ML20083E406

From kanterella
Jump to navigation Jump to search
Forwards Ebasco Svcs,Inc Proposal, Audit of Program to Verify Quality of Const & Continuation of Const Plan, for NRC Approval,Per 821112 Order to Show Cause Requiring Independent Auditor
ML20083E406
Person / Time
Site: Zimmer
Issue date: 12/06/1983
From: Williams J
CINCINNATI GAS & ELECTRIC CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
Shared Package
ML20083E402 List:
References
CLI-82-33, LOZ-83-0249, LOZ-83-249, NUDOCS 8312290200
Download: ML20083E406 (2)


Text

-

l TIIE CINCINNATI GAS & ELECTRIC COMPANY CINCINN ATI,OHlO 45201 December 6, 1983 LOZ-83-0249 J. WILLIAMS, JR SENIOR WCE PREseDENT NUCLEAR OPERAff0NS i[ W ftk STAFF Docket No. 50-358 nfx1

@[

-q. .

U.S. Nuclear. Regulatory Commission Region III ,

gg"r^gh-3pp- 7 7-+- -

,7 799 Roosevelt Road

  • F--- >f T Glen Ellyn, Illinois 60137 gip Fi M A -

Attention: Mr. J.G. Keppler Regional Administrator Gentlemen:

RE: WM. H. ZIMMER NUCL. EAR POWER STATION - UNIT 1 INDEPENDENT AUDIT.0F'THE QUALITY OF CONSTRUCTION W40. 57300, JOB E-5590, FILE NO. 956C The NRC Order to Show Cause (CLI-8 2-33) of November 12, 1982, requires that the Plan to Verify the Quality of Construction (PVOC) include-an audit-by a cualified outside organization, which.did not perform the activities being audited, to verify the adecuacy of the cuality of construction. In addition, Comment 4 of enclosure 1 to NRC (RIII) letter to CG&E of November 15, 1983, states:

"The auditor should meet the competence and independence criteria outlined in.the February 1, 1982, letter from the NRC to Congressmen Ottinger and Dingell. The auditor should be approved by the NRC. Any communications between the independent overviewer or auditor of the PVOC and CG&E are subject to the ' Protocol Governing Communications between CG&EJand Independent Organizations Conducting Reviews or

~

Audits under the Commission's Order' sent to you by letter dated March 2, 1983."

CG&E letter serial LOZ-83-0239 of November 23, 1983, to NRC (RIII) reported CG&E's intent to expand the scope of the independent' audit'of the PVQC to cover the QA/QC aspects of the Continuation-of Construction Plan (CCP) so that all QA/QC activities through the issue of the Operating License prior to fuel load will be subject to an independent audit.

The-purpose of this letter is to report the selection of the Independent-Auditor and to recuest NRC approval of this selection in accordance with the reauirements stated above.

8312290200 831222 PDR ADOCK 05000358 C6 A PDR dd

  • 15-P*r 'M*' r Wfa ref e e'TW' 't& 4w_

s-,v u

Mr. J.G. Keppler Regional Administrator December 6,-1983 LOZ-83-0249 Page 2 Based on CG&E's evaluation of the proposals received, as regards the independence, competence, and approach, Ebasco Services Incorporated (EBASCO) has been selected for the role of Independent Auditor. Attached as Enclosure 1 is EBASCO's proposal, which describes the corporate cualifications of EBASCO for this audit,which describes the cualifications of the-key individuals to be assigned to the work, which confirms EDASCO's independence relative to the Zimmer project in accordance with the criteria imted above, and which summarizes the approach EBASCO intends to take when developing the audit plan.

Your timely approval of EBASCO to function as the Independent Auditor of the PVQC and of QA/OC aspects of the CCP is reauested.

Very truly yours, THE CINCINNATI GAS & ELECTRIC COMPANY B

J. WILLIAMS, JR.

SENIOR VICE PRESIDENT GFC/sfr Enclosure cc: . (without Enclosure)

NRC Office of Inspection & Enforcement Washington, D.C. 20555 NRC Resident Site Supervisor ATTN: W.M. Hill NRC Zimmer Project Inspector, Region III ATTN: E. R. Schweibinz J