Responds to NRC 810408 Ltr Re Violations Noted in IE Insp Repts 50-358/80-16 & 50-358/80-25.Corrective Actions:All Insp & Const Procedures Revised.No Proprietary Info Contained in Ltr
ML20041E265
Person / Time
Site: Zimmer
Issue date: 02/12/1982
From: Borgmann E
CINCINNATI GAS & ELECTRIC CO.
To: Norelius C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
QA-1631, NUDOCS 8203100307
Download: ML20041E265 (2)


Text

.a O *>

THE CINCINNATI GAS & ELECTRIC COMPANY set CIN CIN N ATI. OHIO 4 5201 February 12, 1982 c.4. onou,uu QA-1631 SE N*OR veC E PRESIDENT g\ /

U. S. Nuclear Regulatory Commission cf c3 Region III [Cy 799 Roosevelt Road /.n ,

g Glen Ellyn, Illinois 60137 t

{ ,S 9'

h _

Attention: Mr. C. E. Norelius, Acting Director y

/qk

] JJ .

Division of Engineering and .. ; ,A, Technical Inspection -

RE: WM. H. ZIMMER NUCLEAR POWER STATION UNIT I I. E. INSPECTION REPORT #81 DOCKET NO.

50-358, CONSTRUCTION PERMIT CPPR-88, W. O.

  1. 57300 JOB E-5590 FILE NO. NRC-1 81-17 Gentlemen:

This letter constitutes a supplement to our letter QA-1606, dated February 1, 1982. It is our opinion that nothing in the letter is of a proprietary nature.

Item E, of the subject report, identified two inspection reports, 50-358/

80-16 and 50-358/80-25 regarding the review and revision of HJK procedures. This is being addressed as part of CG&E activities in response to your Immediate Action Letter, dated April 8, 1981. Our last correspondence indicated that all inspection procedures would be revised prior to our committed date of January 30, 1982, with construction procedure revisions scheduled to be complete by February 28, 1982.

Some procedures have been identified which are listed as administrative proce-dures because they control the interface between various organizations and therefore, did not receive review and approval by CC&E prior to January 30, 1982. Since these procedures delineate the responsibilities for Quality Assurance personnel involved in the specified processes, these procedures will be reviewed and approved by CG&E as Quality Assurance procedures. These procedures will be processed along with the other administrative and construction procedures and are scheduled to be completed by February 28, 1982 as previously committed.

1EI '

j 8203100307 820212 PDRADOCK05000g ,

gggj g

- 3 l

r

  • .o Mr. C. El Norelius U. S. Nuclear Regulatory Commission Region III February 12, 1982 - QA-1631 Page 2 We trust the above will serve as an acceptable supplementary response to the subject Inspection Report.

Very truly yours, THE CINCINNATI GAS & ELECTRIC COMPANY u &

f E. A. BORGMANN SENIOR VICE PRESIDENT FKP:ac cc: NRC Resident Inspector c

Attn: W. F. Christianson NRC Office of Inspection & Enforcement Washington, D.C. 20555