IR 05000498/1988064

From kanterella
Jump to navigation Jump to search
Insp Repts 50-498/88-64 & 50-499/88-64 on 880921-24.No Violations or Deviations Noted.Major Areas Inspected:Unit 2 Structural Integrity Test & Containment Integrated Leak Rate Test
ML20204F581
Person / Time
Site: South Texas  STP Nuclear Operating Company icon.png
Issue date: 10/12/1988
From: Ray Azua, Seidle W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20204F546 List:
References
50-498-88-64, 50-499-88-64, NUDOCS 8810210600
Download: ML20204F581 (4)


Text

_ _ _ _ _ _ _ _ _ _ _ -

.

. APPENDIX U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

NRC Inspection Report: 50-498/88-64 Operating License: NPF-76 50-499/88-64 Construction Permit: CPPR-129 Docket: 50-498 50-499 Licensee: Houston Lighting & Power Company (HL&P) -

P.O. Box 1700 Houston, Texas 77001 Facility Name: South Texas Project (STP), Unit 1 and 2 Inspection At: STP, Matagorda County, Texas Inspection Conducted: September 21-24, 1988 Inspector: _

- /0 2_/r/

'

T Azua, IF,eactor/Insgctor, Test Programs A . Date Section, Division of Reactor Safety Approved: , _ /o z!#

6 W. C. Seidlef/ Chief.d(st Programs Section Date / {

Division of Reactor Safety '

i inspection Summary Inspection Conducted September 21-74, 1988 (Report 50-498/88-64)

Areas Inspected: No inspection of Unit I was conducte !

Results: Not applicabl Inspection Conducted Sectember 21-24, 1988 (Report 50-499/88-64) 1 Areas Inspected: Routine, announced inspection of the South Texas Project, Unit 2, 5tructural Integrity Test (SIT) and the Containment Integrated Leak Rate Test (CILRT).

Results: Within the areas inspected, no violations or deviations were identifie i SS10210600 891013 PDR ADOCL OM OO498 O PDC I

_ _ _ _ _ - _ _ - - _

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

_,

.

. .

,. .

DETAILS

, Persons Contacted HLLP V. Albert Systems Division Manager, Plant Engineering Department J. Mertink. Lead Engineer, Containment Integrated Leak Rate Test (CILRT)

and Structural Integrity Test (SIT) Direc;or R. Worley, Systems Engineer, Plant Engineering Department M. Polishak Lead Engineer, Project Compliance Group S. Phillips. Engineer, Project Compliance Group J. Niess, Systems Engineer, Plant Engineering Department, CILRT Coordinator A. Morrison, Operations, Quality control J. Snyder, Startup Engineer D. Ruthven, Operations Engineer Bechtel C. Sczesny, Quality Control D. Shank, Contractor L. Yourn, SIT Coordinator WJS R. Krause, SIT Consultant NRC J. Tapia, Senior Resident Inspector D. Garrison, Resident Inspector $1T (63050) and CILRT Procedure Review (70307)

The NRC inspector reviewed Procedure No. 2C0195S1013, Revision 03,

"Specification for the Performance of Structural Integrity 'iest on Reactor Containment Building, Units 1 and 2." and Procedure No. 2-RC P-03, Revision 0, "Containment Integrated leak Rate Test (CILRT)."

The NRC inspector reviewed the procedures to verify that the licensee had incorporated the associated regulatory requirements and comitrent The two procedures were also reviewed to check that they both coincided and allowed for the fluid performance of the test. In addition, both proceduros were verified to have the proper approvals a 'icated by appropriate signature The calibration documentation for the test equiptrent (elastic wire strain reter, RTDs, dewpoint hygrometers, voltmeters, and pressure gauges) was

_ __ _ _ _ _ _ _ - _ _ - - _ .

r

'

. s ,, .

f

)

{

!

inspected by the NRC inspector. No errors were detected and all l instruments were found to be in calibration for the period encompassing i these tests. The NRC inspector reviewed the certification and training i records of technicians involved in calibrating the test equipment. In  !

addition some randomly selected systems, which were addressed in Procedure l No. 2-RC-P-03, were reviewed against the licensee's Piping and ,

Instrumentation Diagrams (P& ids). This was done to detemine that all .

the appropriate valves in the system were addressed in valvo line up t sheet 9.8.1, and that the valve test positions, listed in the same -

sheet, set their associated systems in correct alignment for the  !

performance of the CILRT. A review was also perfonned by the NRC j inspector to detemine that all appropriate systems were addressed in valve line up sheet 9. !

Finally, both procedures were reviewed by the NRC inspector for technical adequac It was noted that the offic... results for the CILRT will be ,

obtained using the total time metho l For the SIT, the NRC inspector verified that the test equipment inside the [

containment building was installed and that a test station was established i outside the containment building to monitor the test. In addition, the  !

NRC inspector witnessed one of the test station operators perfoming a i channel check on some of the elastic wire strain meters. The NRC l inspector also inspected the designated areas of the containment building f which were mapped to monitor concrete cracks. Finally, during the [

co.tainment building pressurization, the NRC inspector witnessed the test k station operators taking data when the reactor building had reached a f pressure of 10 psig (data taking required by Procedure No. 200195S1013, Step 4.2.4).

i Due to time constraints, the NRC inspector was unable to monitor the l complete tes j No violations or deviations were identified in the review of this program are { C!LRT Surveillance (70313) {

l The NRC inspector perfomed several tours of the Unit 2 reactor buildin [

This was done in an effort to monitor the installation of the test  ;

equipment, the insitu calibration of this equipments and the valve line up '

] process.

j

<

l While monitoring the line up process, it was noted that the valve line up f i

sheet in Procedure No. 2-RC-P-03, Revision 0, did not contain a sign off l

for independent verification, it was also noted that the tags that were

being used to identify the valves listed in the procedure were ' CAUTION" i

tags, which also did not have any sign offs for independent verification.

! The NRC inspector addressed this to the licensee. The licensee stated -

! that they were aware that the CILRT procedure did not contain a means to [

l record the independent verification, but that they were in the process of  :

'

perfoming, not one, bmt two independent verifications, which were being I

.

I i I L___,~_,___, _i

. _ . . _ _ _ _ _ _ - _ _ _ _ - _ - _ . _ _ _ _ __

.

.

. . . , .

recorded separatel> hun che procedure, and filed in a cabinet located behind the Unit 2 control room. The NRC inspector reviewed these files and found them to be adequate. In addition, the NRC inspector witnessed a systems engineer performing one of the independent verifications of the containment building CILRT valve lineup, and also found it to be adequat The licensee assured the NRC inspector that the CILRT procedure would be improved, once the plant goes into operation. This is due to the fact that procedures that become part of plant operations must meet the administrative procedure on independent verification, which contains specific guidelines on how it is perfortred and recorde The NRC inspector reviewed a sample of fifty valves that had been positioned and tagged for this test. No errors or discrepancies were note The NRC inspector accompanied the licensee on the final walkdown of the reactor building on September 23, 1988. This was followed by the closing of the personnel airlock after it was verified that all personnel had been evacuated from the reactor buildin Due to time constraints, the NRC inspector was unable to monitor the corrplete test. The remainder of the test will be monitored by the resident inspector, and the results of that inspection will be addressed in a separate repor No violations or deviations were identified in the review of this program are . Exit Interview An exit interview was held on September 24, 1988. At this exit interview, the NRC inspector sumarized the scope and findings of the inspectio The licensee did not identify as proprietary any of the infonnation provided to, or reviewed by, the NRC inspector.