r ,

u AC40. R A NRC MONTHLY OPERATING REPORT DOCKET NO 50-361 DATE Pla y 13,1983 COMPLETED BY _ L Havweather TELEPHONE 714/492-7700 -

EXT 56223 OPER_ATING ST ATUS San Onofre Nuclear Generatino Station, Unit 2

1. Unir Name:
2. Reporting Period 1 April,1983 through 30 April,1983 _

3,390

3. Licensed Thermal Power (Mhti:

1,127

4. Nameplate Rating (Grou MWel
5. Design Electrical Rating (Net Mhe); 1,087 1,127
6. Masimum Dependable Capacity (Gron Mhel 1,087
7. Maximum Dependable Capacity (Net Mhe).

3

8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report. Give Reasons-NA -

=

9. Power Lese! To which Restricted. lf Any (Net Mhe) NA 10 Reason, For Restriction <. lf Any . NA This Month Yr to Date Cumulatne 719 2,879 5,339.2 11 Hour, in Reporting Penod 0 796 .0 1,829.5 1: Number Of Hours Reactor ka, Critica!

0 0 0

13. Reactor Reserse Shutdown Hours 0 476.9 1 ,3 01 l 14. Houn Generator On-Line 0 0 0 l~ 15 Unit Resene Shutdown Houn
16. Grom Thermal Energy Generated (MWH i 0.0 700.690 1.629.030 0.0 164,600 359,612 17 Grte Electrical Eners) Generated (MWH, 0.0 117,100 243,120 lb. Net Deetncal Energy Generated (MWH, NA NA NA 19 Urut Senice Factor NA NA NA 20 Unit Asailability Factor 0 0 0
21. Unit Capacit3 Factor (Using MDC Neti 0 0 0 2.' Unit Capacity Factor (Umg DER Net) l 0 0 0 23 Unit Forced Outage Rate f

' 24. Shutdowns Scheduled Oser Nest 6 Month tType.Date.and Duration of Earti None p

25 If Shot Down At End Of Report Period. Estansted Date of Startup 36 Unit In Test Status tPrx,r io Commeecial Operationi- Focecast Achsrwd 7/17/82 7/26/82 INITI AL CRIT 6C ALID 9/82 9/20/62 INITI AL ELECTRICin COMMERCI AL OPER ATIOs Under review 8306160489 830513 PDR ADOCK 05000361 R PDR

r .

\-

. l i

AVERAGE DAILY UtiIT P0&ER LEVEL  ;

i DOCKET 10. 50-361 l UNIT SOtGS - 2 DATE 5/13/83 j

. C0tPLETED BY L.Mayweather l .

TELEPH0tE 714/492-7700 Ext. 56223 l

M0tml APRIL 1983 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (We-Net)

(We-Net) 17 0 1 0 18 0 2 0 19 0 3 0 20 0 4 0 21 0 _

5 0 22 0 6 0 23 0 7 0 _ . _ _

24 0 8 0 25 0 9 0 26 0 10 0 27 0 11 0 i

) 28 0 12 0 29 0 13 0 30 0' 14 0 31 NA 15 0 16 0

UNIT SHUTDOWNS AND FOWER RFDUCTIONS DOCKETNO, - 361 UNIT NAME SONGS- 2 ,

DATE Ma v 13. 1983 Rf 70RI MONfff APRIL) 983 COMPLETEn eY I 582 w :ither TEl.EPHONE 714 /f47.770n Ex t 56223 r -

% lhie F-1-e 3- ]geEi I.itenwe g *,, fg Cauw A Currecine 4 2 iveni ay a. ? Ao..in io S j$ d Rep.ni er 40

^ '

j 5, g }' P event Recurrente -

6

  • 10 830211 F 71 9 0 4 NA NA NA Outage continued to perform .

maintenance on various systems IJnit awaiting removal _of regulatorv restrictions on reactor trip breakers and PASS prior to restart.

~

l 2 3 4 I IMeted Renin Methmi S N hedulcil A 1 quipment Fadure(Emplain)

I.stnhis F . Instrucinnis 1 -Man ual sor Prepar.itnen of Da'a

' R Maleneninice or Test .' Manual St ram 1.ntes Sheris los I ssensee -

l' Itclucling 1 Auiornaiw S uen. I veni Rep...I 11 i Ri l etc tNI'R1 (.

Il Hery'ii.ns Restriction 4 Continuation frGm p"*Vfous Ultili I Opcuina leaming A Inense I sanimaison month F Atinunneraive t; o nuininal liene ll =plami 5. Reduction of 20% or greater ll oilire ai spl.nio in the past 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> ' "b" I l 5'""""'#

9.0ther (Explain) 0... q ... ,. . ., .

f .

SUMMARY

OF OPERATItG EXPERIENCE FOR TIIE M3!Tril DOCKET 10. 50-361 UNIT SOtGS 2 DATE 5/13/1983 00f9LETED BY L.Mayweather TELEPHONE 714/492-7700 Ext. 5627T~~

April 1, 0001 Unit is in Mode 4 at 2100F. A cooldown is in progress to repair 2W-8248 containment isolation valve. No positive reactivity changes are being made pending completion of the evaluation of failed surveillance tests of the reactor trip breakers. Revision of the license condition concerning the PASS (extending the date of required operability) is required prior to Mode 2 entry.

April 1, 0029 Ditered Mode 5 April 2, 0603 2W-8248 operable following valve replacemnt.

April 2, 0955 Entered Mode 4.

April 4, 0510 Entered Mode 3.

4 April 4, 1345 2W-8248 declared inoperable due to erroneous valve position indication.

April 4, 1440 Comenced cooldown in accordance with LCO 3.0.3.

April 4, 1752 Notified the NRC via the red phone and the site inspector that 2W-8248 is operable and cooldown has been terminated.

April 5, 1930 PASS denonstration for the NRC completed.

April 6, 1455 Entered Mode 4.

April 6, 1945 Satisfactorily coupleted hydroset testing of pressurizer safety valve setpoint.

r .

sumary of Operating Experience for the Month of April, 1983 Page 2 of 2 April 7, 0520 started TPCW pump 3P-120 to split out TPCW from Unit 2.

April 7, 0525 Stopped WCW pump 3P-120. W CW surge tank was pressurized to the discharge head of the TpCW pur.ps as a result of a mispositioned valve and the removal of an automatic control feature. 'Ihe tank bottom bowed and all anchor bolts parted.

April 7, 1300 mtered Mode 5 and comenced outage activities consistent with NRC approval for return to Mode 2 and power operation.

April 18 2034 Placed W CW in service following cocpletion of repairs to surge tank.

April 24, 2050 Entered Mode 4.

April 28, 1312 Entered Mode 3.

April 29, 1240 Notified that NRC has given approval for Unit 2 to enter Mode 2 (interim approval on reactor trip breakers and license amendment for PASS).

April 30, 2359 Unit is in Mode 3 at 530 0F, 2250 psia.

preparations for Mode 2 entry are in progress.

Safety evaluation report from the NRR on the reactor trip breaker incident is required prior to proceeding to Mode 1.

f. .

REFUELI!C INFOR%TIOtt DOCKET 10. 50-361 UtIIT SONGS 2 l DATE 5/13/83 l COMPLETED BY L.Mayweather .

l TELEPHOtIE 714/492-7700 Ext. 56223

1. Scheduled date for next refueling shutdown.

Not yet determined.

2. Scheduled date for restart following refueling.

Not yet determined.

3. Will refueling or resunption of operation thereafter require a Technical Specification change or other license amendment?

Not yet determined.

What will these be?

Not yet determined.

4. Scheduled date for submitting proposed licensing action and supporting information.

Not yet determined.

[ 5. Important Licensing considerations associated with refueling, e.g. new or different fuel design or supplier, t

unreviewed design or performance analysis methods, l significant changes in fuel design, new operating procedures.

Not yet determined.

6. '1he number of fuel assemblies.

a) In the core. 217 b) In the spent fuel storage pool. O.

7. Licensed spent fuel storage capacity. 800 Intended change in spent fuel storage capacity. PR _
8. Projected date of last refueling that can be discharged to spent fuel storage poole assuming present capacity. E l

0554u

  • ~

AC40 R A NRC MONTHLY OPERATING REPORT DOCKET NO 50-362 DATE May 13.1983 COMPLETED BY I M2 maather TELEPHONE 714/4922700 EXT 56223 OPER ATING ST ATUS I. Unit Name.

San Onofre Nuclear Generating Station, Unit 3

2. Reporting Period 1 April,1983 throuch 30 Acril .1983 3,390
3. Licenwd Thermal Power (Mht t 1,127
4. Nameplate Rating IGross MWet 1,087
5. Design Electrical Rating (Net MWe):

1,127

6. Masimum Dependable Capacit) (Gross Mhe,
7. Masimum Dependable Capoeity (Net MWe). 1.087
8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report.Gise Reasorm NA
9. Power Lese! To Which Restricted. If Any (Net MWe). NA
10. Renon, F or Restnetiens. lf Any : NA This Month Yr to Date C umul:,t n e 2,879 4 ,007 II Hours in Reporting Penod 0 0 0 12 .sumber Of Hours Reactor has Critical 0 0 0 13 Reactor Rewne Shutdown Houn 0 0 0 14 Hours Generator On Line 0 0 0
15. Unit Resene Shutdown Houn 0 0 0 16 Grom Thermal Energy Generated (MWH, O O O 17 Gros Electrical Energy Ge wroted (MWHI 0 0 0 lb. Net Electncal Energy Generated (Mh H, NA NA NA
19. Unit Senice Factor NA NA NA 20 Urut Asailability Factor 0 0 0 21 Unit Capacits Factor IUsing MDC Neti 0 0 0 22 Unit Capacits Factor IUung DER Net) 0 0 0 23 Urut Forced Outage Rate 24 Shutdomm Scheduled Oser Nest 6 Month-(Type. Date.and Duration of Each t.

None NA

25. If Shut Dumn At End Of Report Penod. Estimated Date of Startup 24 Unit In Test Status (Prmt :o Commernal Operationi Forecast Achrsed 1%IT14L CRITIC ALIn Under review Under review l%ITI A L ELECTRICin Under review COMMERCI AL OPER 4TIOs p n . . t . ) . . . . . . . ...

( .

AVERAGE DAILY UNIT POWER LEVEL DOCKET 10. 50-362 UNIT ~ SONGS - 3 DATE 5/13/83 COMPLETED BY L.Mayweather TELEPHONE 714/492-7700 Ext. 56223 M0tCH APRIL 1983 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL i (We-Net) (We-Net) 1 ~0 17 0 2 0 18 0 3 0 19 0 4 0 20 0 5 0 21 0 6 0 22 0 7 0 23 0 8 0 24 0 i-9 0 25 0 10 0 26 0 11 0 27 0 12 0 28 0 13 0 29 0 14 0 30 0 15 0 31 NA 16 0

DOCKET NO. 50-36 2 UNIT SHUTDOWNS AND POWER RFIDUCTIONS UNIT NAME SONGS ,

DATE May 13 . 983 REPOR I MON TH APRIL 1983 icoMPLETEp my i Mavwpather

~

TELEPHONE 714'/492.77cn Ext. 56223 3 -

$? 3 h Ek I.nenwe [ r, Cause A Correttive f*1

% lble h 3? 4 2sE l' vent 3,7 n. Attism in f: E j f, g Rcrant er mO j' Prevent Recurrente 6

i NA NA NA NA NA NA NA NA NA NA I 2 1 4 I I~orced Reau en Methi=1 l.nluhis F Insitutinais

% Sc heduled A liquipment Failure IEmplain) l-Manual los Prepar.ition of Data R.Maintenarwe os Test .' Manual % raan 1.ntrg Sheets Ios I aensee C.Mclucting i Autorn.iisc S r.lin. I veni Repois t1 I HlI ~ile t'411NI G

1) Megut.ii.ns Restriction 4 Continuation from previous Olf,Il 1 Opciatos Itaining A L nense I xanunation month F Admennliall<c
5. Reduction of 20% or greater

' ' '" '" ' I I S' " " * " " ' '

'li-' ihen o"l'" 11 ' ' """ ' " "' d ' I ''" '

spl ini in the Past 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> 9.0ther (Explain) ,

o. ..i . i . .. .. . .,,.

p -

SUMMARY

OF OPERATI!G EXPERIENCE FOR THE lOf7ITI DOCKET NO. 50-362 UNIT SOtGS 3 DATE 5/13/1983 COMPLETED BY L.Mayweather TELEPHCHE 714/492-7700 Ext. 56223 April 1, 0001 Unit is in Mode 5 in an extended outage to replace the CEDM coil stacks on all 91 control rods. No positive reactivity changes are to be made pending completion of the evaluation of failed surveillance tests of the reactor trip breakers. Revision of the license condition concerning the PASS (extending the date of required operability) is required prior to Mode 2 entry.

April 5, 1930 PASS demonstration for the NRC coupleted.

April 15, 0800 CEDM coil stack replacement complete.

Construction of steam generator nozzle dams underway.

April 25, 0800 Steam generator nozzle dam work is couplete. Comenced preparations for filling the Reactor Coolant System.

April 29, 0450 Comenced filling of the Reactor Coolant System.

April 30, 0450 Unit is in Mode 5 at 1320F RCS fill and vent is in progress.

F *

.c ~

REFUELING INFORMATION DOCKET NO. 50-362 UNIT SONGS 3 DATE 5/13/83 .

COMPLETED BY L.Mayweather TELEPHONE 714/492-7700 Ext. 56223

1. Scheduled date for next refueling shutdown.

Not yet determined.

2. Scheduled date for restart following refueling.

Not yet determined.

3. Will refueling or resu@ tion of operation thereafter require a 'Iechnical Specification change or other license amendment?

Not yet determined.

What will these be?

Not yet determined.

4. Scheduled date for submitting proposed licensing action and supporting information.

Not yet determined.

5. Inportant Licensing considerations associated with refueling, e.g. new or different fuel design or supplier, f unreviewed design or performance analysis methods, significant changes in fuel design, new operating procedures.

tbt yet determined.

6. 'Ihe number of fuel assenblies, a) In the core. 217 h
b) In the spent fuel storage pool. O.

f 7. Licensed spent fuel storage capacity. 800 Intended change in spent fuel storage capacity. la

8. Projected date of last refueling that can be discharged to spent fuel storage poole assuming present capacity. g l

0554u

f r*

7. .

Southern California Edison Company h5

$ AN ONOFRE NUCLE AR GENER ATING ST ATION

. P .O. B O M 128

  • S A N C LEMENT E. C A LIFORNt a 92672 TELEPHONE j . H. 8. R AY STATION M AN AGE R (7149 492 7700 May 13,1983 Director Office of Management Information and Program Analysis U. S. Nuclear Regulatory Commission Washington DC 20555

Dear Sir:

Subject:

Docket Nos: 50-361/50-362 Monthly Operating Reports for April, 1983 San Onofre Nuclear Generating Station, Units 2&3 Enclosed are the Monthly Operating Reports as required by Section 6.9.1.10 of Appendix A, Technical Specifications to Facility Operating Licenses NPF-10 and NPF-15 for San Onofre Nuclear Generating Station, Units 2 and 3, respectively.

Please contact us-if we can be of further assistance.