Responds to NRC Ltr Re Violations Noted in Insp Rept 50-400/83-29.Current Projected Date for Completing Verification of Previously Installed Fasteners Is 860110
ML20127E364
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 03/29/1985
From: Parsons R
CAROLINA POWER & LIGHT CO.
To: Grace J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
Shared Package
ML20127E343 List:
References
CON-NRC-342 NUDOCS 8505200047
Download: ML20127E364 (2)


Text

- - - -

,s.

og.j' CD&L Carolina Power & Light Company su

^  ;

B 5 MR '?.O. ox 1 , New Hill, NC 27562 March 29,1985 Dr. 3. Nelson Grace NRC-342 United States Nuclear Regulatory Commission Region II 101 Marietta Street, Northwest (Suite 2900)

Atlanta, Georgia 30323

Dear Dr. Grace:

The following is the status of our progress to date on resolving the violation identified in RlhGFM/RLP 50-400/83-29. This letter supercedes our July 25,1984, response (NRC-242).

In 'our December 9,1983, letter NRC-152, we advised you of actions we planned to take to resolve the violation.

In our February 1,1984, letter NRC-177, we advised that we had revised our specifications as required to allow substitution of standard marked fasteners to- simplify identification. We also expanded the scope of our fastener identification program to cover fasteners supplied un-installed by vendors.

In our July 25, 1984, letter NRC-242, we stated that a site administrative procedure, AP-XII-04 (Purchasing Bolting Materials), had been issued governing identification of bolting material and establishing controls to ensure similar Q and Non-Q fasteners are not issued. Until the procedure was issued and the various disciplines had a chance to become familiar with its requirements, we also routed all requisitions through the Civil Resident Engineer's office to assure uniformity and conformance with the procedure.

The special routing of requistions, having served its purpose, has been discontinued.

Investigation for acceptability of previously installed fasteners has been continuing, but additional time to complete the investigation will be required.

In some areas, the investigation for acceptability will include reinspection as individual documentation packages are completed and verified prior to system turnover. Our previous projection for completing this investigation was based on the, then current, fuel load and in-service dates which have now been re-scheduled.

O XEX-dh4/1-OS5

{

llI Dr. 3. Nelson' Grace NRC-342 Our current projected date for completing verification of previously installed fasteners is January 10,1986.

Thank you for your consideration in this matter.

Yours very truly, WW R. M. Parsons ~

Project General Manager Completion Assurance Shearon Harris Nuclear Power Plant RMP:dd cc: Messrs. G. Maxwell /R. Prevatte (NRC-SHNPP)