Revised Page El-2 for Plant Hatch Unit 1 Monthly Operating Report May 1996 NOTE: The attached page is being revised u a result of an error in calculation of several parameters due to the use of Central Standard Time (CST) rather than Eastern Standard Time (EST).
1 l
HL 5218 9608130180 960809 PDR ADOCK 05000321 R
l.
OPERATING DATA REPORT DOCKET NO.:
50-321 DATE: JUNE 6, 1996 COMPLETED BY:
S. B. ROGERS i
TELEPHONE:
(912) 367-7781 x2878 OPERATING STATUS l
- 1. UNIT NAME:
E. I. HATCH - UNIT ONE
- 2. REPORT PERIOD:
MAY 1996 MWt :
2558
- 3. LICENSED THERMAL POWER (MWe :
- 4. NAMEPLATE RATING (GROSS 850 5
- 5. DESIGN ELECTRICAL RATING (N T MWe):
776.3
- 6. MAXIMUM DEPENDABLE CAPACITY (GROSS MWe):
840
- 7. MAXIMUM DEPENDABLE CAPACITY (NET MWe):
805
- 8. IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS 3 THROUGH 7) SINCE LAST REPORT, GIVE REASONS:
was increased Licensed Thermal Power (Item #3)imum Dependable from 2436 to 2558 MWt, Gross Max Capacity (Item #6) was increased from 789 to 840 l
MWe, and Net Maximum Dependable Capacity (Iteu #7) was increased from 756 to 805 MWe due to Power 1
Uprate.
- 9. POWER LEVEL TO WHICH RESTRICTED, IF ANY (NET MWe):
NO RESTRICTIONS
- 10. REASONS FOR RESTRICTION, IF ANY:
N/A THIS MONTH YEAR-TO-DATE CUMULATIVE
- 11. HOURS IN REPORTING PERIOD:
744.0 3647 178966
- 12. NUMBER OF HOURS REACTOR WAS CRITICAL:
715.3 2694.2 137095.8 j
- 13. REACTOR RESERVE SHUTDOWN HOURS:
0.0 0.0 0.0
- 14. HOURS GENERATOR ON LINE:
648.0 2530.3 131790.4
- 15. UNIT RESERVE SHUTDOWN HOURS:
0.0 0.0 0.0 1495726 5408810 297217577
- 16. GROSS THERMAL ENERGY GENERATED (MWHt)He):
- 17. GROSS ELECTRICAL ENERGY GENERATED (MW 477528 1713910 95586242
- 18. NET ELECTRICAL ENERGY GENERATED (NWHe):
454326 1617225 90980765
- 19. UNIT SERVICE FACTOR:
87.2%
69.4%
73.6%
- 20. UNIT AVAILABILITY FACTOR:
87.2%
69.4%
73.6%
- 21. UNIT CAPACITY FACTOR USING MDC NET):
75.9%
57.9%
67.9%
- 22. UNIT CAPACITY FACTOR USING DER NET):
78.7%
57.1%
65.2%
- 23. UNIT FORCED OUTAGE RA E:
12.6%
7.2%
10.6%
- 24. SHUTDOWNS SCHEDULED OVER THE NEXT 6 MONTHS (TYPE, DATE, AND DURATION OF EACH):
NA
- 25. IF SHUTDOWN AT END OF REPORT PERIOD ESTIMATED DATE OF STARTUP:
NA 26.UNITSINTESTSTATUS(PRIORTOCOMMERCIALOPERATION):
NA El-2