IR 05000498/1989001
| ML20236C476 | |
| Person / Time | |
|---|---|
| Site: | South Texas |
| Issue date: | 03/09/1989 |
| From: | Andrea Johnson, Stetka T NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV) |
| To: | |
| Shared Package | |
| ML20236C472 | List: |
| References | |
| 50-498-89-01, 50-498-89-1, 50-499-89-01, 50-499-89-1, NUDOCS 8903220173 | |
| Download: ML20236C476 (9) | |
Text
"
.
j
]
.
,
APPENDIX U.S. NUCLEAR REGULATORY COMMISSION L
REGION IV
>
i NRC Inspection Report:
50-498/89-01 Operating Licenses:
.,
50-499/89-01 NPF-78 j
.
Dockets:
50-498
.
l
_50-499 l
' Licensee: Houston Lighting & Power Company (HL&P)
Ll P.O. Box 1700
'
Houston, Texas 77001
Facility Name: South Texas Project, Units I and 2'(STP)
l i
Inspection At:
STP, Matagorda County, Texas Inspection Conducted: January 9-13 and 23-27, 1989 Sk/M Inspector:
/\\
d
)
A y
A. R. Jbhnson, Reactor IMspector, Plant Systems Date Section Division of Reactor Safety'
,
i
'
$ [9!'[rf Approved:
Mffik T. Stetta, Chief, Plant Systems Section Date
<
Division of Reactor Safety
,
!
Inspection Summary
Inspection Conducted January 9-13 and 23-27, 1989 (Report 50-498/89-01)
~ Areas Inspected: Routine, unannounced inspection of the licensee's Technical 4 Specification (TS) required calibration program, and the preventive maintenance (PM) program related to the calibration of plant instrumentation
,.
'
for components not addressed in the TS.
Results: Within the areas inspected, no violations or deviations were identified.
'
The licensee's plant surveillance (PS) calibration program for the control and evaluation of installed instrumentation and control (IAC) devices, specified by
'
the TS is effectively being implemented and no weaknesses were noted.
h $po h 0500049e 890313
,
Q
"
.
\\
,
_
_ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ -
'
.
-2-An apparent weakness was identified, however, in the licensee's calibration program for I&C devices not addressed in the TS. The apparent weakness involves a lack of procedural controls which resulted in a large number of installed I&C device calibration deferrals. This issue has been identified as an.aresolved item.
Inspection Conducted January 9-13 and 23-27, 1989 (Report 50-499/89-01)
Areas Inspected:
No inspection of Unit 2 was conducted.
Results: Not applicable.
....
_____ _ _ _ _
_ _ _ _ _ _ _ _ -.
__
._
.
.
.'
.
-
.
-3-
I DETAILS 1.
Persons Contacted l
HL&P_
I
- W..H. Kinsey, Plant Manager
.
- M. R. Wisenburg, Plant Superintendent ~, Unit 1-
- S. L..Rosen, General Manager,. Operations Support
.
- S. M. Dew, Manager, Operations Support
!
- G. E. Vaughn, V.P. Nuclear Operations l
- M. A. McBurnett, Licensing Manager
- P. L. Walker, Senior Licensing Engineer l
- K. L. Trippel, Lead Engineer i
- R. Fast, Instrumentation & Control (ISC) Maintenance
- S. M. Head, Supervisor, Licensing Engineering
- W. J. Jump, Maintenance Manager
- M. H. Carney, I&C Supervisor
- J. L. Lewis, I&C Technical Supervisor
.
.
- S. E. Hill, Maintenance Support Administrative Supervisor
- R. A. Ferguson, Licensing Engineer.
-
J. Geiger, General Manager, Nuclear Assurance
.l R. Balcom Quality Assurance, Operations
'
NRC
- J. E. Bess, Senior Resident Inspector, Unit'1'
- R. J. Evans, Resident Inspector, Unit 1 -
,
- Attended exit interview on January,13, 1989.
- Attended exit interview on January ~27,:1989.
The NRC inspector contacted other licensee personnel during the inspection, i
2.
Calibration of Plant Instrumentation (56700)
This inspection was to accertain whether the licensee had developed and
.
implemented a program for the calibration and testing of plant installed I
I&C devices. This includes the I&C devices specified in the Technical'
Specification (TS) and-I&C devices that are used for the operation and testing.
of equipment but not specifically addressed in the TS as requ' iring
!
calibration.
l
.
l J
..
,.
.
,
-4-
!
2.1 Calibrations Specified by TS Calibrations required by TS are controlled as part of the STP Plant Surveillance (PS) Program. The inspection determined.that procedures for calibration of plant. installed I&C devices, specified by.TS, are being implemented in accordance with the calibration program administrative-i
'
controls, as prescribed by the STP FS/.R. Sections 7.0 and 17.2, and related commitments to Regulatory Guides and Standards. The TS surveillance program data base is well established and re flects.the status.of. all planned 'in-plant
'
surveillance tests and inspections. This schedule.is outlined in STP Operations QA Plan - Instrumentation and Calibration Control (QAP),
.
l-Section 12, phragraph 6.1, and STP Plant Procedures Manual.(PPM)
l OPG P03-ZM-0016, Revision 1.
Technical Specification surveillance and
'
calibration requirements'are further controlled by Procedure OPG P03-ZE-0004, Revision 2, and together with the QAP include requirements-that verify
..
completion of, surveillance tests.and inspections required by the TS.
)
The NRC inspector verified that installed I&C device channel calibrations (CCs), analog channel operational tests (ACOTs), trip l
actuating device operational tests (TAD 0Ts), actuation logic tests (ALTs),
master / slave relay tests (MRTs/SRTs), and response time tests (RTTs),
specified by the TS were performed.at the required frequencies. The NRC inspector used the TS Surveillance Program Data Base for STP-1 dated January 11, 1989.
.
.
.
l The NRC inspector examined completed test and calibration procedures (documentation packages) for surveillance performed during the last 18 months. This review verifiedi (1) test documentation was complete; (2) approved procedures were utilized; (3) acceptance criteria were met; (4) performance was in accordance with the procedures; and (5) completed procedures contained "as found" conditions.
The specific documentation packages examined by the NRC' inspector are listed below:
Engineered Safety Features Actuation System (ESFAS) Instrumentation Surveillance Requirements
'
Procedure No.
Revision No.
. Title 1 PSP 02-SP-0004-1
ESF Manual Initiation, TADOT 1 PSP 03-SP-0005R
SSPS Train Logic, Train R ALT IPSP03-SP-0007A-1
SSPS Train A, MRT IPSP03-SP-0008A-1
SSPS Train A, SRT 1 PSP 05-RC-0455-1
Pressurizer Pressure Set 1. CC 1 PSP 02-RC-0455-1
Pressurizer Pressure Set 1, ACOT
_
,
_ _ _ _ _ _ _ _ _ _
-
.
.
-5-IPSP05-MS-0514-1
Steam Pressure Loop 1 Set 1, CC IPSP02-MS-0544-1
Steam Pressure Loop 4 Set 1, ACOT IPSP02-MS-0524-1
Steam Pressure Loop 2 Set 1, ACOT 1 PSP 02-HC-0936-1
Containment Pressure Set 2, ACOT IPSP05-HC-0935-1
-Containment Pressure Set 3, CC 1-SP-P-03
Solid State Protection System, RTT, Credit Package (for 1 PSP 13-HC-0934, 0935, & 0936)
1-SP-P-03
Solid State Protection System, RTT, Credit Package (for IPSP13-RC-0465, 0466, 0467,
& 0468)
Reactor Trip System (RTS) Instrumentation Surveillance Requirements Procedure No.
Revision No.
Title 1 PSP 02-RC-0420-1
Delta T and T Average Loop 2 Set 2, ACOT IPSP05-RC-0410-1
Delta T and T Average Loop 1 Set 1, CC 1 PSP 02-RC-0465 1
Pressurizer Level Set 1, ACOT IPSP05-RC-0465-1
Pressurizer Level Set 1, CC IPSP02-RC-0481-1
RCS Flow Loop 1, Set 2, ACOT 1 PSP 05-RC-0418-1
RCS Flow Loop 1, Set 2, CC IPSP03-SP-0006R-1
Train R Reactor Trip Breaker, TAD 0T The NRC inspector made the following observations with regards to the licensee's PS program:
2.1.1 RTT Procedures Data packages were prepared by HL&P, using preoperational test data prior to station startup of STP-1, in lieu of RTT requirements by TS.
Many RTT procedures for frequencies of 18-months and greater, have l
not yet been issued.
At the tine of this inspection, 207 out of I
y,.y,,,
,......,. - - - - - -.
,
.,.,........ -
._
.
..
.
.
--... - - - - -
,
.
"
.
~
.
' 6-
-
approximately 1000 RTT procedures still remain in draft form.
These procedures will be issued at STP-1 prior to the first TS required RTT period.
2.1.2 CC Procedures Preoperational test data packages for STP-1 were used in lieu of. CC procedures to meet initial CC surveillance requirements. The CC surveillance were short-period calibrations which have since been
!
accomplished using newly issued CC procedures. The NRC inspector estimated that 10 percent of STP-1 CC surveillance were performed, taking credit for test data packages.
2.1.3 ACOT, TADOT, ALT, MRT, and SRT Procedures All initial and' subsequent ACOTs, TAD 0Ts, ALTs, MRTs, and SRTs-for STP-1 are being. accomplished using issued surveillance procedures.
No' violations or deviations were identified.
,
2.2 Calibrations Not Specified by TS The programmatic controls for the calibration of installed I&C devices used at STP for safety-related/ quality-related applications, associated:
but not addressed in the TS, are part of the STP preventive maintenance (PM)
<
,
l Program. These instruments are used during surveillance testing and -
operation of safety-related equipment and are referred to in the STP plant routine operating procedures.
The schedule of calibration and verification for these insta11ed'I&C devices is outlined in the STP QAP, Section 12 and
,
l Procedure No. OPGP03-ZM-0002, Revision 16. "PM Program."
HL&P has accomplished an engineering review of some 7000 safety-related/
quality-related instrument devices to determine their requirements with regards to PM calibration activities.
HL&P has established an approved and active PM list of approximately 1500 instrument devices based on the following criteria:
HL&P reviewed the Architect Engineer's (Bechtel's) instrument index
l and included safety-related instrument classification groups on the approved PM list.
HL&P reviewed all STP routine operating and surveillance procedures and included all instruments contained in these procedures on the
'
approved PM list.
HL&P accomplished an engineering review of the STP main control room
and included all these instruments on the approved PM list.
,
,
_
_
-
.
._
-
.
.. -
.,
H
.
'
"
,
.
1:
.I
,7,.
l i
The.NRC inspector reviewed the licensee's implementation of Procedure OPGP03-ZM-0002 to ascertain whether calibration of'the, selected-
~
instrument devices in the.PM program were~being accomplished effectively.
d-The NRC inspector reviewed the licensee's PM Schedule. Data Base,L ated
,
January 25, 1989.' The data base.is used by HL&P to prioritize:the scope and frequency of the required PM calibration activities. - The NRC -
~
.,
inspector. sampled PM data packages listed on the data base-for::
.
'
(1) backlog of past due calibrations; (2) reasons' for deferrals, inactivations,.and cancellations; (3) availability of approved procedures.
for calibration of instrument devices; and.(4) examination of technical
'
content. The sample PM data packages were limited to instrument device calibrations performed by the maintenance. I&C division. - The-followingL is a list of PM procedures reviewed:
PM No.
Description Fre-Due
- Da'te quency Fate TerTormed (Weeks)
IC-1-AS86011921=
Calibration, Aux Steam
05/29/89 10/14/88
'
'
To LWPS, HELB A Protection (Tag #A1ASPDSH8838A)
IC-1-CH-86009893 Calibration, ECHW Train A, 24'
05/01/87
Chiller VCH004, Compressor Discharge (Tag # NICHPI9504B)
l
!
IC-1-CH-86009895 Calibration, ECHW Train A,
01/27/89 07/01/88 I
i l
Chiller VCH004, Compressor
1 Suction Pressure l
(Tag # NICHPI9504A)
f IC-1-CH-86009896 Calibration, ECHW Train A,
.05/01/87.
Chiller VCH004, Compressor
.
Lube Oil Pressure (Tag # NICHPI9504)
IC-1-CH-86009900 Calibration ECHW Train C, 24:
02/07/89 07/12/88 Chiller VCH006, Compressor Lube Oil Pressure (Tag # NICHPI9516)
fC-1-CH-86009902 Calibration, ECHW Train C,
02/07/89 07/12/88 ~
'
Chiller VCH006, Compressor
.
Suction (Tag # NICHPI9516A)
l-IC-1-CH-86009903 Calibration. ECHW Train C,~.24 02/07/89 07/12/88 Chiller VCH006,' Compressor Discharge Pressure (Tag #NICHPI9516B)
.
.
_ _ _ _ - - _ _ -.
,
..
.
.
,
,
k
..
-
l
.-
-
-8-
'IC-1-CH-86009909-Calibration, ECHW Train B,
12/01/88 05/05/88 Chiller VCH005, Compressor Lube Oil Pressure (Tag # NICHPI95108)
,
.IC-1-CH-86009911 Calibration, ECHW Train B,
-12/01/88 05/05/88 Chiller VCH005, Compressor Suction Pressure (Tag # NICHPI9510A)-
L TC-1-CH-86009913 Calibration ECHW Train B,
12/01/88 05/05/88-Chiller VCH005, Compressor.
l Discharge Pressure (Tag # NICHP19510)
1C-1-CH-87011946-Calibration, Mild
02/13/89- -*
Environment, ECHW Train A, Chiller.VCH004, Purge High-Pressure (Tag # AICHPSH9533)
IC-1-CH-87011947 Calibration, Mild
'26 06/09/89 10/25/88 Environment, ECHW Train B, l
Chiller VCH005, Purge High l
Pressure (Teg # B1CHPSH9534)
'
IC-1-CH-87014078 Calibration, ECHW Train A,
07/04/88
Chiller VCH004, 011 Heater-Thermostat (Tag #A1CHTSH9435)-
IC-1-CH-87014080-Calibration, ECHW Train C,.45 12/22/88
l l
Chiller'VCH006, 011 Heater Temperature (Tag # ICHTSH9437)
,
l IC-1-DG-86003021 Calibration, Diesel
03/27/88
i
Generator #11, Engine Speed (Tag # AIDGSI5476B)
-IC-1-D0-86007536 Calibration, Diesel
03/27/88.
- 1 Generator #11, Fuel Oil Drain Tank (Tag # AIDOLSHL5470)
IC-1-EW-86002645 Calibration, Diesel
06/24/88- *
Generator Heat Exchanger Outlet Temperature, Train A
.
'(Tag # A1EWFT6855)
IC-1-EW-86003348-
' Calibration, CCW Pump
'09/23/88
Cooler Outlet, Train A (Tag # A1EWFT6856)
!
L_z_____..___________ _.
t q
'
,
,
, 'c,,,
.
..
'
.g.
,
,
'
- -
TC-1-MS-860011155 Calibration, Steam:
.
- 10/04/89
)
Generator-ID, PORV High
. 1 Hydraulic Pressure (Tag'f 01MSPSH7441)
IC-1-MS-86011156 Calibration. Steam-78-10/04/89
Generator ID P Low
,
l Hydraulic Pressure
,
(Tag # D1MSPSL7441).
l ODenotes not' performed yet.
- The NRC inspector determined that' the PM' data' packages were complete;
.
i acceptance criteria had been met; the proper approved test procedures.had been
l used; and technical contents were-acceptable.- However, the.NRC inspector
L noted that many calibrations.had exceeded their due dates and still required:
'
performance. The backlog _of past.due calibrations appeared to.be-a' result ~
of inadequate procedural controls atiSTP resulting,in a(failure to meet.
required calibration frequencies as outlined by Procedure OPGP03-ZM-0002.
The NRC inspector discussed the backlog of past 'due calibrations; problem with, the licensee and determined that the-licensee had identified this issue and
{
was in the process of taking appropriate and timely corrective action. This
.
i issue is considered to be an unresolved: item ~pending. correction by the licensee and subsequent review by the NRC..
~
Unresolved Item (498/8901-.01):. Complete corrective. actions.to pr' event overdue
~
calibrations of instrumentation not specified by the TS.
~
3.
Exit Interview i
The inspection scope and findings were. summarized on January 27, 1989, with the licensee personnel indicated in paragraph 1 above. The licensee did not identify as proprietary any of the materials:provided to or reviewed by the NRC inspectors during the-inspection.
i l
l
,
l
-__-__-_.~.__-.-_3.
_ -
._
_.. _ _ _ _ _
-
____..-______.:_____m-____.a_
_ _ - _ _ _ _ _.
-
-