire barrier components such as doors and dampers.
9 i