ML20206U398

From kanterella
Jump to navigation Jump to search
Insp Rept 50-416/99-02 on 990222-26 & 0308-12.Non-cited Violations Noted.Major Areas Inspected:Engineering
ML20206U398
Person / Time
Site: Grand Gulf Entergy icon.png
Issue date: 05/18/1999
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20206U390 List:
References
50-416-99-02, 50-416-99-2, NUDOCS 9905250198
Download: ML20206U398 (74)


See also: IR 05000416/1999002

Text

v-

.

5

ENCLOSURE

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Docket No.:

50-416

License No.:

NPF-29

Report No.:

50-416/99-02

Licensee:

Entergy Operations, Inc.

Facility:

Grand Gulf Nuclear Station

Location:

Waterloo Road

Port Gibson, Mississippi

Dates:

February 22-26 and March 8-12,1999

Inspectors:

M. Runyan, Senior Reactor Inspector, Engineering and Maintenance Branch

P. Alter, Resident inspector, Project Branch A

W. McNeill, Reactor inspector, Engineering and Maintenance Branch

J. Whittemore, Senior Reactor inspector, Engineering and Maintenance Branch

Accompanying

H. Anderson, Consultant

Personnel

B. Gupta, Consultant

Approved By:

Dr. Dale A. Powers, Chief, Engineering and Maintenance Branch

Division of Reactor Safety

ATTACHMENTS:

Attachment 1:

Supplemental Information

,

Attachment 2:

Design Engineering White Paper

'

Attachment 3:

Instrument Setpoint Program

I

9905250198 990518

PDR

ADOCK 05000416

0

PDR

_

1

-

-

.

!

-2-

EXECUTIVE SUMMARY

Grand Gulf Nuclear Station

NRC Inspection Report No. 50-416/99-02

Enaineerina

A noncited violation was identified concerning an unusually high number of errors that

were identified in the Updated Final Safety Analysis Report. The licensee's prior

contracted review had missed many of the discrepancies identified by the team. The

licensee's onsite review of the subject sections had not yet taken place. None of the

errors resulted in an operability concern. However, the number of errors identified

suggested a potential overall fidelity problem with the Updated Final Safety Analysis

Report, as well as suggested weaknesses regarding the adequacy of the Updated Final

Safety Analysis review and update project (Sections E1.1.1, E1.2.1, and E8.8).

A noncited violation was identified for failure to ensure that Valve P81-F032A, " Engine A

Air Motors (2) Air Supply," which provides starting air to the high pressure core spray

dit:sel generator, remained open, as required. The team found this valve to be partially

closed. A concern was ider,tified that the design of the system combined with licensee

operating policies (these va ves were not locked open) could result in failure to detect

mispositioned diesel air supply valves. The team did not find any requirement for the

licensee to lock these valves open; although, this is the normal industry practice given

the importance of these valves and their susceptibility to mispositioning (Section E1.1.3).

.Setpoint and scaling calculations did not exist for many of the technical specification

parameters associated with the diesel generators, and a setpoint calculation reviewed

by the team was observed to be marginal, in that it did not address loop uncertainties or

sensor types and installations. The adequacy of the bases for instrument setpoints was

considered unresolved pending further NRC review (Section E1.2.1).

The licensee was satisfactorily implementing the requirements of 10 CFR 50.59 for

applicable changes, tests, and experiments. Initial training for individuals performing

<

safety evaluations was adequate; although, formal requalification training was not being

conducted (Section E2.1).

The corrective action program was effective in the identification of design and design

basis issues related to the emergency diesel generators. With respect to problem

resolution, ono notable exception involved an issue related to the Division 111 emergency

diesel generator lube oil inventory, where an excessive oil consumption problem created

inconsistencies between the technical specification bases and the design bases.

Additionally, the team identified three other instances in which the corrective actions

were either limited in scope or did not fully resolve the problems (Section E2.2).

The licensee's temporary modification program was sensitive to design issues and

effectively preserved the design bases for equipment and systems affected by

temporary alterations. However, a problem was identified concerning the

documenting of justification for temporary alterations that remained open past

the original corrective action due date. However, a recent NRC inspection (NRC

,_

--

.

.

3-

Inspection Report 50-416/99-03) of the li:ensee's corrective action program identified a

concern with the control and tracking of tamporary or interim solutions, some of which

may have been used instead of the modifcation process (Section E2.3).

Five motor-operated valves had marginal thrust capabilities to perform their design

=

safety functions. Depending on the available thrust margins, this could result in a trip of

the torque switch and a valve stopping in midcycle. The licensee intended to modify

these valves during the next two refueling outages (Section E8.1).

Corrective actions for two previous violations were limited in scope (Sections E8.2

and E8.3).

,

.

-4-

Report Details

Summary of Plant Status

The unit was shutdown during the first week of the inspection to repair a mein condenser boot

seal. The unit operated at full power during the second week of the inspection.

111. Enaineerina

E1

Conduct of Engineering

E1.1

Diesel Generators and Ventilation - Mechanical

E1.1.0

System Description

-

The plant included three separate, independent diesel generator systems (two standby

diesel generator systems and one high pressure core spray system diesel generator

system). Each of these diesel generator systems was housed in a dedicated room.

Each system had a separate, outside underground fuel oil storage tank with capacity

sufficient to operate the respective diesel generator under postulated loading conditions

'

for a period of 7 days. Fuel oil was transferred by a dedicated fuel oil transfer pump

from the respective storage tank to the associated diesel generator day tank. Each

.

diesel generator had a separate engine lubrication system. Each diesel generator had

'

an air-start system that was rnaintained at an adequate capacity to enable at least five

successive start attempts without recharging. Each diesel generator's jacket cooling

water system removed heat during operation and provided a " keep warm" function

during standby conditions. Each diesel generator room had a separate ventilation

system to provide room temperature control and a sufficient supply of incoming air to

support the combustion process.

E1.1.1

Desian Review

a.

Inspection Scope (93809)

The team reviewed mechanical calculations, drawings, procedures, test results,

licensing and design basis information, other related documentation, and the as-

installed plant condition to ascertain the consistency and accuracy of design information

pertaining to the diesel generators, supporting ventilation systems, and associated

switchgear.

b.

Observations and Findinas

The team identified several discrepancies involving the Updated Final Safety Analysis

Report, design calculations, and drawings as discussed below. Unless stated, these

items were not previously identified by the licensee.

l

.

l

.

-5-

Updated Final Safety Analysis Reoort Discrepancies

1.

Updated Final Safety Analysis Report, page 9.5-24, indicated that the high

pressure core spray diesel generator day tank was located above the

suction elevation of the motor-driven fuel oil pump to assure a slight positive

pressuie at the pump inlet. This elevation difference was questioned by the

team during the plant walkdown. In response, the licensee initiated Condition

Report CR-GGN-1999-0256 to document that the day-tank was actually slightly

below the suction elevation of the motor-driver. fuel oil pump by a small amount

(several inches). The team determined that the as-built configuration did not

present an operational concern because the elevation differences were not large

enough to cause a net positive suction head problem.

2.

Updated Final Safety Analysis Report, pages 9.5-25a/26, indicated that Entergy

Mississippi, Inc., has fuel oil storage facilities at two of its conventional power

plants - Baxter Wilson Steam Electric Station (had 50,000 barrels storage

(

capacity) and Natchez Plant (had a 5,000 barrel storage capacity). The storage

l

facilities at both of these plants were stated as being rnaintained at 50-percent

I

capacity or greater. The licensee had previously identified and confirmed that

these capacities were not maintained as indicated in the Updated Final Safety

Analysis Report. The team determined that the failure to meet the stated

I

capacities did not represent an operational concern because other sources of

fuel oil were available.

3.

Updated Final Safety Analysis Report, page 9.5-30, indicated that the standby

,

diesel engine and the high pressure core spray diesel engine can operate for a

minimum of 30 days without additional Jacket water being required. The licensee

had previously identified that this statement could not be met. The team

determined that the manual makeup capability was sufficient to ensure continued

operability of the diesel engines.

4.

Updated Final Safety Analysis Report, Table 9.5-3, incorrectly indicated a heat

l

removal design margin of 175 percent for the diesel generators (Divisions I and

l

ll). This should have been 34 percent. The team determined that the 34 percent

margin was satisfactory.

5.

Updated Final Safety Analysis Report, page 9.5-37, indicated that the standby

diesel generator air-start system piping was installed at an elevation lower than

the engine inlet, and was provided with a drip leg to provide for removal of any

water, which may accumulate in the lines. After being questioned by the team,

the licensee's representatives reviewed drawings and determined that the

system piping between the air receivers and the engine inlet was not always at

an elevation lower than the engine inlet. However, the air-start system piping

l

installation was configured so that drainage of moisture would be toward the drip

legs and away from the inlet air-start solenoid valves to the diesel generators.

Therefore, the team determined that the piping, as configured, would not be

vulnerable to moisture accumulation.

.

.

-6-

6.

Updated Final Safety Analysis Report, page 9.5-37a, indicated that the

performance of the diesel generator air-starting system filters and strainers for

the standby diesel generators was monitored by a pressure sensor located just

upstream of the solenoid valves, which admit air to the air header on the engine.

The report also stated that the pressure sensor detected pressure downstream

of the final strainer. During the walkdown, the team observed the pressure

sensor, but noted that it was not located just upstream of the solenoid valves and

was also not located downstream of the final strainer. The team determined that

the installed pressure sensor configuration did not cause an operability problem

but that it did raise a concern related to the ability to detect mispositioned valves

in the air-start system, which is discussed in Section E1.1.3 of this report.

7.

The Updated Final Safety Analysis Report, Chapter 3, discussion of a

commitment to Regulatory Guide 1.137, " Fuel-Oil Systems for Standby Diesel

Generators," January,1978, did not list several nonconformances to the

Regulatory Guide or to the standard it endorsed (ANSI N195-1976, " Fuel Oil

Systems for Standby Diesel-Generators"). These nonconformances are listed

below:

(a)

Suction from the day tanks was essentially from the bottom (only slightly

offset from the bottom), whereas ANSI N195-1976, Section 6.1," Tanks,"

stipulated that the suction from the day or integral tank or tanks shall be

from above the tank bottom. No exception was identified in the Updated

Final Safety Analysis Report discussion (on page 3A.1.137-1/-2) of the

nonconformance with the Re Mory Guide / ANSI Standard in this regard.

The licensee initiated Condition Report CR-GGN-1999-0325 to document

1

this discrepancy. The team did not consider the day-tank fuel oil suction

i

configuration to represent an operational concern because, historically,

sediments have not been a concern in these tanks.

(b)

Flame arrestors were not installed in the fuel oil storage tank gooseneck

vents. The Updated Final Safety Analysis Report included a statement

that the flame arrestors were not installed. However, no exception was

identified in the Updated Final Safety Analysis Report discussion (on

page 3A.1.137-1/-2) of the nonconformance with the Regulatory

Guide / ANSI Standard in this regard (which required that flame arrestors

be installed). Condition Report CR-GGN-1999-0325 was initiated to

document this discrepancy. Based on the configuration of the vents and

the lack of proximate, credible ignition sources, the team did not consider

the absence of the flame arrestors to constitute an operational concern.

(c)

ANSI N195-1976, Section 5.2," Single-Unit Nuclear Stations," indicated

that the onsite oil storage shall be sufficient to operate the minimum

number of diesel-generators following the limiting design basis accident

for either 7 days or the time required to replenish the oil from sources

outside the plant site following any limiting design-basis event, whichever

is longer. The licensee's representative was unable to locate

documentation that an evaluation was performed to determine the worst-

case replenishment time. Condition Report CR-GGN-1999-0331 was

1

-

-

-7-

)

initiated to review this matter. Because of the nearby availability of many

]

fuel oil sources, the team did not believe that the worst-case

1

replenishment time would exceed 7 days.

(d)

ANSI N195-1976, Section 6.1, " Tanks," indicated that day-tank capacity

shall be sufficient to maintain at least 60 minutes of operation at the level

where oil is automatically added to the day tank. The day-tank level at

which the associated transfer pump starts corresponded to a volume

sufficient to maintain only 30 minutes (not 60 minutes) of operation.

Although the team did not have an operational concern with this design

feature, there was not a clear exception taken in the Updated Final Safety

Analysis Report (on page 3A.1.137-1/-1) to this apparent inconsistency

with the Regulatory Guide.

8.

Updated Final Safety Analysis Report, page 9.5-23, Section 9.5.4.2, indicated

that each standby diesel generator fuel oil storage tank included a usable

capacity of 62,000 gallons. This number was identical to the technical

specification requirement. Calculation MC-01P75-90190," Diesel Fuel Storage

Requirements for the Division i Diesel Generator," Revision 1, determined a

usable capacity of 61,914 gallons, which was then " rounded up" by 86 gallons to

62,000 gallons. The corresponding calculation for the high pressure core spray

diesel generator resulted in 41,158 gallons, which was also rounded up by 42

gallons to the Updated Final Safety Analysis Report / technical specification value

of 41,200 gallons. However, the team noted the calculation conservatively did

not include the much larger additional volumes that would be contained in the

ends of the horizontal tanks. These would more than offset the

nonconservatisms introduced by the rounding up operations. Therefore, no

operational concern existed.

9.

Updated Final Safety Analysis Report, page 9.5-23, Section 9.5.4.2, indicated

that, for each standby diesel generator, the fuel not consumed by the engine was

returned to the fuel oil drip tank from which it was pumped and returned to the

day tank by the fuel oil drip return pump. In response to the team's questions,

the licensee confirmed that this statement was not completely accurate because

it neglected the flow of unconsumed fuel oil from the injector pumps, which was

also routed back to the fuel oil day tank.

Combined with the discrepancies identified in Sections E1.2.1 and E8.8 of this report,

these errors raised a general concern with the fidelity of the Updated Final Safety

Analysis Report. However, no operability concerns were raised as a result of the

identification of these discrepancies.

10 CFR 50.71(e) requires that the safety analysis report be periodically updated to

ensure that the material contained in this document remains accurate. The licensee's

failure to correctly update the items discussed above and those items listed in

Sections E1.2.1 and E8.8 of this report represent a violation of 10 CFR 50.71(e).

i

,

l

.

-

-8-

{

The licensee was in the process of reviewing the Updated Final Safety Analysis Report

for accuracy and had not completed reviews of any of the sections reviewed by the

team. The team noted that the first-stage contractor reviews of these sections had

missed many of these discrepancies. The team did not believe that the licensee's

review would have likely identified most of the discrepancies identified by the team.

However, becana none of the discrepancies involved a safety or operability concem

)

and the ;;censee immediately placed each discrepancy into their corrective action

program, this Severity Level IV violation is being treated as a noncited violation

(50-416/9902-01), consistent with Appendix C of the NRC Enforcement Policy. This

'

violation is in the licensee's corrective action program as various condition reports that

were initiated to document these items (i.e., 1999-0256,1999-0325,1999-0331,

1999-0319,1999-0317,1999-0279, and 1999-0261).

i

Following the onsite inspection, the licensee submitted to the NRC an " Engineering

'

White Paper" (Attachment 2) to explain their position regarding the Updated Final Safety

Analysis Report discrepancies identified by the team. The white paper acknowledged

t

the discrepancies, but emphasized the lack of safety significance resulting from the

identified errors and the fact that some of the items were more misleading than

incorrect. The team concurred with this assessment.

Desian Calculation Discrecancies

i

Calculation 7.6.9C, " Diesel Generator Fuel Oil Supply System - Calculate the Discharge

Pressure for the Diesel Generator Fuel Oil Transfer Pumps," Revision C, was based on

seven 90-degree elbows in the fuel oil transfer line from the underground transfer

pumps to the respective fuel oil day tanks. The sketch contained in the calculation

indicated there were eight 90-degree elbows. The licensee's representative verified

from plant drawings that there were actually more than eight 90-degree elbows in the

respective lines. The licensee initiated Condition Report CR-GGN-1999-279 to

document this discrepancy. Based on the available margin, the team confirmed that this

discrepancy did not affect the operability of this system.

Calculation 7.6.26, " Standby Diesel Generator System - To Determine the Line Size for

the Discharge Line from PSVF026 A & B," Revision 0, did not address, in evaluating the

potential back pressure on the relief valve, that there would be flow in the subject

discharge line from both the relief valve (when the relief valve is open) and the injector

pumps' lubrication flow (when the diesel generator is running). The calculation

conservatively evaluated the flow from the relief valve through the discharge line at

j

35 gallons per minute, and evaluated a maximum allowable backpressure on the relief

valve of 4 pounds per square inch. The calculation did not address the cor$stant

backpressure on the relief valve, which would result from the injector pumps' lubrication

flow when the diesel generator was running. Because this effect was enveloped by the

other conservatisms in the calculation, the team had no concerns with the final result of

'

the calculation.

The team noted that these calculational discrepancies did not affect the operability of

the affected systerns.

'

.

.

.

,

-9-

Drawina Discrepancy

The "as-surveyed" elevation levels from Calculation SC-1P75-LT-N004, " Standby

Diesel Generator Fuel Oil Day Tank Volume and Level Instrumentation Scaling

Calculation (1 P75-LT-N004A&B,1 P81-LT-N004)," Revision 0, were identified by the

team to differ from Drawing J-1692, " Level Setting Diagram Standby Diesel Generator

Fuel Oil Day Tank A (B) Q1P75A004A (B)," Revision 5. In response to the team's

finding, the licensee issued Condition Report CR-GGN.1999-0328. The team evaluated

the olevation differences, which were in the range of severalinches, to be of no

operational concern.

c.

Conclusions

The team identified several discrepancies in the Updated Final Safety Analysis Report.

This was identified as a concern related to the fidelity of this document. The subject

sections of the Updated Final Safety Analysis Report were reviewed previously by a

licensee contractor as part of the fidelity review program (discussed in Section E8.8 of

this report). This review missed many of the problems found by the team. However, the

licensee had not completed the onsite review of the contractor's work. While none of

the errors resulted in an operability concern, multiple problems were identified by the

NRC as noted further in Sections E1.2.1.b and E8.8.b.

)

' The team identified several minor errors in calculations and drawings but did not

consider the number or nature of these items to be excessive. None of the

discrepancies identified resulted in an operability concern.

,

E1.1.2

Surveillance Test

a.

Inspection Scope (93809)

The team reviewed surveillance test documentation in relation to fuel oil transfer pump

inservice performance, starting air receiver tank / starting air system leakago testing,

starting air admission solenoid valve operation, relief valve set pressure testing, and

Jacket water cooler and heat exchanger performance.

b.

Obsenvations and Findinas

No significant concerns were identified concerning these test results. However, the

team noted that there existed a potential for instrument measurement uncertainties to

mask the results of the starting air receiver tank and starting air system leakage tests.

This was because the measured leakage was often less than the instrument uncertainty.

However, because tra measured leakage was less than the limiting values, the team

considered the results to be acceptable.

c.

Conclusions

Surveillance test results reviewed by the team were satisfactory.

F

1

-

\\

.

-10-

)

E1.1.3

System Walkdown

,

a.

Insoection Scoce (93809)

Team members participated in a walkdown of the standby diesel generators (Divisions I

)

and 11), the high pressure core spray diesel generator (Division Ill), and associated

ventilation systems. The plant walkdown, however, concentrated on the Division I and

)

lli diesel generator rooms and associated equipment.

b.

Observations and Findinas

At 11 a.m. on February 23,1999, the team found High Pressure Core Spray Diesel

Generator Starting Air System Manualisolation Valve P81-F032A," Engine A Air Motors

(2) Air Supply," partially closed. The valve's self-locking operating lever was found

unlatched with the lever not in line with the system flow path. The three other

corresponding isolation valves were found to be fully open, as required. The system

]

engineer who was present at the time informed the control room and the team verified

that the valve had been restored to a fully open position by 1 p.m. on the same day.

The licensee initiated Condition Report 1999-0235 and performed a valve lineup

'

verification on the high pressure core spray diesel generator starting air system.

No other mispositioned valves were discovered. The licensee speculated that the valve

was inadvertently bumped during maintenance work.

j

The position of Valve P81-F032A was not routinely checked on the nonlicensed

operators, "Outside Rounds Sheet," Revision 102. A valve lineup was also not required

)

as part of Surveillance Procedure 06-OP-1P81-M-0002,"HPCS Diesel Generator

j

Functional Test," Revision 104. The system engineer reported that the position of this

1

valve was monitored by a low pressure switch, PSL-N111 A, located downstream of the

valve, which causes a " Low Air Pressure" alarm locally and a common trouble alarm in

the control room. The team determined that a low pressure condition would not be

sensed by this pressure switch during a static standby condition with Valve P81-F032A

in a throttled position, in that significant pressure losses would only occur in the high-

flow conditions accompanying an engine start. However, in this instance, the other pair

of air-start motors for that engine would have been available, as well as both sets of air-

start motors for Engine B. Therefore, with starting air available to at least one half cf

the high pressure core spray diesel generator air-start motors, there was no operability

concern. Based on engineering judgment, the team considered the as-found

configuration of Valve P81-F032A to be such that there would have been no significant

restriction of air flow to the air-start motors. Based on these considerations, the team

agreed with the licensee's assessment that operability was not affected by this incident.

Grand Gulf Technical Specification, Section 5.4.1, requires that written procedures be

established, implemented, and maintained for the following activities: (a) the applicable

procedures recommended in Regulatory Guide 1.33, Revision 2, Appendix A, February

1978. The requirement applies to system operating procedures for the high pressure

core spray diesel generator. System Operating Instruction 04-1-01-P81-1,"High

Pressure Core Spray Diesel Generator," Revision 44, Attachment 1," Manual Valve

Lineup Checksheet," requires Valve P81 F032A to be open. The failure to maintain

Valve P81-F032A in the open condition was a violation of Technical Specification 5.4.1.

.

.

-11-

Because the high pressure core spray diesel generator remained operable and

immediate corrective action was taken by the licensee, this Severity Level IV violation is

being treated as a noncited violation (50-416/9902-02), consistent with Appendix C of

the NRC Enforcement Policy. This violation is in the licensee's corrective action

program as Condition Report 1999-0235.

The team identified a cor.cern related to the licensee's decision to not lock open the air-

start valves on the three divisions of diesel generators. As mentioned above, the

downstream pressure sensors would not detect a partially closed valve, nor would

operator rounds identify this condition. Therefore, if redundant air-start valves were in a

partially closed position, the diesel generator could potentially be unable to start;

although, this condition may not be discovered until the next monthly functional test.

The team discussed this concern with the licensee and determined that no regulatory

requirements were applicable to this matter.

In discussions following the exit meeting, the licensee's representative stated that the air

start valves were not locked open because they were redundant and no single valve

being out of position could cause a loss of function. This reasoning followed the

licensee's interpretation of single-failure protection. On the other hand, valves that

could singly defeat safety-related functions if mispositioned were placed into the locked

valve program. The team acknowledged the licensee's policy, but still considered the

general industry practice of locking these valves open to be prudent considering the

critical nature of these valves and their susceptibility to being mispositioned.

c.

Conclusions

A noncited violation was identified for failure to ensure that Valve P81-F032A, * Engine A

Air Motors (2) Air Supply," remained open as required. The licensee's detection

capability of mispositioned diesel generator air supply valves was limited.

E1.2

Diesel Generators and Ventilation - Electrical

E1.2.0

System Description

Normally, offsite power supplies the nonsafety-related buses and three 4.16 kV safety-

related Engineered Safety Features Buses 15AA,16AB and 17AC. On degraded

voltage or loss of voltage from offsite power sources, each engineered safety features

bus is supplied by its own standby diesel generator. The loss-of-offsite power or the

loss-of-coolant accident signals automatically start the standby diesel generators.

Standby diesel generator operation is supported by the auxiliary subsystems (fuel oil,

lube oil, jacket water, etc.) and by 4.16 kV engineered safety features distribution and

diesel generator building ventilation systems. In the event of a loss of offsite power or a

loss-of-coolant accident, all the loads are shed from engineered safety features buses

(except the loads connected by 480 motor-control centers) and are then reconnected

back to the bus sequentially after the diesel generators are supplying adequate voltage

and frequency.

,

.

.

-12-

E1.2.1

Desian Review - Electrical

a.

Inspection Scoce (93809)

The team reviewed design documents including the Updated Final Safety Analysis

Report, design calculations, specifications, and drawings to determine the plant's

conformance to the design basis.

b.

Observations and Findinas

Updated Final Safety Analysis Reoort Discrepancies

The team identified several discrepancies in the Updated Final Safety Analysis Report,

as discussed below.

1.

Updated Final Safety Analysis Report, Section 8.3.1.1, page 8.3-1, stated that

during normal operation, with all three engineered safety features transformers

available, each division of load (i.e., Division I,11, and Ill) is supplied from a

separate winding of each two-winding engineered safety features transformer.

However, Division ll and Division lll were being supplied from the same

transformer (Engineered Safety Features Transformer 21). The team

determined that this configuration was acceptable from an operational standpoint

because Transformer 21 was capable of supplying the design loads with an

acceptable voltage profile and redundancy was maintained with two of the three

transformers lined up to supply power.

2.

Updated Final Safety Analysis Report, Figure 8.3-0078 (Grand Gulf Drawing E-

1026, "One Line Meter and Relay Diagram,120 and 240v ac Uninterruptible

Power Supplies" ), did not accurately represent the current plant configuration.

This figure, as identified by licensee records, was identical to Drawing E-1026,

i

Revision 10, while the current plant drawing was Drawing E-1026, Revision 12.

The differences between these two drawing revisions were minor, mainly

consisting of changes to informational notes.

3.

Updated Final Safety Analysis Report, Section 8.3.1.1.3, page 8.3-9, stated that

the load shedding and sequencing system did not prevent load shedding of the

emergency buses in response to a loss of preferred power or a loss-of-coolant

accident signal once the onsite sources were supplying power to all sequenced

loads on the buses. This statement was misleading because it was true,

independent of the power supply status of the onsite sources.

4.

Updated Final Safety Analysis Report, Figure 8.3-9, and associated load

sequencing Drawing E-1039, erroneously showed a 0.9-second time delay for a

degraded voltage relay versus 9.0 seconds stated in the technical specifications.

This discrepancy was an editorial problem only.

5.

Updated Final Safety Analysis Report, Table 8.3-9, listed Load 1R20 FDR

Breaker 152-1603 (transformer for drywell chi!!ers) twice; once on page 3 and

again on page 4. There was no operationalimpact associated with this error,

j

i

'

.

.

-13-

6.

Motor-operated valve loads were not accounted for within a listing of engineered

safety features bus standby diesel loads in Updated Final Safety Analysis

Report, Tables 8.3-1 and 8.3-2, and within Calculation E-DCP82/5020-1,

" Transient Loading on Diesel Generators during Load Sequencing," Revision A.

Even when motor-operated valves do not actuate, they require loading for

indicating lights, relays, etc. Additionally, motor-operated valves could actuate at

any time when certain operating conditions exist. As such, motor-operated

valves should have been included within the engineered safety features bus

loads for the standby diesel generators. The team confirmed that the failure to

list motor-operated valves within the loading analysis did not result in an

operability concern, as sufficient margin was available to account for motor-

operated valve operation.

These discrepancies, in combination with those discussed in Sections E1.1.1 and E8.8

of this report, were indicative of a fidelity problem with the Updated Final Safety Analysis

Report. This concern, along with the enforcement aspects of this issue, are discussed

in Section E1.1.1 of this report.

Technical Specification Bases and Plant Confiauration

The team identified the following two errors within the technical specification bases:

1.

Technical Specification Bases, page B 3.8-2, stated, "The load shedding

sequencer circuits actuate on loss of offsite power or a loss-of-coolant accident

signal. The system starts the diesel generators and, if an undervoltage exists on

a Division i or ll bus, it sheds nonvital loads from the affected bus." The team

identified two discrepancies associated with this description. The load shedding

sequencer sheds the loads whether bus undervoltage exists or not. Secondly,

all loads, including safety-related loads, would be shed except 480 V load

centers and motor-control centers. The team considered the as-built design of

this system to be acceptable, and the error to be editorial in nature.

2.

Technical Specification Bases, page B 3.3-226, stated that nominal trip setpoints

for plant instruments were specified within setpoint calculations. It further stated

that the analytical limits were derived from the limiting values of the process

parameters obtained from the safety analysis, and that the allowable values were

derived from the analytical limits, corrected for calibration, process, and some of

the instrument errors. However, there were no setpoint calculations delineating

the analytical setpoint values. This issue is further discussed below.

Setooint and Scalino Calculations

The team reviewed calculations and other documents to verify that the plant's analytical

parameters were properly represented in instrument setpoints and that scaling

calculations provided the required relationship of technical specification parameters

(such as fuel oil quantity in gallons) to the indicated plant values (such as a graduated

,

scale on a level indicator).

.

.

-14-

The team reviewed a document entitled, " Methodology for the Generation of Instrument

Loop Uncertainty & Setpoint Calculations," GGNS-JS-09, Revision 0. The team noted

that the methodology did not identify or define technical specification allowable values

with respect to the methodology's allowable values. In response to the team's

questions, the licensee's representative stated that the methodology's analytical value

was the same as technical specification analytical value. Based on this response, the

team commented that the difference oetween the analytical value and the setpaint was

not adequate since it did not include measuring and test equipment uncertainties in the

difference. The narrow difference between the setpoint and the analytical value might

result in technical specification parameters being out of limits.

The team found that the licensee did not have setpoint and scaling calculations for

technical spec ~fication parameters involving the diesel generators. Also, no

,

documentation existed for recording loop uncertainties in the absence of formal setpoint

calculations. The licensee could not demonstrate the amount of loop uncertainties

(including measuring and test equipment) in support of the current setpoints.

The team reviewed Calculation JC-01P75-90040, " Standby Diesel Generator Fuel

Oil Day Tank Volume and Level Setpoint Calculation," Revision 3, for Level

Switches 1P75-LIS-N602A/B. These switches start the fuel oil transfer pump to transfer

dieseliuel from the storage tank to the day tank. The calculation relied on the day-tank

volume calculation to determine the inches of tank height (37.5 inches) where the

transfer pump should start. The calculation used 39 inches (allowing 1.5 inches margin)

as the setpoint to start the fuel transfer pump. The calculation did not include any

details about the type of level sensor, level sensor installation, type of level loop

components, or the compilation of any loop in accuracies or uncertainties.

1

The team reviewed Technical Specification Surveillance Requirement 3.8.3.1.a (fuel oil

1

storage tank 262,000 gallons of fuel for Diesel Generators 11 and 12). The team asked

for information that translated the tank volume to the indicated values including loop

i

uncertainties. Typically, a scaling calculation would have information about the tank

volume and level sensor details, including an installation drawing and other information

on other loop components such as the transmitter and indicator. A scaling calculation of

this type would compile total loop uncertainties, as applicable to the indicator, which was

used to meet the technical specification variable. However, the licensee did not have

j

any such calculation or documentation.

The licensee's setpoint calculational program did not address all the technical aspects

typically supporting setpoint and scaling calculations. The team was generally able to

determine that the current technical specification setpoints relating to the diesel

generators appeared conservative, but noted that the accompanying documentation was

not comprehensive. The adequacy of the bases for instrument setpoints will remain

)

unresolved pending further NRC review (50-416/9902-03).

I

Following the onsite inspection, the licensee submitted a document entitled " Instrument

Setpoint Program" (Attachment 3) to explain their position regarding the instrument

.

.

-15-

t

setpoint program. This paper acknowledged the lack of calculational support for many

of the safety related setpoints in the plant, but emphasized that the methodologies used

t

to establish the setpoints were technically sound, and that the existing setpoints were

conservative. The team acknowledged this information. Through further inspection, the

NRC will determine whether the licensee's conclusions are accurate.

c.

Conclusions

The team did not identify any operability concerns related to the electrical design of the

diesel generators or associated ventilation and switchgear.

Numerous errors were identified within the Updated Final Safety Analysis Report, which,

when combined with those errors discussed in Section E1.1.1 of this report, raised a

concern with the general fidelity of the Updated Final Safety Analysis Report, and the

adequacy of the licensee's Updated Final Safety Analysis Report update and review

project.

The team determined that setpoint and scaling calculations did not exist for many

technical specification parameters, and one setpoint calculation reviewed by the team

was observed to be marginalin that the extent and quality of setpoint and scaling

documentation appeared to be lacking.

E1.2.2

Surveillance Test

a.

Insoection Scope (93809)

The team reviewed diesel generator electrical surveillance procedures to determine their

j

conformity with the plant's design and licensing bases. The team reviewed the

functional test and calibration data for the degraded voltage and loss of voltage

,

setpoints test performed on February 3,1999.

b.

Observations and Findinas

The reviewed surveillance procedures were satisfactory. The results of the test

described above were documented properly and test results were within acceptable

limits.

c.

Conclusions

The team did not identify any concerns related to surveillance testing of the diesel

generator electrical design features.

E1.2.3

System Walkdown

a.

Inspection Scope (93809)

The team conducted a walkdown inspection of the electrical portions of the standby

diesel generators and high pressure core spray diesel generator.

.

.

-16-

b.

Observations and Findinas

The team found the visible electrical features of the diesel generators and suppor1

subsystems to be in acceptable condition,

c.

Conclusions

The electrical portions of the standby diesel generator and support system equipment

were in visually acceptable condition.

E1.2.4

Modifications

a.

Insoection Scoce (93809)

The team reviewed three modifications associated with the Division I and ll standby

diesel generators day-tank high level alarm and hardware evaluation in regard to

fire-induced failures of safety-related circuits,

b.

Observations and Findinas

The team found that these modifications were performed properly

c.

Conclusions

Modifications reviewed by the team were found to be acceptable.

E2

Engineering Support of Facilities and Equipment

E2.1

Evaluation of 10 CFR 50.59 Safety Evaluation Proaram

a.

Insoection Scone (93809)

The team reviewed procedures and other documentation, safety evaluations, and the

training and qualification program to determine whether the licensee was properly

implementing the requirements of 10 CFR 50.59,

b.

Observations and Findinas

Procedures

The team determined that the procedures defining the 10 CFR 50.59 program were

{

consistent with the requirements of 10 CFR 50.59.

!

Imolementation

The team reviewed 28 safety evaluations. Through discussions with licensee

representatives, the team was able to resolve all questions concerning these

-

-

.

-17-

evaluations. In each case, the team concluded that the licensee's determination that an

unreviewed safety question did not exist was correct. Generally, the documentation in

{

the safety evaluations was adequate in scope to understand the issues without a need

to reference other documents.

Trainino and Qualifications

To be qualified to perform or review a 10 CFR 50.59 evaluation, an individual must have

completed an approved training course and be designated as a reviewer. The site

management was responsible for determining the technical competence of each

reviewer to perform evaluations in any particular area. The team reviewed various

I

training documents and determined that the level and depth of the training was

appropriate and consistent with the procedural guidelines.

'

However, there was no requireinent for formal requalification training on a periodic

basis. In response to this observation, the licensee's representative stated that there

were two rneans by which performers and reviewers of safety evaluations received

continuing training. First, the plant safety rcview committee's review of each safety

evaluation was viewed as a defacto requalification, in that, the individual would receive

feedback for any problems identified in one's work. The team considered this policy to

be adequate hr those individu@ who performed or reviewed evaluations on a regular

basis, but many reviewers did not coutinely perform evaluations. The second means of

continuing training was the required reading of quarterly safety evaluation newsletters,

which discussed ongoing issues related to violations of 10 CFR 50.59 and related policy

matters. The team reviewed a sampe of the newsletters and observed that they could

effectively enable such training. The 'icensee's representative also stated that the site

would be converting to an Entergy-wide 10 CFR 50.59 procedure before the end of

1999. The licensee's representative anticipated that this new procedure would provide

for requalification training; although, a final decision on this matter was still pending.

The team reviewed the licensee's list of approved 10 CFR 50.59 safety evaluators. A

total of 433 individuals were qualified as of October 26,1998.

c.

Conclusions

The licensee was satisfactorily implementing the requirements of 10 CFR 50.59 for

applicable changes, tests, and experiments. Initial training for individuals performing

safety evaluations was adequate; although, formal requalification training was not

offered at the time of the inspection.

E.2.2 Condition Reoorts

a.

inspection Scope (93809)

The team reviewed licensee Procedure 01-S-03-10,"GGNS Condition Report,"

Revision 3, and the condition reports listed in the attachment that reported anomalies

for the emergency diesel generators and their supporting systems. The sample was

selected to assess the effectiveness of the corrective action system to identify and

address design and design basis issues related to the emergency diesel generators.

.

.

.

-18-

I

b.

Observations and Findinas

Division 111 Emeraency Diesel Generator Lube Oil Sumo Level

Condition Report 1996-0174, initiated by operations personnel, requested engineering to

define operability limits for the lube oil sump levels in the Division ill emergency diesel

generator lube oil sumps for standby and loaded conditions. (The level in the sumps

varied with the engine condition.)

According to the Updated Final Safety Analysis Report, Sections 9.5.7.2.1 and 9.5.7.2.2,

the Division 111 diesel generator lube oil sump tanks contained a sufficient quantity of oil

for 7 days of diesel generator operation at rated load without adding lube oil.

Table 9.5.6 of the Updated Final Safety Analysis Report also indicated that the total

capacity of each Division lli engine lube oil sump was 306 gallons with 234 gallons

usable.

According to Grand Gulf Nuclear Station System Design Criteria,"HPCS [high pressure

core spray) Diesel Generator System," Revision 0, Section 4.21, the high pressure core

spray (Division Ill) diesel engines ". . . shall have a lube oil pan with capacity to hold

sufficient usable lube oil for 7 days operation at rated load without replenishing the sump

lube oil inventory."

Technical Specification 3.8.3.B required that the usable sump inventory be at least

101 gallons. A level below 101 but greater than or equal to 87 gallons required the

emergency diesel generator to be declared inoperable if inventory was not restored to at

least 101 gallons within 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br />. According to a licensee representative, the crankcase

dipsticks " FULL" and " LOW" marks equated to respective usable inventories of 101 and

87 gallons. The basis for Technical Specification 3.8.3.B was to provide sufficient oil to

operate at full load for 7 days, assuming the normal lube oil consumption rate. The

normal consumption rate, according to the vendor, was 0.6 gallons per hour and,

therefore,101 gallons of usable inventory would meet the 1-week (168 hour0.00194 days <br />0.0467 hours <br />2.777778e-4 weeks <br />6.3924e-5 months <br />)

requirement. With sump inventories less than a 7-day supply (below the " FULL" mark),

it was acceptable to operate with a 6-day supply (corresponding to 87 gallons) after

entering a 48-hour action statement that allowed time to replenish the oilinventory. Any

inventory less than or equal to the dipstick " LOW" mark would immediately place the unit

j

in an inoperable condition.

This documented guidance was complicated by the exhibition of different inventories

during standby and loaded conditions. The licensee had established that this difference

in inventory amounted to about 40 millimeters less on the dipstick when the unit was

running and loaded. The solution arrived at by the licensee was to calibrate and mark

the dipstick above the " FULL" mark, and maintain the inventory at least 40 millimeters

above the dipstick " FULL" mark in the standby condition. Thus, when a loaded run was

commenced, the drawn down oil inventory would be at the " FULL" mark and the facility

license condition would be satisfied. This action was completed and Condition

Report 1996-0174 was closed.

_-

_____

.

.

-19-

Condition Report 1998-0733 identified that under loaded conditions, the Division ill

tandem diesel engines were consuming oil at greater than the normal rate. Testing

eventually revealed a consumption rate of about 0.95 gallons per hour, which was about

'

60 percent above the vendor stated normal rate of 0.6 gallons per hour. The two

elements of oil consumption during operation of the equipment were thought to be oil

leakage anct the buming of oilin the engine during the combustion process. The

licensee was unable to quantify how much oil was leaking from the engines and how

much was being consumed by the combustion process.

The team recognized an additional complication that the licensee had not considered.

The pressure in a running engine crankcase is normally less than atmospheric due to a

crankcase scavenging system designed to minimize the buildup of explosive gasses in

the crankcase. For a running engine, the crankcase atmosphere is continuously

evacuated through a pressure regulating system to the turbo-blower. Because the

open-ended tube for the dipstick extends down into the sump inventory, there is

potential to displace the oil level in the tube and distort the level measurement if there is

a pressure difference between the crankcase and the room atmosphere. Therefore,

with a lower pressure in the engine crankcase, the dipstick would produce a reading

lower than the actual sump level. According to the licensee's representative, a

temporary sump level standpipe consisting of a clear plastic hose attached to a drain

line below the sump level was used for level indication during some of the engine test

runs. The same level anomaly would be produced for this configuration unless the

upper end of the standpipe was exposed to crankcase pressure. The licensee could not

provide a normal value for the crankcase pressure as this parameter was not logged or

recorded.

The licensee's representative stated that no exhaust gas analysis had been performed

to determine if lube oil was being consumed (burned) by the cylinder combustion

process, but inspections requiring some engine teardown were planned to see if this

problem existed. An engineering evaluation in Condition Report 1998-0733 steted that

burning oil would have made the engine exhaust gas dark and noticeable. The team

disagreed and believed that the combustion of lube oil in the engine cylinders would

have resulted in light blue or gray exhaust, similar to Otto-Cycle (gasoline) engines.

l

One solution considered by the licensee was to increase the sump inventory. However,

the standby level was already maintained 40 millimeters (1.57 inches) above the " FULL"

mark, and according to the vendor there was a max mum of 5 inches between the

extreme limit of engine crankshaft motion and the dipstick " FULL" mark. It was

undesirable for the crankshaft to interface with or rotate into the sump lube oil. In the

l

interim, the licensee had received conflicting data from the vendor regarding the sump

I

capacity and the usable portion of that capacity. Eventually, the licensee undertook

efforts to determine the exact volume of oil in the engine sump at various levels and to

further determine if there existed a usable volume that would meet the technical

I

specification basis for the increased consumption rate. At the start of the inspection, the

licensee could not verify if the diesel generator was operating within the design basis

(

during extended runs.

1

!

l

1

r

.

.

-20-

Engineering Report GGNS-99-0005," Evaluation of DIV lli D/G Lube Oil Sump Volume,"

dated March 8,1999, was provided to the team on March 9,1999. The report indicated

that through an onsite testing effort and extensive consultation with the vendor, the

licensee had determined the following:

3.

Volume to " LOW" mark on dipstick was 58.8 gallons

4.

Volume to " FULL" mark on dipstick was 191.97 gallons

5.

Usable volume below the " LOW" mark was 19.67 gallons

Therefore, the total usable volume of 152.84 (191.97 - 58.8 + 19 67) gallons at the

dipstick full mark was not sufficient for 7-days operation, as indicated in the technical

specification basis. The licensee determined that 10 mm above the " FULL" mark would

satisfy the higher consumption rate. In order to accommodate the perceived drawdown

of 40 mm level between standby and full-load conditions, the licensee established a

standby level of 50 to 80 millimeters (1.97-3.15 inches) above the dipstick " FULL" mark.

The team was satisfied that the licensee's current operating procedures ensured that

the Division lli emergency diesel generator was meeting the technical specifications and

the design bases. However, the team determined that, because of the excessive oil

consumption rate, the design criteria and design basis were not consistent with the

technical specification limits or bases. Also, the team was unsure if the licensee had

accurately determined the oil consumption rate. The licensee was aware of the need to

address the differences that existed among the design criteria, the design bases, and

the license limit / bases.

The licensee's handling of this event was lacking in that it appeared that the final

resolution of the issue was driven by the questioning from the team. However, the team

determined that the safety significance of the event was low because the licensee was

capable of adding lube oil while the unit was operating.

Installation of Wrona Breaker

Condition Report 1997-0758 reported the installation of a wrong breaker in a safety-

related application for the Division I emergency diesel generator jacket water heater.

This problem was identified during post-maintenance testing and the incorrect breaker

was never placed into service. The new breaker that was installed was a spare breaker

from a cubicle in the same switchboard. Apparently, craft personnel performing the

work order met the intent of Procedure 07-S-01-205," Conduct of Maintenance

Activities," Revision 102, as they verified that the new breaker model number was

identical to the breaker that was replaced. However, unknown to craft personnel, the

current transformer that provided input to the breaker trip coil was different in the new

breaker; hence, the breaker overcurrent trip setpoint was different.

The team determined that a failure of the work control and planning processes was a

contributing cause of the problem. However, the licensee had not addressed this

potential generic issue in the scope of their corrective actions. Because of this

omission, the team determined that the licensee's corrective actions for this condition

report were weak.

.

.

-21-

Division II Emeraency Diesel Generator Load Transients

Condition Report 1997-0014 reported load transients on the Division 11 emergency diesel

generator during a test run. According to a licensee representative, this was a second

occurrence of this anomaly. The licensee performed extensive troubleshooting to

identify the cause(s) of the event, but no cause was found. Licensee maintenance

personnel replaced a motor-operated potentiometer in the engine speed control system

load-control circuitry. Subsequent testing of the removed potentiometer did not indicate

a cause of the event, and the event could not be duplicated. The unit was tested

successfully and returned to operable status.

The team inquired about the licensee's plans if the transients occurred again. Licensee

engineering personnel explained to the team that a binder had been developed to

provide effective troubleshooting guidance. The binder contained uncontrolled,

undated, and unapproved information to assist licensee personnel in performance of

troubleshooting for any problem with Division I or ll emergency diesel generators. The

guidance was generic and there was no specific plan or troubleshooting start point for a

repetitive transient load event. The team considered this approach to be weak,

considering that it involved a potential event that could render the diesel generator

j

inoperable, and for which a cause had not been identified.

Relief Valve Cyclina

Condition Report 1999-0212 reported that the Division 11 standby service water pump

relief valve would not reseat during a quarterly pump run for inservice pump testing.

This safety-related system supplies cooling water to the Division 11 emergency diesel

generator. The team reviewed this event to determine if the operability of the

emergency diesel generator would be impacted by failure of this valve to reseat.

The team found this to be a recurring problem that the licensee had not fully addressed.

The 6-inch relief valve was set to lift at 159 +/- 5 psig and had remained open in the test

(recirculation) mode with system pressure at 138 psig. Licensee personnel provided a

vendor specification sheet that indicated that the valve was designed to provide a

20 percent blowdown and, therefore, would not reseat until underseat pressure dropped

'

to about 127 psig. Thus, the valve lifting and staying open at 138 psig was not an

anomaly. The valve's reseat pressure could not be attained until the flow path to the

i

residual heat removal heat exchanger was automatically established. Automatic

l

positioning of system valves to establish flow to the heat exchanger normally took about

1 minute. Therefore, the relief valve opened and remained open during system testing,

and opened and reseated after approximately 1 minute on normal system startup.

The team performed further review to determine whether the valve sticking open (failing

to reseat on normal system startup) would decrease the standby service water flow rate

below that used in the safety analysis. The team determined that with the valve stuck

fully open, given the pump performance indicated and trended by the licensee's

.

.

-22-

inservice testing program, the assumed accident flow rate would be met. Therefore,

operability of the emergency diesel generators was not impacted. However, the team

determined that it was poor engineering practice to risk valve degradation and failure by

allowing a relief valve to open on every system startup, which, according to the

licensee's engineering staff, could total as many as 60 times per year.

c.

Conclusions

The team concluded that the corrective action program was generally effective in the

identification of design and design basis issues related to the emergency diesel

generators. An issue related to the Division ill emergency diesel generator lube oil

inventory, where an excessive oil consumption problem created inconsistencies

between the technical specification and the design bases, was indicative of a lack of

questioning attitude. The team also identified three other issues in which the causes

were not identified or addressed, or the corrective actions did not fully resolve the

problem.

E.2.3 Temoorary Alterations

a.

Inspection Scope (93809)

The team reviewed licensee Procedure 01-S-06-3," Control of Temporary Alterations,"

Revision 28, and all open temporary alterations. After these reviews, the team

performed an assessment to determine if the licensee's implemented temporary

alteration program effectively preserved the existing design bases.

b.

Observations and Findinos

There were 19 open temporary alterations, six of which were past the originally-

established corrective action due dates. The oldest open temporary alteration

(93-00230) was installed in 1992 to lift instrument leads to preclude nuisance

annunciator alarms from a failed condensate pump vibration monitoring probe.

According to a licensee representative, the probe could only be replaced when the pump

was removed from the system for overhaul, which was not scheduled in the near future.

The team considered this to be valid reason for the lengthy duration of this temporary

modification. The inspectors determined that four additional temporary alterations that

were past their corrective action due dates also had valid reasons for remaining open.

Additional review and discussion with the licensee representative revealed that the work

needed to close Temporary Alteration 97-0012 (tank manway covers removed for

submersible pump access) had been performed prior to the end of 1998. However, the

personnel responsible for closing out the temporary alteration had not been informed

and the item remained open. Once the condition was identified, the licensee initiated

the closure process.

The team also determined that the appropriate drawing for Temporary

Alteration 98-0032 (M-0180, which depicted a discharge register above test equipment

.

.

-23

in the hot chemistry lab) had not been updated to reflect the configuration of the

alteration (which had installed a blank to preclude dust and dirt intrusion to the

instruments). However, the drawing was not classified as operations sensitive or critical

and, therefore, according to Procedure 01-S-06-3, was not required to reflect the

temporary alteration configuration.

A licensee operations representative stated that he intended to initiate a procedure

'

improvement to require the generation of documentation of approval for extending the

required corrective action completion dates and to better define the qualifications and

j

responsibilities of personnelinvolved in the process.

j

The team did not identify any example where the design bases was compromised by a

temporary alteration. However, as identified in a separate NRC inspection (NRC

Inspection Report 50-416/99-03), a concern has been identified relative to the licensee's

control and tracking of temporary or interim solutions. It appeared that the licensea, on

occasion, used such temporary or interim solutions in lieu of the modification process.

c.

Conclusions

The licensee's temporary alteration program effectively preserved the design bases for

equipment and systems affected by temporary alterations. However, the team noted

that, in a number of instances, there was a lack of documented justification for

temporary alterations that remained open past the initial corrective action due dates.

A recent NRC inspection (NRC Inspection Report 50-416/99-03) identified a concern

relative to the licensee's control and tracking of temporary or interim solutions. It

appeared that the licensee, on occasion, used such temporary or interim solutions in lieu

of the modification process.

E8

Engineering-Miscellaneous issues (92903)

E8.1

(Ocen) Insoevtion Followuo item 9603-01: review long-term justification for

methodology and assumed valve factors.

During a previous inspection, the NRC noted that two motor-operated valve groups had

been assigned bounding valve factors that appeared non-conservative and which were

not adequately justified by test-based evaluations.

The licensee had completed additional testing to support the valve factors assigned

to the two subject motor-operated valve groups: Powell 600/900 pound class gate

valves and Powell 150 pound class gate valves. The team concluded that the additional

tests performed on two valves in the 150 pound class were adequate to establish the

assignment of a 0.62 valve factor to this group. However, the additional tests performed

on two valves in the 600/900 pound class group did not provide sufficient justification for

the 0.5 valve factor assigned to this group. The two valve tests revealed valve factors of

.

.

-24-

0.48 and 0.50. These results, combined with previous test results from this group, did

not provide confidence in the 0.5 group valve factor. That is, there appeared to be a

high probability that some of the valves in this group (that had not been tested) could

have valve factors greater than 0.5. If this were the case, the estimated thrust loads

would be less than actual. Depending on the available thrust margins, this could result

in a trip of the torque switch and a valve stopping in mid-cycle.

The team reviewed a listing of valves in the Powell 600/900 pound class and the current

available margins for these valves based on a 0.5 valve factor. The listed margins did

not account for rate of loading. Six valves (01G33F028, Q1B21F016, Q1821F019,

Q1E51F059,01E51F063, and 01G33F039) had control switch trip margins that were

between 10 and 20 percent, and these were the most marginal of the 35 valves in the

group. Given that the rate of loading (which is often in the range of 10-15 percent) was

not included in the margin calculation and that the 0.5 valve factor was not adequately

justified, the team was concerned that some of the valves in'this group may be marginal

in terms of their ability to open or close against design basis differential pressure and

flow conditions. However, the team did not consider these valves to be inoperable

because of other conservatisms in the analysis. The concern was of less significance

with Valve O1E51F063 since it was limit positioned and would not experience a rate of

loading effect. The licensee intended to perform margin-enhancing modifications to the

five valves listed above (except for 01E51F063) during Refueling Outages 10 and 11

(October 1999 and approximately March 2001).

The team considered the marginal status of the five valves to be potentially significant.

Consequently, this item was left open pending completion of the planned modifications.

E8.2

(Closed) Violation 50-416/9705-01: design control issues rela' ted to (1) two alarm

response procedure updates and (2) ensuring an adequate drain path for normal and

expected standby service water pump shaft seat leakage.

The licensee issued Condition Reports GGCR 1997-0297-00 and GGCR 1997-0294-00

in response to the two alarm response procedures. Corrective actions established in the

condition reports revised setpoints contained in the procedures in question and reviewed

other alarm procedures to detect other potential similar errors (none were found). The

team considered these corrective actions to be satisfactory.

Condition Report GGCR 1997-0264-01 was issued in response to the drainage issue.

A floor drain was installed in the room in question after the room had been sealed to

prevent flooding from external sources. Actions to prevent recurrence included

revisions to Procedures 02-S-01-21, * Plant Change Review and Training," Revision 5,

Section 6.0; and 01-S-16-1, " Plant Change implementation," Revision 102,

Attachment Xil. Thesc revisions strengthened the required review of design changes

to determine the impact on procedures and equipment. The team considered these

corrective and preventive actions satisfactory to resolve the violation.

Although the team considered the licensee's actions to be acceptable to resolve this

violation, weaknesses were observed in the corrective action process in that no other

action was apparently taken to determine the extent of the condition. Regarding the first

two examples, the licensee did not review other procedures (operations, surveillance,

.

.

-25-

calibrations, etc.) to assure that other design changes were properly incorporated into

procedures. In the second example, the licensee considered the design change

associated with the sealing of the room to be unique. However, the team considered

the development of the scope of corrective actions to be limited. The licensee did not

review other design changes to assure that changes did not have similar adverse effects

on the equipment modified.

E8.3 (Closed) Violation 50-416/9705-03: failure to update the Updated Final Safety Analysis

Report with the latest material developed related to (1) incomplete cooling tower failure

analysis, (2,3) fuel pool heat load increase dues to reracking the spent fuel pool (two

examples), (4) change from 2-unit to 1-unit facility, and (5) an inaccurate figure with

respect to a peak heat rate for the ultimate heat sink.

The licensee issued Condition Report GGCR 1997-0262-01 to address the five

examples of this violation. Corrective actions established in the condition report revised

Updated Final Safety Analysis Report, Tables 9.2-16 and 9.2-17, and Figures 9.2-5

and 9.2-6a in response to items 2 through 5 listed above. Example 1 was documented

in Condition Report GGCR 1996-0552-00. The licensee planned to revise Updated

Final Safety Analysis Report, Table 9.2-2, when calculations were completed.

Preventive actions were also established. The licensee issued a memorandum to the

engineering staff management expressing expectations on reporting Updated Final

Safety Analysis Report discrepancies. The team considered these corrective and

preventive actions satisfactory to resolve the violation.

The team noted that the scope of the corrective actions applied to this violation was

limited in that the review for similar problems was limited to Revision 6 of the Updated

Final Safety Analysis Report. Revisions prior to Revision 6 were performed with

contractor support, and subsequent revisions were all processed independently by the

licensee. The licensee's review of Revision 6 identified that 10 of the 71 change notices

had discrepancies associated with them. The licensee did not have a justification that

the problems were unique to Revision 6.

Although not directly tied to the corrective actions scheduled for this finding, an effort

has been undertaken by the licensee to perform a fidelity review of the Updated Final

Safety Analysis Report. This project is discussed in Section E8.8 of this report.

E8.4 (Closed) Inspection Followuo item 50-416/9705-04: adequacy of long-term freeze

protection measures.

The licensee had previously documented this item within Condition

Report GGCR 1996-0553-00 before it was identified by the NRC in 1997. This condition

report was open at the time of the current inspection. However, most of the corrective

actions were complete in response to recommendations within Engineering Request

96/1022-00, Revision 2. Current freeze protection measures required a start of a

standby service water pump rather than just a start of the fans. In addition, scaffolding

was to be installed in case of freezing conditions for safe access to observe ice

accumulation. The team considered these measures to be more workable than

previous measures and to be satisfactory to resolve this item.

m

..

9

-26-

E8.5 (Closed) Inspection Followuo item 50-416/9705-05: unexplained pump performance

curve discrepancies.

The licensee addressed this item within Condition Reports GGCR 1997-0438-00 and

GGCR 1997-0365-00. The licensee established that the discrepancies between the

curves were caused by instrument errors associated with the standby service water

pumps and by calculational errors associated with the high pressure core spray pumps.

' The team noted that the discrepancies did not affect the operability or design bases of

the pumps. Corrective actions were to replace the inaccurate instruments and to correct

the calculations. These corrective actions have been completed. The licensee's

representative reported that differences did not exist between other pump vendor curves

and the baseline data. The team considered that these actions were satisfactory to

resolve the item.

E8.6

Enaineerina Backloa

,

a.

Insoection Scooe (93809)

- The team reviewed the licensee's engineering backlog and the manner in which it was

being trended, in addition, the team discussed the backlog with appropriate licensee

personnel,

b.

Observations and Findinas

The engineering backlog consisted of engineering requests, open modifications, open

corrective action items, work orders on engineering hold, and other miscellaneous

items. For design engineering, the backlog had increased from approximately 370 items

in July 1997 to approximately 560 in January 1999. The system engineering backlog

= bad' increased over the same time period from approximately 480 to 590 items.

However, the increased backlog was primarily a result of a November 1998 change in

the corrective action program software, which began tracking individual corrective action

items for each condition report. This software change fully accounted for the increased

numbers of items listed above. Therefore, the team determined that the actual

engineering backlog had been relatively constant since July 1997.

l

1

.

c.

- Conclusions

The team concluded that the engileering backlog had been maintained relatively

constant.

E8.7 ' System /Desian Enaineerina Staffina

a.

Insoection Scope (93809)

The team discussed the status of the onsite engineering staffing with the applicable

department managers. In addition, the team interviewed some of the system and

design engineers.

.

.

-27-

b.

Observations and Findinas

The system engineering department consisted of approximately 28 engineers and first-

line supervisors, with each system engineer being responsible for four to eight systems.

The design, system, and performance engineering groups were in the process of being

1

l

reorganized. The system engineers interviewed stated that the number of onsite

engineers had changed little over the past few months. However, many systems and

projects had been re-assigned as the engineering departments were reorganized. The

result of these changes within onsite engineering had led to a decrease in the average

individual engineer's experience level with respect to the current systems and project

areas assigned.

c.

Conclusions

Onsite engineering support was in the process of reorganization. As a result, there had

been a decrease in the individual engineer's experience level within project areas and

l

systems assigned.

I

E8.8 Updated Final Safety Analysis Reoort Update and Review Proarams

a.

Inspection Scope (93809)

The team reviewed the licensee's program for reviewing and updating the Updated

Final Safety Analysis Report. The team reviewed Grand Gulf Administrative

Procedure 01-S-15-10, " Control of Licensing Documents," Revision 101, used in

part to track changes to the Updated Final Safety Analysis Report and portions of

the " Grand Gulf Nuclear Station Design Bases initiatives Program Plan," dated

December 16,1998, which is used to monitor the current Updated Final Safety

Analysis Report review effort.

b.

Observations and Findinas

Updated Final Safety Analysis Report Uodate Proaram

l

The latest revision of the licensee's Updated Final Safety Analysis Report was

completed on November 11,1998. Subsequently,20 of the 33 controlled copies of the

,

Updated Final Safety Analysis Report were replaced with electronic computer disc

copies in January 1999. In addition, a controlled copy of the Updated Final Safety

j

Analysis Report was placed on the licensee's Internet home page. The licensing

document control process initiated and tracked changes to the Updated Final Safety

Analysis Report in accordance with Procedure 01-S-15-10. A master tracking system

computer program maintained the linkage among the various licensing control

documents, engineering work documents, and the corrective action program.

The team discovered several errors in the latest revision of the Updated Final Safety

Analysis Report, as described in Sections E1.1.1 and E1.2.1 of this report. In addition to

these findings, two engineering drawings the team used as part of the detailed

f

engineering inspection of the plant's standby diesel generators were observed to contain

the wrong revision:

.

._

_.

_ _ _ _ _ _ _

_ _ _ _ _ -

.

.

-28-

Updated Final Safety Analysis Report Figure 9.5-011, " Standby Diesel Generator

System Unit 1" (Division l) was Revision 30 of P&lD M-1070A dated October 31,

1997, whereas the current revision of P&lD M-1070A was Revision 31 dated

November 11,1998.

Updated Final Safety Analysis Report Figure 9.5-012," Standby Diesel Generator

i

System Unit 1" (Division ll) was Revision 26 of P&lD M-1070B dated October 3,

)

1997, whereas the current revision of P&lD M-10708 was Revision 27 dated

j

November 13,1998.

'

Updated Final Safety Analysis Report Review Proaram

The licensee initiated the " Updated Final Safety Analysis Report Consistency Review

Project," in response to the November 9,1996, NRC letter issued under 10 CFR 50.54

requiring licensees to provide added confidence and assurance that their plants are

operated and maintained within their design bases. The licensee had incorporated this

project into a larger " Design Bases Initiatives Program." The project began in March

1997 when offsite contractors began a consistency review of 16 systems within the

Updated Final Safety Analysis Report. These reviews were completed and delivered to

the licensee in December 1997 and January 1998. A second group of 8 systems was

added to the scope of the project in late 1998. The licensee planned to include another

6 systems to be reviewed by the end of 2000.

The project, as outlined in Project instruction "GGNS Updated Final Safety Analysis

Report Consistency Review Project," Revision 2, required, in part, a line-by-line review

of the Updated Final Safety Analysis Report for identification of system-related attributes

and verification that they were consistent with relevant design basis information (system

design criteria, calculations, modifications, design correspondence, etc.). The licensee

project manager reported that none of the offsite contractor system reviews had been

'

approved by the onsite engineering departments. There were approximately

450 deficiencies and open items identified by the offsite contractors. The licensee

had a goal to complete their review of these discrepancies by the end of 1999.

The team determined that the initial Updated Final Safety Analysis Report consistency

review performed by the offsite contractors did not identify many of the discrepancies

identified by the team. The team discussed with the licensee's management the need to

consider this fact when conducting their scheduled onsite reviews of this material.

Based on the number of discrepancies identified during this inspection, the team

considered the general fidelity of the Updated Final Safety Analysis Report to be in

question pending the results of further reviews to be conducted by the licensee. This

matter is further discussed in Section E1.1.1 of this report.

c.

Conclusions

The licensee's ongoing Updated Final Safety Analysis Report update and review

pmjects did not identify multiple discrepancies that were identified by the team during

the inspec' ion. This was indicative of a potentially broader problem involving the fidelity

of the Updated Final Safety Analysis Report.

_ _ _ - _ _ _ _

_ _ - - _

.

.

-29-

M8

Maintenance-Miscellaneous issues (92902)

M8.1 (Closed) Inspection Followuo liem 50-416/9701-03: tracking licensee actions related to

equipment unavailability.

The licensee documented this item in Condition Report GGCR 1997-0227-00. The

three examples discussed in the NRC inspection report were corrected and the impact

of the corrections did not affect their Maintenance Rule program status. Preventive

actions included revisions to the shift supervisor's turnover checklist, plant supervisor's

turnover checklist, and the plant status checksheet, so that operations personnel would

be more aware of the Maintenance Rule program requirements to report unavailability.

The Maintenance Rule coordinator reviewed historical records and established that no

additional hours of unavailability were missed as a result of the oversight by the

operations staff. The team found that a recent period of unavailability of the emergency

diesel generators was properly reported. The team considered these actions

satisfactory to resolve the item.

M8.2 (Closed) Inspection Followuo item 50-416/9701-06: structures monitoring program.

In response to this item, the licensee revised Engineering Report GGNS-96-0075,

" Assessment of Grand Gulf Compliance with the Guidelines of NEl 96-03," Revision D,

sn unnumberad document entitled," Maintenance Rule for Monitoring the Condition of

Structures," Revision 1, and Procedure GGNS-C-399.0," Maintenance Rule for

Structures inspections," Revision 3. These revisions identified the structures in the

scope of the Maintenance Rule program and established a basis for their inclusion. The

revisions also ir ciuded identification of the risk-significant structures.

V. Manaaement Meetinas

XI

Exit Meeting Summary

'

The team presented the preliminary inspection results in an exit meeting to members of

licensee management on March 11,1999. A supplemental exit meeting was conducted

by telephone on May 18,1999. The licensee's management acknowledged the findings

presented.

The licensee's staff was asked whether any materials examined during the inspection

should be considered proprietary. The licensee's management stated that no

proprietary information was reviewed by the team.

3

.

-

.

ATTACHMENT 1

SUPPLEMENTAL INFORMATION

PARTIAL LIST OF PERSONS CONTACTED

Licensee

A. Barfield, Manager, Mechanical / Civil Engineering

R. Byrd, Licensing Supervisor

N. Deshpande, Supervisor, Design Engineering

J. Edwards, Manager, Planning and Scheduling

A. Goel, Site 50.59 Coordinator

E. Harris, Superintendent, System Engineering

C. Holifield, Senior Licensing Engineer

,

C. Lambert, Director, Design Engineering

i

M. Renfroe, Manager, Engineering Programs

J. Roberts, Director, Quality Programs

J. Venable, General Manager

W. White, Engineering Supervisor

i

NRC Personnel

D. Powers, Chief Engineering and Maintenance Branch

J. Russell, Acting Senior Resident inspector

INSPECTION PROCEDURES USED

37001

10 CFR 50.59 Evaluations

92902

Followup- Maintenance

92903

Followup-Engineering

93809

Safety System Engineering Inspection

ITEMS OPENED, CLOSED, DISCUSSED

Opened

50-416/9902-01

NCV

UFSAR Discrepancies

50-416/9902-02

NCV

Failure to Maintain Diesel Generator Air Start Valve

Open

50-416/9902-03

URI

instrument Setpoint Program Weaknesses

.

.

-2-

Qlpsed

50-416/9701-03

IFl

Track Licensee Actions Related to Equipment

Unavailability

50-416/9701-06

IFl

Structures Monitoring Program

50-416/9705-01

VIO

Design Control Discrepancies

50-416/9705-03

VIO

Failure to Update the UFSAR with the Latest Material

Developed

50-416/9705-04

IFl

Adequacy of Long-Term Freeze Protection Measures

50-416/9705-05

IFl

Unexplained Pump Performance Curve Discrepancies

50-416/9902-01

NCV

UFSAR Discrepancies

50-416/9902-02

NCV

Failure to Maintain Diesel Generator Air Start Valve

Open

Discussed

50-416/9603-01

IFl

Review Long-Term Justification for Methodology and

Assumed Valve Factors

DOCUMENTS REVIEWED

Procedures

01-S-06-24, " Safety and Environmental Evaluations," Revision 103

316 "10 CFR 50.59 Safety Evaluations," Revision 12

EDP-032, Nuclear Plant Engineering Desk Top Procedure, " Instrument Loop Uncertainty and

Setpoint Calculations," Revision 1

GG-1-LP-OTH-50591.00," Lesson Plan, Non-Licensed Training, Licensing Basis 50.59

(Lesson 1)," Revision 0

GG-1-LP-OTH-50592.00, " Lesson Plan, Non-Licensed Training,10 CFR 50.59 Safety

Evaluations (Lesson 2)," Revision 0

GG-1-HO-OTH 5059M.00," Lesson Plan, Non-Licensed Training, Licensing Basis 50.59

Manual," Revision 0

01-S-06-3," Control of Temporary Alterations," Revision 28

01-S-03-10, "GGNS Condition Report," Revision 3

a

l

.

3-

04-1-02-1H22-P400-1 A-C1, " Alarm Response instruction - Diesel Fuel Oil Tanks High Low,"

Revision 10

04-1-03-A30-1, " Equipment Performance Instruction - Cold Weather Protection, Non-Safety

Related," Revision 10

06-OP-1 P75-M-0001, " Surveillance Procedure - Standby Diesel Generator (SDG) 11 Functional

Test, Safety Related," Revision 107

07-S-24-P75-E001 A-1, " Preventive Maintenance instruction - Division 1 Diesel Generator

Starting Air System Leakage Test, Safety Related," Revision 2

07-S-24-P75-E001 B-1, " Preventive Maintenance Instruction - Division 2 Diesel Generator

Starting Air System Leakage Test, Safety Related," Revision 1

06-EL-1R21-M-0001, "4.16 kV Degraded Voltage Functional Test and Calibration,"

Revision 102

06-OP-1 P81-M-0002, "HPCS Diesel Generator 13 Functional Test," Revision 104

06-OP-1R21-M-0002 Attachment I, "Div. I Load Shedding and Sequencing Functional Test,"

Revision 100

01-S-15-10," Control of Licensing Documents," Revision 101

GG-UFSAR-CR-01, "GGNS UFSAR Consistency Review Project," Revision 2

04-1-01-P81-1, High Pressure Core Spray Diesel Generator," Revision 44, November 18,1998

Guidelines

"10 CFR 50.59 Guidelines," Revision 5'

"10 CFR 50.59 Review Program Guidelines," Revision 1

Safety Evaluations

94-0058-R02, " Evaluation 93/0050, Revision 1," December 10,1996

94-0072-R00, " Evaluation of MCP 94/1014 & SCN 94/0001 A to M-273.0," April 18,1996

95-0026-R01," Technical Specification Update through Amendment 120," August 21,1997

95-0080-R00, "DCP 91/042-1 Rev. 0," March 19,1996

95-0085-R00, " Evaluation of MCP 95/1020," May 13,1997

95-0097-R00, "MNCR 0206-95, Supplement 1," February 6,1996

.

.

-4-

96-0004-R00, " Licensing Document Change Request 96-0004, UFSAR 4.2.3.3.10," March 21,

1996

96-0019-R00, "DCP 89/0069," February 17,1998

96-0023-R00," Evaluation of Various P&lD and UFSAR Changes," July 9,1996

96-0040-R00, "MCP 95/1042," April 29,1997

96-0074-R00," TEMP. ALT. 96/0014," August 29,1996

96-0080-R00, " Evaluation of ER 96/0514," Revision 0, October 17,1996

96-0112-R00, "ER 96/0803-01-00 (GGCR 1996-0270-00)," November 1,1996

97-0012-R00, "ER 96/J056-00-00," November 11.,1997

97-0031-R00," Evaluation of MCP/1002, SCN 97/0002A to MS-02, and SCN 97/0006A to

M-189.3," January 14,1998

l

98-0035-R01, " Evaluation of Mechanical Standard 48.0, Revision 6, Core Operating Limits

1

'

Report," May 12,1998

97-0037-R00," Evaluation of ER 96/0964-00-00," October 2,1997

97-0073-R00, " Calculation XC-01G41-97007, Rev.0," October 21,1997

$

97-0076-R00, " Evaluation of ER 97/0588-00," dated April 24,1998

97-0083-R00," Evaluation of Spent Fuel Pool Time-to-Boil," February 10,1998

97-0093-R00, " Evaluation of ER 97/0114-00-00," December 18,1998

97-0096-R00," Evaluation of Temporary Alteration 97-0013," December 12,1997

f

97-0103 R00, " Evaluation of ER 97/0352-00-00," March 28,1998

98-0040-R00," Evaluation of TSR 98-008," April 28,1998

98-0018-R00," Evaluation of Various FSAR changes," March 3,1998

{

98-0019-R00, " Evaluation of ER 96/0936-04, SCN 98/0002A," April 3,1998

98-0079-R00," Evaluation of ER 98/0558-01, October 10,1998

98-0094 R00," Evaluation of LDC# 1998092, November 11,1998

1

.

-5-

Condition Reports

1996-0144

1996-0447

1997-0914

1997-1393

1999-0279

1996-0146

1997-0014

1997-0942

1998-0733

1999-0308

1996-0147

1997-0152

1997-0944

1998-1423

1999-0325

)

1996-0174

1997-0438

1997-0981

1998-1512

1999-0328

'

1996-0247-

1997-0744

1997-1032

1999-0212

1999-0331

1996-0393

1997-0758

1997-1197

1999-0218

1996-0442

1997-0851

1997-1317

1999-0256

Enaineerina Reauests

ER 96/1014-00

ER 97/0588-00

ER 97/0682-00

ER 97/0682-01

Enaineerina Reports

GGNS-99-0005," Evaluation of DIV lli D/G Lube Oil Sump Volume," dated March 8,1999

Temoorary Alterations

'

93-0023

98-0014

98-0020

98-0025

98-0032

97-0008

98-0015

98-0021

98-0027

98-0033

97-0012

98-0017

98-0023

98-0028

99-0008

98-0002

98-0018

98-0024

98-0029

1

Calculations

2.2.11.0, " Standby Service Water System - Net Positive Suction Head Requirements for

dbndhv 9arvice Water Pumps," Revision E

7.6.4B, " Diesel Generator Fuel Oil System - Sizing of Diesel Generator Fuel Oil Transfer Pumps

(Flow Capacities)," Revision B

7.6.9C, " Diesel Generator Fuel Oil Supply System - Calculate the Discharge Pressure for the

Diesel Generator Fuel Oil Transfer Pumps," Revision C

7.6.26," Standby Diesel Generator System - To Determine the Line Size for the Discharge Line

from PSVF026 A & B," Revision 0

JC-01 P75-90040, " Standby Diesel Generator Fuel Oil Day Tank Volume and Level Setpoint

Calculation," Revision 3

MC-Q1111-90197," Emergency Core Cooling System Network Configuration Evaluation,"

Revision 0

.

.

-6-

MC-01P41-97020 " Determination of Minimum Allowable Standby Service Water Flows (Loss

of Coolant Analysis Lineup) to Safety Related Heat Exchangers," Revision 1

MC-01 P41-97035, " Standby Service Water Heat Exchanger Thermal Performance Instrument

Uncertainty," Revision 1

MC-O1P75-90190, " Diesel Fuel Storage Requirements for the Division i Diesel Generator,"

Revision 1

MC-01P75-91119," Maximum Allowable Leakage from Division I and 11 Diesel Generators

Starting Air Storage Tanks," Revision 0

MC-01P81-88022, " Division 111 Diesel Generator Fuel Oil Transfer System Study for Material

Nonconformance Report 1173-86," Revision 0

MC-01P81-90188, " Diesel Fuel Storage Requirements for the Division lli Diesel Generator,"

Revision 1

l

MC-01X77-85005, " Cooling Requirements for Division I and 11 Diesel Generator Control

Cabinets," Revision 1

SC-1P75-LT-N004, " Standby Diesel Generator Fuel Oil Day Tank Volume and Level

Instrumentation Scaling Calculation (1P75-LT-N004A & B,1P81-LT-N004)," Revision 0

E-DCP82/5020-1," Transient Loading on Diesel Generators during Load Sequencing,"

Revision A

EC-01R20-91040," Verification of Protective Coordination for Motor Control Centers and

Associated Feeders," Revision 0

Calculation E-49, "MCC Overcurrent Protection," Revision 0

EC-O1111-90028," Load Flow & Voltage Drop Analysis Report Attachment 7A2," Revision 0

Condition Identification

Cl# 076570, Work Order # 00220628 " Identified as - Cable Tray @ South End of DIV1 D/G

under Exhaust Silencer has Insul. Material that Needs Cleaned," Reported Date March 04,

1999

,

Drawinas

E-1042," Logic Diagram Engineered Safeguards Feature Division i Diesel," Revision 9

M-1070-A, " Piping and instrumentation Diagram - Standby Diesel Generator System Unit 1,"

Revision 31

.

.

7

M-1070-B, " Piping and Instrumentation Diagram - Standby Diesel Generator System Unit 1,"

Revision 27

M-1070-C, " Piping and Instrumentation Diagram - Standby Diesel Generator System Unit 1,"

Revision 15 -

M-1070-D, " Piping and Instrumentation Diagram - Standby Diesel Generator System Unit 1,"

Revision 13

J-1692," Level Setting Diagram Standby Diesel Generator Fuel Oil Day Tank A(B)

01P75A004A(B)," Revision 5

Fidelity Review

GGNS-98-0057, " Grand Gulf Nuciear Station - System Design Criteria Review / Updated Final

Safety Analysis Report Consistency Review, Standby Diesel Generator System - Attachment

6.6, Discrepancy Form"

OlN# P75-65, " Consistency Review (System Design Criteria Review / Updated Final Safety

Analysis Report Consistency Review) - Subject: In the fourth paragraph of Section 9.5.6 3, the

reference to . . . ." (Fidelity evaluation discrepancy) December 27,1998

Material Nonconformance Reoort

Material Nonconformance Report 0269-87, December 1,1987

Memoranda

GIN: 92/00968," Subject: System P75 Setpoint Calculation - Start Air Pressure Available, Diesel

A (B) (Emergency Start Lockout at 120 psig," February 21,1992

Proarams

Program Plan Change Notice No.98-006 against Program Plan No. GGNS-M-189.1," Pump

and Valve Inservice Testing Program," Revision 8

Reports

9645-M-018.0," Qualification Test for De Laval Engine Generator Set, Grand Gulf Nuclear

Stations #1 & #2, Middle South Energy, Inc., Engine Unit No.1," Revision 2 and specifically

Test Number 2.6.4," Starting Air System - Starting Air Compressor Capacity Test,"

December 29,1976

Startuo Field Reoorts

Startup Field Report (SFR) No.1-M-403, " Subject: M-1070A and M-1070B, Revision 7,"

March 6,1980

.

.

-8-

Startup Field Report Reply No.1-M-403, " Standby Diesel Generator / P75 - Disposition,"

March 6,1980

Test Data - Air Droo Results

E-Mail, "D. R. Franklin to T. E. Dykes, - Subject 'Most Recent Air Drop Test,'" February 23,

1999

Work Order 00218010," Perform 1P75E001B Standby Diesel Generator Starting Air System

Leakage Check," December 29,1998

Work Order 00218011 " Perform 1P75E001 A Standby Diesel Generator Starting Air System

Leakage Check," December 29,1998

Test Data - Fuel Transfer Pumo Performance

" Standby Diesel Generator Fuel Transfer Pump IP75C002A - Inservice Testing Performance

Results," Summary for dates between May 24,1988, through November 17,1998

" Standby Diesel Generator Fuel Transfer Pump 1P75C002B - Inservice Testing Performance

Results," Summary for dates between January 8,1988, through December 12,1998

"High Pressure Core Spray Diesel Generator Fuel Transfer Pump 1 P81C001 - Inservice

Testing Performance Results," Summary for dates between May 28,1987, through

December 12,1998

Test Data - Heat Exchanaer Performance

" Thermal Data (Jacket Water Cooler / Heat Exchanger Performance Data) for P75B004A,"

several dates

" Thermal Data (Jacket Water Cooler / Heat Exchanger Performance Data) for P75B004B,"

several dates

" Thermal Data (Jacket Water Cooler / Heat Exchanger Performance Data) for P81B001 A,"

i

several dates

Test Data - Relief Valve Results

Work Order 00068480, " Remove, Test, and Reinstall Safety / Relief Valve, Check Setpoint

Pressure . . . Fuel Oil Return Line PSV 1P75F026A," March 26,1992

Work Order 000105483," Remove, Set Pressure Check & Adjustment and Reinstall

Safety / Relief Valve . . . Fuel Oil Return Line PSV 1P75F026B," August 31,1993

F

,

i

-

-9-

1

Desian Basis Documents

Updated Final Safety Analysis Report Sections 8.1,8.2 and 8.3

Technical Specification Sections 3.3.8.1,3.8.1,3.8.2,3.8.3, and their bases

One Line Diaarams

E-0001, " Main One Line Diagram," Revision 26

E-1006,"One Line Meter & Relay Diagram 4.16 kV BOP Bus 13 AD," Revision 13

E-1007, "One Line Meter & Relay Diagram 4.16 kV BOP BUS 14AE," Revision 17

E-1008, "One Line Meter and Relay Diagram 4.16 kV ESF System Buses 15AA & 16AB,"

Revision 17

E-1009,"One Line Meter and Relay Diagram 4.16 kV ESF System Bus 17AC," Revision 9

E1022, "One Line Meter & Relay Diagram 125V DC Buses 11DD,11DE & 250V DC

BUS 11DF," Revision 26

E1023,"One Line Meter & Relay Diagram 125V DC Buses 11DA,11DB & 11DC," Revision 33

E-1025, " Meter & Relay Diagram * 24V DC System," Revision 13

E-1026,"One Line Meter and Relay Diagram 120V AC ESF Uninterruptible Power Supplies,"

Revisions 10 and 12

Loaic Diaarams

E-1039, " Logic Diagram - Load Shedding & Sequencing Panel," Revision 17

E-1042, " Logic Diagram ESF Division I Diesel," Revision 9

E-1043, " Logic Diagram ESF Division 11 Diesel," Revision 6

Schematic Control Drawinas for Diesel Start Circuits

E-1110-012 "P75 Stand-by Diesel Generator Sys Div. I Train A Start & Stop Circuit,"

Revision 15

E-1110-013, " Stand-by Diesel Generator Sys Div. I Train 8 Start Circuit," Revision 17

E-1111-012. "P75 Stand-by Diesel Generator Sys Div.11 Train A Start & Stop Circuit,"

Revision 12

.

[

.

.

-10-

E-1111-013,"P75 Stand-by Diesel Generator Sys Div.11 Train B Start Circuit," Revision 13

Modifications

96-0641, " Standby Diesel Generator Day Tank High Level Alarm"

97-0443," Fire-induced Failures Affecting Safety-Related Systems"

97-0645," Replacement of Dresser Couplings of EDG Cylinder Head"

instrument Setooints and Scalina Calculations

GGNS-JS-09, " Methodology for the Generation of instrument Loop Uncertainty & Setpoint

Calculations," Revision 0

JC-01P81-N036A-1,"HPCS Diesel Generator Starting Air interlocks 1P81N036A/B,

1P81N107A/B, and 1P81N108A/B Setpoint Calculations," Revision 0

JC-O1P75-90040," Standby Diesel Generator Fuel Oil Day Tank Volume and Level Setpoint

Calculation," Revision 3

JC-01X77-N6001," Instrument Loop Uncertainty and Setpoint Determination for System X77,

Loop N600, N601, N602 Diesel Generator Room Fan Speed Control," Revision 1

j

JC-O1P81-N111-1," Uncertainty Calculation for the HPCS Diesel Generator Starting Air

Pressure Loops," Revision 0

,

SC-1 P75-LT-N004, " Standby Diesel Generator Fuel Oil Day Tank Volume and Level

Instrumentation Scaling Calculation," Revision 0

i

MC-01P75-90190, " Diesel Fuel Storage Requirements for the Division i Diesel Generator,"

l

Revision 1

)

Miscellaneous Documents

MC-01P75-91119, " Maximum Allowable Leakage From Division I and 11 Diesel Generators

i

Starting Air Storage Tanks," Revision 0

04-1-01-R21-17," System Operating Instruction ESF Bus 17AC," Revision 3

04-1-01 R21-16," System Operating Instruction ESF BUS 16AB," Revision 11

I

04-1-01-R21-15, " System Operating instruction ESF BUS 15AA," Revision 8

Project Plans

"GGNS UFSAR Review Project," January 1998

'

" Grand Gulf Nuclear Station Design Bases initiatives Program Plan," December 16,1998

l

i

.

.

-11-

l

Reports

GGNS-98-0016, "UFSAR Consistency Review for 4.16 kV ESF Division I & il Distribution

i

System (R11 & R12)," May 19,1998

i

GGNS-98-0032, "UFSAR Consistency Review for High Pressure Core Spray Diesel Generator

System (P81)," January 19,1998

GGNS-98-0057, "SDC Review & UFSAR Consistency Review for Standby Diesel Generators

,

(P75)," Decernber 30,1998

]

i

-

.

.

ATTACHMENT 2

DESIGN ENGINEERING WHITE PAPER

l

.

l

G

e

ATTACHMENT 3

INSTRUMENT SETPOINT PROGRAM

.

.

1

ATTACHMENT 1

SUPPLEMENTAL INFORMATION

,

i

PARTIAL LIST OF PERSONS CONTACTED

l

i

Licensee

t

'

A. Barfield, Manager, Mechanical / Civil Engineering

R. Byrd, Licensing Supervisor

N. Deshpande, Supervisor, Design Engineering

J. Edwards, Manager, Planning and Scheduling

A. Goel, Site 50.59 Coordinator

E. Harris, Superintendent, System Engineering

C. Holifield, Senior Licensing Engineer

C. Lambert, Director, Design Engineering

)

M. Renfroe, Manager, Engineering Programs

1

J. Roberts, Director, Quality Programs

)

J. Venable, General Manager

j

W. White, Engineering Supervisor

NRC Personnel

D. Powers, Chief, Engineering and Maintenance Branch

J. Russell, Acting Senior Resident inspector

INSPECTION PROCEDURES USED

37001

10 CFR 50.59 Evaluations

92902

Followup- Maintenance

92903

Followup-Engineering

93809

Safety System Engineering Inspection

ITEMS OPENED, CLOSED, DISCUSSED

.

Opened

50-416/9902-01

NCV

UFSAR Discrepancies

50-416/9902-02

NCV

Failure to Maintain Diesel Generator Air Start Valve

Open

50-416/9902-03

URI

Instrument Setpoint Program Weaknesses

__

.

i

.

-2-

Closed

50-416/9701-03

IFl

Track Licensee Actions Related to Equipment

r

Unavailability

-50-41&9701-06

IFl

Structures Monitoring Program

.50-416/9705-01

VIO

Design Control Discrepancies

50-416/9705-03

VIO

Failure to Update the UFSAR with the Latest Material

Developed

50-416/9705-04

IFl

Adequacy of Long-Term Freeze Protection Measures

50-416/9705-05

IFl

Unexplained Pump Performance Curve Discrepancies

50-416/9902-01

NCV

UFSAR Discrepancies

50-416/9902-02

NCV

Failure to Maintain Diesel Generator Air Start Valve

Open

Discussed

50-416/9603-01

IFl

Review Long-Term Justification for Methodology and

Assumed Valve Factors

DOCUMENTS REVIEWED

Procedures

01-S-06-24, " Safety and Environmental Evaluations," Revision 103

i

316,"10 CFR 50.59 Safety Evaluations," Revision 12

EDP-032, Nuclear Plant Engineering Desk Top Procedure," Instrument Loop Uncertainty and

Setpoint Calculations," Revision 1

GG-1-LP-OTH-50591.00," Lesson Plan, Non-Licensed Training, Licensing Basis 50.59

'

(Lesson 1)," Revision 0

~ GG-1-LP-OTH-50592.00, " Lesson Plan, Non-Licensed Training,10 CFR 50.59 Safety

Evaluations (Lesson 2)," Revision 0

GG-1 HO-OTH-5059M.00," Lesson Plan, Non-Licensed Training, Licensing Basis 50.59

Manual," Revision 0

01-S-06-3," Control of Temporary Alterations," Revision 28

01-S-03-10,"GGNS Condition Report," Revision 3

-

..

-3-

04-1-021H22-P400-1 A-C1, " Alarm Response Instruction - Diesel Fuel Oil Tanks High-Low,"

Revision 10

04-1-03-A30-1, " Equipment Performance instruction - Cold Weather Protection, Non-Safety

Related," Revision 10

06-OP-1P75-M-0001, " Surveillance Procedure - Standby Diesel Generator (SDG) 11 Functional

Test, Safety Related," Revision 107

07-S-24-P75-E001 A-1, " Preventive Maintenance Instruction - Division 1 Diesel Generator

Starting Air System Leakage Test, Safety Related," Revision 2

07-S-24-P75-E0018-1, " Preventive Maintenance Instruction - Division 2 Diesel Generator

Starting Air System Leakage Test, Safety Related," Revision 1

06-EL-1R21-M-0001, "4.16 kV Degraded Voltage Functional Test and Calibration,"

Revision 102

06-OP-1P81-M-0002, "HPCS Diesel Generator 13 Functional Test," Revision 104

06-OP-1R21-M-0002 Attachment I, "Div. I Load Shedding and Sequencing Functional Test,"

Revision 100

01-S-15-10," Control of Licensing Documents," Revision 101

GG-UFSAR-CR-01, "GGNS UFSAR Consistency Review Project," Revision 2

04-1-01-P81-1, High Pressure Core Spray Diesel Generator," Revision 44, November 18,1998

i

Guidelines

'

"10 CFR 50.59 Guidelines," Revision' 5

i

'

"10 CFR 50.59 Review Program Guidelines," Revision 1

Safety Evaluations

.

94-0058-R02, " Evaluation 93/0050, Revision 1," December 10,1996

94-0072-R00, " Evaluation of MCP 94/1014 & SCN 94/0001 A to M-273.0," April 18,1996

95-0026-R01," Technical Specification Update through Amendment 120," August 21,1997

95-0080-R00, "DCP 91/042-1 Rev. 0," March 19,1996

95-0085-R00, " Evaluation of MCP 95/1020," May 13,1997

4

95-0097-R00, "MNCR 0206-95, Supplement 1," February 6,1996

.

.

-4-

96-0004-R00, " Licensing Document Change Request 96-0004, UFSAR 4.2.3.3.10," March 21,

1996

96-0019-R00, "DCP 89/0069," February 17,1998

96-0023 R00," Evaluation of Various P&lD and UFSAR Changes," July 9,1996

96-0040-R00, "MCP 95/1042," April 29,1997

96-0074-R00," TEMP. ALT. 96/0014," August 29,1996

96-0080-R00, " Evaluation of ER 96/0514," Revision 0, October 17,1996

96-0112-R00, "ER 96/0803-01-00 (GGCR 1996-0270-00)," November 1,1996

97-0012-R00, "ER 96/0056-00-00," November 11,1997

97-0031-R00, " Evaluation of MCP/1002, SCN 97/0002A to MS-02, and SCN 97/0006A to

M-189.3," January 14,1998

98-0035-R01," Evaluation of Mechanical Standard 48.0, Revision 6, Core Operating Limits

Report," May 12,1998

97-0037-R00, " Evaluation of ER 96/0964-00-00," October 2,1997

97-0073-R00, " Calculation XC-O1G41-97007, Rev.0," October 21,1997

97-0076-R00, " Evaluation of ER 97/0588-00," dated April 24,1998

97-0083-R00, " Evaluation of Spent Fuel Pool Time-to-Boil," February 10,1998

97-0093-R00, " Evaluation of tsR G7/0114-00-00," December 18,1998

97-0096-R00," Evaluation of Temporary Alteration 97-0013," December 12,1997

97-0103 ROO, " Evaluation of ER 97/0352-00-00," March 28,1998

98-0040-R00," Evaluation of TSR 98-008," April 28,1998

98-0018-R00," Evaluation of Various FSAR changes," March 3,1998

98-0019-R00," Evaluation of ER 96/0936-04, SCN 98/0002A," April 3,1998

98-0079-R00," Evaluation of ER 98/0558-01, October 10,1998

98-0094-R00," Evaluation of LDC# 1998092, November 11,1998

.

.

-5-

Condition Reports

1996-0144

1996-0447

1997-0914

1997-1393

1999-0279

1996-0146

1997-0014

1997-0942

1998-0733

1999-0308

1996-0147

1997-0152

1997-0944

1998-1423

1999-0325

1996-0174

1997-0438

1997-0981

1998-1512

1999-0328

1996-0247

1997-0744

1997-1032

1999-0212

1999-0331

1996-0393

1997-0758

1997-1197

1999-0218

1996-0442

1997-0851

1997-1317

1999-0256

Enaineerina Reauests

ER 96/1014-00

ER 97/0588-00

ER 97/0682-00

ER 97/0682-01

Enaineerina Reports

GGNS-99-0005, " Evaluation of DIV lli D/G Lube Oil Sump Volume," dated March 8,1999

Temoorarv Alterations

93-0023

98-0014

98-0020

98-0025

98-0032

97-0008

98-0015

98-0021

98-0027

98-0033

97-0012

98-0017

98-0023

98-0028

99-0008

98-0002

98-0018

98-0024

98-0029

Calculations

2.2.11.0, " Standby Service Water System - Net Positive Suction Head Requirements for

Standby Service Water Pumps," Revision E

7.6.48, " Diesel Generator Fuel Oil System - Sizing of Diesel Generator Fuel Oil Transfer Pumps

(Flow Capacities)," Revision B

7.6.9C, " Diesel Generator Fuel Oil Supply System - Calculate the Discharge Pressure for the

Diesel Generator Fuel Oil Transfer Pumps," Revision C

7.6.26, " Standby Diesel Generator System - To Determine the Line Size for the Discharge Line

from PSVF026 A & B," Revision 0

JC-01 P75-90040, " Standby Diesel Generator Fuel Oil Day Tank Volume and Level Setpoint

Calculation," Revision 3

MC-C1111-90197," Emergency Core Cooling System Network Configuration Evaluation,"

Revision 0

L

-

.

.

-6-

1

MC-01P41-97020," Determination of Minimum AUowable Standby Service Water Flows (Loss

of Coolant Analysis Lineup) to Safety Related Heat Exchangers," Revision 1

MC-01 P41-97035, " Standby Service Water Heat Exchanger Thermal Performance instrument

Uncertainty," Revision 1

MC-01P75-90190, " Diesel Fuel Storage Requirements for the Division i Diesel Generator,"

Revision 1

MC-01P75-91119, " Maximum Allowable Leakage from Division I and 11 Diesel Generators

Starting Air Storage Tanks," Revision 0

MC-Q1P81-88022, " Division Ill Diesel Generator Fuel Oil Transfer System Study for Material

Nonconformance Report 1173-86," Revision 0

MC-01P81-90188, " Diesel Fuel Storage Requirements for the Division ill Diesel Generator,"

Revision 1

MC-01X77-85005, " Cooling Requirements for Division I and 11 Diesel Generator Control

Cabinets," Revision 1

SC-1P75-LT-N004, " Standby Diesel Generator Fuel Oil Day Tank Volume and Level

Instrumentation Scaling Calculation (1P75-LT N004A & B,1P81-LT-N004)," Revision 0

i

E-DCP82/5020-1, " Transient Loading on Diesel Generators during Load Sequencing,"

Revision A

j

EC-01R20-91040, " Verification of Protective Coordination for Motor Control Centers and

Associated Feeders," Revision 0

Calculation E-49,"MCC Overcurrent Protection," Revision 0

EC-01111-90028," Load Flow & Voltage Drop Analysis Report Attachment 7A2," Revision 0

Condition identification

Cl# 076570, Work Order # 00220628 " Identified as - Cable Tray @ South End of DIV1 D/G

under Exhaust Silencer has insul. Material that Needs Cleaned," Reported Date March 04,

1999

Drawinas

E-1042," Logic Diagram Engineered Safeguards Feature Division I Diesel," Revision 9

M-1070-A, " Piping and Instrumentation Diagram - Standby Diecel Generator System Unit 1,"

Revision 31

--

~

l

-7-

,

M-1070-B," Piping and Instrumentation Diagram - Standby Diesel Generator System Unit 1,"

Revision 27

M-1070-C, " Piping and Instrumentation Diagram - Standby Diesel Generator System Unit 1,"

'

Revision 15

M-1070-D, " Piping and instrumentation Diagram - Standby Diesel Generator System Unit 1,"

Revision 13

,

J-1692," Level Setting Diagram Standby Diesel Generator Fuel Oil Day Tank A(B)

01P75A004A(B)," Revision 5

l

]

Fidelity Review

GGNS-98-0057, " Grand Gulf Nuclear Station - System Design Criteria Review / Updated Final

Safety Analysis Report Consistency Review, Standby Diesel Generator System - Attachment

6.6, Discrepancy Form"

OlN# P75-65," Consistency Review (System Design Criteria Review / Updated Final Safety

Analysis Report Consistency Review)- Subject: In the fourth paragraph of Section 9.5.6.3, the

reference to . . . ." (Fidelity evaluation discrepancy) December 27,1998

Material Nonconformance Report

Material Nonconformance Report 0269-87, December 1,1987

Memoranda

GIN: 92/00968," Subject: System P75 Setpoint Calculation - Start Air Pressure Available, Diesel

A (B) (Emergency Start Lockout at 120 psig," February 21,1992

Proarams

Program Plan Change Notice No.98-006 against Program Plan No. GGNS-M-189.1," Pump

and Valve Inservice Testing Program," Revision 8

Reports

9645-M-018.0, " Qualification Test for De Laval Engine Generator Set, Grand Gulf Nuclear

Stations #1 & #2, Middle South Energy, Inc., Engine Unit No.1," Revision 2 and specifically

Test Number 2.6.4, " Starting Air System - Starting Air Compressor Capacity Test,"

December 29,1976

Startuo Field Reports

Startup Field Report (SFR) No.1-M-403," Subject: M-1070A and M-10708, Revision 7,"

March 6,1980

l

I

\\

.

.

-8-

Startup Field Report Reply No.1-M-403, " Standby Diesel Generator / P75 - Disposition,"

March 6,1980

Test Data - Air Droo Results

E-Mail, "D. R. Franklin to T. E. Dykes, - Subject 'Most Recent Air Drop Test,'" February 23,

1999

Work Order 00218010, " Perform 1P75E001B Standby Diesel Generator Starting Air System

Leakage Check," December 29,1998

Work Order 00218011, " Perform 1P75E00.1 A Standby Diesel Generator Starting Air System

Leakage Check," December 29,1998

Test Data - Fuel Transfer Pumo Performance

" Standby Diesel Generator Fuel Transfer Pump 1P75C002A - Inservice Testing Performance

Results," Summary for dates between May 24,1988, through November 17,1998

" Standby Diesel Generator Fuel Transfer Pump 1P75C002B - Inservice Testing Performance

Results," Summary for dates between January 8,1988, through December 12,1998

"High Pressure Core Spray Diesel Generator Fuel Transfer Pump 1P81C001 - Inservice

Testing Performance Results," Summary for dates between May 28,1987, through

December 12,1998

Test Data - Heat Exchanaer Performance

" Thermal Data (Jacket Water Cooler / Heat Exchanger Performance Data) for P75B004A,"

several dates

' Thermal Data (Jacket Water Cooler / Heat Exchanger Performance Data) for P75B004B,"

several dates

" Thermal Data (Jacket Water Cooler / Heat Exchanger Performance Data) for P818001 A,"

several dates

.

Test Data - Relief Valve Results

Work Order 00068480, " Remove, Test, and Reinstall Safety / Relief Valve, Check Setpoint

Pressure . . . Fuel Oil Return Line PSV 1P75F026A," March 26,1992

Work Order 000105483," Remove, Set Pressure Check & Adjustment and Reinstall

Safety / Relief Valve . . . Fuel Oil Return Line PSV 1P75F026B," August 31,1993

,

, . .

f-

.

-9-

Desian Basis Documents

.

Updated Final Safety Analysis Report Sections 8.1,8.2 and 8.3

Technical Specification Sections 3.3.8.1,3.8.1,3.8.2,3.8.3, and their bases

One Line Diaarams .

E-0001, " Main One Line Diagram," Revision 26

E-1006, "One Line Meter & Relay Diagram 4.16 kV BOP Bus 13 AD," Revision 13

E-1007, "One Line Meter & Relay Diagram 4.16 kV BOP BUS 14AE," Revision 17

E-1008,"One Une Meter and Relay Diagram 4.16 kV ESF System Buses 15AA & 16AB,"

Revision 17

E-1009, "One Line Meter and Relay Diagram 4.16 kV ESF System Bus 17AC," Revision 9

E1022,"One Line Meter & Relay Diagram 125V DC Buses 11DD,11DE & 250V DC

BUS 11DF," Revision 26

E1023, "One Line Meter & Relay Diagram 125V DC Buses 11DA,11DB & 11DC," Revision 33

E-1025," Meter & Relay Diagram * 24V DC System," Revision 13

'

E-1026,"One Line Meter and Relay Diagram 120V AC ESF Uninterruptible Power Supplies,"

Revisions 10 and 12

Loaic Diaorams

E-1039, " Logic Diagram - Load Shedding & Sequencing Panel," Revision '17

E-1042, " Logic Diagram ESF Division I Diesel," Revision 9

E-1043, " Logic Diagram ESF Division ll Diesel," Revision 6

Schematic Control Drawinas for Diesel Start Circuits

E-1110-012, "P75 Stand-by Diesel Generator Sys Div. I Train A Start & Stop Circuit,"

Revision 15 -

E-1110-013," Stand-by Diesel Generator Sys Div. I Train B Start Circuit," Revision 17

j

E-1111-012, "P75 Stand-by Diesel Generator Sys Div.11 Train A Start & Stop Circuit,"

Revision 12

.

'

-10-

'

E-1111-013, "P75 Stand-by Diesel Generator Sys Div. Il Train B Start Circuit," Revision 13

Modifications

)

96-0641," Standby Diesel Generator Day Tank High Level Alarm"

97-0443," Fire-Induced Failures Affecting Safety-Related Systems"

97-0645," Replacement of Dresser Couplings of EDG Cylinder Head"

Instrument Setooints and Scalina Calculations

GGNS-JS-09," Methodology for the Generation of instrument Loop Uncertainty & Setpoint

Calculations," Revision 0

JC-01P81-NO36A-1, "HPCS Diesel Generator Starting Air Interlocks 1P81NO36A/B,

1P81N107A/B, and 1P81N108A/B Setpoint Calculations," Revision 0

JC-01P75-90040, " Standby Diesel Generator Fuel Oil Day Tank Volume and Level Setpoint

Calculation," Revision 3

JC-01X77-N600-1," Instrument Loop Uncertainty and Setpoint Determination for System X77,

Loop N600, N601, N602 Diesel Generator Room Fan Speed Control," Revision 1

JC-01P81-N111-1, " Uncertainty Calculation for the HPCS Diesel Generator Starting Air

Pressure Loops," Revision 0

SC-1P75-LT-N004, " Standby Diesel Generator Fuel Oil Day Tank Volume and Level

Instrumentation Scaling Calculation," Revision 0

MC-01P75-90190, " Diesel Fuel Storage Requirements for the Division i Diesel Generator,"

Revision 1

Miscellaneous Documents

MC-OIP75-91119," Maximum Allowable Leakage From Division I and ll Diesel Generators

Starting Air Storage Tanks," Revision 0

04-1-01-R21-17, " System Operating instruction ESF Bus 17AC," Revision 3

04-1-01-R21-16, " System Operating Instruction ESF BUS 16AB," Revision 11

l

04-1-01-R21-15," System Operating Instruction ESF BUS 15AA," Revision 8

i

i

Project Plans

"GGNS UFSAR Review Project," January 1998

" Grand Gulf Nuclear Station Design Bases Initiatives Program Plan," December 16,1998

_ - _ _

.

.

-11-

Reoorts

GGNS-98-0016 "UFSAR Consistency Review for 4.16 kV ESF Division I & ll Distribution

System (R11 & R12)," May 19,1998

GGNS-98-0032,"UFSAR Consistency Review for High Pressure Core Spray Diesel Generator

System (P81)," January 19,1998

GGNS-98-0057, "SDC Review & UFSAR Consistency Review for Standby Diesel Generators

(P75)," December 30,1998

i

9

e

A1TACHMENT 2

DESIGN ENGINEERING WHITE PAPER

l

1

.

.

,

Design Engineering White Paper

to provide EOI's view of

NRC Safety System Engineering Inspection

i

UFSAR Discrepancies Issues

i

i

{

l

p

-

.

Y hita Paper to Address NRC SSEI UFSAR Discrepancies Issus

.

During the NRC exit meeting held on 3/1IM9 for the GGNS Safety System Engineering

Inspection (SSEI) for the Standby Emergency Diesel Systems and Support Sptems, the

NRC inspection team leader expressed a concern over the number oMscrepancies noted

by the team during the course of the inspection. Since there were no operability issues

identified from the discrepancies, the main concem was over the aggregate number of

discrepancies.

The NRC team requested additional feedback on the station's view of these findings. The

purpose of this white paper is to review, categorize, and summarize the discrepancies

noted by the NRC sad provide EOI's perception of those findings.

While we do not believe that these findings materially affect any safety or licensed

activities of the facility or indicate any current programmatic breakdown in the UFSAR

update process, we believe the GGNS review efforts warrant additional discussion. We

also believe that the specific inspector concerns can best be put into perspective by

identifying the nature of the discrepancies and distinguishing between information that

should be improved for clarity and that information that is technically wrong (i.e., errors).

GGNS UFSAR and Review Proer.am

The GGNS UFSAR is expected to be maintained accurate and complete with emphasis

on that information regarding aspects of safety and licensed activities.10 CFR 50.34(b)

provides the general requirements for FSAR content. The requirements include: a

i

description of the facility, a presentation of the design bases, limits on operation, and the

'

safety analyses of systems, components and stmetures as well as safety analyses of the

facility as a whole. The emphasis of these descriptions and analyses are on the

performance requirements, bases, and technicaljustifications which show that safety

functions can be accomplished. In panicular,10 CFR 50.34(b) states, "The description

shall be sufficient to permit understanding of system designs and their relationships to

safety evaluations."

The GGNS UFSAR consists of 19 volumes and in many cases provides excessive details

that are not necessary for the understanding of how the system is capable of performing

its safety function in relation to safety analyses. In other cases, the absence of detail may

lead to an incomplete understanding of the system design or operation. In addition, the

GGNS UFSAR contains redundant information in different sections, which at times have

i

been found to be inconsistent. Although the UFSAR contains some information that is

unclear or in error, the results from various reviews, assessments, and inspections

associated with the UFSAR provide a high degree of confidence that these discrepancies

do not materially affect the ability of safety systems to perform their design function and

that an appropriate level of defense-in-depth protection is being maintained in accordance

with NRC regulations. The results of these reviews also have not revealed any recurring

failures to meet the requirements of 50.71(c) that would indicate current ,'rogrammatic

failures. Many of the discrepancies or ambiguities identified are early eroblems

-

.

White P per to Address NRC SSEI UFSAR Discrep;ncies Issue

.

associated with the original writing or revising the UFSAR. In addition, reviews,

assessments, and inspections have not found any significant issues regarding the quality

or conclusions of 50.59 safety evaluations which indicate that the UFSAR information is

of sufficient quality to support correct 50.59 evaluations.

GGNS has conducted several review initiatives beginning as early as 1984 to provide

assurance that the terms and conditions of the operating license and NRC regulations are

being complied with. In 1984, GGNS conducted a review to ensure that the Technical

Specifications were consistent with the FSAR, the SER, and the plant as-built design. In

1987 and 1988. GGNS conducted two independent reviews of the entire UFSAR to

ensure consistency and proper implementation of procedurally required activities. Over

3,000 items were entered into a plant database and cross-referenced to procedures that

implemented the requirements to ensure that these requirements were being properly

maintained.

In the wake of the Millstone issues in 1996, EOI conducted a sampling assessment of the

sites' UFSARs to determine with reasonable assurance the fidelity of and compliance

with the UFSAR. This initial review initiative was later adopted by NEI as a model for

other licensees. The general nature and scope of any discrepancies found by the reviews

were considered in order to determine whether additional significant resources should be

diverted to a comprehensive review effort. Some discrepancies were found in the GGNS

UFSAR, however no safety issues were identified. While some corrections and

clarifications were needed, the UFS AR was found to be reasonably accurate and most of

the discrepancies were found to be from original FSAR introduced errors. There were no

significant current programmatic failures identified.

As a result of the EOI assessment and the 50.54(f) letter regarding the adequacy and

availability of design basis information, GGNS initiated a review program with the scope

and resources that we believe is consistent with the safety significance of our findings. In

addition, personnel awareness of UFSAR discrepancy issues were heightened as has been

demonstrated by an increased number of Condition Reports written over the past two

i

years compared to previous years. The efforts include various types of UFS AR reviews

as described below:

1. Line-by-line reviews.

These reviews are a complete review of chapters or sections that may not be

considered in a system review but are judged to be susceptible to errors or to have

unclear wording.

2.' System consistency reviews

The UFSAR is being reviewed for identification of system related attributes which are

verified to be consistent with relevant system design basis information (i.e., SDCs,

calculations, modifications, design correspondence, etc.). Also, the system

commitment database information is reviewed to ensure the UFS AR properly reflects

this information when applicable. This review did not include a line-by-line

i

'

.

White Peper to Address NRC SSEI UFSAR Discrepancies Issu

.

verification of compliance with Regulatory Guides associated with system design

guidance.

3. Review of miscellaneous topics

)

The UFSAR is also being reviewed by electronic search of special topics such as

{

operating condition restrictions associated with testing and UFSAR consistency with the

Improved Tech Specifications.

The present and past GGNS UFSAR review efforts are not designed to make the UFSAR

100% accurate cover to cover, but rather to provide reasonable assurance that plant

i

operation is consistent with the intended design and licensing basis. We believe the best

{

utilization of finite resources is to address issues commensurate with the safety

significance. Based on the nature of the items found to date, diversion of significant

.

additional resources to this review effort beyond what is already planned does not appear

I

warranted.

NRC Inspection Findings

The NRC inspection team findings are generally consistent with the type of discrepancies

identified during our previous reviews in that they are not the types of errors that raise

operability issues or otherwise materially affect safety or licensed activities. In addition

i

many are mistakes or ambiguities introduced early in the original writing of the FS AR or

i

during early UFSAR updates. We believe that the concerns can best be put into

perspective by identifying the nature of the discrepancies and distinguishing between

j

information that should be improved for clarity and that information that is technically

wrong (i.e., errors). Based upon review of the discrepancies three categories have been

identified:

Vague / Misleading Wording - the wording of the UFSAR section was not technically

incorrect but led to the misunderstanding of the description or requirement. In our

opinion, we believe these should not be categorized as errors, but rather as areas needing

improvement or clarification.

Incorrect / Outdated Information - the description in the UFSAR was incorrect or had not

been revised to reflect changes made to the plant design or operation.

Typographical / Administrative Errors - these could be either technical or merely editorial

in nature and include one discrepancy that involved a missing figure from one controlled

copy of the UFSAR.

.

The attached discussion categorizes each issue according to the above types of findings.

m

r

.

White Peper to Address NRC SSEI UFSAR Discrepancies Issun

.

Discussion of Discrepancies:

' A. Category:

Vague / Misleading Wording (Not Incorrect)

1. UFSAR Section 9.5.6.3 (Safety Evaluation for Diesel Starting Air Systan)

UFSAR Section 9.5.6.3 (page 9.5-37),3"' paragraph, states:

"... The system piping is installed at an elevation lower than the engine inlet, and is

provided with a drip leg to provide for removal of any water which may be present in the

lines..."

The inspector noted that not all of the air start system piping was below the engine inlet,

the portion coming from the top of the storage tanks is above the engine inlet.

Subsequent investigation by Design Engineciing found that the starting air for the

Division 1 and 2 diesels leaves the starting air storage tanks (2 per engine) at

approximately elevation 149' and that the engine inlet is at approximately 142'7" (for the

"B" and "D" trains "A" and "C" engine inlets are at approximately 143'7"). The portion

of the piping above the engine inlet elevation is approximately 21 feet long. Prior to

entering the engine the piping (for all four starirg air trains) drops to at least 136'4" for

some portion of it's run (the length of the portion below the engine inlet is at least 15

feet) and does include a drip leg for water removal as described in the UFSAR.

The UFSAR Consistency Reports for both the P75 and the P81 systems correctly

included this UFSAR Section for discussion but neither identified a discrepancy.

Thus, while this section is not literally correct (i.e. It overstates how much of the

system piping is below the engine inlet elevation), it is correct in its conclusion that

the starting air system piping design provides adequate provision for water removal

from the engine starting air. We agree that additional clarifying information is

needed.

2. UFSAR Section 8.3.1.1.3

UFSAR Section 8.3.1.1.3, page 8.3-9,5* paragraph, states:

l

"The load shedding and sequencing system does not prevent load shedding of the

emergency buses in response to a loss of preferred power or a LOCA signal once the

,

onsite sources are supplying power to all sequenced loads on the buses."

The use of the word " preferred" is misleading. This gives the impression that the

!

discussion is about the offsite power source rather than emergency diesel

generators. Subsequent paragraph b has the same wording problem. We agree that

.

White Pcper to Address NRC SSEI UFSAR Discrep:ncies Issue

.

clarification is needed. (It should be noted that the Load Shedding and Sequencing

system (system R21-1) has not yet had a Design Basis review.)

Discussion of Discrepancies:

A. Category:

Vague / Misleading Wording (Continued)

3. UFSAR Section 9.5.8.3

d

UFSAR Section 9.5.8.3 (page 9.5-45,2 paragraph) which discusses the NEMA 12 (i.e.

dustproof) electrical enclosures associated with diesel generator electrical equipment -

appears to contain a typographical error " flyings". It was believed that this should be

" filings" or " flying insects".

-

Subsequent investigation by Design Engineering found that the term " flyings" is a

correct (if somewhat esoteric) technical term for " materials of a larger particle size

than dust which are not normally in suspension in air" (Reference: Crouse-Hinds

definition of terms. Note that NFPA 70, National Electrical Code,1990 Edition,

paragraph 500-7(a); and OSHA Standards; Part 1910.334; Subpart S(d) both make

use of the term " flyings").

4. UFSAR Appendix 3A (ComDliance with NRC Regulatory Guides)

The inspector noted that in UFSAR Appendix 3A, there was no exception to our

commitment to Regulatory Guide 1.137 regarding the use of flame arrestors on fuel oil

storage tank vents in accordance with section 7.5 of ANSI N195-1976.

UFSAR Appendix 3A states that GGNS complies with the January 1978 (Revision 0)

,

version of this Reg. Guide. This Reg. Guide in general invokes the standards of ANSI

)

N195-1976. However, section 7.5 of ANSI N195-1976 is specifically excluded from the

Regulatory Guide.

RG 1.137 position C.I.h states:

" Section 7.5 of the standard includes requirements for fire protection for the diesel-

generator fuel-oil system. The requirements of section 7.5 are not considered a part

of this regulatory guide since this subject is addressed separately in more detail in

other NRC documents. Thus a commitment to follow this regulatory guide does not

imply a commitment to follow the requirements of Section 7.5 concerning fire

protection."

Therefore, exception to section 7.5 of ANSI N195-1976 should not he required for

compliance with RG 1.137.

.

White Paper to Address NRC SSEI UFSAR Discrepancies Issue

i

In Q&R 040.48 of the FSAR, the NRC requested that we revise some FSAR figures

to show name arrestors on the fuel storage tank vent lines like we did on the day

tank vent lines. Our response was provided in revised subsection 9.5.4.3. which

states that flame arrestors are not provided.

Discussion of Discrepancies:

A. Category:

Vague / Misleading Wording (Continued)

5. UFSAR Appendix 3A (Compliance with NRC Reeulatory Guides)

Appendix 3A states that GGNS complies with the January 1978 (Revision 0) version of

this Reg. Guide. This Reg. Guide invokes the standards of ANSI N195-1976.

Regulatory Guide 1.137 Fuel Oil Systems for Standby Diesel Generators includes the

following requirements which are not met at GGNS:

Section 6.1 of RG 1.137 specifies that the day tank suction shall be above the bottom of

the tank.

The GGNS day tank design is such that the suction is not off the side of the tank and

does not include a standpipe. However, the suction is not on the very bottom of the

tank (suction is off center and approximately 1" above the very bottom of the tank).

6. UFSAR Annendix 3A (Compliance with NRC Regulatory Guides)

Appendix 3A states that GGNS complies with the January 1978 (Revision 0) version of

this Reg. Guide. This Reg. Guide invokes the standards of ANSI N195-1976.

Regulatory Guide 1.137 Fuel Oil Systems for Standby Diesel Generators includes the

j

following requirements which are not met at GGNS:

Section 5.3 of ANSI N195-1976 specifies that the fuel cil storage shall be sufficient for

seven days of operation or the time required to replenish the oil from sources outside the

plant site following a design bases event or accident, without interrupting the operation of

'

the diesel (s), whichever is longer.

The evaluation of the ability to replenish oil within seven days described in the

UFSAR (Section 9.5.4.3) appears to have been informal (insufnciently detailed) and

j

there is no action plan in place to ensure that this can be done. However, there is no

specific requirement in the Reg. Guide for either a formal evaluation or that an

action plan be developed and maintained regarding the seven day replenishment

criteria.

.

White Peper to Address NRC SSEI UFSAR Discrepancies Issue

,

Discussion of Discrepancies (Continued):

B. Category:

Incorrect / Outdated Information

1. UFSAR Section 8.3.1.1

d

UFSAR Section 8.3.1.1, page 8.3-1,2 paragraph, states:

4

"The ESF loads are divided in'to three divisions, each fed from an independent ESF bus...

'

During normal operation, with all three ESF transformers available, each division of load

(i.e., Division 1,2, and 3) is supplied from a separate winding of each two-winding ESF

transformer..."

We believe that this may have been interpreted in the past as correct because each ESF

transformer is a two winding transformer and each division ofload is supplied from a

separate winding. There may have been some confusion also since the original design

was for the three transformers to supply both of the planned GGNS units (six ESF

busses). However, we agree that this description is not in accordance with present GONS

operating procedures which establish the preferred lineup with the 15AA bus being

powered off ESF transformer 11 while buses 16AB and 17AC are powered by ESF

transformer 21 (ESF transformer 12 from Port Gibson line is not used because the Port

i

Gibson supply was felt to be less reliable than the other supplies ).

The GGNS procedure consistency review noted this UFSAR section but stated that "The

load distribution of ESF buses among ESF transformers is a function of the Load

Sequencing System as discussed in Section 8.3.1.1.3 (R21-1) and should be verified with

that system."

It should be noted that the Load Shedding and Sequencing system (system R21-1)

has not yet had a Design Basis review.

2. UFSAR Section 9.5.4.2

UFSAR Section 9.5.4.2, page 9.5-24, states:

"Each standby diesel generator is provided with a 100-percent capacity engine-driven fuel

oil pump... The day tanks are located above the suction elevation of the engine driven

pumps to assure a slight positive pressure on the inlet to the pumps, even at low fuel

l

level."

The inspector noted that the UFSAR Section 9.5.4.2 discussion regarding relative

'

elevation of the day tank vs. the engine driven fuel pumps arrangement (i.e. that the day

tank level is above the fuel pump suctions) did not appear to be true of the HPCS diesel

based upon what he observed during the NRC team walkdown of the system. His

e

.

White P per to Address NRC SSEI UFSAR Discrep;ncies Issua

_

question was: Is the day tank elevation really higher than the inlet elevation of the fuel

oil booster pumps?

Discussion of Discrepancies (Continued):

B. Category:

Incorrect / Outdated Information (Continued)

2. UFSAR Section 9.5.4.2 (Continued)

)

The UFSAR paragraph describing the fuel oil arrangement for the HPCS engines (page

9.5-24,6* paragraph) states that "...The day tank is located above the suction elevation of

the motor-driven pump to assure a slight positive pressure on the pump inlet."

Subsequent investigation by Design Engineering found that the minimum HPCS

day tank elevation (i.e. the level at which the fuel oil transfer pump turns on) is

approximately 6 inches above the motor driven fuel pump inlet piping connection

,

(which is the end of the fuel oil piping going to the motor driven pump shown on the

l

piping isometric) but approximately 2 inches below the centerline of the HPCS

engine motor driven pumps (not shown on the piping isometric) and therefore is not

correct. However, per information from the HPCS DG vendor manual, both of

these pumps need only 12 feet of suction pressure (absolute) and therefore there is -

no operability concern even at minimum HPCS day tank level.

1

It is worth noting that, while the system P75 UFSAR Consistency Report did not

,

identify this statement concerning the fuel oil piping arrangement as a discrepancy,

'

it did identify the need for a review of available NPSH to the fuel oil pumps and the

need to clarify exactly what was meant by the wording in this section.

3. UFSAR Section 9.5.6.3

UFSAR Section 9.5.6.3, page 9.5-37a,1" paragraph, states:

"The performance of the DGSS filters and strainers for the standby diesel generators is

monitored by a pressure sensor located in each of the starting air lines just upstream of

the solenoid valves which admit air to the air header on the engine. The pressure sensors

detect pressure downstream of the final strainer in the system and signal an alarm on the

engine control panel when the starting air pressure is low ."

The actual configuration is that the strainers are downstream of the pressure

switches and therefore this description of the configuration and function of the

pressure switch is incorrect.

.

Whit Paper to Address NRC SSEI UFSAR Discrepancies Issue

.

It is worth noting that the System P75 UFSAR Consistency Review Report did

identify a problem with the description in this section not being correct (but did not

identify the exact same discrepancy regarding the pressure sensor being upstream of

the inlet strainers),

J

i

l

l

..

White Peper to Address NRC SSEI UFSAR Discrep ncies Issue

.

I

Discussion of Discrepancies (Continued):

B. Category:

Incorrect / Outdated Information (Continued)

4. UFSAR Finure 8.3-007B

UFSAR Figure 8.3-007B was noted to be two revisions out of date.

No record of LDC transmittal could be found for these later revisions to E-1026. It

was noted that neither the E-1026 drawing nor UFSAR Figure 8.3-007B contain

cross-references to the other in their title block, this may have been a contributing

cause.

5. UFSAR Anoendix 3A (Compliance with NRC Renulatory Guides)

Section 2G of RG 1.137 states that provision should be made for adding fuel to the

storage tanks at low tank levels while the engine is mnning without causing sediment

contamination of new fuel.

It does not appear that any such provision has been made in the GGNS design.

i

i

i

q

<

I

.

- Whits P per is Address NRC SSEI UFSAR Discrepancies Issus

.

Discussion of Discrepancies (Continued):

C. Category:

Typographical / Administrative Errors

1. UFSAR Firure 8.3-9

UFSAR Figure 8.3-9 was noted to have a typographical error:

j

"L.O.R" should be "LO.P"

2. UFSAR Firure 8.3-9

UFSAR Figure 8.3-9 was noted to have an error:

0.9 second time delay should be 9.0 seconds.

It should be noted that the Load Shedding and Sequencing system (system R21 1)

has not yet had a Design Basis review.

.

3. UFSAR Table 8.3-9

Table 8.3-9 has 'lR20 FDR BRKR 152-1603 (XFMR FOR DRYWELL CHILLERS)'

listed twice, once on page 3 and again on page 4, additionally, the comments in the

" Remarks" column is not the same for each listing.

4. UFSAR Firure 9.2-06A

UFSAR Figure 9.2-06A was noted to be missing from the UFSAR set provided to the

NRC audit team.

This UFSAR set was immediately decontrolled and designated "For Information

Only" pending a page check. A spot check was conducted of three other controlled

UFSAR sets and all were found to properly include this figure. The omission is

therefore considered an isolated case regarding maintenance of an EOI manual.

The updated figure had been submitted to the staff in accordance with

10CFR50.71(e).

.

Whit Paper to Address NRC SSEI UFSAR Discr:pincies Issue

-

Summary

A total of 15 UFSAR discrepancies were identified by the NRC review team during the

course of the SSEI. The breakdown by category was:

Six discrepancies for vague / misleading wording.

Five discrepancies for Incorrect / Outdated Information.

Four discrepancies were Typographical / Administrative Errors.

Of the six identified " discrepancies" in the vague / misleading wording category the first

j

two involved a minor description or wording problem. The third identified discrepancy

'

(" flyings") is technically correct but alternate wording might be considered since this a

somewhat esoteric term. The fourth discrepancy related to the ANSI N195-1976 standard

for fuel oil storage tank vent flame arrestors is not truly a discrepancy since Reg. Guide 1.137 already takes exception to this requirement. The remaining two discrepancies are

related to Reg. Guide 1.137 requirements which, strictly speaking, have actually been met

'

by GGNS.

Of the five discrepancies in the Incorrect / Outdated Information category three involved

minor wording or description problems, one involved failure to properly update

drawings / figures, and one involved incomplete compliance with Regulatory Guide 1.137

requirements (or failure to properly take exception to the requirement).

Of the four discrepancies in the typographical error category one was an insignificant

spelling error ("L.O.R." vs. "L.O.P."), one was a minor UFS AR figure error (0.9 vs. 9.0

seconds), one involved a duplicate table listing, and one involved improper mamtenance

of one controlled UFSAR set.

As was stated in the GGNS response to the NRC 50.54 (f) letter:

1. "... As an enhancement, selected systems / sections of the FSAR will be reviewed for

consistency with the supporting engineering documents. Licensing basis

improvements will be developed as appropriate."

A line-by-line review of the entire UFSAR for typographical and minor technical errors

was not intended. It was (and is) not believed that a massive review of this sort is

necessary or worthwhile. Per the GGNS response the review was performed for selected

systems only. A number ofinconsistencies and errors (i.e., typographical and minor

technical errors) have been noted by the review contractors during the course of their

consistency reviews and it is expected that still more will be found when the review

reports are reviewed by GGNS design engineering staff. The GGNS design engineering

reviews for systems P75, P81, R21, R21-1, and X77 have not yet been completed.

l

.

..

White Pzper to Address NRC SSEI UFSAR Discr:pancies Issus

..

It is current GGNS practice to identify and correct such errors when they are noted (using

either the Consistency Review Report Discrepancy process or the Condition Report

process, as required).

~ The Design Basis review scope was clearly intended to identify significant

' inconsistencies between the UFSAR and the design and regulatory basis documentation.

Given the type of discrepancies identified to date, GGNS plans to continue the UFSAR

consistency review as identified in the response to the 50.54(f) letter. Additionally, based

on the SSEI review discrepancies related to compliance with NRC Regulatory Guide 1.137, a review of GGNS compliance with selected NRC Regulatory Guides is planned.

Consistent with our current practice, the scope of this review may be expanded based on

the scope or nature of the findings resulting from the review.

1

I

P

1

1

ATTACHMENT 3

INSTRUMENT SETPOINT PROGRAM

i

l

.

!

a

l

)

I

.

Page1

,

.

INSTRUMENT SETPOIN f PROGRAM

The purpose of this paper is to address the observations of the

Instrument Setpoint Program made during the Safety System Engineering

'

Inspection during February 22-26 and March 8-12,1999. The observations

indicated that the program appeared to be an area of weakness based on the

lack of setpoint calculations for some applications and setpoint calculations

which were not considered to be adequate.

10CFR50 Appendix A provides part of the regulatory basis for programs

to establish and maintain instrument setpoints. General Design Criterion

!

(GDC) 13, Instrumentation and Control, requires in part that instrumentation

j

be provided to monitor variables and systems, and that controls be provided to

maintain these variables and systems within prescribed operating ranges. GDC 20, Protection System Functions, requires in part that the protection system be

]

designed to initiate operation of appropriate systems to ensure that specified

acceptable fuel design limits are not exceeded. Regulatory Guide 1.105,

' Instrument Setpoints', describes a method for complying with the regulations

with regard to ensuring that the instrument setpoints in systems important to

safety initially are within and remain within the specified limits.

The

regulations require that where a limiting safety setting is specified for a

variable on which a safety limit has been placed, the setting be so chosen that

automatic protective action will correct the most severe abnormal situation

anticipated before a safety limit is exceeded. The Reg. Guide endorses the

requirements established in ISA-S67.4-1982 for ensuring that instrument

setpoints in safety-related systems are initially within and remain within the

Technical Specif~ication limits. GGNS is not committed to Reg. Guide 1.105

as noted in UFSAR Appendix 3A based on the applicability date given in the

Instrumentsetpoint. doc

.

Page 2

e

guide. However, GGNS has established a program to generate and maintain

instrument loop uncertainty and setpoint calculations. The methodology

employed by this program is defined in GGNS Instrumentation and Control

Standard JS-09 and is based on ISA RP67.04, Part 2, Methodologies for the

Determination of Setpoints for Nuclear Safety-Related Instrumentation. This

recommended practice provides guidance for the implementation ofISA-S67-

04, Part 1. The GGNS program also employs methodology based on NEDC- 31336P-A, General Electric Instrument Setpoint Methodology.

Entergy Operations has established a corporate philosophy regarding

instmment uncertainties and their consideration at all EOI sites.

This

philosophy is discussed in Design Engineering guidance and incorporated into

site-specific standards. The philosophy recognizes that the formality and level

of detail provided to document instrument uncertainty and setpoints may vary

with respect to the importance to nuclear safety. The following types of

instrumentation applications typically require formal calculations due to their

high level of safety importance: safety-related Technical Specification

Limiting Safety System Setpoints (LSSS), safety-related Non-Reactor

Protection System Setpoints (instrumentation with active safety functions), and

Regulatory Guide 1.97 Type A Parameters. The methodology applied or the

necessity for a calculation should be commensurate with the safety

significance of the function evaluated.

The focus of the subject inspection was the emergency diesel generator

systems and their supporting auxiliary systems including the ventilation

system. The applicable Technical Specifications for these systems include

Section 3.3.8.1, Loss of Power Instrumentation (LOP), and Section 3.8,

Electrical Power Systems. The LOP instrumentation specification contains

allowable values for loss of voltage and degraded voltage setpoints. The

setpoints are established from original design criteria to support the equipment

connected to the bus. The setpoint values have been confirmed in detailed load

flow and voltage drop analyses from the bus down to the connected load. The

Instrumentsetpoint. doc

,

.

Page 3

i

e

sensing devices that monitor bus voltage are bi-stable devices which are highly

accurate and repeatable. However, margin is added in surveillance procedures

to account for the uncertainty associated with these devices and the calibration

equipment. It is noted that technical specification bases discuss setpoint

l

calculations which specify nominal setpoints.

This bases section was

incorrectly incorporated from the generic improved technical specification

]

bases in NUREG-1434 and did not consider the existing analyses. The voltage

drop analyses adequately demonstrate that sufficient power is available to

.

emergency buses to support successful operation of the required safety

s

functions during accident conditions.

Section 3.8 of the Technical Specifications contains requirements for AC

power sources (3.8.1 ) and for Standby Diesel Engine parameters including fuel

oil, lube oil and starting air (3.8.3). Section 3.8.1 also includes parameters

related to the availability of the onsite AC power source such as fuel oil day

tank volume and fuel oil transfer system automatic operation. The values for

these parameters in the GGNS Technical Specifications are based on the

requirements of Reg. Guide 1.137 which state that the day tank shall maintain

a volume equivalent to 60 minutes of operation at the level where fuel oil is

automatically added and shall alarm at a level equivalent to 30 minutes of

operation. ~ GGNS maintains an instrument setpoint calculation for these

parameters which establishes nominal trip setpoints telated to analysis of fuel

j

oil consumption rates for each diesel. It was noted during the inspection that

j

this calculation does not include a rigorous application of instrument

i

uncertainty. The basis established for the treatment of this parameter was that

the requirements being met are nominal values derived from standard practice.

The 60-minute and 30-minute volume requirements are not ultimate limits for

operation of the diesel. Therefore, there are no requirements for inclusion of

uncertainty.

The calculation demonstrates that the instrumentation is

appropriate for the application. This graded approach is consistent with

Section'4.0 ofISA S67.04, Part I which recognizes that for setpoints that may

not have the same level of stringent requirements as limiting safety system

setpoints, such as those that are not credited in the safety analyses or that do

not have limiting values, the setpoint determination methodology could be less

rigorous.

Section 3.8.3 of the Technical Specifications includes volume

requirements for fuel oil storage tank and lube oil volume as well as starting

air receiver pressure. The lube oil is measured via a dipstick directly in the

lube oil reservoir and the required volume is considered a nominal value.

There are no setpoint calculations for this measurement. The fuel oil storage

tank volume is measured by level instrumentation in the tank. The technical

specification requirement is based on inventory required for seven days of

Instrumentsetpoint. doc

-

a

-

Page 4

,

,

operation at maximum expected post-LOCA loading coaditions. These load

l

requirements are conservatively calculated with margin including an allowance

for uncertainty in the level measurement used to confirm the volume. The

level is monitored by Operations personnel- to ensure the Technical

Specification value is met. There are no instrument uncertainty calculations

based on the inclusion of uncertainty in the fuel consumption analysis. In

addition, alarm setpoints are established at nominal values based on original

design criteria. These alarms serve to alert operators of changing conditions.

Uncertainties are adequately controlled by use ofinstrumentation that has been

properly chosen and that is maintained and calibrated in accordance with

established site practices.

4

The starting air pressure requirements in the Technical Specifications are

based on a minimum capacity for a required number of start attempts. The air

pressure value is confirmed by conservative design analysis of the system and

is maintained by procedure with margin to account for various uncertainties.

Sufficient margin is maintained for Division I and II to ensure performance of

the function. The Division III Diesel Generator has initiation logic with

starting air pressure interlocks. A setpoint calculation is maintained for these

interlocks based on the safety function performed by the instrumentation. The

pressure switches utilized are direct acting with no electronic components.

Therefore, the loop uncertainty is limited to the accuracy of the switches.

,

Environmental effects are negligible based on the location of the switches.

The setpoints were established as nominal volumes by the diesel manufacturer

I

and were determined to be acceptable for their application. This approach is

consistent .with the setpoint methodology in Standard JS-09 discussed

previously. An instrument uncertainty calculation is also maintained for the

Division III starting air pressure loops which are categorized as Reg. Guide 1.97 variables and are required for post accident monitoring. This calculation

accounts for applicable environmental conditions to determine the total loop

uncertainty associated with the measurement in accordance with the

methodology in Standard JS-09. These calculations were discussed during the

inspection.

Additional system setpoints required for operation of the diesel generators

were reviewed and determined to be adequate based on design requirements

established by the manufacturer. In many cases the switches are utilized as

logic devices to indicate that conditions have been met and instrument

accuracy was not considered to be critical for the applications. Therefore,

setpoint calculations have not been performed for these instruments. The

setpoints are maintained under design control and calibrated in accordance

with established site practices.

1

Instrumentsetpoint. doc

.

-

..

..

.

.

.

'*

Page5

,

GGNS does maintain detailed instrument setpoint calculations for

safety-related active function setpoints that are performed in accordance with

standard methodology. There are presently almost fifty instrument setpoint

calculations for parameters included in the Technical Specifications and over

thirty instrument uncertainty and setpoint calculations for safety related

j

.

parameters which have been performed in accordance with the standard

methodology.

It is noted that the systems reviewed during the recent

'

inspection have only a limited number of these calculations. Based on

discussion of the applications above, however, it is felt that the existing

analyses are appropriate and meet applicable requirements. In addition, the

setpoint program established at GGNS is considered acceptable for providing

i

assurance that automatic actions will occur before safety limits are exceeded.

l

)

1

,

Instrumentsetpoint. doc