ML110270190

From kanterella
Jump to navigation Jump to search
IR 05000302-10-005, on 10/01/2010 -12/31/2010, Crystal River Unit 3, Routine Integrated Report
ML110270190
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 01/27/2011
From: Rich D
NRC/RGN-II/DRP/RPB3
To: Franke J
Progress Energy Florida
References
IR-10-005
Download: ML110270190 (38)


See also: IR 05000302/2010005

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

245 PEACHTREE CENTER AVENUE NE, SUITE 1200

ATLANTA, GEORGIA 30303-1257

January 27, 2011

Mr. Jon A. Franke

Vice President, Crystal River Nuclear Plant

Crystal River Nuclear Plant (NA2C)

15760 W. Power Line Street

Crystal River, FL 34428-6708

SUBJECT: CRYSTAL RIVER UNIT 3 - NRC INTEGRATED INSPECTION REPORT

05000302/2010005

Dear Mr. Franke:

On December 31, 2010, the US Nuclear Regulatory Commission (NRC) completed an

inspection at your Crystal River Unit 3. The enclosed inspection report documents the

inspection findings, which were discussed on January 10, 2011, with you and other members of

your staff.

The inspection examined activities conducted under your license as they related to safety and

compliance with the Commissions rules and regulations and with the conditions of your license.

The inspectors reviewed selected procedures and records, observed activities, and interviewed

personnel.

Based on the results of this inspection one licensee identified violation, which was of very low

safety significance, is listed in Section 4OA7 of the report. If you contest the non-cited violation,

you should provide a response within 30 days of the date of this inspection report, with the basis

for your denial, to the Nuclear Regulatory Commission, ATTN.: Document Control Desk,

Washington DC 20555-001; with copies to the Regional Administrator Region II; the Director,

Office of Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-

0001; and the NRC Resident Inspector at the Crystal River Unit 3 site.

FPL 2

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its

enclosure will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records (PARS) component of the NRCs document

system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-

rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Daniel W. Rich, Chief

Reactor Projects Branch 3

Division of Reactor Projects

Docket No. 50-302

License No. DPR-72

Enclosure: Inspection Report 05000302/2010005

w/Attachment: Supplemental Information

cc w/encl: (See page 3)

___ML110270190______________ G SUNSI REVIEW COMPLETE

OFFICE RII:DRP RII:DRP RII:DRS RII:DRS RII:DRS RII:DRS RII:DRP

SIGNATURE TXM1 via email RJR1via email DRich for RKH1 via email WTL via email DRich for SRS5 via email

NAME TMorrissey RReyes RChou RHamilton WLoo CDykes SSandal

DATE 01/21/2011 01/21/2011 01/27/2011 01/21/2011 01/25/2011 01/27/2011 01/21/2011

E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO

OFFICE RII:DRS RII:DRP RII:DRS RII:DRS RII:DRS

SIGNATURE DRich for WXD1via email RSB2 via email MKM3 via email LFL via email

NAME PHiggins WDeschaine RBaldwin MMeeks LLake

DATE 01/27/2011 01/21/2011 01/27/2011 01/21/2011 01/24/2011

E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO

OFFICE RII:DRS RII:DRP RII:DRP RII:DRS

SIGNATURE REW1 via email SON DWR1 RFA via email

NAME RWilliams SNinh DRich RAiello

DATE 01/20/2011 01/21/2011 01/27/2011 01/26/2011

E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO

FPC 3

cc w/encl: Joseph W. Donahue

R. J. Duncan, II Vice President

Vice President Nuclear Oversight

Nuclear Operations Carolina Power and Light Company

Carolina Power & Light Company Electronic Mail Distribution

Electronic Mail Distribution

Jack E. Huegel

Brian C. McCabe Manager, Nuclear Oversight

Manager, Nuclear Regulatory Affairs Crystal River Nuclear Plant

Progress Energy Carolinas, Inc. Electronic Mail Distribution

Electronic Mail Distribution

David T. Conley

James W. Holt Associate General Counsel

Plant General Manager Legal Dept.

Crystal River Nuclear Plant (NA2C) Progress Energy Service Company, LLC

Electronic Mail Distribution Electronic Mail Distribution

Stephen J. Cahill Mark Rigsby

Engineering Manager Manager, Support Services - Nuclear

Crystal River Nuclear Plant (NA2C) Crystal River Nuclear Plant (NA2C)

Electronic Mail Distribution Electronic Mail Distribution

R. Alexander Glenn Attorney General

Associate General Counsel Department of Legal Affairs

(MAC - BT15A) The Capitol PL-01

Florida Power Corporation Tallahassee, FL 32399-1050

Electronic Mail Distribution

Ruben D. Almaguer

Christos Kamilaris Director

Director Division of Emergency Preparedness

Fleet Support Services Department of Community Affairs

Carolina Power & Light Company Electronic Mail Distribution

Electronic Mail Distribution

Chairman

William A. Passetti Board of County Commissioners

Chief Citrus County

Florida Bureau of Radiation Control 110 N. Apopka Avenue

Department of Health Inverness, FL 36250

Electronic Mail Distribution

Daniel R. Westcott

Supervisor

Licensing & Regulatory Programs

Crystal River Nuclear Plant (NA1B)

Electronic Mail Distribution

FPC 4

Letter to Jon Franke from Daniel Rich dated January 27, 2011

SUBJECT: CRYSTAL RIVER UNIT 3 - NRC INTEGRATED INSPECTION REPORT

05000302/2010005

Distribution w/encl:

C. Evans, RII

L. Douglas, RII

OE Mail

RIDSNRRDIRS

PUBLIC

RidsNrrPM Crystal River Resource

U.S. NUCLEAR REGULATORY COMMISSION

REGION II

Docket No.: 50-302

License No.: DPR-72

Report No.: 05000302/2010005

Licensee: Progress Energy (Florida Power Corporation)

Facility: Crystal River Unit 3

Location: Crystal River, FL

Dates: October 1, 2010 - December 31, 2010

Inspectors: T. Morrissey, Senior Resident Inspector

R. Reyes, Resident Inspector

R. Chou, Reactor Inspector (Section 4OA5.2)

R. Hamilton, Senior Health Physicist (Sections 2RS6, 40A1.2)

W. Loo, Senior Health Physicist (Sections 2RS1, 40A1.2, 40A5.4)

C. Dykes, Health Physicist (Sections 2RS8)

S. Sandal, Senior Reactor Inspector (Section 4OA5.2 and 4OA5.3)

P. Higgins, Senior Reactor Inspector (Section 4OA5.3)

W. Deschaine, Reactor Inspector (Section 4OA5.3)

R. Baldwin, Senior Operations Engineer (Section 4OA5.5)

M. Meeks, Operations Engineer (Section 4OA5.5)

L. Lake, Senior Reactor Inspector (Section 4OA5.2)

G. Thomas, Structural Engineer (Section 4OA5.2)

F. Farhad, Senior Structural Engineer (Section 4OA5.2)

R. Williams, Reactor Inspector (Section 4OA5.6)

R. Aiello, Senior Operations Engineer (Section 1R11)

Approved by: D. Rich, Chief,

Reactor Projects Branch 3

Division of Reactor Projects

Enclosure

SUMMARY OF FINDINGS

IR 05000302/2010005; 10/01/2010 -12/31/2010; Crystal River Unit 3; Routine Integrated

Report.

The report covered a three month period of inspection by resident inspectors, regional

operations engineers, regional reactor inspectors, headquarters inspectors, and regional health

physicists. The NRCs program for overseeing the safe operation of commercial nuclear power

reactors is described in NUREG-1649, Reactor Oversight Process, Revision 4, dated

December 2006.

A. NRC Identified & Self-Revealing Findings

No findings were identified

B. Licensee Identified Violations

One violation of very low safety significance, which was identified by the licensee, has

been reviewed by the inspectors. Corrective actions taken or planned by the licensee

have been entered into the licensees corrective action program. The violation and

corrective action tracking number is listed in Section 4OA7 of this report.

Enclosure

REPORT DETAILS

Summary of Plant Status:

Crystal River 3 began the inspection period with the full core off-loaded to the spent fuel pool.

On November 19, 2010, the licensee commenced transfer of reactor fuel assemblies to the

reactor vessel. On November 27, 2010, after fuel reload was complete and the reactor head

fully tensioned, the unit entered Mode 5. Unit 3 remained in Mode 5 for the remainder of the

inspection period.

1. REACTOR SAFETY

Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity

1R01 Adverse Weather Protection

.1 Seasonal Susceptibility: Cold Weather Preparation

a. Inspection Scope

The inspectors evaluated the licensees readiness for mitigating cold weather to assure

that vital systems and components were protected from freezing in accordance with the

licensees administrative instruction AI-513, Seasonal Weather Preparations, Section

4.1, Cold Weather Preparations. The inspectors walked down portions of the

systems/areas listed below to check for any unidentified susceptibilities. Operability of

heat trace circuits and set points of temperature controls was verified. Nuclear condition

reports (NCRs) were reviewed to verify that the licensee was identifying and correcting

cold weather protection issues.

  • EGDG-1A and 1B rooms
  • Emergency feed water pump EFP-3 building including EFP-3 heat tracing
  • Intermediate building 95 elevation EFP-1 and EFP-2 areas

b. Findings

No findings were identified.

.2 Site Specific Weather Condition

a. Inspection Scope

During the period listed below, the inspectors verified that the licensee implemented

Administrative Instruction AI-513, Seasonal Weather Preparations, Sections 4.2

(Freezing Weather) and/or 4.3 (Freezing Weather Monitoring). The inspectors walked

down portions of the A and B emergency diesel generator (EGDG) systems; the

alternate AC diesel generator system; and the EFP-3 building to check for any

unidentified susceptibilities to cold weather. Nuclear condition reports were reviewed to

Enclosure

4

verify that the licensee was identifying and correcting cold weather protection issues.

This completed one sample for a site specific weather related condition.

  • December 1-2 with nightly outside temperatures below freezing

b. Findings

No findings were identified.

1R04 Equipment Alignment

.1 Partial Equipment Walkdowns

a. Inspection Scope

The inspectors performed walkdowns of the critical portions of the selected trains to

verify correct system alignment. The inspectors reviewed plant documents to determine

the correct system and power alignments, and the required positions of select valves

and breakers. The inspectors verified that the licensee had properly identified and

resolved equipment alignment problems that could cause initiating events or impact

mitigating system availability. The inspectors verified the following three partial system

alignments during system walkdowns using the listed documents:

pump SWP-1B trains using operating procedure OP-707, Operation of the ES

Emergency Diesel Generators, and OP-408, Nuclear Services Cooling System, while

the A train systems (EGDG, RW and SW) were out of service to support planned

maintenance

generator EGDG-1C, using OP-707 and OP-707C, Operation of The Alternate AC

Diesel Generator, while EGDG-1B was out of service for testing

  • B train decay heat (DH) and the decay heat closed cycle cooling (DC) systems using

OP- 404, Decay Heat Removal System; and the 4160/480 Volt switch gear rooms,

using OP-703, Plant Distribution System, while the A train DH, DC, and emergency

diesel generator were out of service for maintenance

b. Findings

No findings were identified.

.2 Complete Equipment Walkdown

a. Inspection Scope

The inspectors conducted a detailed review of the condition of the emergency feed water

system (turbine driven emergency feed water pump EFP-2 and the diesel driven EFP-3)

and of the makeup system (makeup pumps 1A, 1B and 1C). A review of outstanding

Enclosure

5

maintenance work orders was performed to verify that any deficiencies did not

significantly affect system function. In addition, the inspectors reviewed NCRs to verify

that system problems were being identified and appropriately resolved. The system

health reports (emergency feed water dated October 29, 2010, and makeup system

dated July 16, 2010) and system equipment walkdown summary reports (makeup and

purification dated July 07, 2010, and emergency feed water dated July 7, 2010), were

reviewed to ensure equipment issues identified were properly addressed in the

corrective action program (CAP). The walkdowns to verify system lineup were not

completed due to delays in returning the systems to service. The completion of this

inspection that will verify proper system lineup will be completed prior to unit restart in

2011. Documents reviewed are listed in the Attachment.

b. Findings

No findings were identified.

1R05 Fire Protection

Fire Area Walkdowns

a. Inspection Scope

The inspectors walked down accessible portions of the plant to assess the licensees

implementation of the fire protection program. The inspectors checked that the areas

were free of transient combustible material and other ignition sources. Also, fire

detection and suppression capabilities, fire barriers, and compensatory measures for fire

protection problems were verified. The inspectors checked fire suppression and

detection equipment to determine whether conditions or deficiencies existed which could

impair the function of the equipment. The inspectors selected the areas based on a

review of the licensees probabilistic risk assessment. The inspectors also reviewed the

licensees fire protection program to verify the requirements of Final Safety Analysis

Report (FSAR) Section 9.8, Plant Fire Protection Program, were met. Documents

reviewed are listed in the Attachment. The inspectors toured the following five areas

important to reactor safety:

  • Emergency Feed Water Initiation and Control (EFIC) Rooms
  • Emergency feed water pump EFP-3 building
  • Make up pump (MUP-1A, 1B and 1C) cubicles
  • Fire pump building
  • Cable spreading room

b. Findings

No findings were identified.

Enclosure

6

1R06 Flood Protection Measures

Internal Flood Protection

a. Inspection Scope

The Inspectors inspected the manholes listed below that are subject to flooding to verify

cables were not submerged in water, cables were intact, and cable support structures

were adequate to perform its function. The inspectors observed four manholes that are

subject to flooding that contain equipment important for the safe operation of the plant.

Documents reviewed are listed in the Attachment.

  • Manhole E-1 (Location: hot machine shop; Circuits: circulating water pump (CWP)

power cables (480 VAC) and intake systems control/alarm circuits)

  • Manhole E-2 (Location: Southeast berm; Circuits: CWP power cables and intake

systems control/alarm circuits)

  • Manhole E-3 (Location: Southwest berm; Circuits: CWP power cables and intake

systems control/alarm circuits)

  • Manhole E-7 (Location: Intake; Circuits: CWP power cables and intake systems

control/alarm circuits)

b. Findings

No findings were identified.

1R11 Licensed Operator Requalification

Annual Review of Licensee Requalification Examination Results

a. Inspection Scope

In February 2010, the licensee completed administering the annual requalification

operating tests which were required to be given to all licensed operators in accordance

with 10 CFR 55.59(a)(2). The inspectors performed an in-office review of the overall

pass/fail results of the individual operating tests, as well as the crew simulator operating

tests. These results were compared to the thresholds established in Manual Chapter

609 Appendix I, Operator Requalification Human Performance Significance

Determination Process.

b. Findings

No findings were identified.

Enclosure

7

1R12 Maintenance Effectiveness

a. Inspection Scope

The inspectors reviewed the licensees effectiveness in performing routine maintenance

activities. The review included an assessment of the licensees practices associated

with the identification, scope, and handling of degraded equipment conditions, as well as

common cause failure evaluations and the resolution of historical equipment problems.

For those systems, structures, and components within the scope of the Maintenance

Rule (MR) per 10 CFR 50.65, the inspectors verified that reliability and unavailability

were properly monitored and that 10 CFR 50.65 (a)(1) and (a)(2) classifications were

justified in light of the reviewed degraded equipment condition. Documents reviewed are

listed in the Attachment. The inspectors conducted this inspection for the following two

equipment issues:

  • NCR 425961, SWP-1A vibration in alert range

In addition, the inspectors reviewed the licensees MR (a)(3) Periodic Evaluation

indicated below to verify that the PE had been completed once per refueling cycle. The

licensee has reviewed MR (a)(1) goals, MR (a)(3) performance criteria, preventative

maintenance and effectiveness of corrective action and industry operating experience.

The licensee has made appropriate adjustments as a result of the PE. This constitutes

an addition sample under this inspection procedure.

  • AR 396407396407 Maintenance Rule (a)(3) Periodic Assessment dated May 2010

b. Findings

No findings were identified.

1R19 Post Maintenance Testing

a. Inspection Scope

The inspectors witnessed and/or reviewed post-maintenance test procedures and/or test

activities, as appropriate, for selected risk significant systems to verify: (1) testing was

adequate for the maintenance performed, (2) acceptance criteria were clear, and

adequately demonstrated operational readiness consistent with design and licensing

basis documents, (3) test instrumentation had current calibrations, range, and accuracy

consistent with the application, (4) tests were performed as written with applicable

prerequisites satisfied, and (5) equipment was returned to the status required to perform

its safety function. The five post-maintenance tests reviewed are listed below:

  • Surveillance procedure SP-344A, RWP-2A, SWP-1A and Valve Surveillance, (SWP-

1A portion only), after performing unplanned maintenance on SWP-1A per work

order (WO) 1833988

Enclosure

8

  • SP-354A-EC-71897-TP2, EC Functional Test Procedure for Protective Relay to

Increase EGDG-A Availability While Paralleled for Testing Generator Run, after

installing modification EC-71897. WO 1846129, which implemented changes to EC- 71897 Revision 11 and tested breakers 3205, 3211, 3207, and 3209

  • Nuclear assurance procedure NAP-02, Preparation and Control of CR3 Site Specific

Special Processes and Guidelines, Appendix 5, Ultrasonic Shear-Wave Examination

of Socket Welds, after installation of decay heat valve DHV-215, per WO 1849124

  • Performance test PT-399, DCV-17, DCV-177, DCV-18, and DCV-178 Stroke Test (A

train only); and preventative maintenance procedure PM-260, Calibration of Decay

Heat Exchanger Closed Cycle Cooling Control Loop after performing maintenance

on DCV-17 per WO 1838581

  • SP-344A, RWP-2A, SWP-1A and Valve Surveillance; and SP-344C, Containment

Cooling System Fan and valve Surveillance, after maintenance affecting service

water valves SWV-43, SWV-151, SWV-152 and SWV-355 per WOs 1136741 and

1567589

b. Findings

No findings were identified.

1R20 Refueling and Outage Activities

Steam Generator Replacement Refueling Outage (RFO16)

a. Inspection Scope

On September 26, 2009, the unit was shut down for a steam generator replacement

refueling outage. NRC integrated inspection reports 05000302/2009005,

05000302/2010002, 05000302/2010003 and 05000302/2010004 documented NRC

outage inspection activities prior to this inspection period. To verify the licensee was

managing fatigue, the inspectors verified that the outage shift schedule allowed for the

minimum days off in accordance with 10 CFR Part 26. In addition, the inspectors

determined that there were no fatigue waiver requests, fatigue self-declarations and

fatigue assessments since this aspect was last reviewed during the 2010 second quarter

inspection period. The inspectors observed and monitored licensee controls over the

refueling outage activities listed below. Additional inspection results for RFO16 will be

documented in next quarters NRC integrated inspection report 05000302/2011002.

Documents reviewed are listed in the Attachment.

  • Outage related risk assessment monitoring
  • Controls associated with shutdown cooling, reactivity management, electrical power

alignments, containment closure, and spent fuel pool cooling

  • Implementation of equipment clearance activities
  • Reduced inventory activities

Enclosure

9

  • Refueling activities including verification that fuel assemblies were loaded in the

correct reactor core locations

  • Reactor mode changes

b. Findings

No findings were identified. During the creation of a temporary opening in the reactor

containment building to support steam generator replacement, the licensee discovered

an internal crack in the concrete containment. The circumstances associated with the

crack in the concrete containment wall were assessed by an NRC special inspection

team. The results of that inspection are documented in NRC special inspection report

05000302/2009007.

1R22 Surveillance Testing

a. Inspection Scope

The inspectors observed and/or reviewed five surveillance tests listed below to verify

that Improved Technical Specification (ITS) surveillance requirements were followed and

that test acceptance criteria were properly specified. The inspectors verified that proper

test conditions were established as specified in the procedures, that no equipment

preconditioning activities occurred, and that acceptance criteria had been met.

Additionally, the inspectors verified that equipment was properly returned to service and

that proper testing was specified and conducted to ensure that the equipment could

perform its intended safety function following maintenance or as part of surveillance

testing.

In-Service Test:

  • SP- 340E, DHP-1B, BSP-1B And Valve Surveillance

Surveillance Test:

  • SP- 417, Refueling Interval Integrated Plant Response To An Engineered

Safeguards Actuation

  • SP-901, 4160V ES Bus B Undervoltage Trip Test and Auxiliary Relay Calibration

b. Findings

No findings were identified.

Enclosure

10

2. RADIATION SAFETY (RS)

Cornerstones: Occupational Radiation Safety (OS) and Public Radiation Safety (PS)

2RS1 Radiological Hazard Assessment and Exposure Controls

a. Inspection Scope

Hazard Assessment and Instructions to workers During facility tours, the inspectors

directly observed labeling of radioactive material and postings for radiation areas, high

radiation areas (HRAs), and airborne radioactivity areas established within the

radiologically controlled area (RCA). The inspectors independently measured radiation

dose rates or directly observed conduct of licensee radiation surveys for selected RCA

areas. The inspectors reviewed survey records for several plant areas including surveys

for alpha emitters, hot particles, airborne radioactivity, gamma surveys with a range of

dose rate gradients, and pre-job surveys for selected Unit 3 (U3) refueling outage (RFO)

work activities. The inspectors also discussed with licensee cognizant representatives

changes to plant operations that could contribute to changing radiological conditions

since the last inspection. For selected U3 RFO jobs, the inspectors attended pre-job

briefings and reviewed radiation work permit (RWP) details to assess communication of

radiological control requirements and current radiological conditions to workers.

Selected work activities included decontamination of the deep end of the cavity, transfer

tube cover work, letdown cooler room work, and insulation work under the reactor

vessel.

Hazard Control and Work Practices The inspectors evaluated access barrier

effectiveness for selected U3 Locked HRA and Very HRA locations. Changes to

procedural guidance for Locked HRA and Very HRA controls were discussed with

selected radiation protection (RP) supervisors. Controls and their implementation for

storage of irradiated material within the spent fuel pool (SFP) were reviewed and

discussed in detail with licensee representatives. Established radiological controls

(including airborne controls) were evaluated for selected tasks including work in auxiliary

building HRAs, and radwaste processing and storage areas. In addition, licensee

controls for areas where dose rates could change significantly as a result of plant

shutdown and U3 refueling operations were reviewed and discussed.

Occupational workers adherence to selected RWPs and RP technician (RPT)

proficiency in providing job coverage were evaluated through direct observations and

interviews with licensee staff. Electronic dosimeter (ED) alarm set points and worker

stay times were evaluated against area radiation survey results for selected U3 RFO

activities. ED alarm logs were reviewed and worker response to dose and dose rate

alarms during selected work activities was evaluated. For HRA tasks involving

significant dose rate gradients, the inspectors evaluated the use and placement of whole

body and extremity dosimetry to monitor worker exposure.

Control of Radioactive Material The inspectors observed surveys of material and

personnel being released from the RCA using small article monitor, personnel

contamination monitor, and portal monitor instruments. The inspectors reviewed records

Enclosure

11

for selected release point survey instruments and discussed equipment sensitivity, alarm

setpoints, and release program guidance with licensee staff. The inspectors compared

recent 10 CFR Part 61 results for the dry active waste (DAW) radioactive waste

(radwaste) stream with radionuclides used in calibration sources to evaluate the

appropriateness and accuracy of release survey instrumentation. The inspectors also

reviewed records of leak tests on selected sealed sources and discussed nationally

tracked source transactions with licensee staff.

Problem Identification and Resolution Nuclear Condition Reports (NCRs) associated

with radiological hazard assessment and control were reviewed and assessed. The

inspectors evaluated the licensees ability to identify and resolve the issues in

accordance with procedure CAP-NGGC-0200, Condition Identification and Screening

Process. The inspectors also evaluated the scope of the licensees internal audit

program and reviewed recent assessment results.

RP activities were evaluated against the requirements of Final Safety Analysis Report

(FSAR) Chapters 11 and 12; Improved Technical Specifications (ITS) Sections 5.4 and

5.8; 10 CFR Parts 19 and 20; and approved licensee procedures. Licensee programs

for monitoring materials and personnel released from the RCA were evaluated against

10 CFR Part 20 and IE Circular 81-07, Control of Radioactively Contaminated Material.

Documents reviewed are listed in the Attachment.

The inspectors completed all specified line-items detailed in Inspection Procedure (IP)

71124.01 (sample size of 1)

b. Findings

No findings were identified.

2RS6 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems

a. Inspection Scope

Effluent Monitoring and Radwaste Equipment During inspector walkdowns, accessible

sections of the liquid and gaseous radwaste and effluent systems were assessed for

material condition and conformance with system design diagrams. The inspection

included floor drain tanks, liquid waste system piping, waste gas decay tanks, monitor

tanks, liquid radwaste monitors, plant stack effluent monitors, and associated airborne

effluent sample lines. The inspectors interviewed licensee staff regarding radwaste

equipment configuration and effluent monitor operation.

The inspectors reviewed performance records and calibration results for selected

radiation monitors, flowmeters, and air filtration systems. For effluent radiation monitors

RMA-3 (main plant stack), RMA-4 (reactor building purge exhaust), RMA-6 (fuel

handling building exhaust), RML-2 Plant Liquid Discharge Line (prior to dilution) and

RML-5 (liquid waste), the inspectors walked down the monitors for material condition

and alignment. The last two surveillances on the control room HEPA/Charcoal air

Enclosure

12

treatment systems also were reviewed. The inspectors evaluated out-of-service effluent

radiation monitors and compensatory action data for the period January 2009 - August

2010.

Installed configuration, material condition, operability, and reliability of selected effluent

sampling and monitoring equipment were reviewed against details documented in the

following: 10 CFR Part 20; Regulatory Guide (RG) 1.21, Measuring, Evaluating and

Reporting Radioactivity in Solid Wastes and Releases of Radioactive Materials In Liquid

and Gaseous Effluents from Light-Water Cooled Nuclear Power Plants; American

Nuclear Standards Institute (ANSI)-N13.1-1969, Guide to Sampling Airborne Radioactive

Materials in Nuclear Facilities; ITS Section 5; the Offsite Dose Calculation Manual

(ODCM); and FSAR, Chapter 12. Documents reviewed are listed in the Attachment.

Groundwater The inspectors reviewed the sites groundwater sampling and analysis

results and discussed the current trends with Chemistry Department personnel.

Effluent Release Processing and Quality Control Activities The inspectors reviewed

recent liquid and gaseous release permits including pre-release sampling results,

effluent monitor set-points, and resultant doses to the public. The inspectors also

reviewed the 2008 and 2009 annual effluent reports to evaluate reported doses to the

public and to review ODCM changes. The inspectors reviewed daily Quality Control

(QC) data logs and calibration records for instruments used to quantify effluent sample

activity including High Purity Germanium (HPGe) detectors and liquid scintillation

counters. In addition, results of the 2009, and 2010 inter-laboratory cross-check

program were reviewed.

Observed task evolutions, count room activities, and offsite dose results were evaluated

against details and guidance documented in the following: 10 CFR Part 20 and

Appendix I to 10 CFR Part 50; ODCM; RG 1.21; RG 1.109, Calculation of Annual Doses

to Man from Routine Releases of Reactor Effluents for the Purpose of Evaluating

Compliance with 10 CFR Part 50 Appendix I; and ITS Section 6. Documents reviewed

are listed in the Attachment.

Problem Identification and Resolution: Selected NCRs associated with effluent release

activities were reviewed and assessed. The inspectors evaluated the licensees ability

to identify, characterize, prioritize, and resolve selected issues in accordance with

procedure CAP-NGGC-0200, Condition Identification and Screening process, Rev.

33.The inspectors also evaluated the scope of the licensees internal audit program and

reviewed recent assessment results. Documents reviewed are listed in the Attachment.

The inspectors completed one specified line-item sample as detailed in IP 71124.06.

b. Findings

No findings were identified.

Enclosure

13

2RS8 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and

Transportation

a. Inspection Scope

Radioactive Material Storage. Inspectors reviewed the FSAR, the Process Control

Program (PCP) and recent effluent release report for information on the types, amounts

and processing of radioactive waste disposed. Quality assurance documents in this

area were reviewed.

During facility walkdowns inspectors observed containers of radioactive waste for proper

labeling in accordance with 10 CFR 20.1904 and 10 CFR 20.1905. Inspectors noted the

satisfactory material condition of containers throughout the facilities inside and out.

Postings around stored radioactive materials were in accordance with 10 CFR 20.

Radioactive Waste System Inspectors evaluated the waste disposal systems during

plant walkdowns, escorted and unescorted, and through discussion with cognizant

employees. Accessible components of the liquid and solid waste systems were

observed some of the many areas that were evaluated such as the Yellow room;

laundry/shower sump tank rooms; miscellaneous waste storage tank pump room; and

the RC evaporator valve alley. Processes for transferring radioactive waste into disposal

containers were reviewed by inspectors.

Radioactive waste characterization and shipping The Annual Effluence report for 2009

were reviewed by inspectors. Major waste streams were reviewed for the primary and

secondary resins, reactor coolant filters and DAW. Inspectors evaluated the analysis for

hard-to-detect nuclides, looked at scaling factors, and reviewed the quality assurance

(QA) comparison results between the licensees contracted laboratory results and

outside laboratory results.

Radwaste processing activities and equipment configuration were reviewed for

compliance with the licensees PCP and FSAR, Chapter 11. Waste stream

characterization analyses were reviewed against regulations detailed in 10 CFR Part 20,

10 CFR Part 61, and guidance provided in the Branch Technical Position on Waste

Classification (1983). Documents reviewed are listed in the Attachment.

Transportation program implementation was reviewed against regulations detailed in 10

CFR Part 20, 10 CFR Part 71, 49 CFR Parts 172-178, as well as the guidance provided

in NUREG-1608. Training activities were assessed against 49 CFR Part 172 Subpart H.

Documents reviewed are listed in the Attachment.

Problem Identification and Resolution The inspectors reviewed selected NCRs and

audits associated with radioactive solid waste processing and radioactive material

handling, storage and transportation. The inspectors evaluated the licensees ability to

identify, characterize, prioritize, and resolve the identified issues in accordance with

procedure CAP-NGGC-0200, Corrective Action Program, Rev. 33.

Enclosure

14

The inspectors completed one sample as detailed by inspection procedure 71124.08.

b. Findings

No findings were identified.

4. OTHER ACTIVITIES

4OA1 Performance Indicator (PI) Verification

.1 Reactor Safety

a. Inspection Scope

The inspectors checked the mitigating system performance indicators (MSPI) listed

below to verify the accuracy of the PI data reported. Performance indicator data

submitted from October 2009 through September 2010 was compared for consistency to

data obtained through review of monthly operating reports, nuclear condition reports,

and control room logs. The inspections were conducted in accordance with NRC

Inspection Procedure 71151, Performance Indicator Verification. The applicable

planning standard, Nuclear Energy Institute (NEI) 99-02, Revision 6, Regulatory

Assessment Performance Indicator Guidelines, and the licensees calculation P06-0002,

CR3 MSPI Basis Document for the CR3 Nuclear Plant, were used to check the reporting

for each data element. The inspectors discussed the PI data with the licensee personnel

associated with performance indicator data collection and evaluation.

  • Emergency AC power
  • Residual heat removal/decay heat system
  • Heat removal system
  • High pressure injection system
  • Cooling water system

b. Findings

No findings were identified.

.2 Radiation Safety

a. Inspection Scope

The inspectors sampled licensee data for the PIs listed below. To verify the accuracy of

the PI data reported during the period reviewed, PI definitions and guidance contained in

NEI 99-02, Regulatory Assessment Indicator Guideline, Rev. 6, were used to verify the

basis for each data element.

Enclosure

15

Occupational Radiation Safety (ORS) Cornerstone

The inspectors reviewed Performance Indicator (PI) data collected from October 1, 2009

through September 30, 2010, for the Occupational Exposure Control Effectiveness PI.

For the reviewed period, the inspectors assessed CAP records to determine whether

HRA, VHRA, or unplanned exposures, resulting in ITS or 10 CFR 20 non-conformances,

had occurred during the review period. In addition, the inspectors reviewed selected

personnel contamination event data, internal dose assessment results, and ED alarms

for cumulative doses and/or dose rates exceeding established set-points. The reviewed

data were assessed against guidance contained in NEI 99-02, "Regulatory Assessment

Indicator Guideline," Rev. 6. Documents reviewed are listed in the Attachment.

Public Radiation Safety (PS) Cornerstone

The inspectors reviewed the Radiological Effluent Technical Specification/Offsite Dose

Calculation Manual Radiological Effluent Occurrences PI results from October 1, 2009

through September 30, 2010. The inspectors reviewed CRs, effluent dose data, and

licensee procedural guidance for classifying and reporting PI events. The inspectors

also interviewed licensee personnel responsible for collecting and reporting the PI data.

Documents reviewed are listed in the Attachment.

The inspectors completed 2 of the required 2 samples for IP 71151.

b. Findings

No findings were identified.

4OA2 Identification and Resolution of Problems

.1 Daily Review

a. Inspection Scope

As required by Inspection Procedure 71152, Identification and Resolution of Problems,

and in order to help identify equipment failures or specific human performance issues for

follow-up, the inspectors performed a daily screening of items entered into the licensees

corrective action program (CAP). This review was accomplished by attending daily plant

status meetings, interviewing plant operators and applicable system engineers, and

accessing the licensees computerized database.

b. Findings

No findings were identified.

Enclosure

16

.2 Annual Trend Review

a. Inspection Scope

As required by Inspection Procedure 71152, Identification and Resolution of Problems,

the inspectors performed a review of the licensees CAP and associated documents to

identify trends that could indicate the existence of a more significant safety issue. The

inspectors review was focused on repetitive equipment issues, but also considered the

results of daily inspector CAP item screening discussed in Section 4OA2.1, plant status

reviews, plant tours, and licensee trending efforts. The inspectors review nominally

considered the six month period of July 2010 through December 2010. The review also

included issues documented in the licensees Plant Health Committee Site Focus List

dated November 2010, and various 3rd quarter 2010 departmental CAP Rollup & Trend

Analysis reports, nuclear oversite reports and maintenance rule (MR) reports.

Corrective actions associated with a sample of the issues identified in the licensees

corrective action program were reviewed for adequacy.

b. Findings and Observations

No findings were identified. The inspectors evaluated the licensees trend methodology

and determined that the licensee had performed a detailed review.

.3 Annual Sample Review

a. Inspection Scope

The inspectors selected NCR 431407 for a detailed review and discussion with the

licensee. This NCR was classified as significance level one requiring an apparent cause

evaluation. The NCR investigated an issue where a recently implemented engineering

change (EC) had been installed on the A emergency diesel generator (EGDG). As

installed, the EGDG would not have been able to load onto the A train emergency

service bus (bus) under three separate conditions. The inspectors checked that the

issues had been completely and accurately identified in the licensees corrective action

program; safety concerns were properly classified and prioritized for resolution; apparent

cause determination was sufficiently thorough; and appropriate corrective actions were

initiated. The inspectors also evaluated the NCR using the requirements of the

licensees CAP as delineated in corrective action procedure CAP-NGGC-0200,

Condition Identification And Screening Process.

b. Findings and Observations

On November 3, 2010, the licensee was performing surveillance test procedure SP-902,

4160 ES Bus A Under Voltage Trip Test And Auxiliary Relay Calibration, and found

that breaker 3211 could not be opened when using the control room switch. The Unit

was in a no-mode condition. The reactor vessel contained no fuel and all fuel was

stored in the spent fuel pool. The unit had been in this mode since October 9, 2009, as

a result of the extended refueling outage. The surveillance procedure isolates the bus

from the off-site power transformer (OPT) by opening breaker 3211 using a manual

Enclosure

17

control switch from the control room. During this step, breaker 3211 would not open and

remained in the closed position. The bus could not be isolated from the OPT using the

control room switch. The licensee backed out of the surveillance and entered the issue

into the CAP. The licensees investigation found that the design of a recently installed

EC had incorrectly removed a control wire for breaker 3211. The licensees apparent

cause evaluation identified that the engineering analysis for the EC lacked appropriate

depth and detail. Neither the responsible engineer nor the independent verifier had

adequately analyzed the proposed design change, which resulted in the failure to

complete an electrical connection required for proper operation of breaker 3211.

Corrective actions to address this issue were comprehensive and included training and

an engineering stand down to review this issue. Additionally, the licensee reviewed

other recently designed and installed ECs to verify adequate design and analyses of

correct depth and detail. No additional deficiencies were identified. A licensee identified

violation of design control was assessed by the inspectors and is documented in Section

4OA7.

4 Annual Sample Review - Operator Work Around

a. Inspection Scope

The inspectors reviewed the operator workaround program to verify the licensee was

identifying workarounds at an appropriate threshold and entering them into the corrective

action program. One operator workaround associated with the control complex chiller

system reliability (NCR 379560) was identified that will be resolved during the next

refueling outage. The inspectors determined that compensatory actions in place are

adequate to address the issue.

b. Findings

No findings were identified.

4OA5 Other Activities

.1 Quarterly Resident Inspector Observations of Security Personnel Activities

a. Inspection Scope

During the inspection period, the inspectors conducted observations of security force

personnel and activities to ensure that the activities were consistent with licensee

security procedures and regulatory requirements relating to nuclear plant security.

These observations took place during normal and off-normal plant working hours. These

quarterly resident inspector observations of security force personnel and activities did

not constitute any additional inspection samples. Rather, they were considered an

integral part of the inspectors normal plant status reviews and inspection activities.

b. Findings

No findings were identified.

Enclosure

18

.2 Steam Generator Replacement Project (SGRP) and Containment Wall Repair (IP

50001)

a. Inspection Scope

The inspectors conducted a review of the licensees Phase 4 concrete placement and

Phase 5 retensioning activities for the repair of the containment wall delamination and

reinstallation of the containment wall opening that was created during the SGRP in the

last quarter of 2009.

Rebar and Formwork Installation

The inspectors examined the rebar installation on Elevation 206 + 5 that was prepared

for concrete pour to ensure that the licensee had measured the reinforcing steel size,

spacing, lap splice length, and concrete minimum protection coverage. The inspectors

determined whether the licensee performed inspections on installation, testing, and

testing frequencies of swaged mechanical splices in accordance with the requirements

of the design drawings, the American Concrete Institute (ACI) Codes, and the American

Society of Mechanical Engineers (ASME) Code Section III Division 2, Concrete

Containment. The inspectors also examined the formwork installation and tendon

sleeve condition.

Concrete Pour

The inspectors reviewed the concrete pre-placement inspection checklist, including

cleaning and debris removal prior to the concrete pour. The inspectors observed

concrete placement activities on Elevation 206 + 5 to verify that activities pertaining to

concrete delivery time, flow distance, layer thickness and concrete consolidation or

vibration conformed to industry standards established by the ACI Codes. Concrete

batch tickets were examined to verify the material and quantity of each component for

concrete mix, truck revolution limit, concrete placement time limit, and water amount

added to the mix. The inspectors observed that concrete placement activities were

continuously monitored by the licensee and contractors quality control personnel and

engineers. The inspectors witnessed in-process testing and reviewed the results for

slump, air content, temperature, unit weight, and molding of the concrete cylinders for

compressive strength testing, and witnessed sample points and truck loads to verify that

concrete samples for the field testing and cylinders for the laboratory testing were

obtained at the point of placement (end of chute line) and the middle portion of the truck

loads. The inspectors reviewed concrete being poured into cylinders to determine

whether it was molded in accordance with applicable American Society for Testing and

Materials (ASTM) requirements of ASTM C 172, Standard Method of Sampling Freshly

Mixed Concrete, and to determine whether appropriate concrete field testing was

performed by Quality Control (QC) inspectors.

The inspectors reviewed or examined the licensee activities to verify that the activities

met the ACI code requirements, licensee procedures, and the industry standards. The

inspectors examined the batch plant for its certification and the preparation of the

concrete pour.

Enclosure

19

Containment Retensioning and Testing

The inspectors reviewed the containment retensioning plan, testing plan, and schedule.

The inspectors interviewed licensee personnel and reviewed documents related to the

retensioning and testing plans. The licensee was conducting a detailed analysis to

develop a tendon retensioning sequence that would minimize the possibility of causing

new cracks or delaminations in the containment during the retensioning process. The

licensee is scheduled to perform a Structural Integrity Test (SIT) after final retensioning

in order to test the structural integrity of the containment. Following the SIT, the licensee

is scheduled to perform an Integrated Leak Rate Test (ILRT) on the containment. The

inspectors review included the licensees plans for post-maintenance testing after

restart.

Document Review

The inspectors reviewed the engineering changes (ECs), specifications, drawings, work

packages, nuclear condition reports (NCRs), concrete compressive testing results, and

documents related to the concrete construction activities. The inspectors reviewed EC 75220, Reactor Building Delamination Repair Phase 4 - Concrete Placement, Revision

21 and EC 75221, Reactor Building Delamination Repair Phase 5 - Retensioning,

Revision 0. The inspectors reviewed SGT Work Packages (WP) 3-3732A, B, C, and D

Restoration of Containment Concrete Wall. The reviews or observations were

conducted in order to verify that the licensee performed activities in accordance with the

approved documents.

The inspectors reviewed records to verify that they met the licensee administrative

control procedures, Quality Control standard, Quality Assurance Program requirements,

and applicable industrial design and construction standards.

b. Findings

No findings were identified.

.3 Annual Sample Review

a. Inspection Scope

The inspectors selected NCR 431407 for a detailed review and discussion with the

licensee. This NCR was classified as significance level one requiring an apparent cause

evaluation. The NCR investigated an issue where a recently implemented engineering

change (EC) had been installed on the A emergency diesel generator (EGDG). As

installed, the EGDG would not have been able to load onto the A train emergency

service bus (bus) under three separate conditions. The inspectors verified that the

issues had been completely and accurately identified in the licensees corrective action

program, safety concerns were properly classified and prioritized for resolution, apparent

cause determination was sufficiently thorough, and appropriate corrective actions were

initiated. The inspectors also evaluated the NCR using the requirements of the

Enclosure

20

licensees CAP as delineated in corrective action procedure CAP-NGGC-0200,

Condition Identification And Screening Process.

b. Findings and Observations

On November 3, 2010, the licensee was performing surveillance test procedure SP-902,

4160 ES Bus A Under Voltage Trip Test And Auxiliary Relay Calibration, and found

that breaker 3211 could not be opened when using the control room switch. The Unit

was in a no-mode condition. The reactor vessel contained no fuel and all fuel was

stored in the spent fuel pool. The unit had been in this mode since October 9, 2009, as

a result of the extended refueling outage. The surveillance procedure isolates the bus

from the off-site power transformer (OPT) by opening breaker 3211 using a manual

control switch from the control room. During this step, breaker 3211 would not open and

remained in the closed position. The bus could not be isolated from the OPT using the

control room switch. The licensee backed out of the surveillance and entered the issue

into the CAP. The licensees investigation found that the design of a recently installed

EC had incorrectly removed a control wire for breaker 3211. The licensees apparent

cause evaluation identified that the engineering analysis for the EC lacked appropriate

depth and detail. Neither the responsible engineer nor the independent verifier had

adequately analyzed the proposed design change, which resulted in the failure to

complete an electrical connection required for proper operation of breaker 3211.

Corrective actions to address this issue were comprehensive and included training and

an engineering stand down to review this issue. Additionally, the licensee reviewed

other recently designed and installed ECs to verify adequate design and analyses of

correct depth and detail. No additional deficiencies were identified. A licensee identified

violation of design control was assessed by the inspectors and is documented in Section

4OA7.

.4 (Closed) NRC Temporary Instruction (TI) 2515/179, Verification of Licensee Responses

to NRC Requirement for Inventories of Materials Tracked in the National Source

Tracking System Pursuant to Title 10, Code of Federal Regulations, Part 20.2207 (10

CFR 20.2207)

a. Inspection Scope

The inspectors performed the TI concurrent with IP 71124.01 Radiation Hazard Analysis.

The inspectors reviewed the licensees source inventory records and identified the

sources that met the criteria for reporting to the NSTS. The inspectors visually identified

the sources contained in various calibration systems and verified the presence of the

source by direct radiation measurement using a calibrated portable radiation detection

survey instrument. The inspectors reviewed the physical condition of the irradiation

device. The inspectors reviewed the licensees procedures for source receipt,

maintenance, transfer, reporting and disposal. The inspectors reviewed documentation

that was used to report the sources to the NSTS. Documents reviewed are listed in the

Attachment.

Enclosure

21

b. Findings and Observations

No findings were identified. The inspectors performed the TI concurrent with IP

71124.01 Radiation Hazard Analysis. The inspectors reviewed the licensees source

inventory records and identified the sources that met the criteria for reporting to the

NSTS. The inspectors visually identified the sources contained in various calibration

systems and verified the presence of the source by direct radiation measurement using

a calibrated portable radiation detection survey instrument. The inspectors reviewed the

physical condition of the irradiation device. The inspectors reviewed the licensees

procedures for source receipt, maintenance, transfer, reporting and disposal. The

inspectors reviewed documentation that was used to report the sources to the NSTS

Documents reviewed are listed in the Attachment.

.5 Operator Licensing Training and Qualification Effectiveness Inspection

a. Inspection Scope

The inspectors reviewed associated documents in preparation for this inspection.

During the week of October 25 - 27, 2010, the inspectors reviewed documentation,

interviewed licensee personnel, and observed the administration of training associated

with the licensees operator requalification program and the Just In Time training

associated with the licensees startup preparations following an extended refueling

outage. The inspectors conducted the inspection under the guidance of IP 41500,

Training and Qualification Effectiveness Inspection. The inspectors evaluated that the

licensee had performed, or had scheduled to be performed, training as specified in a

letter from M. Widmann to J. Franke dated March 8, 2010. The inspectors directly

observed three unevaluated simulator scenarios for training, including the operating

crews self-critique; and reviewed the evaluated simulator scenario that was to be

administered to all licensed operators for this training cycle. The inspectors directly

observed classroom training that was given on the integrated plant start-up procedure,

including a presentation from chemistry personnel on some of the off-normal chemistry

concerns that were anticipated during the plant startup. The inspectors reviewed

documentation to include licensee self-assessment reports, watchstanding records for

proficiency, training attendance records, overall training plans and schedules, individual

training lesson plans, and documentation associated with evaluated simulator scenarios.

Documents reviewed are listed in the Attachment.

b. Findings

No findings were identified.

.6 (Closed) NRC Temporary Instruction 2515/172, Reactor Coolant System Dissimilar

Metal Butt Welds

a. Inspection Scope

The inspectors conducted a review of the licensees activities regarding licensee

dissimilar metal butt weld (DMBW) mitigation and inspection implemented in accordance

Enclosure

22

with the industry self imposed mandatory requirements of Materials Reliability Program

(MRP) 139, Primary System Piping Butt Weld Inspection and Evaluation Guidelines.

Temporary Instruction (TI) 2515/172, Reactor Coolant System Dissimilar Metal Butt

Welds, Revision 1 was issued May 27, 2010, to support the evaluation of the licensees

implementation of MRP-139.

On December 8, 2010, the inspectors performed a review in accordance with TI

2515/172, Revision 1 as described in the Observation Section below:

b. Observations

The licensee has met the MRP-139 deadlines for baseline examinations of all welds

scoped into the MRP-139 program. TI 2515/172, Revision 1 is considered closed. In

accordance with requirements of TI 2515/172, Revision 1, the inspectors evaluated the

following areas:

(1) Implementation of the MRP-139 Baseline Inspections

This portion of the TI was not inspected during the period of this inspection report, but

was previously covered in NRC Inspection Report 05000302/2008002.

(2) Volumetric Examinations

This portion of the TI was not inspected during the period of this inspection report, but

was previously covered in NRC Inspection Report 05000302/2009005.

(3) Weld Overlays

This portion of the TI was not inspected during the period of this inspection report, but

was previously covered in NRC Inspection Report 05000302/2008002.

(4) Mechanical Stress Improvement (SI)

There were no stress improvement activities performed or planned by this licensee to

comply with their MRP-139 commitments.

(5) Application of Weld Cladding and Inlays

There were no weld cladding nor inlay activities performed or planned by this licensee to

comply with their MRP-139 commitments.

(6) Inservice Inspection Program

This portion of the TI was not inspected during the period of this inspection report, but

was previously covered in NRC Inspection Report 05000302/2008005.

c. Findings

No findings were identified.

Enclosure

23

4OA6 Meetings, Including Exit

Exit Meeting Summary

On January 10, 2011, the resident inspectors presented the inspection results to Mr. J.

Franke, Site Vice President, and other members of licensee management. The

inspectors confirmed that proprietary information was not provided or examined during

the inspection.

4OA7 Licensee Identified Violations

The following issue of very low safety significance (Green) was identified by the licensee

and was a violation of NRC requirements. This issue met the criteria of Section 2.3.2 of

the NRC Enforcement Policy, NUREG-1600, for being dispositioned as a Non-Cited

Violation.

10 CFR 50 Appendix B, Criterion III, Design Control, requires, in part, that measures

shall be established to assure that applicable regulatory requirements and design basis

for those structures, systems, and components are correctly translated into

specifications, drawings, procedures and instructions. Engineering corporate

procedures EGR-NGGC-0011, Engineering Rigor; and EGR-NGGC-0155, Specifying

Electrical / I&C Modification Related Tests, implement those requirements. Contrary to

the above, the licensee failed to translate the design basis into drawings and procedures

when performing design modification EC 71897. This resulted in an electrical circuit

error in the A EDG breaker logic circuitry. The inadequate EC removed a switchgear

internal control wire that supplied DC control power to the following: 1) OPT differential

lockout relay to trip breaker 3211, 2) MCB control switch open contacts to trip breaker

3211, and 3) emergency safety A-bus under-voltage trip circuit to trip breaker 3211. As

a result of breaker 3211 not being able to trip under any of these three signals, the A

EDG would not have been able to meet the logic required to load onto the safety bus

when required. The licensee determined that engineering personnel did not have an

adequate understanding of assessing the correct engineering depth and detail involved

in designing and implementing the EC. The process deficiency of failing to provide

adequate depth and detail on the EC is more than minor because, if left uncorrected,

would have the potential to lead to a more significant safety concern. The finding was

determined to be of very low safety significance (Green) because there were no diesel

operability requirements during the time the inadequate EC had been installed.

Additionally, the inadequate EC was identified and corrected by the licensee prior to the

emergency generator being required by plant technical specifications to be available to

support a change in mode. This issue was documented in the licensees corrective

action program as NCR 431407. Additional information regarding this issue can be

found in Section 4OA2.3.

ATTACHMENT: SUPPLEMENTAL INFORMATION

Enclosure

KEY POINTS OF CONTACT

Licensee personnel:

B. Akins, Superintendent, Radiation Protection

M. Bishara, SGR Design Engineering Manager

S. Cahill, Manager, Engineering

J. Cravens, SGR Welding Engineer

F. Dola, Nuclear Oversight Superintendent

P. Dixon, Manager Training

D. Douglas Manager, Maintenance

P. Fagan, Repair Design and Construction Engineering Supervisor

J. Franke, Vice President, Crystal River Nuclear Plant

R. Griffith, SGR Task Manager

K. Henshaw, SGR Rigging Supervisor

D. Herrin, Licensing Engineer

J. Holt, Plant General Manager

J. Huegel, Manager, Nuclear Oversite

D. Jopling, SGR Civil Structural Supervisor

B. Kelley, RT Level III

D. Mayes, SGR Welding Engineer

W. Nielsen, SGR QC Supervisor

C. Poliseno, Supervisor, Emergency Preparedness

S. Powell, SGR Licensing engineer

J. Terry, SGR Project Manager

R. Vessley, SGR QC Supervisor

D. Westcott, Supervisor, Licensing

I. Wilson, Manager Outage and Scheduling

B. Wunderly, Manager, Operations

NRC personnel:

D. Rich, Chief, Branch 3, Division of Reactor Projects

LIST OF ITEMS OPENED, CLOSED AND DISCUSSED

Closed

05000302/2515/179 TI Verification of Licensee Responses to NRC

Requirement for Inventories of Materials

Tracked in the National Source Tracking

System Pursuant to Title 10, Code of

Federal Regulations, Part 20.2207 (10 CFR

20.2207), Revision 1 (Section 4OA5.4)

05000302/2515/172 TI Reactor Coolant System Dissimilar Metal

Butt Welds Revision 1 (Section 40A5.6)

Attachment

2

Discussed

05000302/2515/177 TI Managing Gas Accumulation in Emergency

Core Cooling, Decay Heat Removal, and

Containment Spray Systems (NRC Generic

Letter (GL) 2008-01) Revision 1 (Section

4OA5.3)

LIST OF DOCUMENTS REVIEWED

Section 1R04: Equipment Alignment

Nuclear Condition Reports (NCRs)

NCR 266531, EFGV-1 Governor oil out of sight high

NCR 286943, EFV-11 Closed without operator action

NCR 287855, EFP-3 Time delay relay setting different from DBD

NCR 301727, Temporary change from not completed within 14 days

NCR 304139, Untimely update of EF maintenance rule event log by system Engineer

NCR 304742, SP-146 Temp Change

NCR 305239, EFP-1 Breaker 52/H deficiency following maintenance

NCR 310438, Emergency feed water control valve stroke time repeatability

NCR 326879, EFV-148, Actuator stripped internally

NCR 331000, Blank flange found removed from EFT-2 building penetration

NCR 354537, SP-146 EFIC D channel would not go to maintenance bypass

NCR 363244, EFIC CH B blown fuse

NCR 371967, EFT-2 oxygen values not expected due to hydrazine levels

NCR 378992, EFP-2 found rotating during standby (on 1&2 aux steam)

NCR 266361, RECL-256 does not agree with RECL-267 within 14.1#

NCR 276666, Failed optical isolator during performance of SP-146

NCR 319008, DFT-4 particulate increasing trend near alert limit

NCR 325123, DFP-2 vibration data per SP-349B has low margin to IST alert

NCR 328103, Surface corrosion noted on EF piping in EFP-3 building

NCR 387621, EF buried piping G-scan inspection results

NCR 296860, PM-152 soil to pipe potentials found out of specification

NCR 295834, EF piping under west berm requires evaluation

NCR 294773, EF piping cathodic protection not performed annually

NCR 427428, MUV-244 significant packing leak

NCR 424905, MUP-1B motor phase resistance inbalance

NCR 400263, Piping not fully qualified

NCR 369532, NRC GL 2008-01 implementation challenges

NCR 358946, MUV-36 check valve disc separation

Section 1R05: Fire Protection

Procedures

AI-2205A, Pre Fire Plan - Control Complex

AI-2205B, Pre Fire Plan - Turbine Building

AI-2205C, Pre Fire Plan - Auxiliary Building

Attachment

3

Al -2205F, Pre Fire Plan - Miscellaneous buildings and Components

SP-804, Surveillance of Plant Fire Brigade Equipment

Section 1R06: Flooding

Model Work Order 614384, Site Manholes and Handhole Inspections

Implementation Work Order 1646872, Site Manholes and Handhole Inspections

Section 1R12: Maintenance Effectiveness

System engineering report SE10-0040, EG to be re-classified as (a)(2)

NCR 265002, Jacket coolant leaks identified during SP-354B

NCR 269400, EGDG Jacket adapter minor leak

WO 01600340, EGDG-1A/B/C EC-73336 for Dresser coupling restraint devices

WO 01357712, Replace Dresser coupling gaskets on EGDG-1A And EGDG-1B

NCR 400460, Minor errors found during periodic assessment

NCR 400462, Maintenance Rule evaluations corrections

AR 262703262703 Maintenance Rule Program (a)(3) Periodic Assessment dated May 2008

Licensee administrative procedure ADM-NGGC-0101, Maintenance Rule Program

WO 1848531, BSP-1B Coupling inspection and lubrication

Section 1R20: Refueling and Outage Activities

Procedures

AI-504, Guidelines for Cold Shutdown and Refueling

CP-341, Containment Penetration Control

FP-410, Reactor Vessel Closure Head Installation

FP-203, Offloading And Refueling Operations

OP-301A, Refueling Outage RCS Drain and Fill Operations

OP-421A, Operation Of The Reactor Building Polar Crane RCCR-1

SP-440, Unit Startup Surveillance Plan

WCP-102, Outage Risk Assessment

Nuclear Condition Reports

NCR 247148, Industry initiatives on heavy loads

NCR 314049, Crystal River 3 Outage Risk Assessment for R16

Calculations

Nureg - 0612 Nine-Month Report Control of Heavy Loads at Nuclear Plants, Crystal River Unit

3, Appendix F, Analysis of the Effect of Reactor Vessel Head Drop on the Reactor Vessel,

October 1983

Section 2RS1: Radiological Hazard Assessment and Exposure Controls

Procedures, Guidance Documents, and Manuals

CAP-NGGC-0200, Condition Identification and Screening Process, Rev. 33

CAP-NGGC-0201, Self-Assessment/Benchmark Programs, Rev. 14

CAP-NGGC-0205, Condition Evaluation and Corrective Action Process, Rev. 12

Attachment

4

CP-123, Restrained Components and Key Control, Rev, 61

DOS-NGGC-0002, Dosimetry Issuance, Rev. 27

FP-605, Spent Fuel Pools Controls and Accountability, Rev. 4

HPP-112, Hard to Detect Radionuclides Analyses, Rev. 2

HPP-202A, Supplemental Instructions to HPS-NGGC-0003: Radiological Surveys and

Inspections, Rev. 35

HPP-215, Health Physics Source Receipt and Control, Rev. 14

HPP-216, Diving Operations in Radiological Environments, Rev. 9

HPP-221, High Radiation Area, Locked High Radiation Area, and Very High Radiation Area

Controls, Rev. 12

HPS-NGGC-0001, Radioactive Material Receipt and Shipping Procedure, Rev. 30

HPS-NGGC-0003, Radiological Posting, Labeling and Surveys, Rev. 15

HPS-NGGC-0013, Personnel Contamination Monitoring, Decontamination, and Reporting,

Rev. 12

HPS-NGGC-0014, Radiation Work Permits, Rev. 8

HPS-NGGC-0016, Access Control, Rev. 6

HPS-NGGC-0023, Remote Radiological Monitoring, Rev. 4

HPS-NGGC-0024, Alpha Monitoring Guidelines, Rev. 2

SEC-NGGC-2162, Keys, Locks, and Combinations, Rev. 3

SS-201, Security Force Personnel General Orders, Duties, and Responsibilities, Rev. 60

Records and Data

2010 DAW Smears, Dated 09/08/10

CP-123, Restrained Components and Key Control, Rev, 61, Enclosure 5, Key Control

Log, Selected Logbook Entries

HPP-221, High Radiation Area, Locked High Radiation Area, and Very High Radiation Area

Controls, Rev. 12, Enclosures 1, HP Key Control Log; and 2, LHRA/SRC Authorization Key

Control Log, Selected Logbook Entries

Health Physics Survey Record (HPSR), Survey No. 10-01-0023, Routine HPP-202Z02,

HP Sources, Dated 01/07/10

HPSR, Survey No. 10-01-0210, Routine HPP-202W14, Survey of Source Storage Area,

Dated 10/15/10

HPSR Survey No. 10-10-0414, 95 Reactor Building Inside and Outside of Letdown

Cooler Room, Dated 10/28/10

HPSR Survey No. 10-11-0444, Under Vessel, Dated 11/30/10

HPSR Survey No. 10-12-0062, Old Letdown Cooler Room, Dated 12/06/10

HPSR Survey No. 10-12-0071, Reactor Building Lower Cavity, Dated 12/06/10

HPSR Survey No. 10-12-0082, Lower Reactor Cavity, Dated 12/07/10

NRC Form 748, National Source Tracking Transaction Report, Crystal River 3 Nuclear Power

Plant, License. No. DPR-72, Docket No. 50-302, Dated 01/05/2010

Personnel Contamination Log, RFO 16

Radiation Work Permit (RWP) Number (No.) 4704, Non-SGR Rad Waste Activities (High

Risk)

RWP No. 4711, Non-SGR Reactor Head/Cavity Activities (High Risk)

RWP No. 4732, Non-SGR Maintenance Activities (High Risk)

RWP No. 4744, Non-SGR Insulation Activities (High Risk)

SEC-NGGC-2162, Keys, Locks, and Combinations, Rev. 11/30/10, Attachment 1,

Attachment

5

Security Shift Key Control and Inventory, Selected Logbook Entries

Spent Fuel Pool Storage SFPA, Dated 10/20/10

Corrective Action Program (CAP) Documents

Action Request 00436795, Red plastic bags used in the RCA, Dated 12/07/10

Assessment No. 310235, Radiation Protection Refuel 16 Readiness, Undated

Assessment No. 382005, Quick Hit Self-Assessment Report, Electronic Dosimetry Set

Points, Undated

Section: 2RS6 Radioactive Gases and Liquid Effluent Treatment and Monitoring Systems

Procedures, Guidance Documents, and Manuals

CP-161, Radiological Environmental Monitoring Program, Rev. 6

SP-187, AHFL-2A/2B/2C/2D (Auxiliary Building) In-Place Filter Testing, Rev. 29

SP-731A, Auxiliary Building Ventilation Continuous Release, Rev.11

SP-731B, Reactor Building Purge Batch Release and Batch to Continuous Release, Rev. 21

SP-731C, Reactor Building Ventilation Continuous Release, Rev. 14

SP-731F, WDT-1A/WDT-1B/WDT-1C Release, Rev.10

SP-731E, Reactor Building Atmospheric Release after Integrated Leak Rate Testing, Rev. 9

SP-736A, WDT-10A Release to the Discharge Canal, Rev. 11

SP-736B, WDT-10B Release to the Discharge Canal, Rev. 12

SP-736C, WDT-11A Release to the Discharge Canal, Rev. 8

SP-736D, WDT-11B Release to the Discharge Canal, Rev. 8

SP-736E, WDT-11A and WDT-11B Combined Release to the Discharge Canal, Rev. 11

SP-736F, SDT-1 / Turbine Building Sump / Condensate Release To The Settling Ponds, Rev.13

SP-736G, SDT-1 Release to the Discharge Canal, Rev. 13

SP-736I, Condensate Release to the Discharge Canal, Rev. 10

Crystal River Unit 3 Off-Site Dose Calculation Manual, Rev. 32

Records and Data Reviewed

Crystal River Unit 3 -2008 Radioactive Effluent Release Report, April 21, 2009

Crystal River Unit 3 -2009 Radioactive Effluent Release Report, April 29, 2010

Release Permit 100138.006, 838.L SDT-1 Release to the Discharge Canal

Release Permit 100137.001.721.L WDT-10A Release to the Discharge Canal

Release Permit 100041.020.571.G Auxiliary Building Ventilation Continuous Release

Release Permit 100044. 018.063. G Reactor Containment Building Purge Batch Release

Results of Radiochemistry Cross Check Program 1st Quarter 2009

Results of Radiochemistry Cross Check Program 1st Quarter 2010

Results of Radiochemistry Cross Check Program 2nd Quarter 2010

Results of Radiochemistry Cross Check Program 3rd Quarter 2010

Surveillance: SP-186 AHFL-4A (Control Room) In-Place Filter Testing, 9/4/2009

Surveillance: SP-186 AHFL-4B (Control Room) In-Place Filter Testing, 9/4/2009

Ground Water Tritium Sampling Results from 2/27/2007 to 9/8/2010

CAP-NGGC-0200, Condition Identification and Screening Process, Rev.33

Crystal River Unit 3 UFSAR Chapter 11, Radioactive Waste & Radiation Protection, Rev. 32

Crystal River 3 10 CFR61 Waste Stream Analysis Results, 9/8/2010

Attachment

6

CAP Documents

NCR 411245, Nitrogen Line outside the RCA Spilled a Small Amount of Contaminated Water

(<1 gallon).

Section 2RS8: Radioactive Solid Waste Processing and Radioactive Material Handling,

Storage, and Transportation

Procedures, Manuals, and Guidance Documents

HPS-NGGC-0001, Radioactive Material and Shipping Procedure, Revision 30

HPP-240, Sampling for Part 61 Waste Stream Analysis, Rev. 0

HPS-NGGC-0002, Vendor Cask Utilization Procedure, Revision 17

Miscellaneous General Manual (MGM), Volume 1, Part 1 PCP, Process Control Program,

Revision 6

WP-105, Radioactive Material Shipping Forms, Revision 2

Records and Data Reviewed

2009 Radioactive Waste Shipment Log

2010 Radioactive Waste Shipment Log

Quick Hit Self-Assessment Report: Storage and Control of Licensed Material, 03/16-26/2009

Shipment Number (No.)09-142, Radioactive material Type A package, 7, UN2915, 11/13/2009

Shipment No.10-136, RQ Radioactive material , low specific activity (LSA-II) fissile

excepted,7,UN3321,09/28/2010

Shipment No.10-148, Radioactive material, excepted package-limited quantity of material, 7,

UN2910, 10-21-10

Crystal River Unit 3 -2008 Radioactive Effluent Release Report, Table 9, Solid Waste and

Irradiated Fuel Shipments

Crystal River Unit 3 -2009 Radioactive Effluent Release Report, Crystal River Unit 3 -2009

Radioactive Effluent Release Report

RADMAN Database Report for Crystal River 3 Nuclear Plant, Change 146

2010 WDT-6 Primary Resin Sample Data Set Evaluation, 9/8/2010

CAP Documents

Nuclear Condition Report (NCR) No. 00419558, AB sump level rate of rise lowered with DW

secured

NCR No. 00415776, Black substance found on ground at rusty building

NCR No. 00416921, Boric Acid removal without oversight from nuclear waste technician or

radwaste supervision

Section 4OA1: Performance Indicator Verification

Procedures, Guidance Documents and Manuals

REG-NGGC-0009, NRC Performance Indicators and Monthly Operating Report Data,

Rev. 10

Records and Data Reviewed

2009 DRDE Evaluations Log

2009-2010 DRD Alarms Logs

Crystal River Unit 3 -2008 Radioactive Effluent Release Report, April 21, 2009

Attachment

7

Crystal River Unit 3 -2009 Radioactive Effluent Release Report, April 29, 2010

Release Permit 100138.006, 838.L SDT-1 Release to the Discharge Canal

Release Permit 100137.001.721.L WDT-10A Release to the Discharge Canal

Release Permit 100041.020.571.G Auxiliary Building Ventilation Continuous Release

Release Permit 100044. 018.063. G Reactor Containment Building Purge Batch Release

CAP Documents

AR 00359577, An individuals electronic dosimeter (ED) audio alarm faulted with a low battery

condition

4OA5: Other Activities

Steam Generator Replacement Inspection (IP50001)

EC 75220, Reactor Building Delamination Repair Phase 4 - Concrete Placement, Revision 21.

EC 75221, Reactor Building Delamination Repair Phase 5 -Retensioning, Revision 0.

Work Packages (WPs) 3-3732A, 3-3732B, 3-3732C, and 3-3732D, Restoration of Containment

Concrete Wall.

SGR EC Closure Schedules

Progress Energy SP-178, Containment Leakage Test-Type A Including Liner Plate

SGT Nonconformance Report (NCR) 1104, Rebar Spacing Did Not Meet the Requirements at

EL. 201 to 206

SGT NCR 1109, #11 Vertical Rebar Spacing at Tendon 34V21 Greater Than Allowable

SGT NCR 1115, Rebar Spacing Did not Meet the Requirements at EL. 216 to 221

Operator Licensing Training and Qualification Effectiveness Inspection

Operator Licensing Training and Qualification Effectiveness Inspection Records

Quick Hit Self-Assessment 421775, CR3 Operations Proficiency Training in Preparation for S/U

From R16, Attachment 8 to CAP-NGGC-0201, 09/28/2010.

Quick Hit Self-Assessment 422394, Restart Readiness, Attachment 8 to CAP-NGGC-0201,

09/17/2010.

Licensed Operator Requalification Training Schedules for Cycles 10A and 11A.

Licensed Operator Continuing Training (LOCT) Attendance Tracking Records (covering 12

training cycles).

Simulator Crew and Individual Evaluation Summaries for SES-69, Crew C, 10/21/2010.

Lesson Plans

OPS-4-54, Decay Heat Removal System, Revision 14, 02/11/2010.

OPS-5-1111, Post R16 Implementation Review for the Steam Generator Replacement (SGR)

and Extended Power Uprate (EPU) Projects, Revision 0, 10/08/2010.

OPS-5-1096, R16 Plant Walkdown, Revision 1, 10/15/2010.

OPS-5-1110, R16 Startup Sequence Overview and Testing Review Training, Revision 0,

10/15/2010.

OPS-5-1105, NGG Leadership Behaviors, Revision 0, 10/05/2010.

OPS-9-3083, Startup & Shutdown JIT Training, Revision 5, 12/21/2009.

OPS-9-3320, Decay Heat System Operations, Revision 0, 06/01/2010.

Attachment

8

Procedures

OP-202A, Refueling Outage Plant Heatup and Startup, Revision 18.

OP-204A, Plant Startup and Power Operations After R16/R17, Revision 3.

OP-304. Soluble Poison Concentration Control, Revision 29.

TRN-NGGC-0420, Nuclear Generation Group Standard Procedure: Conduct of Simulator

Training and Evaluation, Revision 0.

Simulator Dynamic Scenario Packages

OPS-9-3326 Scenario #2: MFWP Trip and Runback, HD Leak Causes Rapid Power Reduction

and Turbine Trip, Revision 1, 10/21/2010.

OPS-9-3326 Scenario #3: Turbine Bypass Valve Fails Open, RCP seal failure, RCP trip and

runback, Spurious Reactor Trip, Revision 1, 10/21/2010.

OPS-9-3326 Scenario #4: ICS Malfunction, Heater Drain System Malfunction, Steam Generator

Tube Rupture, Revision 1, 10/21/2010.

SES-69: Gland Steam Oscillations, High Main Generator Temperatures, ICS Neutron Error

Malfunction, Steam Generator Tube Leak with Complications, Revision 0, 10/04/2010.

NRC Temporary Instruction (TI) 2515/177, Managing Gas Accumulation in Emergency Core

Cooling, Decay Heat Removal, and Containment Spray Systems (NRC Generic Letter (GL) 2008-01)

Licensing Bases Documents

ML081330239, Crystal River Unit 3 - Three Month Response to NRC Generic Letter 2008-01,

Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and

Containment Spray Systems, May 8, 2008

ML082890555, Crystal River Unit 3 - Nine Month Response to NRC Generic Letter 2008-01,

Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and

Containment Spray Systems, October 13, 2008

ML102860131, Crystal River Unit 3 - Nine Month Supplemental (Post-Outage) Response to

NRC Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay

Heat Removal, and Containment Spray Systems, October 8, 2010

ML100270031, Crystal River Unit 3 - Generic Letter 2008-01 Managing Gas Accumulation in

Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems, Response to

a Request for Additional Information, January 25, 2010

Miscellaneous

CAP-NGGC-0201-8-14, Quick Hit Self-Assessment Report - Assessment Number: QRPT

00397728, Rev. 14

EC 71569, High Point Vent Valves - Master (GL 2008-01 Outside the RB), Rev. 5

EC 72034, MUV-654, MUV-655, and MUV-657 High Point Vent Valves - Child (Master EC 71569), Rev. 1

Letter to R. Dulaney from LOCA Integrated Services (Westinghouse), Subject: PWROG Position

Paper on Non-condensable Gas Voids in ECCS Piping; Qualitative Engineering Judgment of

Potential Effects on Reactor Coolant System Transients Including Chapter 15 Events, Task 3 of

PA-SEE-450, Reference number: LTR-LIS-08-543, August 19, 2008

OP-103B, Plant Operating Curves, Rev. 40

Attachment

9

WO 01423288-01, GL2008-01; Perform Hanger Adjustment

WO 01423288-04, GL2008-01; Perform Hanger Adjustment

Drawings

FD-302-641, Decay Heat Removal, Rev. 81

FD-302-661, Make-up & Purification, Rev. 85

FD-302-711, Reactor Building Spray, Rev. 68

P-304-662, Make-up & Purification System Plan at EL. 95-0 Auxiliary Building, Rev. 20

PI-305-858, From MUV-69 to Make-up pump suctions 3A-3B-3C, Rev. 1

PI-305-811, GL 2008-01 Walkdown Schematic BS System

PI-305-810, GL 2008-01 Walkdown Schematic BS System

PI-305-815, GL 2008-01 Walkdown Schematic DH System A Train

Calculations

M09-0049, Evaluation of Gas Accumulation in CR3 LPI/DHR Suction Piping, Rev. 1

M09-0051, Evaluation of Gas Accumulation in CR3 DH and ECCS Discharge Piping, Rev. 1

M94-0053, Allowable MUT-1 Indicated Overpressure vs. Indicated Level, Rev. 7

NAI-1459-001, Comparison of GOTHIC Gas Transport Calculations with Test Data, Rev. 0

Action Requests Reviewed During Inspection

262601, SER 2-05 Revision 1 Gas Intrusion in Safety Systems

263132, Implementation Plan for GL 2008-01

284159, Track CR-3 Gas Accumulation Project Plan Actions Assignment Numbers 1 through 41

293769, Voiding Found in A BS Train of Discharge Side of BSP-1A

298140, Air Found in Abandoned Tee in MUP Discharge Header during UT

302656, OE27625 - RHR System Inoperability in Modes 3 and 4

312009, UT Examination of A DH Discharge Pipe Reveals Voiding

315347, UT Examination of A DH Discharge Pipe Reveals Minor Void

344364, Common Suction to Make-up Pumps had Minor Gas Pockets

346131, Existing Acceptable Gas Voids MUP Common Suction from MUV-60

358532, Gas/Void Found at MUV-37

358790, MUV-42 Upstream Elbow Just Over 50% Full Based on UT

365715, NSAL-09-8 Presence of Vapor in Emergency Core Cooling System

382171, Void Pocket Observed in DH Dropline during UT Inspection

417759, Fill and Vent Sequence for B DH Train

Procedures

EGR-NGGC-0005, Engineering Change, Rev. 31

EOP-6, Steam Generator Tube Rupture, Rev. 20

NDEP-0438, Ultrasonic Procedure for Determination of Liquid Level in Components

SP-630, MU/HPI Check Valves Full Flow Test, Rev 21

SP-340B, DHP-1A, BSP-1A and Valve Surveillance, Rev 63

SP-340E, DHP-1B, BSP-1B and Valve Surveillance, Rev 43

OP-402, Makeup and Purification System, Rev 159

OP-404, Decay Heat Removal System, Rev 155

SP-435, Valve Testing During Cold Shutdown, Rev 68

Attachment

10

Completed Testing

WO 01426356-01, DHV-41/5/6 GL2008-01; UT Inspection

WO 01627233-01, DHV-41, GL2008-01; UT Inspection

WO 01627234-01, DHV-6, GL2008-01; UT Inspection

WO 01663114-01, DHV-5, GL2008-01; UT Inspection

WO 01679519-01, DHV-41, GL2008-01; UT Inspection

WO 01679520-01, DHV-6, GL2008-01; UT Inspection

WO 01713641-01, DHV-5, GL2008-01; UT Inspection

WO 01725959-01, DHV-41, GL2008-01; UT Inspection

WO 01725960-01, DHV-6, GL2008-01; UT Inspection

WO 01757745-01, DHV-5, GL2008-01; UT Inspection

WO 01767042-01, DHV-6, GL2008-01; UT Inspection

NCRs Generated As a Result of Inspection

429660, During NRC Inspection for GL 08-01 Ziplevel Uncertainty

429889, NRC GL 08-01 Inspection Identified WO Discrepancies

429950, GL 08-01 NRC Inspection Identified DH ISO C/D Not Evaluated

430217, Suspect Information Found on VT-3 Document for MUH-518

430255, NRC GL 08-01 Inspection Identifies Need for LER Review

430264, NRC GL 08-01 Inspection Identified QH-SA Deficiency

Attachment