|
---|
Category:Letter
MONTHYEARIR 05000302/20240012024-09-23023 September 2024 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3, NRC Inspection Report No. 05000302/2024001 ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24226B2392024-08-27027 August 2024 Application for License Amendment Request to Add License Condition to Include License Termination Plan Requirements – Acknowledgement of Withdrawal ML24179A0702024-07-26026 July 2024 SHPO S106 Completion Crystal River Unit 3 ML24205A2202024-07-24024 July 2024 Tribal S106 Completion Crystal River Unit 3_Miccosukee Tribe of Florida ML24205A2192024-07-24024 July 2024 Tribal S106 Completion Crystal River Unit 3: Muscogee Nation ML24205A2182024-07-24024 July 2024 Tribal S106 Completion Crystal River Unit 3: Seminole Nation of Oklahoma ML24179A0912024-07-24024 July 2024 Tribal S106 Completion Crystal River Unit 3: Seminole Tribe of Florida ML24190A1912024-07-0808 July 2024 Fws Concurrence for Crystal River Unit 3 ML24172A2552024-06-20020 June 2024 Fws to NRC Species List: Florida Ecological Services Field Office 06/20/2024 ML24170A9242024-06-18018 June 2024 024-0023697 Crystal River License Termination Plan Unit 3 ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities ML24114A2262024-04-24024 April 2024 Amended Special Package Authorization for the Cr3 Middle Package (Crystal River 3 Middle Package - Docket No. 71-9393) IR 05000302/20230022024-04-17017 April 2024 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report No. 05000302/2023002 ML24054A0812024-04-0202 April 2024 Tribal S106 Initiation Crystal River Unit 3-Osceola, Marcellus ML24054A0612024-04-0202 April 2024 Request to Initiate Section 106 Consultation Regarding the License Termination Plan for Crystal River Unit 3 in Citrus County, Florida ML24079A2492024-04-0202 April 2024 Tribal S106 Initiation Crystal River Unit 3-Johnson, Lewis Johnson ML24079A2482024-04-0202 April 2024 Tribal S106 Initiation Crystal River Unit 3-Hill, David Hill ML24079A2472024-04-0202 April 2024 Tribal S106 Initiation Crystal River Unit 3-Cypress, Talbert ML24054A0582024-04-0202 April 2024 Achp S106 Initiation Crystal River Unit 3 - Letter 1 ML24089A0362024-03-29029 March 2024 Response to Audit Plan in Support of Accelerated Decommissioning Partners and Request to Add License Condition to Include License Termination Plan Requirements. W/Enclosures 1 to 5 ML24073A1922024-03-11011 March 2024 Fws to NRC, List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected by Your Proposed Project ML24054A6452024-02-29029 February 2024 Letter - Reply to Request for RAI Extension Related to the Crystal River License Termination Plan ML24030A7482024-02-12012 February 2024 Audit Report Cover Letter and Report - Crystal River Unit 3 Nuclear Generating Plant LTP ML23342A0942024-01-0909 January 2024 – Independent Spent Fuel Storage Installation Security Inspection Plan ML23354A0632023-12-22022 December 2023 Cover Letter - Crystal River License Termination Plan Request for Additional Information ML23345A1882023-12-0606 December 2023 Fws to NRC Crystal River Species List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected by Your Proposed Project ML23313A1322023-11-15015 November 2023 Request for Additional Information for the Environmental Assessment of the License Termination Plan for Crystal River Unit 3 Nuclear Generating Plant ML23310A0712023-11-0707 November 2023 Audit Plan Cover Letter - Crystal River Unit 3 Nuclear Generating Plant LTP ML23187A1112023-07-25025 July 2023 Acceptance of Requested Licensing Action License Request to Add License Condition to Include License Termination Plan Requirements ML23107A2722023-06-13013 June 2023 Letter Transmitting NRC Survey Results for East Settling Pond ML23160A2962023-06-0909 June 2023 Response to Crystal River, Unit 3 – Supplemental Information Needed for Acceptance on the Application for a License Amendment Regarding Approval of the License Termination Plan ML23107A2732023-06-0707 June 2023 Orise Independent Survey Report Dcn 5366-SR-01-0 ML23103A1902023-04-19019 April 2023 Request for Supplemental Information Cover Letter IR 05000302/20220032023-03-22022 March 2023 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River, Unit 3 - NRC Inspection Report No. 05000302/2022003 ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities ML22265A0192022-09-26026 September 2022 Nuclear Generating Plant - U.S. Nuclear Regulatory Commissions Analysis of ADP CR3, LLCs Decommissioning Funding Status Report (License No. DPR-72, Docket Nos. 50-302 and 72-1035) IR 05000302/20220022022-08-0909 August 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report 05000302/2022002 IR 05000302/20220012022-05-0303 May 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report 05000302/2022001 ML22116A1752022-04-27027 April 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3- Independent Spent Fuel Storage Installation Security Inspection Report 07201035/2022401 ML22105A3992022-04-18018 April 2022 Nuclear Generating Plant - Change in NRC Project Manager ML22011A1362022-01-31031 January 2022 Independent Spent Fuel Storage Installation Security Inspection Plan ML22024A2142022-01-24024 January 2022 Nuclear Generating Plant - NMFS NRC Letter - Crystal River Energy Complex Biological Opinion Status (License No. DPR-72, Docket Nos. 50-302 and 72-1035) IR 05000302/20210042022-01-24024 January 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report No. 05000302/2021004 ML21351A0052021-12-20020 December 2021 NRC Analysis of ADP CR3, LLC Decommissioning Funding Status Report for the Crystal River Unit 3 Nuclear Generating Plant (License No. DPR-72, Docket Nos. 50-302 and 72-1035) ML21322A2702021-11-24024 November 2021 Nuclear Generating Plant - Issuance of Amendment No. 260 Approving the Independent Spent Fuel Storage Installation Only Security Plan, Rev 3 IR 05000302/20210032021-11-0909 November 2021 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report Nos. 05000302/2021003 and 07201035/2021001 ML21288A4292021-10-18018 October 2021 Letter - Crystal River Unit 3 Nuclear Generating Plant - Correction to Safety Evaluation Related to the Issuance of Amendment No. 259 Approving the Independent Spent Fuel Storage Installation Only Emergency Plan ML21238A0952021-10-13013 October 2021 Issuance of Amendment No. 259 Approving the ISFSI-Only Emergency Plan, Revision Draft a IR 05000302/20210012021-08-12012 August 2021 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report Nos. 05000302/2021001 and 05000302/2021002 2024-09-23
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION rch 5, 2012
SUBJECT:
CRYSTAL RIVER UNIT 3 NUCLEAR GENERATING PLANT - NRC EMERGENCY PREPAREDNESS ANNUAL INSPECTION REPORT NO 05000302/2011502
Dear Mr. Franke:
On December 31, 2011, the NRC staff completed its annual inspection of the Emergency Preparedness Program at the Crystal River Nuclear Plant. This inspection began on January 1, 2011. Issuance of this letter closes Inspection Report Number 2011502. Inspection activities charged to this report includes conducting midcycle/end of cycle assessment activities, responding to technical questions from resident inspectors or licensee personnel, and, in some cases, performing traditional enforcement activities. Any observations and findings in these areas were provided to you via separate correspondence.
In accordance with 10 CFR 2.390 of the NRC Rules of Practice, a copy of this letter, and your response, if any, will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Brian Bonser, Chief Plant Support Branch 1 Division of Reactor Safety Docket No.: 50-302 License No.: DPR-72 cc w/encl.: (See page 2)
ML12069A399 X SUNSI REVIEW COMPLETE OFFICE RII: DRS RII: DRS RII: DRP SIGNATURE RA/BB For MS RA/BB RA/DR NAME M. SPECK B. BONSER D. RICH DATE 03/05/2012 03/05/2012 03/05/2012 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO
PROGRESS ENERGY 2 cc w/encl:
Kelvin Henderson, General Manager Daniel R. Westcott, Supervisor Nuclear Fleet Operations Licensing & Regulatory Programs Progress Energy Crystal River Nuclear Plant (NA1B)
Electronic Mail Distribution Electronic Mail Distribution Robert J. Duncan II, Vice President Joseph W. Donahue, Vice President Nuclear Operations Nuclear Oversight Progress Energy Progress Energy Electronic Mail Distribution Electronic Mail Distribution Brian C. McCabe Jack E. Huegel Manager, Nuclear Oversight Manager, Nuclear Oversight Shearon Harris Nuclear Power Plant Crystal River Nuclear Plant Progress Energy Electronic Mail Distribution Electronic Mail Distribution David T. Conley, Senior Counsel Terry Hobbs Legal Department Plant General Manager Progress Energy Crystal River Nuclear Plant (NA2C) Electronic Mail Distribution 15760 W. Power Line Street Crystal River, FL 34428-6708 Mark Rigsby Manager, Support Services - Nuclear Stephen J. Cahill Crystal River Nuclear Plant (NA2C)
Director - Engineering Nuclear Electronic Mail Distribution Crystal River Nuclear Plant (NA2C)
Electronic Mail Distribution Senior Resident Inspector U.S. Nuclear Regulatory Commission R. Alexander Glenn, General Counsel Crystal River Nuclear Generating Plant Progress Energy U.S. NRC Electronic Mail Distribution 6745 N Tallahassee Rd Crystal River, FL 34428 Jeffrey R. Swartz Director Site Operations Attorney General Crystal River Nuclear Plant Department of Legal Affairs Electronic Mail Distribution The Capitol PL-01 Tallahassee, FL 32399-1050 Donna B. Alexander Manager, Nuclear Regulatory Affairs Bryan Koon, Director Progress Energy Florida Division of Emergency Management Electronic Mail Distribution Electronic Mail Distribution Thomas Sapporito Chairman Consulting Associate Board of County Commissioners Post Office Box 8413 Citrus County Jupiter, FL 33468 110 N. Apopka Avenue Inverness, FL 36250 William A. Passetti, Chief Florida Bureau of Radiation Control Department of Health Electronic Mail Distribution