ML20151L868

From kanterella
Jump to navigation Jump to search
Insp Rept 50-416/88-10 on 880523-27.No Violations or Deviations Noted.Major Areas Inspected:Licensee Response to Generic Ltr 83-28,including post-trip Review,Equipment Classification & Vendor Interface
ML20151L868
Person / Time
Site: Grand Gulf Entergy icon.png
Issue date: 07/13/1988
From: Conlon T, Ruff A
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20151L852 List:
References
50-416-88-10, GL-83-28, NUDOCS 8808040166
Download: ML20151L868 (23)


See also: IR 05000416/1988010

Text

r

'

.

.

.

[prue

~

, UNITED STATES

g ,g

,

k'JCLEAR REGULATORY COMMISSION

o '* REGION 11

j[ 101 MARIETTA ST., N.W.

e,,,, ATLANTA. GEORGIA 30323

Report No.: 50-416/88-10

Licensee: System Energy Resources, Inc.

Jackson, MS 39205

Docket No.: 50-416 License No.: NPF-29

Facility Name: Grand Gulf

Inspection Conducted: May 23-27, 1988

Inspector: d. W WJ

A. B. Ruff, Telivltfader, Region II

__

7 /pF

Eate' Signed

Team Members:

C. Paulk, Region II Inspector

C. Smith, Region II Inspectior

L. Foster, Region II Consultant

Approved by: N A- 7//3/F9'

Date Signed

T. E. Conlon, Chief 8

Plant Systems Section

Engineering Branch

Division of Reactor Safety

SUMMARY

Scope: This special announced inspection was performed to assess the

licensee's response to Generic Letter 83-28, Required Actions Based

on Generic Implications of Salem Anticipated Transient Without Scram

(ATWS) Events. Areas inspected included post-trip review, equipment

classification and vendor interface, post-maintenance testing,

reactor trip system (RTS) reliability, lic" s 's action on IEB's,

IEN's, and previous inspection findings.

Resul ts: In the areas inspected, no violations or deviations were identified.

8808040166 880721

PDR ADOCK 05000416

G PNU

9

,--

-

..

i. .

-

.

,

REPORT DETAILS

1. Persons Contacted

Licensee Employees

  • 8. Angle, Manager 0AS
  • M. D. Bakarich, Support Systems

D. Bottemiller, Simulator Training Supervisor

S. Cothran EngineeringSupervisor(SIMSProject)

8. Crow,IECForeman

  • D. Cupstid, Plant Support
  • L. F. Daughtery, Compliance Supervisor
  • M. A. Dietrich, Supervisor Quality Audits
  • J. Dimmette, Jr Manager - Plant Maintenance
  • W. C. Eiff, Prilicipal Quality Engineer, NPE

T. Errington Nuclear Engineer, Technical Support

'D. Graves,15CForeman

  • F. Hennington, Planning Supervisor
  • C. A. Hutchinson, General Plant

B. Higginbotham, I&C Technician

G. Imes, Component Data Base Supervisor (SIMS Project)

F. Key, Instrumentation and Control (I&C) Technician

  • D. L. Pace, Manager, Nuclear Design
  • J. Reaves, Manager Quality Systems
  • J. Roberts, PM&C, Manager
  • R. F. Rogers, Manager SpecialProjects

, *W.R. Rogers,MaterialsManagementSupport

M. Rowland, QA Engineer (SIMS Project)

  • P. Simpson, Licensing Engineer

J. Simpson, Material Management Superintendent

  • J. Summers, Compliance Coordinator

J. Tahler, Project Manager (SIMS Proiect)

  • F. Titus, Director Nuclear Plant Eng neer

R. Wells, Engineering Supervisor (SIMS Project)

D. Williams, 0)erational Analysis Section

  • H. J. Wright, Manager Plant Support
  • G. Zinke, Technical Support Superintendent

Other licensee employees contacted during this inspection included

craftsmen, engineers, operators, mechanics, security force members,

technicians, and administrative personnel.

NRC Resident Inspectors

  • R. Butcher, Senior Resident Inspector
  • J. Mathis, Resident Inspector

t

!

-._, - . - - - . - - _ - ~ . . - . . . . _ , . - - - . , . - _ . - - . _ ~ . - ._- - ,_._ _ _

.

_ .- , - - . . . _ , , , , _ . . - - -

'

.

.

.

'

2

  • Attended exit interview

2. Background

On February 25, 1983, both of the scram circuits at Unit 1 of the Salem

Nuclear Power Plant failed to open upon an automatic reactor trip signal

from the reactor protection system. This incident was terminated manually

by the operator about 30 seconds after the initiation of the automatic trip signal. The failure of the circuit breakers was determined to be

related to the sticking of the undervoltage trip attachment. Prior to

this incident, on February 22, 1983, at Unit 1 of the Salem Nuclear Power

Plant, an automatic trip signal was generated based on steam generator

low-low level during plant start-up. In the case, the reactor was triaped

manually by the operator almost coincidentally with the automatic tr p.

This failure of the breaker to open upon an automatic reactor trip signal

was undetected by the licensee prior to plant restart.

As a result of the problems identified with circuit breakers at Salem and

at other plants, NRC issued Generic Letter (GL) 83-28, Required Action

Based on Generic Implications of Salem ATWS Events, dated July 8,1983.

This letter required licensees of operating plants to respond to

intermediate-term actions to ensure reli bility of the Reactor Trip System

(RTS). Actions to be performed by the licensees included development of

programs to provide for post-trip review, classification of equipment,

vendor interface, post-maintenance testing, and RTS reliabil:ty

improvement.

The licensee responded to GL 83-28 in several letters dated from

November 4, 1983 to April 1, 1988. These responses described the

licensee's compliance with NRC positions in GL 83-28. This inspection was

performed to verify com)11ance to the licensee's responses and to assess

the adequacy of the 1icensee's current program, planned program

improvements and implementation of present procedures associated with

post-trip review, equi classification, vendor interface,

post-maintenance testing,pmentand RTS reliability for the Grand Gulf Nuclear

Station (GGNS). The results of the inspection are discussed in the

paragraphs that follow.

3. Post-Trip Review

The licensee was requested in GL 83-28, Required Actions Based on Generic

Implications of Salem ATWS Events, to describe their program, procedures

and data collection capabilities to assure that the causes for unscheduled

reactor scrams, as well as the response of safety-related equipment, are

fully understood and applicable corrective actions completed before plant

restart.

The licensee's response to GL 83-28 provided a description of their

program pertinent to performing post-trip reviews. The inspector reviewed

their program, procedures, and interviewed key personnel to assess the

adequacy of the licensee's program for post-trip reviews. In addition,

.

'

.

. .

.

3 ,

the evaluation and conclusion items of the NRC Safety Evaluation Report

(SER) in letters to GGNS on May 5,1985 and October 22, 1985 were verified

to be established. The inspection was formatted to verify that a post-

trip review program has been implemented and meets the following

attributes:

Procedures and equipment exist to cover post-trip review.

Safety assessments of the reactor trip are clearly delineated as part

of the post-trip review.

Post-trip review procedures are reviewed periodically by an onsite

safety review committee such as Plant Safety Review Committee (PSRC)

and upgraded in any areas that have been identified as deficient.

Plant personnel preparing and/or reviewing post-trip documentation

receive initial training and refresher training in post-trip review.

Responsibilities and authorities of plant personnel who will preform

the review and analysis of these events are clearly defined.

Criteria for determining the acceptability of authorized restart have

been established.

Criteria for comparing plant information with known or essential

plant benavior have been established.

Guidelines are established for preservation of evidence of reactor

trips.

The licensee's program with respect to each of tnese attributes is

discussed individually as follows:

a. Procedure and Equipment Exist to Cover Post-Trip Review.

Procedures that were used to verify program actions and documentation

are listed in paragraph 9. For simplicity and clarity, they will be

referred to in the the body of this report by number only.

AP-01-S-06-26 is the primary procedure for post-trip reviews.

ONEP-05-1-02-I-1 addresses immediate action for a reactor trip (or

what to do if a reactor trip should have occurred and did not) and

leads the operctor into 10I 03-1-01-4 for scram recovery. Procedure

01-S-06-5 specifies requirements to document incident reports and

requires notification of reportable events to applicable agencies.

All unplanned reactor trips require an incident report. 01-S-06-76,

addressed NRC and INP0 concerns in the area of reactor trips and is

intended, inpart, to aid in reducing the number of reactor trips. In

addition, the licensee is a member of the BWR Owners Group Scram

Frequency Reduction program.

'

.

.

.

'

4

AP-01-S-06-26 provides the folicwing information:

(1) Purpose

(2) Responsibilities

(3) Definitions

(4) Date Collection

(5)On-shiftAnalysis

. (6) Restart Decision

(7) Off-shift Analysis

(8) Report Distribution

(9) BWR Scram Report for BWR Owners Group Scram Frequency Reduction

_ _

. Committee

.  ;

The above procedure also provides for:

(1) Written statements from individuals involved in the event.

(2) Pre-trip plant status including pre-trip activities which could

(3) potential

Post-trip have

plant contributed

status to the event

(4) Plant response and verification that Reactor Protection System

(RPS) operated properly i

(5 Capture of plant transient information through charts, logs, etc

(6 Engineered safety feature actuations

(7 Cause of trip and Root cause identification

(8) Trip Classification

(9) Sequence of Event Description

(10) Restart Authorization

The reactor trip review places a reactor trip into one of four

classes:

Class I -

The cause of the trip is positively known and has

been corrected; all Safety-Related and other important

equipment functioned properly during the trip.

Class II -

The cause of the trip is positively known and has

been corrected: some Safety-Related equipment did not

function properly; however, the malfunction has been

corrected or a Technical Specification constraint does -

not prohibit'a startup

'

Class III - The cause of the trip is positively known and had not

been corrected or the cause of the trip is not

positively known.

Class-IV -

Some Safety-Related and/or other important equipment

functioned in an abnormal or degraded manner during

the trip and the malfunction has not been corrected or

prevents startup due to Technical Specification

Constraints. '

>

i

.v--g-.- - r ,e ,- r-n- -ew-.e~m, - - - - - - - - - -- - = - - - - - - -

-

.

.

.

5

The data collected for the event includes sequence of events from 80P

and NSSS Alarm Typers, NSSS Post trip log from NSSS Alarm Typer and

80P Post trip log from 80P on-demand typer. During plant operation

the GETARS (General Electrical Transient Analysis Recording System)

is in the Sentinel mode. It is capable of recording many parameters

(channels) for which plots can be made. GGNS presently records 263

channels of information with GETARS in Sentinel mode. The GETARS

data is recorded and saved for approximately 4.67 minutes during a

transient involving a scram ( a) proximately 47 seconds pre-trip and

233 seconds post-trip). Typical parameters monitored and capable of

being plotted from GETARS Sentinel program or other records are:

Narrow Range Level

Narrow Range Dome Pressure

Wide Range Dome Pressure

Total Steamline flow

APRM A thru H

Total Core Flow

Wide Ran e Level

Total Fe dwater Flow

The inspector observed a demonstration of the GETARS and reviewed

post trip analysis for scram numbers 48 and 49. The post trip

analysis were considered to be satisfactory.

b. Safety assessments of the reactor trip are delineated as part of the

post-trip review.

The safety assessment is clearly delineated in procedure 01-S-06-26

under "On-shift Analysis" to determine:

(1) Verification of the proper operation of safety-related systems

and other important equipment involved in the trip operated as

expected

(2) Abnormal indications or degraded trends in equipment performance

(3) Event occurring out of the normal or expected sequence

(4) Failed or abnormal response of equipment to control signals

(5) Unusual chemistry results or radiation readings

(6) Determination if a Technical Specification Safety Limit was

exceeded.

Restart decisions are all made by the General Manager, and if the

reactor trip is a Class III event, the PSRC's recommended actions

have to be resolved and/or completed.

1

.

.

.

.

6

c. Post-trip review procedures are reviewed periedically by an on-site

safety review committee such as PSRC and upgraded in any areas that

have been identified as deficient.

Administrative Procedure 01-S-02-02 provides for biennial review of

AP-01-S-06-26. The Document Control Supervisor initiates and tracks

the review process by distributing a two year Review of Directives

form to responsible managers and section su3ervisors/superiendents

who in turn will assign a knowledgeable incividual to review the

directive / procedure. The Document Control Section retains all

returned two-year review forms as quality records,

d. Plant personnel pre 3aring and/or reviewing post-trip documentation

receive initial training and refresher training in post-trip review

procedures.

The Shift Technical Advisor's (STA) Training program provides for

initial training on the reactor trip procedure. This includes

reading and understanding the procedure, performing on-shift post

trip analysis, determining the cause of scram and completing a post

trip analysis report (See Lesson Plans SC-STA-SIM-LP-021-00, and

LP-013-00, and OP-AD-701/Rev 2). This training is documented on the

STA Qualification Card. Other licensed personnel license

candidates, and designated plant staff members receive training

through periodic required reading in accordance with AP-01-05-04-15.

e. Responsibilities and authorities of plant personnel who will perform

the review and analysis of these events are defined.

AP-01-5-06-26 requires that an on-shift analysis be performed by the

STA or shift supervisor. And when necessary, the PSRC reviews and

make recommended actions for a Class III event. The off-shift

analysis is done within ten working days after permission for plant

restart is given by the General or Duty Manager.

This off-site analysis must be done by a senior Reactor Operator, a

certified STA or by persons having equivalent experience and

background knowledge of the plant to perform the analysis.

Subsequent analysis of the Reactor Trip review is performed by

Operational Analysis Section (0AS) in accordance with NPE 701.

f. Criteria for determining the acceptability of authorized restart have

been established.

As discussed in Section b. the safety assessment determines if all

pertinent plant parameters were within Technical Specification

limits, safety related equipment operated as expected and events

occurred in a proper sequence. All restart decisions are made by the

General or Duty Manager.

'

.

.

.

'

7

g. Criteria for comparing plant information with known or essential

plant behavior have been established.

The trip analysis, AP-01-S-06-26, provides a step by step check list

and based on the analyzer's knceledge, operations are verified to

have occurred as expected. Plant behavior is com

values contained in the Technical Specifications. pared to limitingAny deviat

noted in the report and evaluated.

h. Guidelines are established for preservation of evidence of reactor

trips.

AP-01-S-06-26, paragraph 6.4.12, requires that the original Post-Trip

analysis package be forwarded to central records. AP-01-S-05-1,

Section 6.3, provides for lifetime (of the plant) retention of these

records in the Central Records. Copies of the report which provides

a summar

actions,y,root

verification of on-shift

cause identification analysis,

and summary

observations of corrective

/ recommendations

and the post-trip analysis (without collected data) are routed to the

General Manager, Plant Operations and Maintenance Managers, various

Superintendents NRC Resident Inspector, Operational Analysis Group

andReactorEngIneeringFile

One comment on AP-01-S-06-26 is that it does not specifically call

attention to a Technical Specification requirement (Section E.7.1.a)

to notify the NRC within one hour after determining that a safety

limit has been exceeded. The licensee stated that this was covered

by AP-01-S-06-05, but since the procedure (AP-01-S-06-26)

specifically requires the STA or Shift Suaervisor (SS) to make this

determination, they would consider adding this comment in

AP-01-S-06-26.

Within the areas examined, no violations or deviations were identified.

4. Equipment Classification

The licensee was requested in Section 2.1 of GL 83-28 to confirm that all

components of the Reactor Tria System (RTS) whose function is required to

trip the reactor are ident fied as safety-related on documents,

procedures, and information handling systems ut ed in the plant. These

safcty-related activities also include maintenance work orders and spare

parts replacement. In Section 2.2 of GL 83-28, the licensee was recuested

to describe their program for ensuring that all components of otler

safety-related systems are also identified as safety-related on documents,

procedures, and information handling systems used at the plant.

The licensee's responses to Sections 2.1 and 2.2 of GL 83-28, dated

November 4, 1983, June 28, 1985, and May 14, 1985, provided details of the

current program and the developments of new programs and procedures for

safety-related equipment classification. In these responses, the licensee

made the following statements:

_ _ _ - - - - - - _ - - - _ - _

, - _ _ . __- _ _ _ _ _ _ _ _ _ _ _ . _ _ _ _

.

4

8

"In a BWR, the components which contribute to the reactor trip

function ate found in several systems. For example, components in

the Neutron Monitoring System, Main Steam System and Reactor

Protection System may have a role in initiating a reactor tri

Therefore, the GGNS information handling system (equipment list)p.will

be reviewed to ensure that the safety related components in the

various systems which contribute to a reactor trip are properly

classified.

The existing Q-List original 1 developed by the architect-engineer is

presently being maintained Nuclear Plant Engineering and that a

new component quality classi ication listing is under development.

GGNS has in place procedures which control and require the use of the

Q-List, provide for equipment classification for work activities not

addressed by the existing Q-List, and provides for the review of

procedures which may be used in safety related activities. A review

will be undertaken to verify that procedures controlling safety-

related activities related to components which contribute to reactor

trip functions are properly identified.

A Master Equi ment List (MEL) is being developed to provide useful

data for equ pment and components in the plant, including their

safety class fications. Procedures have been developed to help

personnel determine component classifications and whether components

affected by activities are safety-related."

a. The inspector reviewed licensee's responses, appropriate procedures,

maintenance work orders, procurement documents, and interviewed

respNsible personnel to confirm that the licensee's program for

equipment classification was being implemented and was consistent

with the responses to GL 83-28. The licensee's actions concerning

the NRC's Request for Additional Information were reviewed and

discussed with responsible personnel. They anticipate that a

response to the latest NRC letter dated May 11, 1988, will be

submitted in late June 1988.

b. Discussions revealed that the licensee is developing a new

comprehensive computer program which will include information

presently contained in the Master Equipment List (MEL) and Equipment

Index (EI). This new program, "Station Information Management

System" (SIMS), was approved for use at GGNS in July 1987, and in

January 1988, the licensee started entering data into the SIMS. The

licensee expects the SIMS to be in full operation by June 1989, and

will include approximately 40,000 items. Ti 1 inspector was informed

that the SIMS is currently in use at Waterford and Arkansas Nuclear

Plants. The licensee and contractor, re9ansible for the SIMS,

demonstrated how component data is obtained, how data is entered, and

how data is retrieved and utilized by plant maintenance, engineering,

procurement, and operating personnel. Site QA is familiar with the

program and an internal audit group have audited the program. The

'

.

.

.

'

g I

inspector requested information for four components be retrieved from

the SIMS 3rogram to verify whether the components were classified as i

safety re'ated and if other technical information was available.

Printouts for the following components were obtained and reviewed:

Reactor Vessel Low Level Switch (Safety Related)

Control Rod Drive-Hydraulic Control Unit (Safety Related)

Technical Support Room Door (Non-Safety Related)

Reactor Vessel Level Transmitter (Safety Related)

The printouts for the above com)onents contained all types of

information such as: Vendor, mocel, serial number, Q Class, safety

class, P&ID, location in , plant, vendor manual number, design

parameters, Technical Specificatlons, associated plant procedures,

drawings, and other data. When the program is completed and in full

production in June 1989, it will include information concerning

maintenance activities, surveillance activities, design changes,

NPRDS,EQ,andotherplantactivities. In addition, the program will

gene"ate maintenance work orders and preventative maintenance orders

for the components. In order to ensure that data for each component

is complete and accurate, the program provides a Component Package

Input Tracking Form which has individual checkoff blocks to verify

completion of data collection such as: system walkdown, equipment

index MEL data, P&ID check, document research, engineering review,

dataInput,dataedit,andQAaudit.

c. The following procedures associated with the classification and

cor, trol of safety-related equipment were reviewed:

(1) Procedure 01-5-07-14, revision 4, dated October 30, 1987,

established the methods and controls for maintaining the

Equipment Index (EI). This index lists technical data on

individual safety-related components. The data includes vendor,

drawing numbers, manual number, QA type, and other pertinent

information required to ensure proper maintenance and

calibration of equipment. Information from this EI is being

transmitted to the SIMS program for use in their data base.

(2) Procedure 01-5-02-4, revision 1, dated August 29, 1985,

described the method for identifying safety-related items to

which the licensee's QA program requirements ap)1y. The

procedure also describes how to determine if i; ems not

previously classified as safety-related should be reclassified.

The responsibility for maintaining the Q-List has been assigned

to the Nuclear Plant Engineering Section. This section also

evaluates and classifies components, activities, structures, and

systems as requested by other personnel.

I

.

.

-

.

.

'

10

Any person using a procedure or performing an activity is

responsible to ensure that the activity, component or procedure

has'been classified. Procedures require that "safety-related"

be on the cover sheet of any activity associated with

safety-related equipment, systems and structures. If the

document has not been classified the user must either classify

or refer the document to knowledgeable personnel for

classification.

If the users Section Superintendent or Supervisor cannot

determine the classification, a Material Nonconformance Report

is 3repared to ensure that the equipment or activity is not

uti:ized until properly classified. The Material Nonconformance

Report is also the official mechanism to request assistance in

evaluation from the Nuclear Plant Engineering Section.

Attachment 1 to the procedure provides a criteria for use in

determining the safety classification and contains adequate

guidelines for classifying items. The guideline also requires

that directives, procedures, etc. , that establish means ~ or

methods of performing activities associated with safety-related

items be stamped "Safety Related" on the cover sheet.

Examination of several directives, procedures, maintenance work

orders, and procurement documents revealed that they were

stamped "Safety Related."

(3) Standard No. SERI-JS-08, Instrument Q-List, dated December 31,

1987, provides information for determining 10 CFR 50,

Appendix B, Quality Assurance Requirements to the design,

procurement, and installation of instrumentation at GGNS. This

standard specifies the classification of all instrumentation and

assigns responsibilities to assure that new and replacement

instrumentation meets Seismic Category I, ASME Section III, and

i

Class IE Electrical requirements.

(4) Procedure 01-502, revision 5, dated January 12, 1987, provides

the requirements for maintaining the Q-List and distribution of

the controlled copies. Revisions to the Q-List are made after

, being reviewed and approved by the Quality Engineer, Quality

Assurance, Manager of Nuclear Services, Site Director, and the

Director of Nuclear Plant Engineering,

d. The inspector reviewed the Q-List, Controlled Copy No.034,

revision No.1, dated January 30, 1987, to determine if the Q-List

was controlled, if the cover sheet showed who prepared, who reviewed,

and who approved the current revision. The Q-List was prepared by

engineering, reviewed by Quality Assurance, Nuclear Services and

Fuels, and the Site Director. The Q-List was approved by the

Director of Nuclear Plant Engineering. The Q-List delineated the

systems, structures, and components that are classified as nuclear

safety-related. It also includes services that are safety-related.

. , _ _ - - - - --

.

'

.

.

.

.

t 11

.

The 0-List also contains a list of Non-Safety Related Items for which

the QA program is applicable

The Q-List did not depict individual components associated with the

4 reactor protection system (RPS), however, the entire RPS was

classified as safety-related. Upon questioning, the licensee

produced other documents which had each component in the RPS listed

as safety-related. This list was broken down by mechanical

components, instrumention, and electr! cal components. Discussions

also revealed that the components in the RPS had been entered into

the SIMS program data sheets.

,

e. Activities associated with the implementation of safety-related

'

classification procedures were examined as listed below.

(1) Four purchase order package were reviewed to verify that the

components had been classified as safety-related. The review

'

revealed that the documents contained detailed information to

ensure that the component design, fabrication, testing, and

'

shipment met the licensee's procedural requirements. Documents

reviewed were:

.

Purchase Order No. M98585 dated March 24, 1987

Purchase Ordei No. MP707810 dated September 19, 1985

Purchase Order No. MP808320 dated March 25, 1988 '

Purchase Order No. MP730615 dated November 10, 1987

<

Procedure 01-S-09-1 depicts how procurement documents are

prepared and reviewed to ensure proper safety clas ifications. -

(2) Several Maintenance Work Orders (MW0s) were reviewed to verify

that the components had been classified as safety-related and

that activities had been completed as specified in procedures.

MWO Nos. E72980, E72984, E72982, and E72986 associated with the

RPS Relay Tests were reviewed. These MW0s were initiated to

determine if GGNS HFA Relays were binding as reported in GE SAL

No. 188.1, NRC IEN 82-13, and 88-80-03. The licensee performed

the tests as specified in GE SAL 188.1, thus closing out IFI

50-416/87-14-02. Documents associated with the above tests were

classified as safety-related.

(3) Other MW0s reviewed were Nos. E68391. E75358, E81676, E822135,

E822448, M82336, E82168, M75730, and 173908. The inspector

found that the safety-related block on MWO No. E81676 had not

been checked. The licensee immediately inve:tigated and

presented the inspector with an acceptable explanation. This

was an isolated case as all other MW0s and associated data

sheets were classified as safety-related.

-

.

12

(4) The surveillance procedures listed below were also examined to

verify that they had been classified as safety related:

06-10-1821-R-0038, RV Steam Come Pressure Electronics Time

Response

06-10-1821-R-0044, RV Water Level Calibration

06-IC-1C11-M-0003, Scram Discharge High Water Level Float

Switch Calibration

06-IC-1833-R-001, Reactor Recirc System FCV Functional Test

06-1C-1C51-0-001, APRM Single Loop /Two Locu Operation

Setpoint Adjustment

A review of several vendor manuals revealed that they were not stamped as

"Safety Related." Discussion with licensee representatives revealed that

the manuals were not actually used to perform maintenance and test

activities. Licensee stated that information in the manuals was used to

prepare plant procedures and instructions which were classified as "Safety

Related." A review of plant procedures verified the licensee's

statements.

Based on interviews and the review of procedures, maintenance work

requests, procurement documents, directives, Q-Lists, and computer

programs discussed above, the inspector confirmed that the licensee has

programs and is implementing them to classify equipment and control safety

related activities.

Within the area examined, no violations or deviations were identified.

5. Vendor Interface and Manual Control

The inspector reviewed the licensee's responses to GL 83-28, reviewed

procedures, and examined the implementation of their program associated

with vendor interface and vendor manual control. Their responses

described the following program.

. Licensee management's response transmitted in their letter AECM-

84/0508, dated November 19, 1984, stated that they maintain an

ongoing interface with General Electric Company (GE) and are a member

of the Boiling Water Reactor Owners Group (BWROG). This ongoing

interface provides them with information through GE's Service

Information Letters (SILs) concerning technical items or conditions

that may be applicable to Grand Gulf. Additionally, in accordance

with recommendations of the Vendor Equipment Technical Information

program (VETIP) they are active participants in the INP0 managed

Nuclear Plant Reliability Data System (NPRDS) and Significant Event

Evaluation and Information Network (SEE-IN) program. They concluded

by stating that a program had been established and was being

implemented for vendor technical manuals.

. . - .. _ -

<

.

.

.

'

'

13

-

Licensce's response transmitted in their letter AECM-85/0157, dated

May 14,1985, stated that in June of 1984, letters were sent to

vendors of safety. related equipment in an attempt to establish a

vendor interface. Thirty-three of the vendors contacted res>onded.

Of those responding, approximately 75 per cent transmitted acditional

technical information. Licensee management determined that the

manpower requirements to continue a program of periodically

contacting vendors was prohibitive compared to the knowledge gained.

They further stated that an avaluation had been performed to assure

proper- division of responsibility between System Energy Resources,

Inc. (SERI) and vendors who provide maintenance or testing service.

They concluded by stating that the VETIP as defined in the March 1984

NUTAC document and the SERI programs described in this letter and

letter AECM-84/0508 were valid responses to GL 83-28, Item 2.2.2.

Licensee's response transmitted in their letter AECM-88/0062, dated

April 1,1988, describes the process for receipt and acknowledgement

of GE Service Information Letters (SIls). They stated that all GE

SIls are sent to SERI addressed to the GGNS Site Director with an

attached receipt acknowledgement form. The form is completed by SERI

and returned to GE. In addition, GE sends SERI, approximately every

six months, a listing of all SIls~ issued to date. This list is used

by SERI to verify receipt of all SILs. Those that have not been '

received are requested from GE.

Procedure No. 0701, specifies requirements for evaluations of onsite

and offsite documents by the Operational Analysis Section (OAS). The

)rocess provides for an initial screening by an Investigative

Engineer to determine if the document is applicable to GGNS or

requires evaluations by reviewing P& ids, system descriptions, the

FSAR, or other pertinent plant documentation. Documents that have

been evaluated and determined not to be ap?1icable to GGNS are closed

out. For situations involving documents t1at are applicable to GGNS,

an evaluation is performed to assess possible technical and safety

concerns. The evaluation is required to be of sufficient depth to

determine root cause, safety significance, generic implications, and

necessery corrective action. Additionally, for component failures

that are applicable to GGNS, a review of NPRDS data base is

performed.

The implementing procedure for the evaluations performed by 0AS is

,

EDP-023. Operating experience information is received from several

sources. Paragraph 7.0 of this procedure saecifies the scope and

nature of the operating experience information and the source from

which they were derived. Typical examples are INP0 Significant

Operating Experience Reports and Significant Eve t Reports (SERs)

received through the mail or accessed via the Ntelear Network

respectively. The inspector verified that the scopr of the operating

experience information described was consistent wtth the program

described in licensee's letters.

- . , .

- .- - . .- _. -

_

. - - __ -. -

'

.

.

.

.

14

Discussions with licensee management revealed that a vendor interface

had been established with the NSSS vendor by means of contracts.

Procedure EDP-023, paragraph 7.2.9 specified requirements for review

of SILs and initiating appropriate corrective action. The inspector

determined that the res)onsibility for evaluation of SILs had not

been adequately definec. Additionally, the evaluation of SIls

performed by 0AS was after the review and disposition of the SILs by

other plant or engineering personnel. This evaluation was in most

cases performed long after receipt of the SIL by the licensee. The

inspector identified a lack of (1) accountability for review of SIls

and (2) responsioility for initiating corrective action. Paragraph

7. 6 specifies a screening process for SILs. Additionally,

programmatic deficiencies in the absence of specific guidance for

completion of the screening process were identified. The licensee

informed the inspector that a Quality Deficiency Report, addressing

these deficiencies, had been written against this procedure. The

inspector reviewed licensee's corrective actions taken to revise

procedure EDP-023. Pursuant to this review and discussions with

licensee personnel, the program requirement described in licensee's

letter AECM-88/0062 was incorporated within the corrective action

plan. Licensee management has scheduled conpletion of these

corrective actions and implementation of revised procedure EDP-023

for June 15, 1988.

LER No. 86-026-00, Inadvertent Centrol Rnd Withdrawal was sent to

the NRC by the licensee on August 22, 1986. Informationconcerning

this possible event had previously been provided to the industry by

GE in SIL 292, dated July 1979. This SIL was never received by the

licensee, therefore, the recommended corrective action pr(vided by

'

the NSSS vendor was never im)lemented. Because of this experience,

licensee management initiatec and completed an ef fort to review for

a plicability to GGNS all SIls that had been provided to the industry

b GE. To assess the adequacy of this effort, the inspector selected

t e following SIls for review.

SIL No. 452, Feedwater Flow Element Inspection and Accuracy,

dated June 8, 1987

SIL No. 292, Inadvertent Control Rod Withdrawal, dated July 1979

SIL No. 310, Stuck CR0 Collect, dated October 1979

SIL No.131, Containment Isolation Logic Channe, dated March 3,

1975

SIL No. 353, HPCI Turbine Mechanical Overspeed Trip, dated

February 18, 1981

SIL No.128 RISRI, Pravo* ,ve Maintenance for CRD Scram Pilot

Valves

.

.

.

'

15

SIL No.128R152, ASCO HVA-90-405 Valves and Chemical Adhesive

Thread Lockers, dated March 2, 1984.

No deficiencies were identified in the evaluation and disposition of

the above SIls.

Licensee management has not established a formal vendor interface

with vendors of other safety related items via contractural

arrangement. However, a program has been established and is being

implemented on site for receipt, evaluation, and disposition of all

vendor informaticn. Vendor interface requirements for engineering

procurement specifications are defiaed in procedure NPEAP No.01-306,

Attachments 5. The review and evaluation of vendor information

provided during the design-engineering precass is specified in

procedure NPEAP No.01-302. Other vendor interfaces are established

through owners group. licensee

management has been As a mecber

involved of the TOI

in the Design Owners

Review / QualGroup,ity

Revalidation (DRQR) prograin for the emergency diesel generators.

Recommended changes in maintenance and surveillance of the diesel-

generator made by this group are being coordinated with the

diesel generator vendor prior to implementation on site.

Procedure Nos. E0P-008, AP-703, and 01-802 were reviewed to assess

the adequacy of the administrative controls established for receipt,

evaluation, and disposition of operating experience and/or vendor

information described in licensee s correspondence.

No deficiencies were identified in the above procedures during this

review.

SERI 03erating Manual, Policy No. 8.801, Vendor Manual Control,

specif:es requirements for the receipt, review, distr'!aution,

maintenance, revision, and use of vendor manuals. The licensee is

areseatly in the process of an Operations and Mdntenance (0&M)

Aanual Update program intended to revise the 0&M manuals for systems

and components associated with the reactor tr'p system (RTS). SERI

interoffice memorandum from R. J. Rogers III to J. E. Cross, Subject:

"G. E. Update of RTS Vendor Manuals , dat;d March 10, 1988, states

that GGNS reactor trip system operatin

be updated as part of the com)any's ponse rer,g snd maintenance

to Generic manuals will

Letter 83-28.

The 0&M manual upgrade will se perfo<med by G. E. under contract to

SERI and the scope of the initial affort includes the following

systein manuals.

Power Range Neutron Monitoring System

Startup Range Neutron Monitoring System

Traversing In-Core Probe Calibration System

Proc.ss Radiation Monitoring System

Reactor Protection System

Nuclear Boiler Process Instrumentation

.

.

.

.

16

Upon completion of the RTS manuals, 327 GEK's and 527 other safety

related manuals will require revalidation.

Pursuant to the above effort, changes are being made to Procedure

Number 01-S-05-4, to accomplish the following:

Implements new SERI policy on vendor manuals.

Divides vendor manuals into categories and assigns responsibility for

their review as indicated below:

Manual Category Responsibility

Reactnr Tri) Systems, I NPE & Plant Staff

Ofesels, Lu)e Oil, Maintenance

Selected Turbine Manuals,

and all Safety Related

Balance of Plant II NPE & Plant Staff

Non-safety blated Maintenance

M&TE III Plant Staff I&C

Nonpermanent IV No review required

Plant Equipment

(Hardware / Software) V Plant Staff

Computer

Computer Related Engineering / Reactor

Engineering

Requires Document Control to track vendor manuals through the review

process.

Requires vendor manuals to be approved and issued prior to sending

them to procedure originators for coordination.

Requires procedures requiring revision because of vendor manual

changes to be revised within 60 days.

Requires Document Control to send vendor manuals to the Materials

Section for review for spare parts information and in-storage

instructions.

The inspector discussed the 0&M manual upgrade program with licensee

t management and requested information concerning the implementation date of

revised Procedure 01-5-05-4. He was informed that the procedure will be

issued for use by July 1,1988. Departmental level procedures required

i for implementation of the new SERI policy on vendor manuals are also

! scheduled for development. Review of the Vendor Manual Task Force meeting

l summary dated May 20, 1988, shows that this effort is on schedule.

l

l

l

'

__

r-

,

o

. -

. ..

.

-

.

'

17

The inspector selected the following components classified as safety ,

related and associated with the RTS to verify that appropriate vendor

furnished information had been incorporated into test procedures,

maintenance procedures, or the Technical Specification.

Component Vendor Manual

Reactor Modes Switch G.E. Instruction GEH-20380,

G.E. Control and Transfer

Switch Type SBN

Reactor Vessel High GEK-73698, Volume, IV,

Water Level (Tab 4)

(821-LT-N080A-D)

Scram Discharge Gould Instruction Manual

Volume High Water PD/PDH3018 Series

Level Trip

(IC11-LT-N012A&B)

Scram Discharge Magnetrol International

Volume High Water Bulletin 46-612, Effective

Level Trip date April 1976.

(IC-11-LS-N013A-D)

Comparison of the requirements delineated in surveillance test procedures, -

maintenance procedures and the Technical Specification revealed no

deficiency.

Within this area, no violations or deviations were identified.

6. Surveillance / Post-Maintenance Testing

a. Surveillance Testing

The inspector observed the performance of Surveillance Test Procedure

Nos. 06-lC-1E31-M-0023, 06-IC-lC71-M-001, and OC-IC-M-1103. A

tabletop walkthrough of Loop Calibration Instructions 07-5-53-C11-21

and 07-5-53-C11-22 was also performed. The procedures, in general,

were very well written and easy to follow. One area of concern

identified during a previous inspection was noted. This item '

(IFI-87-26-01) deals with verifying continuity by use of digital

voltmeter (DVM). The procedure calls for a reading of "approximately

0 VAC", yet the reading was approximately 20 VAC and decreasing. The

licensee plans to provide the technicians training in the short term

and implement long term training in the annual training program.

This training should ensure that an understanding of "approximately"

L

is the same for all.

L

"-

.

.

.

.

18

During the review. of 01-S-07-1, it was noted that five Test Change

Notices (TCNs) were outstanding for this procedure. Procedure

01-S-02-2 requires a revision to the procedure be issued within sixty

days after the third TCN is issued, unless an 3xtension is granted by

the Plant General Manager. The licensee identified that it exceeded

the sixty day limit and issued QDR-140-88. The ins

a minor discrepancy in that TCN 45 (issued 2/26/88) pectorTCN

referenced identified

44

(issued 2/29/88). The licensee -then issued QDR-163-88 identifying

the fact that -a TCN . referenced a TCN that was ~not issued at 'that-

time.

b. Post Maintenance Testing

The inspector reviewed the licensee's -maintenance and

ost-maintenance testing records. Seven Maintenance Work Orders

p(W0s) were randomly selected for review. The packages were reviewed

for compliance with 01-S-07-2, for completeness, and for ensuring

data was within the allowed ranges. The W0s audited were as

follows:

W O No. Description

1. I66250 RHR Heat Exchanger 2A/2B Outlet Temp

2. E77176 CTMT Spray Time Delay Relay Channel 6

3. 175953 Turb Control Valve Press Comp Point

4. I64301 Interface Valve Pressure

5. M66292 Outboard Isolation Valve

6. ESO426 RCIC Isolation Valve

7. M75972 FPCC to Filter Demineralizer

No discrepancies were noted on the W0s.

Within this area, no violations or deviations were identified.

7. Surveillance Testing of the Diverse Reactor Trip Functions of the Reactor

Trip System

The licensee performs on-line testing of the Reactor Protection System

during periodic functional channel tests, channel checks, and scram timing

of control rods. On-line testing of the backup scram solenoid valves is

not possible without scramming the plant; however, testing of the backup

scram valves will be performed durin,g each refueling outage. The

inspector confirmed that the licensee s Loop Calibration Instructions

07-5-53-C11-21 and 07-5-53-C11-22 will independently test each backup

scram solenoid valve once every 18 months while the plant is shutdown.

Within this area, no violations or deviations were identified.

_ _ _ _ _ _ - _ - _ _ _ _ _ . _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ - _ - - _ _ _ _ _ _ _ _ _ _ _

.

.

19

8. Inspection Follow-up Items

a. -(Closed) IE Bulletin 88-01, Defects in Westinghouse Circuit Breakers.

The licensee responded to IEB 88-01 by letter dated March 22, 1988,

stating .that the Westinghouse DS series breakers identified in the

bulletin were not used at GGNS. Based on this submittal, this item

is closed.

b. (Closed) IE Bulletin 88-03, Inadequate Latch Engagement in HFA TYPE

Latching Relays Manufactured by General Electric (GE) Company.

As stated in licensee letter AECM-88/0094 dated March 24, 1988, SERI

investigated the use of latching-type HFA relays and had determined

that these type of relays are not used in Class 1E application at

GGNS. Three of these type relays were found in non Class 1E

applications. One of these three has been inspected per GE Letter

No.190.1 and the other two will be inspected during the next

refueling. To ensure that this type of GE relay is not installed

without inspection, a caution statement has been added to the

Material Management Information System (MMIS). Based on the

licensee's letter, this item is closed.

c. (Closed) Inspector Follow-up Item (IFI), 416/87-14-02, Inspection

and/or Replacement of GE HFA Relays Referenced in SAL 188.1.

GE Service Advisory Letter (SAL) No.188.1 dated November 14, 1986,

reported binding problems with type HFA relays. The binding concern

only applies to HFA relays manufactured prior to October 24, 1986.

Tha licensee investigated the problem and found eight potential

effected relays installed in the Reactor Protection System. These

eight relays were checked in accordance with GE instructions during

refueling outage 2 under MW0s E72979 thru E72986 and were found to be

free of mechanical binding. Licensee's Document Review Summary Sheet

No. 8-035, dated April 4,1988, summarized the licensee's investi-

gation. Based on the above, this item is closed.

d. (Closed) IE Information Notice (IEN) 88-14, Potential Problems with

Electrical Relays

, This notice provided licensees with potential 3roblems involving HFA,

PVD 218, FVD 210, and HGA relays manufactured ay General Electric Co.

Grand Gulf Nuclear Station (GGNS) has been evaluating the potential

problems with these type relays since 1932. GGNS's Operational

Analysis Section screens and evaluates NRC Bulletins, NRC Information

Notices, GE's Service Advice Letters (SALs) and Service Information

Letters (SIls), and INP0 Network documents for applicability at GGNS.

This information is being computerized for easy retrievability. Upon

request by the inspector, the licensee retrieved Document Review

Summary Sheets which gave the background and summary of finding /

action taken on these relays. Results of licensee's actions revealed

that they had closed out the GE HFA relay problems in 1982 per PMI

F by

.

- -

..

4

20

82/1152, SER 6-82 dated April 15, 1982. Action o- PVD 21 relays were

closed out in documents dated April 26, 1983, Nr< ember 17, 1983, and

March 8, 1986. GE Century Series Relays were c hsed out in documents

dated December 23, 1982, and March 4,1986. Li:ensee action on GE

SAL No.188.1 concerning HFA relays was completed and closed out by

Document Review Summary Sheet No. B-035.

Licensee action en HGA II and HGA III relays was documented in PMI

83/12746 1983. GGNS's HGA II and I:1 re'ays all

have coilsdated

whichNovember

are normal 15,ly energized; therefore, do not fall into

the 2 millisecond contact opening criteria. GE letter MP GE-83/20

dated September 20, 1983, also stated that the 2 millisecond criteria

was not applicable at GGNS. Based on review of documents and

-

interviews with cognizant licensee personnel,-IEN 88-14 is considered

closed.

e. (Closed) NRC Information Notice No. 88-19, Questionable Certification

of Class 1E Components.

,

Licensee management performed an IE Information Notice Review in

response to the above. This review dated May 13, 1988, stated that

the information notice is not applicable to GGNS because Planned

Maintenance System (PMS) was never approved as a quality supalier and

was never added to the Qualified Supplier List (QSL). The inspector

asked if the licensee had verified that PMS was not a subcontractor

to a qualified supplier on the QSL. In response to this question,

-licensee manacement verified that Telemecanique war ~ the only vendor

who had supp1'ed Class IE fuses for use at GGNS. They further added

that Telemecanique had never qualified PMS as a supplier and they had

never procured Class IE fuses from PMS for use at GGNS. Based on the

above licensee actions, this item is closed,

f. (Closed) Deviation 87-27-01, Offsite Power System Monitoring and

Surveillance

The licensee had a UFSAR commitment to perform functional checks of

relay and control equipment for the offsite power system on a two

year or less interval. It was identified that the last completed

functional check on the protection relay system for the 500 KV system

was performed in June 1983.

The licentee has reviewed its License Commitment Tracking (LCTS)

database to assure that SERI has been assigned as the responsible

organization, where appropriate, and revised the database where

necessary. Chapter 3 of the UFSAR was re-reviewed to ensure all

commitments have been pre;,erly entered into LCTS. Procedure

01-5-15-8 was issued to govern the tracking of new commitments.

Procedure NLAP-2.7 is in the review and approval chain and will

govern the entire database, including updating and changing existing

commitments, assigning responsibilities for meeting the commitment,

and assigning intermediate due dates to ensure the commitment date

G .

j;

ix 3:

'

21'

is not exceeded. Provisions are made to keep management informed

when problems arise in meeting the due dates so that action may be -

taken at the appropriate level.

Based on the corrective action taken and the response in letter dated

February 10, 1988, this item is closed. l

9. Procedures Reviewed

The following procedures were used and/or reviewed for this GL 83-28

inspection:

a.

b.

ONEP 05-1-02-I-1, Reactor Scram

IOP 03-01-4, Scram Recovery

j '

c. AP 01-5-06-26, Post-Trip Analysis

d. I0I 03-1-01-1, Cold Shutdown to Generator Carrying Minimum Load '

e. AP 01-5-02-2, Control and Distribution of the GGNS Operations Manual

f. AP 01-S-05-1, Nuclear Records Procedure

g. NPE AP 710, OAS Document Evaluation

'

h. AP 01-S-04-15, Required Reading Program

i. 10-S-01, Activation of the Emergency Plan i

j. AP 01-S-06-05, Incident Reports / Reportable Events  !

k. 06-IC-IE31-M-0023, Rev. 25, TCN 17, RCIC/RHR and RCIC Steam Line Hi

Flow / Flow (RCIC Isol)  :

FunctionalTest  !

1. 06-IC-IC71-M-0001, Rev. 25, Drywell High Pressure Functional Test

(RCP/PCIS) i

m. 06-IC-IC71-M1003, Rev. 23, Turbine Control Valve Fast Closure '

(RPS/EOC RPT) Functional Test

n. 07-5-53-CII-21, Rev. O, Backup Scram Valve A Functional Test  ;

o. 07-5-53-CII-22, Rev. O Backup Scram Valve B Functional Test

'

p. NLAP-2.7, Rev. O, Licen,see Commitment Tracking (LCTS)

q. 01-S-15-8, Rev. O, Licensee Commitment Tracking (LCTS) for Plant

Staff

!

r. EDP-023, OAS Review Handling and Dis 30sition of Operating Experience i

s. NPE AP-01-306, Engineering Document Requirements

t. EDP-008, Nuclear Plant Reliability Data System Data Submission and

Retrieval

u. AP 703, See-in-Utilization

v. A?01-802, Processing and Evaluation of 10 CFR 21 Potential Defects

w. NPE AP 01-302, Review of Supplier Documents

x. 01-S-07-1, Control of Work on Plant Eculpment and Facility t

g y, 01-5-07-14, Control and Use of the GGh5 Equipment Index

'

z. 01-S-09-1, Procurement of Materials and Services .

aa. 01-S-02-4, Rev.1 Adm. Proc. Determination of Safety / Quality  !

Classifications, Safety Related  !

bb.01-502, Q-List Control

ec. Standard No. SERI-JS-08, Instrument Q-List  !

!

i

A

_ _. _. . _ _ _ - _ _ _ _ _ _ _ _ _

,

.

.

-

'

'

22

10. Exit Interview

The inspection scope and results were summarized on May 24, 1988, with

those persons indicated in paragraph 1. The inspectors described the

areas inspected and discussed in detail the inspection results listed in

the above paragraphs. Although reviewed during this inspection

proprietary information is not contained in this report. Dissenting

comments were not received from the licensee.