Forwards Correction to 831006 Response to NRC Request for Info Re Control of Heavy Loads.All Cranes & Hoists Purchased to Sargent & Lundy Specs
ML20082V215
Person / Time
Site: Zimmer
Issue date: 12/09/1983
From: Williams J
CINCINNATI GAS & ELECTRIC CO.
To: Harold Denton
Office of Nuclear Reactor Regulation
References
REF-GTECI-A-36, REF-GTECI-SF, RTR-NUREG-0612, RTR-NUREG-612, TASK-A-36, TASK-OR LOZ-83-0219, LOZ-83-219, NUDOCS 8312200022
Download: ML20082V215 (4)


Text

_ _ _ _ _ _ _ _ _ _ _ _ _ _

sq

-== - r(m TIIE CINCINNATI GAS & ELECTILIC COMI%NY 85 ~

CINCINN ATI. OHIO 4 5201 December 9, 1983 LOZ-83-0219 J. WILLIAMS JR sf NION V6CE PRESIDENT NUCLEAR OPERAYlONS Docket No. 50-358 Mr. Harold Denton, Director Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C.

20555

Dear Mr. Denton:

RE:

WM. H.

ZIMMER NUCLEAR POWER STATION UNIT 1 - CONTROL OF HEAVY LOADS OCTOBER 6, 1983/ SUBMITTAL - ERRATA The Electrical Overhead Crane Institute (EOCI) standard No.

61 cited in our earlier response was inadvertently referred to as CMAA No. 61.

A correct copy of our earlier response is attached for your convenience.

Very truly yours, THE CINCINNATI GAS & ELECTRIC COMPANY By

. WILLIAMS, J SENIOR VICE PR SIDENT SJT/sfr 0?

h0 u I 8312200022 831220 PDR ADOCK 05000358 A

PDR s

O

Mr. Harold Denton Director December 9, 1983 LOZ-83-0219 Page 2 cc:

John H. Frye III Frank F. Hooper M. Stanley Livingston Lynne Bernabei, Esc.

Troy B. Ccnner, Jr.

Andrew B. Dennison John E. Dolac.

James P. Fenstermaker G. C. Ficke W.M. Hill, Jr.

J.G. Keppler L.L. Kintner Stephen F. Koziar David K. Martin William J. Moran George E. Pattison Samuel H. Porter Steven G. Smith Deborah F. Webb John D. Woliver EG&G

.P.O. Box 1625 Idaho Falls, ID. 83415 ATTN: T.H. Stickley 1

' REQUEST The Phase I objective of NUREG-0612, identified in article 5.1.1, is to ensure that all load handling systems at nuclear power plants are designed and operated such that their probability of failure is uniformly small and appropriate for the critical tasks in which they are employed.

Enclosed in Mr. Youngblood's August 11, 1983 letter to CG&E is a report prepared by EG&G, " Control of Heavy Loads at Nuclear Power Plants, Wm. H. Zimmer Nuclear Power Station (PHASE I)", dated July, 1983.

The report stated that design information is not presented for Item No. 301 (Turbine Building Crane) and that further information is needed.

The report also stated that for Hoist Item 108, the general listings rate the hoist at'18 tons and at 20 tons.

This data should be consistent.

REPLY All cranes and hoists purchased for use at the Wm. H. Zimmer Nuclear Power Station were purchased to Sargent & Lundy (S&L) specifications.

These specifications are based upon various standards applicable at the time of eauipment purchase.

Structural reauirements were based upon Electric Overhead Crane Institute (EOCI) and American Institute for Steel Construction (AISC) standards for overhead bridge cranes and ANSI B30.ll or ANSI B30.16, as appropriate, for underhung cranes or hoists.

Electrical eauipment for motor operated cranes was specified to meet and be tested to applicable United States of America Standards Institute (USASI) i standards or ANSI B30.2.0.

In addition, the reauirements of l

EOCI No. 61 or CMAA No. 70 were specified, as well as applicable IEEE and NEMA standards.

l Item No. 301 (Turbine Building Crane) was specified per the structural recuirements of EOCI and AISC standards for overhead bridge cranes.

The electrical crane eauipment for Item No. 301 was specified to meet USASI standards, and the recuirements of EOCI No. 61.

l Item No. 108 (Main Steam Isolation Valve Hatch Slab Hoist) was specified per the structural reauirements of ANSI B30.16.

The electrical motor eauipment for Item No. 108 was specified to meet ANSI B30.2.0, and the recuirements of CMAA No. 70.

l Item No. 108 is rated at 20 Tons.

L

LOZ-83-0219 Attachment Page 2 I

Additional clarification applies to Item No. 101.

The June 1, 1983 CG&E report, "Wm. H. Zimmer Nuclear Power Station-Unit 1, Heavy Loads Report", stated that Item No. 101 (Reactor Building Crane) was specified per the reauirements of CMAA.

The Sargent & Lundy purchase specification stated that electrical eauipment for motor operated cranes meet the requirements of EOCI No. 61.

Item No. 101 was not specified to meet the reauirements of CMAA No. 70.