MONTHYEARHL-5845, Monthly Operating Repts for Sept 1999 for Ei Hatch Nuclear Plant.With1999-09-30030 September 1999 Monthly Operating Repts for Sept 1999 for Ei Hatch Nuclear Plant.With HL-5836, Monthly Operating Repts for Aug 1999 for Edwin I Hatch Nuclear Plant.With1999-08-31031 August 1999 Monthly Operating Repts for Aug 1999 for Edwin I Hatch Nuclear Plant.With HL-5818, Monthly Operating Repts for July 1999 for Ei Hatch Nuclear Plant,Units 1 & 2.With1999-07-31031 July 1999 Monthly Operating Repts for July 1999 for Ei Hatch Nuclear Plant,Units 1 & 2.With HL-5805, Monthly Operating Repts for June 1999 for Ei Hatch Nuclear Plant,Units 1 & 2.With1999-06-30030 June 1999 Monthly Operating Repts for June 1999 for Ei Hatch Nuclear Plant,Units 1 & 2.With HL-5795, Monthly Operating Repts for May 1999 for Ehnp Units 1 & 2. with1999-05-31031 May 1999 Monthly Operating Repts for May 1999 for Ehnp Units 1 & 2. with HL-5784, Monthly Operating Repts for Apr 1999 for Ei Hatch Nuclear Plant,Units 1 & 2.With1999-04-30030 April 1999 Monthly Operating Repts for Apr 1999 for Ei Hatch Nuclear Plant,Units 1 & 2.With HL-5766, Monthly Operating Repts for Mar 1999 for Ei Hatch Nuclear Plant,Units 1 & 2.With1999-03-31031 March 1999 Monthly Operating Repts for Mar 1999 for Ei Hatch Nuclear Plant,Units 1 & 2.With HL-5755, Monthly Operating Repts for Feb 1999 for Ei Hatch Nuclear Plant,Units 1 & 2.With1999-02-28028 February 1999 Monthly Operating Repts for Feb 1999 for Ei Hatch Nuclear Plant,Units 1 & 2.With HL-5726, Monthly Operating Repts for Dec 1998 for Ei Hatch Nuclear Plant,Units 1 & 2.With1998-12-31031 December 1998 Monthly Operating Repts for Dec 1998 for Ei Hatch Nuclear Plant,Units 1 & 2.With HL-5714, Monthly Operating Repts for Nov 1998 for Ei Hatch Nuclear Plant,Units 1 & 2.With1998-11-30030 November 1998 Monthly Operating Repts for Nov 1998 for Ei Hatch Nuclear Plant,Units 1 & 2.With HL-5706, Monthly Operating Repts for Oct 1998 for Hatch Nuclear Plant Units 1 & 2.With1998-10-31031 October 1998 Monthly Operating Repts for Oct 1998 for Hatch Nuclear Plant Units 1 & 2.With HL-5691, Monthly Operating Repts for Sept 1998 for Ei Hatch Nuclear Plant,Units 1 & 2.With1998-09-30030 September 1998 Monthly Operating Repts for Sept 1998 for Ei Hatch Nuclear Plant,Units 1 & 2.With HL-5675, Monthly Operating Repts for Aug 1998 for Ei Hatch Nuclear Plant,Units 1 & 21998-08-31031 August 1998 Monthly Operating Repts for Aug 1998 for Ei Hatch Nuclear Plant,Units 1 & 2 HL-5667, Monthly Operating Repts for July 1998 for Ei Hatch Nuclear Plant,Units 1 & 21998-07-31031 July 1998 Monthly Operating Repts for July 1998 for Ei Hatch Nuclear Plant,Units 1 & 2 HL-5653, Monthly Operating Repts for June 1998 for Ei Hatch Nuclear Plant,Units 1 & 21998-06-30030 June 1998 Monthly Operating Repts for June 1998 for Ei Hatch Nuclear Plant,Units 1 & 2 HL-5640, Monthly Operating Repts for May 1998 for Ei Hatch Nuclear Plant,Units 1 & 21998-05-31031 May 1998 Monthly Operating Repts for May 1998 for Ei Hatch Nuclear Plant,Units 1 & 2 HL-5628, Monthly Operating Repts for Apr 1998 for Ei Hatch Nuclear Plant1998-04-30030 April 1998 Monthly Operating Repts for Apr 1998 for Ei Hatch Nuclear Plant HL-5604, Monthly Operating Repts for Mar 1998 for Edwin I Hatch Nuclear Plant,Units 1 & 21998-03-31031 March 1998 Monthly Operating Repts for Mar 1998 for Edwin I Hatch Nuclear Plant,Units 1 & 2 HL-5585, Monthly Operating Repts for Feb 1998 for Ei Hatch Nuclear Plant,Units 1 & 21998-02-28028 February 1998 Monthly Operating Repts for Feb 1998 for Ei Hatch Nuclear Plant,Units 1 & 2 HL-5571, Monthly Operating Repts for Jan 1998 for Edwin I Hatch Nuclear Plant,Unit 11998-01-31031 January 1998 Monthly Operating Repts for Jan 1998 for Edwin I Hatch Nuclear Plant,Unit 1 HL-5551, Monthly Operating Repts for Dec 1997 for Ei Hatch Nuclear Plant,Units 1 & 21997-12-31031 December 1997 Monthly Operating Repts for Dec 1997 for Ei Hatch Nuclear Plant,Units 1 & 2 HL-5533, Monthly Operating Repts for Nov 1997 for Ei Hatch Nuclear Plant,Units 1 & 21997-11-30030 November 1997 Monthly Operating Repts for Nov 1997 for Ei Hatch Nuclear Plant,Units 1 & 2 HL-5514, Monthly Operating Repts for Oct 1997 for Edwin I Hatch Nuclear Plant,Units 1 & 21997-10-31031 October 1997 Monthly Operating Repts for Oct 1997 for Edwin I Hatch Nuclear Plant,Units 1 & 2 HL-5493, Monthly Operating Repts for Sept 1997 for Ei Hatch Nuclear Plant1997-09-30030 September 1997 Monthly Operating Repts for Sept 1997 for Ei Hatch Nuclear Plant HL-5475, Monthly Operating Repts for Aug 1997 for Ei Hatch Nuclear Plant,Units 1 & 21997-08-31031 August 1997 Monthly Operating Repts for Aug 1997 for Ei Hatch Nuclear Plant,Units 1 & 2 HL-5447, Monthly Operating Repts for July 1997 for Edwin I Hatch Nuclear Plant,Units 1 & 21997-07-31031 July 1997 Monthly Operating Repts for July 1997 for Edwin I Hatch Nuclear Plant,Units 1 & 2 HL-5416, Monthly Operating Repts for May 1997 for Ei Hatch Nuclear Plant Units 1 & 21997-05-31031 May 1997 Monthly Operating Repts for May 1997 for Ei Hatch Nuclear Plant Units 1 & 2 HL-5393, Monthly Operating Repts for Apr 1997 for Ei Hatch Nuclear Plant Units 1 & 21997-04-30030 April 1997 Monthly Operating Repts for Apr 1997 for Ei Hatch Nuclear Plant Units 1 & 2 HL-5364, Monthly Operating Repts for Mar 1997 for Ei Hatch Npp,Units 1 & 21997-03-31031 March 1997 Monthly Operating Repts for Mar 1997 for Ei Hatch Npp,Units 1 & 2 HL-5332, Monthly Operating Repts for Feb 1997 for Ei Hatch Nuclear Plant1997-02-28028 February 1997 Monthly Operating Repts for Feb 1997 for Ei Hatch Nuclear Plant HL-5314, Monthly Operating Repts for Jan 1997 for Ei Hatch Nuclear Plant1997-01-31031 January 1997 Monthly Operating Repts for Jan 1997 for Ei Hatch Nuclear Plant HL-5296, Monthly Operating Repts for Dec 1996 for Ei Hatch Nuclear Plant,Units 1 & 21996-12-31031 December 1996 Monthly Operating Repts for Dec 1996 for Ei Hatch Nuclear Plant,Units 1 & 2 HL-5283, Monthly Operating Repts for Nov 1996 for Edwin I Hatch Nuclear Plant,Unit 1 & 21996-11-30030 November 1996 Monthly Operating Repts for Nov 1996 for Edwin I Hatch Nuclear Plant,Unit 1 & 2 HL-5265, Monthly Operating Repts for Oct 1996 for Ei Hatch Nuclear Plant Units 1 & 21996-10-31031 October 1996 Monthly Operating Repts for Oct 1996 for Ei Hatch Nuclear Plant Units 1 & 2 HL-5249, Monthly Operating Repts for Sept 1996 for Ei Hatch Nuclear Plant Unit 1 & 21996-09-30030 September 1996 Monthly Operating Repts for Sept 1996 for Ei Hatch Nuclear Plant Unit 1 & 2 HL-5237, Monthly Operating Repts for Aug 1996 for Ei Hatch Nuclear Plant Units 1 & 21996-08-31031 August 1996 Monthly Operating Repts for Aug 1996 for Ei Hatch Nuclear Plant Units 1 & 2 ML20116J3821996-07-31031 July 1996 Monthly Operating Repts for Jul 1996 for Ei Hatch Nuclear Plant Units 1 & 2 HL-5202, Monthly Operating Repts for June 1996 for Ei Hatch Nuclear Plant Units 1 & 21996-06-30030 June 1996 Monthly Operating Repts for June 1996 for Ei Hatch Nuclear Plant Units 1 & 2 ML20112J0661996-05-31031 May 1996 Monthly Operating Repts for May 1996 for Ehnp ML20116J3971996-05-31031 May 1996 Revised MOR for May 1996 for Ei Hatch Nuclear Plant Unit 1 ML20112J0691996-04-30030 April 1996 Revised MOR for April 1996 for Ei Hatch Nuclear Plant ML20116J3901996-04-30030 April 1996 Revised MOR for April 1996 for Ei Hatch Nuclear Plant Unit 1 ML20111B0061996-04-30030 April 1996 Monthly Operating Repts for April 1996 for Ei Hatch Nuclear Plant HL-5144, Monthly Operating Repts for Mar 1996 for Ei Hatch Nuclear Plant1996-03-31031 March 1996 Monthly Operating Repts for Mar 1996 for Ei Hatch Nuclear Plant ML20111B0131996-03-31031 March 1996 Revised Pages E2-4 for March 1996 for Ei Hatch Nuclear Plant Unit 2 ML20101B1911996-02-29029 February 1996 Monthly Operating Repts for Feb 1996 for Ei Hatch Nuclear Plant,Units 1 & 2 HL-5111, Monthly Operating Repts for Jan 1996 for Ei Hatch Nuclear Plant1996-01-31031 January 1996 Monthly Operating Repts for Jan 1996 for Ei Hatch Nuclear Plant ML20101B2001996-01-31031 January 1996 Revised Page E1-2 for Monthly Operating Rept for Jan 1996 for Ei Hatch Unit 1 HL-5098, Monthly Operating Repts for Dec 1995 for Ei Hatch Nuclear Plant1995-12-31031 December 1995 Monthly Operating Repts for Dec 1995 for Ei Hatch Nuclear Plant HL-5085, Monthly Operating Repts for Nov 1995 for Ei Hatch Nuclear Plant1995-11-30030 November 1995 Monthly Operating Repts for Nov 1995 for Ei Hatch Nuclear Plant 1999-09-30
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20217D3061999-10-13013 October 1999 SER Accepting Licensee Proposed Changes to Edwin I Hatch Nuclear Plant Emergency Classification Scheme to Add Emergency Action Levels Related to Operation of Independent Spent Fuel Storage Installation HL-5845, Monthly Operating Repts for Sept 1999 for Ei Hatch Nuclear Plant.With1999-09-30030 September 1999 Monthly Operating Repts for Sept 1999 for Ei Hatch Nuclear Plant.With ML20217A1691999-09-22022 September 1999 Part 21 Rept Re Engine Sys,Inc Controllers,Manufactured Between Dec 1997 & May 1999,that May Have Questionable Soldering Workmanship.Caused by Inadequate Personnel Training.Sent Rept to All Nuclear Customers ML20212A6641999-09-13013 September 1999 Safety Evaluation Authorizing Relief Request RR-V-16 for Third 10 Yr Interval Inservice Testing Program HL-5836, Monthly Operating Repts for Aug 1999 for Edwin I Hatch Nuclear Plant.With1999-08-31031 August 1999 Monthly Operating Repts for Aug 1999 for Edwin I Hatch Nuclear Plant.With ML20210J9631999-08-0202 August 1999 SER Finding That Licensee Established Acceptable Program to Verify Periodically design-basis Capability of safety-related MOVs at Edwin I Hatch Nuclear Plant,Units 1 & 2 ML20210J9271999-08-0202 August 1999 SER Finds That Licensee Performed Appropriate Evaluations of Operational Configurations of safety-related power-operated Gate Valves to Identify Valves at Plant,Susceptible to Pressure Locking or Thermal Binding HL-5818, Monthly Operating Repts for July 1999 for Ei Hatch Nuclear Plant,Units 1 & 2.With1999-07-31031 July 1999 Monthly Operating Repts for July 1999 for Ei Hatch Nuclear Plant,Units 1 & 2.With HL-5805, Monthly Operating Repts for June 1999 for Ei Hatch Nuclear Plant,Units 1 & 2.With1999-06-30030 June 1999 Monthly Operating Repts for June 1999 for Ei Hatch Nuclear Plant,Units 1 & 2.With ML20207E7631999-06-0303 June 1999 Safety Evaluation Concluding That Licensee Proposed Alternative to Use Code Case N-509 Contained in RR-4 Provides Acceptable Level of Quality & Safety.Considers Rev 2 to RR-4 & RR-6 Acceptable HL-5795, Monthly Operating Repts for May 1999 for Ehnp Units 1 & 2. with1999-05-31031 May 1999 Monthly Operating Repts for May 1999 for Ehnp Units 1 & 2. with ML20206G1691999-05-0404 May 1999 SER Approving Requirements of Istb 4.6.2(b) Pursuant to 10CFR50.55a(a)(3)(ii) HL-5784, Monthly Operating Repts for Apr 1999 for Ei Hatch Nuclear Plant,Units 1 & 2.With1999-04-30030 April 1999 Monthly Operating Repts for Apr 1999 for Ei Hatch Nuclear Plant,Units 1 & 2.With HL-5766, Monthly Operating Repts for Mar 1999 for Ei Hatch Nuclear Plant,Units 1 & 2.With1999-03-31031 March 1999 Monthly Operating Repts for Mar 1999 for Ei Hatch Nuclear Plant,Units 1 & 2.With ML20207M1891999-03-11011 March 1999 SER Accepting Relief Request for Authorization of Alternative Reactor Pressure Vessel Exam for Circumferential Weld HL-5755, Monthly Operating Repts for Feb 1999 for Ei Hatch Nuclear Plant,Units 1 & 2.With1999-02-28028 February 1999 Monthly Operating Repts for Feb 1999 for Ei Hatch Nuclear Plant,Units 1 & 2.With ML20206P6981999-01-0707 January 1999 Ehnp Intake Structure Licensing Rept HL-5726, Monthly Operating Repts for Dec 1998 for Ei Hatch Nuclear Plant,Units 1 & 2.With1998-12-31031 December 1998 Monthly Operating Repts for Dec 1998 for Ei Hatch Nuclear Plant,Units 1 & 2.With ML20196J4931998-12-0707 December 1998 Safety Evaluation Accepting Proposed Alternatives in Relief Requests RR-V-12,RR-V-15,RR-P-15,RR-V-7,RR-V-12,RR-V-14 & RR-V-15 HL-5714, Monthly Operating Repts for Nov 1998 for Ei Hatch Nuclear Plant,Units 1 & 2.With1998-11-30030 November 1998 Monthly Operating Repts for Nov 1998 for Ei Hatch Nuclear Plant,Units 1 & 2.With HL-5706, Monthly Operating Repts for Oct 1998 for Hatch Nuclear Plant Units 1 & 2.With1998-10-31031 October 1998 Monthly Operating Repts for Oct 1998 for Hatch Nuclear Plant Units 1 & 2.With ML20155B6121998-10-28028 October 1998 Safety Evaluation of TR SNCH-9501, BWR Steady State & Transient Analysis Methods Benchmarking Topical Rept. Rept Acceptable HL-5691, Monthly Operating Repts for Sept 1998 for Ei Hatch Nuclear Plant,Units 1 & 2.With1998-09-30030 September 1998 Monthly Operating Repts for Sept 1998 for Ei Hatch Nuclear Plant,Units 1 & 2.With ML20153G2481998-09-24024 September 1998 SE Concluding That Licensee Implementation Program to Resolve USI A-46 at Plant Adequately Addressed Purpose of 10CFR50.54(f) Request ML20239A2531998-09-0303 September 1998 SER Accepting Licensee Request for Relief Numbers RR-17 & RR-18 for Edwin I Hatch Nuclear Plant,Units 1 & 2.Technical Ltr Rept on Third 10-year Interval ISI Request for Reliefs for Plant,Units 1 & 2 Encl HL-5675, Monthly Operating Repts for Aug 1998 for Ei Hatch Nuclear Plant,Units 1 & 21998-08-31031 August 1998 Monthly Operating Repts for Aug 1998 for Ei Hatch Nuclear Plant,Units 1 & 2 ML20238F7131998-08-31031 August 1998 9,change 2 to QAP 1.0, Organization HL-5667, Monthly Operating Repts for July 1998 for Ei Hatch Nuclear Plant,Units 1 & 21998-07-31031 July 1998 Monthly Operating Repts for July 1998 for Ei Hatch Nuclear Plant,Units 1 & 2 HL-5657, Ro:On 980626,noted That Pami Channels Had Been Inoperable for More than Thirty Days.Cause Indeterminate.Licensee Will Replace Automatic Function W/Five Other Qualified Pamis of Like Kind in Drywell & Revised Procedures1998-07-30030 July 1998 Ro:On 980626,noted That Pami Channels Had Been Inoperable for More than Thirty Days.Cause Indeterminate.Licensee Will Replace Automatic Function W/Five Other Qualified Pamis of Like Kind in Drywell & Revised Procedures ML20236W3441998-07-30030 July 1998 Safety Evaluation Accepting Relief Requests for Second 10-yr ISI for Plant,Units 1 & 2 ML20236V5191998-07-28028 July 1998 Safety Evaluation Accepting Proposed License Amend Power Uprate Review ML20236N6751998-07-0909 July 1998 Part 21 & Deficiency Rept Re Notification of Potential Safety Hazard from Breakage of Cast Iron Suction Heads in Apkd Type Pumps.Caused by Migration of Suction Head Journal Sleeve Along Lower End of Pump Shaft.Will Inspect Pumps ML20236L1821998-07-0707 July 1998 Safety Evaluation Accepting 980428 Proposed Alternative to ASME Boiler & Pressure Vessel Code,Section Xi,Repair & Replacement Requirements Under 10CFR50.55a(a)(3) HL-5653, Monthly Operating Repts for June 1998 for Ei Hatch Nuclear Plant,Units 1 & 21998-06-30030 June 1998 Monthly Operating Repts for June 1998 for Ei Hatch Nuclear Plant,Units 1 & 2 HL-5640, Monthly Operating Repts for May 1998 for Ei Hatch Nuclear Plant,Units 1 & 21998-05-31031 May 1998 Monthly Operating Repts for May 1998 for Ei Hatch Nuclear Plant,Units 1 & 2 ML20248B8651998-05-15015 May 1998 Quadrennial Simulator Certification Rept HL-5628, Monthly Operating Repts for Apr 1998 for Ei Hatch Nuclear Plant1998-04-30030 April 1998 Monthly Operating Repts for Apr 1998 for Ei Hatch Nuclear Plant HL-5604, Monthly Operating Repts for Mar 1998 for Edwin I Hatch Nuclear Plant,Units 1 & 21998-03-31031 March 1998 Monthly Operating Repts for Mar 1998 for Edwin I Hatch Nuclear Plant,Units 1 & 2 ML20216B2711998-02-28028 February 1998 Extended Power Uprate Safety Analysis Rept for Ei Hatch Plant,Units 1 & 2 HL-5585, Monthly Operating Repts for Feb 1998 for Ei Hatch Nuclear Plant,Units 1 & 21998-02-28028 February 1998 Monthly Operating Repts for Feb 1998 for Ei Hatch Nuclear Plant,Units 1 & 2 HL-5571, Monthly Operating Repts for Jan 1998 for Edwin I Hatch Nuclear Plant,Unit 11998-01-31031 January 1998 Monthly Operating Repts for Jan 1998 for Edwin I Hatch Nuclear Plant,Unit 1 HL-5551, Monthly Operating Repts for Dec 1997 for Ei Hatch Nuclear Plant,Units 1 & 21997-12-31031 December 1997 Monthly Operating Repts for Dec 1997 for Ei Hatch Nuclear Plant,Units 1 & 2 ML20199B0561997-12-31031 December 1997 Rev 0 GE-NE-B13-01869-122, Jet Pump Riser Weld Flaw Evaluation Handbook for Hatch Unit 1 HL-5581, Annual Operating Rept for 1997, for Ei Hatch Nuclear Plant Units 1 & 21997-12-31031 December 1997 Annual Operating Rept for 1997, for Ei Hatch Nuclear Plant Units 1 & 2 HL-5533, Monthly Operating Repts for Nov 1997 for Ei Hatch Nuclear Plant,Units 1 & 21997-11-30030 November 1997 Monthly Operating Repts for Nov 1997 for Ei Hatch Nuclear Plant,Units 1 & 2 HL-5514, Monthly Operating Repts for Oct 1997 for Edwin I Hatch Nuclear Plant,Units 1 & 21997-10-31031 October 1997 Monthly Operating Repts for Oct 1997 for Edwin I Hatch Nuclear Plant,Units 1 & 2 ML20212A1981997-10-16016 October 1997 Safety Evaluation Denying Licensee Request for Relief from Implementation of 10CFR50.55a Requirements Re Use of 1992 Edition of ASME Code Section XI for ISI of Containments ML20211M6491997-10-0808 October 1997 Addenda 1 to Part 21 Rept Re Weldments on Opposed Piston & Coltec-Pielstick Emergency stand-by Diesel gen-set lube-oil & Jacket Water Piping Sys.Revised List of Potentially Affected Utils to Include Asterisked Utils,Submitted ML20211H5311997-10-0101 October 1997 Rev 2 to Unit 1,Cycle 17 Colr ML20211H5251997-10-0101 October 1997 Rev 3 to Unit 1,Cycle 17 Colr 1999-09-30
[Table view] |
Text
- - - - - . _ - _ _ - . -- --
i i
GEORGIA POWER I
COMPANY
- M O NTH LY OPERATING DATA REPORTS PLANT HATCH UNITS i
! 1 AND 2 l 4
/j:
- /
- _
- / :
lI Od!!!ll[I71/ :
hi :,,I"'t l mu uin o m i t i! i iiii ,
\ '
J a.
1 o a ' .
1 m.
Silgs2gggg gggg;gn 8 m .-
/ l
Georgia Power d ENCLOSURE 1 TABLE OF CONTENTS PLANT HATCH - UNIT 1 NRC DOCKET 50-321 MONTHLY CPERATING REPORT APRIL 1988 NARRATIVE REPORT Page El-1 OPERATING DATA REPORT Page El-2 AVERAGE DAILY P0HLR LEVEL Page El-3 UNIT SHUTDOWNS AND POWER REDUCTIONS Page El-4 0276I wrs
o .'
l NARRATIVE REPORT DOCKET NO. 50-321 UNIT 1 DATEt MAY 4, 1988 COMPLETED BY: R. M. SEARD TELEPHONE: (912) 367-7781 n2078 April 1 0000 Maintaining 1001 power.
April 1 0953 Reducing load to 390 6MWe for Rod Sequence Exchange, MS!V Testieg, Weekly Turbine Valve / Auxiliaries Test, and CR0 Esercise.
April 1 1520 Returning to 100% power.
April 4 2104 Reduenng lead for normal plant shutdown to investigate and recair source (s) of high crymell leakage.
April 5 0809 Main generator off line. ;
i April 5 1003 Manuel react',r scram inserted.
April 11 0511 Began rod withdrawal for reactor startup.
April 11 0605 Reactor critical.
April 12 1048 Main generator on line. Power ascension in progrses.
April 16 0007 Reducing load to 735 GMWe for Rod Pattern Adjustment, Weekly Turbine Valve / Auxiliaries Test, and CRD Esercise.
April 16 0305 Returning to 1001 power.
April 19 0802 Automatic reactor scras due to a turbine trip caused by a signal from the Thrust Bearing Wear Det ctor.
Aprii 20 1718 Reactor placed in cold shutdown per management decision.
April 30 2400 Maintaining cold shutdown.
e 1
El-1 L
o - '.>
OPERATING DATA REPORT DOCKET NO. 50-321 DATE: MAY 4, 1968 COMPLETED BYi R. M- BEARD TELEPHONE: (912) 367-7781 =2870 OPERATING STATUS ;
- 1. UNIT NAME: E. !. HATCH UNIT 1
- 2. REPORT PERIOD: APRIL, 1998 30 LICENSED THERMAL POWER (MWt): 2436
- 4. NAMEPLATE RAT!N6 (GROSS MWelt 650
- 5. OfSIGN ELECTRICAL RATING (NET MWe): 776.3
- 6. MAXIMUM DEPENDABLE CAPACITY (GROSS MWe): 789.6
- 7. MAI! MUM DEPENDASLE CAPACITY (NET MWe): 755.6
- 8. IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS 3 THROUGH 7) SINCE LAST REPORY. $1VE REASONS: NO CHANGES
- 9. POWER LEVEL TO WHICH RESTRICTED, IF ANf (NET MWe): NO RESTR!CTIONS
- 10. REASONS FOR RESTR!CTION, IF ANY: N/A THIS MONTH YR. TO DATE CUMULATIVE
!!. HOURS IN REPORTING PERIOD: 719 2903 108094
- 18. NUMBER OF HOURS REACTOR WAS CRITICAL: 299.0 2442.9 77282.1
- 13. REACTOR RESERVE SHUTDOWN HOURS 0.0 0.0 0.0 14 HOURS GENERATOR ON-LINE: 268.5 2401.5 73172.9
- 15. UNIT RESERVE SHUTDOWN HOURS: 0.0 0.0 0.0
- 16. GROSS THERMAL ENERIY SENERATED (MWH): 568830 5732092 158656708
- 17. GROSS ELEC. ENER6Y GENERATED (MWH): 176110 1845330 51234000 it. NET ELEC. ENERSY SENERATED (MWH): 162785 1756987 49676551 '
- 19. UNIT SERV!CE FACTOR: 37.31 82.71 67.7%
- 20. UNIT AVA!LAl!LITY FACTOR: 37.3% 02.71 67.7%
- 21. UNIT CAPACITY FACTOR (USING MDC NET): 30.01 80.1% 60.0%
- 22. UNIT CAPACITY FACTOR (USING DER NET): 29.2% 70.0% 57.6%
- 23. UNIT FORCED 00TA6E RATE: 51.0% 12.4% 15.2%
- 24. SHUTDOWNS SCHEDULED OVER THE NEIT 6 MONTHS (TYPE, DATE AND DURATION OF EACH):
Refueling Outagei September 21, 1988 65 Days ;
- 25. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP: N/A l
- 26. UNITS IN TEST STATUS ( PRIOR TO COMMERCIAL OPERAT!DN): N/A
~
i El-2
- , - - - - - - - a ,-,,,--.------,---.---._,-,n--n .- y..,. -w -,-.--,-,.-._,-,,--,,,y.n. -
- -m --- ~ , - - ,
s i UNIT 1 AVERwGE DAILY DOCKET NO. 50-321 Daft: MAY 4, 190s
~
POWER LEVEL
! APRIL, 1988 COMPLifED BY: R. M. ItARD TELEPHONE: (912) 367-7701 x2078 DAY Net MW 1 ......... 565 2 ......... 693 3 ......... 710 4 ......... 713 5 ......... 59 6 ......... O j 7 ......... 0
, 9 ......... 0 9 ......... O i
10 ......... 0 11 ......... 0 12 ......... 51 I 13 ......... 260 14 ......... 657 15 ......... 751
- 16 ......... 752 1 17 ......... 750 18 ......... 755 19 ......... 242 20 ......... 0 l 21 ......... O i 22 ......... 0 23 ......... 0 24 ......... 0 25 ......... 0 4 26 ......... O j 27 ......... 0 20 ......... 0 29 ......... O i 30 ......... 0 l
El-3
+ . .
UNIT SHUTDOWNI AND POWER REDUCTIONS DOCKET NO. 50-321 ,
- DATE
- FAY 4, 1980 UNIT NAME: E.I. HATCH 1 COMPLETED BY: R. M. IEARD TELEPHONE: (912) 367 7701 s2878 i l
REPORT MONTH APRIL. 1988
..........g...
..........g...........................................
I I I I IEI EI IY I I I i 1 1TI I A i i ILICENSEEl SC1 ! I I I iY! ISI H ! EVENT ! T 0 ICOMPONENTI CAUSE b CORRECTIVE I I i ! P IDURATIONI O I O1 REPORT I ED1 CODE I ACTION TO !
I NO. I DATE I E 1(HOURS) i N I O! NUMBER I M E l(SUBCODEli PREVENT RECURRENCE I l.......l......l...l........l...! 1.....l.........l.............................I I I I I i ! ! i i l i 108-003 18804051 S1 0 1Ci5i N/A ! CI I VESSEL IPower reduction for uhit i I I I I i ! ! I I (D) ishutdown.(eaintenance outagell >
1 1 ! ! I i ! I i l i 188-004 18804061 5 1 170.7 iC1 2i N/A I C! l VESSEL lunit shutdown to investigate i I ! ! I i 1 1 1 1 (D) land repair source (si of high I l l 1 1 I i i i ! Idryus!! leakage. !
4 1 1 I I i i ! ! ! ! I ;
181-005 18904191 F I 250.0 I H I 3 11-08-005! HA 1 INSTRU lAutomatic scras due to l l I I I I i ! ! I (E) linadequate procedure for i ;
1 I I i 1 1 1 1 1 Isus.pping of turbine tube oil 1 '
I I I i 1 1 I I I tcoolers which caused a trip i i l I i i ! I I i leignal to be generated by thel i 1 i l i ! i l i IThrust Bearing Wear Detector I i i l i i ! I I l lon the sal
- turbine. I I I i l I i i l 1 I l I I I j l i I I I I I I ,
1 I I I i ! ! I i i i I I I I I i l I I i ! +
i 1 1 I I I I 1 1 1 1 I ! ! ! ! 1 ! I I l I I i i i i ! ! I 1 1 I 1
! I I i ! ! ! I I I !
I I I I I i 1 I I I I l.......l......l...l........l...l...l........l.....l.........!.............................I ,
1 F: FORCED REASON: METHOD: EVENTS REPCRTED INVOLVE 5: SCHEDULED A.EGUIPMENT FAILURE (EIPLAIN) 1 . MANUAL A GREATER THAN 20%
2 - MANUAL SCRAM REDUCTigN IN AVERAGE :
B-MAINTENANCE OR TEST C-REFUELING 3 - AUTO. SCRAM DA!LY POWER LEVEL FOR D-REGULATORY RESTRICTION 4 - CONT!NUATIONS THE PRECEEDINS 24 HOURS.
E-OPERATOR TRAINING & LICENSE 5 - LOAD REDUCTION F-ADMIN!STRAT!VE 9 - OTHER (EIPLAIN)
- G.0PERATIONAL ERROR (EIPLAIN)
H.0THER (EIPLA!N)
.I El-4 e
0 Georgialbwer ENCLOSURE 2 TABLE OF CONTENTS PLANT HATCH - UNIT 2 (
NRC DOCKET 50-366 l HONTHLY OPERATING REPORT {
AER1L1938 l 1
NARRATIVE REPORT Page E2-1 OPERATING DATA REPORT Page E2-2 AVERAGE DAILY POWER LEVEL Page E2-3 UNIT SHUTDOWNS AND POWER REDUCTIONS Page E2-4 l
0276I rx . . .
e NARRATIVE REPORT DOCKET NO. 50-366 UNIT 2 DATE: MAY 4, 1900 COMPLETED BY R. M. DEARD ;
TELEPHONE: (912) 367-7781 x2078 April 1 0000 Maintaining 100% power, April 2 2150 Reducing load to 400 GMWe for Red Pattern Adjusteent, '
Weekly Turbine Valve /A'ailliert es Test, and CRD Exercise.
April 3 0745 Returning to 100% power.
April 9 1720 Reducing lead to 730 GMWe for Rod Pattern Adjustaent, Weekly Turbine Valve /Auxillaries Test, and ClD Exercise. t April 9 2100 Returning to 100% power.
April 17 0043 Reducing load to 440 GMWe for Turbine Control Valve Testing, Weekly Turbine Valve /Aamiliaries Test, and CRD Esercise.
April 17 0155 Automatic reactor scram due to a turbine trip caused by a spurious screa signal in conjunction with Turbine Stop Valve Testing. .
1 April 19 2140 Reactor placed in cold shutdown per asnagement decision.
Aprt! 30 2400 Maintaining cold shutdonn. ,
I r
t l
i E2*! '
l
. 1
~ ' I 9
h f
OPERATING DATA REPORT DOCKET NO. 50-366 i DATE: MAY 4, 1900 l COMPLETED BY R. M. DEARD j TELEPHONE: (912) 367-7701 m2878 OPERAT!NS STATUS:
- 1. UNIT NAME: E. 1. HATCH UNIT 2 20 REPORTING PERIOD: APRIL, 1988
- 3. LICENSED THERMAL POWER (MWt): 2436
- 4. NAMEPLATI RATING (OR0ll MWel 850
- 5. DES!BN ELECTRICAL RATINS (NET MWe): 784 60 M411 MUM DEPENDABLE CAPACITY (GROSS MWe): 801.3 I
- 7. MAIIMUM DEPENDABLE CAPA?!TV (NET MWe): 768.3
- 8. !F CHANSES OCCUR IN CAPACITY RATINGS (ITEMS 3 THROUGH 7) SINCE LAST REPORT. SIVE REASONS: NO CHANBES
- 9. POWER LEVEL TO WHICH RESRTICTED. IF ANY (NET MWe): NO RESTRICTIONS
- 10. REASONS FOR RESTRICTION, !F ANY: N/A
[
l TH: S MONTH YR-TO-DATE CUMULATIVE
- 11. HOURS IN REPORT!NS PERIOD: 719 2903 75720
- 12. t:UMIER OF HOURS REACTOR WAS CRITICAL: 354.9 1000.6 53543.5
- 13. REACTOR RESERVE SHUTDOWN HOURS: 0.0 0.0 0.0
- 14. HOURS GENERATOR ON LINE: 304.9 193.9 51324.1
- 15. UNIT RESERVE SHUTDOWN HOURS: 0.0 0.0 0.0
- 16. 8R0ll THERMAL ENERBY SENERATED (MWH): 916949 1936255 11022453I
- 17. SRoll ELEC. ENERSY GENERATED (MWM): 306900 602050 36223660 100 NET ELEC. ENERlY IENERATED (MWH): 290369 560025 34465511 t
- 19. UNIT SERVICE FACTOR: 53.5% 30.01 67.8% ,
- 20. UNIT AVAILA31LITY FACTOR: 53.5% 30.8% 67.8%
- 21. UNIT CAPACITY FACTOR (USING MDC NET): 52.6% 25.1% 59.5%
- 22. UNIT CAPACITY FACTOR (UBINS DER NET): 51.5% 24.71 58.1%
- 23. UNIT FORCED OUTAGE RATE: 46.5% 27.71 9.0% ,
34 SHUTDOWNS SCHEDULED OVER THE NEIT S!! MONTHS (TYPE. DATE. AND DURATION OF EACH): N/A
- 25. IF SHUTDOWN AT END OF REPORT PERIOD. EST! MATED DATE OF STARTUP: N/A
- 26. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERAfl0N): N/A I
i r
l E2-2 l
l 1
> . . '.~
e r
i UN!7 2 AvtRAlt DAILY 00CKt7 NO. 50-366 f POWER LEVEL CA7t: MAY 4, 1998 ,
APRIL, 1988 COMPLt7tD BY R. M. ItARD :
7tLEPHONE: 1912) 367-7701 m2078 ;
DAY Net MW t ......... 765 ;
2 ......... 748 ,
3 ......... 606 4 ......... 769 :
5 ......... 772 6 ......... 772 i 7 ......... 776 8 ......... 779 !
9 ......... 765 l i
10 ......... 771 11 ......... 777 12 ......... 752 13 ......... 770 14 ......... 770 15 ......... 775 16 ......... 776 17 ......... 39 il ......... 0 19 ......... 0 20 ......... 0 21 ......... 0 22 ......... 0 23 ......... 0 24 ......... 0 25 ......... 0 26 ......... 0 27 ......... 0 21 ......... 0 29 ......... 0 30 ......... 0 (2-3
s.
UNIT SHuf DONt'C AND PONER REDUCTIONS DOCKET NU. 50-166 DATE MAY 4, 1998 UNIT NAMil E.I. HATCH 2 COMPLETED BYi R. M. IEARD TELEPHONE: (912) 367-7791 m2878 REPORT MONTH APRIL. 1988
! l 1 1 IE1 E1 IY l ! !
I I ITI I A1 f ILICEN5 eel SC1 1 I I I IYl i S1 H FVENT I T 0 ICOMPONENTI CAUSE & CORRECTIVE I i 1 1 P IDURATIONI O 1 0: 4EPORT 1 ED1 CODE I 4CTION 70 t i NO, 1 DA'r ' E l(HOURS) l N i D1 NudiER I M E !(SUICODEli PREVENT RECURRENCE I
!.......l.. .. ..l........!...;...!........I.....l.........!.............................I
! ! l 1 ! ! ! ! ! !
100-005 196 4: #1 334.1 1 W l 3 l2-99 0!!! !A 1 INSTRU IDuring the performance of thel
! I i i ! ! ! I I (1) tweekly turbine stop valve !
! 1 1 1 1 1 : 1 I ltest (which causes a screa l I i ! ! I I ! ! 1 tsignal to entst in the !
I I ! 1 1 ! 1 1 1 ! associated RPS channel) a !
l 1 1 I i 1 ! ! 1 Isourious straa signal was I
! l 1 1 ; I i 1 1 ! received in the redundant i I i 1 1 1 I l t 1 IRPS ch6nnel. The existance i i ! ! ! ! ! ! 1 I lof screa signal in both RPS I i 1 1 I I i i 1 1 Ithannels simultaneously i I I I I l l 1 1 I ! caused the reactor to straa. I
! l I I I I ! ! I I I I I I I I i ! ! ! 1 1
! ! I I I l ! ! I I I l t i I I I l ! ! ! 1 1 I l t i I l i I I I I I i ! i i i ! I I I i l I i i I ! ! I t I i l I i ! I I i l l I l.......l......l...l........l...l...!........l.....l.........!.............................I F: FORCED REASON: METHOD: EVEilfS REPORTED INVOLVE la SCHEDULED A-EGulPMENT FAILURE (EIPLAIN) 1 - MANUAL A GREATER THAN 20%
B-MAINTENANCE OR TEST 2 - MANUAL SCRAM REDUCTION IN AVERAGE C-REFSELING 3 . AUTO. SCRAM DAILY POWER LEVEL FOR D RESULATORY RESTRICTION 4 - CONTINUATIONS THE PRECEEDING 24 HO'JRS.
E-OPERATOR TRAINING & LICENSE 5 - LOAD REDUCTION F-ADMIN!lTRATIVE 9 - OTWER (EIPLA!N) 6-0PERAfl0NAL ERROR (EIPLAIN)
H-0THER (EXPLAIN)
E2-4
(
can a pse cewy -
313 f.ede 29. Aw-u a :a cwc:a :cnn TO' row:n 404 526 6526 t!a-: rg A rtc f'est C" ce 6 0s 4N5 awa coga x w Georgia Power Executive Department .
SL-4671 0276I X7GJ17-H510 May 13, 1988 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Hashington, D. C. 20555 PLANT HATCH - UNITS 1, 2 NRC DOCKETS 50-321, 50-366 OPERATING LICENSES DPR-57, NPF-5 MONTHLY OPERATING REPORTS Gentlemen:
Enclosed are the Monthly Operating Reports for Plant Hatch Unit 1, Docket Number 50-321, and for Plant Hatch Unit 2, Docket Number 50-366.
These reports are submitted in accordance with the requirements of Technical Specifications Section 6.9.1.10.
Sincerely,
~ '
R. P. Mcdonald Executive Vice President, Nuclear Operations l LGB/1g i
Enclosures:
- 1. Monthly Operating Report for Hatch-1 l 2. Monthly Operating Report for Hatch-2 l
l c: (see next page) 1 1 < '
l I t
L_
-+
Georgia Power A Director, Office of Manage:oent and Program Analysis May 13, 1988 Page Two c: Georaia Power Comoany Mr. J. T. Beckham, Jr., Vice President - Plant Hatch Mr. L. T. Gucwa,. Manager Nuclear Safety and Licensing GO-NORMS U. S. Nuclear Reaulatory Commission. Hashinaton. D. C.
Mr. L. P. Crocker, Hatch Licensing Project Manager U. S. Nuclear Regulatory Commission. Region II Dr. J. N. Grace, Regional Administrator Mr. P. Holmes-Ray, Senior Resident Inspector - Hatch r
0276I