IE Insp Rept 50-416/81-10 on 810316-0417.No Noncompliance Noted.Major Areas Inspected:Walkdown of RHR Sys,Qa Manual Review Control & Auxiliary Bldg Tour & Test Procedures Review
ML20004D269
Person / Time
Site: Grand Gulf Entergy icon.png
Issue date: 04/27/1981
From: Cantrell F, Wagner A
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20004D265 List:
References
50-416-81-10, NUDOCS 8106090092
Download: ML20004D269 (5)


Text

.

.

_

_ _ _ _ _ _ _

.

" /

i UNITED STATES

~ ;.

NUCLEAR REGULATORY COMMISSION o

$

E REGION IP a#

e 101 MARIETTA ST., N.'.d., SUITE 3100 b

g*

ATLANTA, G EOHGIA 30303

.

o

.....

Report No. 50-416/81-;:'

Licensee: Mississippi Power and Light Company

'

Jackson, MS Rcilit3

-

Ger.f Gulf Docket No. 50-416

License No. CPPR-118 Inspector:

1 A.'G. Wagner

/'

(

Dste Signed Approved by:

//!22 F. 5. Cantrell, Sect'iopief, RRPI Division D6te Signed SUMMARY Inspection on March 16, thru April 14, 1981 Areas Inspected This routine announced inspection involved 97 inspector-hours on site in the areas of test procedures review, system walkdown, quality assurance manual review and plant tour.

Results Of the four areas inspected, no violations or deviations were identified.

310609O @

.

..

.

-. -

"

j

.

r

.

DETAILS 1.

Persons Contacted Licensee Employees

  • G. B. Rogers, Site Manager
  • T. H. Cloninger, Proje i Engineering Manager
  • C, R. Hutchinson, Startup Manager
  • S. E. Tanner, Quality Assurance Engineer L. C. Eichenberger, Test Supervisor J. C. Roberts, Startup Supervisor M. H. Madison, Test Supervisor
  • At;:nded exit interview 2.

Exit Interview The inspection scope and findings were summarized on April 14, 1981 with those persons indicated in Paragraph 1 above. The licensee had no comments regarding the inspection findings.

3.

Licensee Action on Previous Inspection Findings Not inspected.

4.

Unresolved Items Unresolved items are matters about which more information is required to determine whether they are acceptable or may involve noncompliance or deviations.

New unresolved items identified during this inspection are

,

discussed in paragraph 8.

I 5.

Test Procedure Review The following test procedures were reviewed for conformance with Regulatory Guide 1.68, FSAR Chapter 6.3, 7.4, 9.3, and 14, Question and Responses 211.194, 423.35, 423.12, 423.20, 423.30, Grand Gulf Startup Manual chapter 5000, 7000 and MPL - Topical-1 Quality Assurance Manual.

a.

1E21PT01 Low Press ~ure Core Spray, approved 3-5-81 (second review the first review was conducted using a draft copy of the procedure.)

1.

Open Item 416/81-10-01 Paragraph 7.5.2.1 does not provide detailed instructions for starting jockey pump or refer to the system operating instruction

as required by FSAR chapter 14 paragraph 14.2.9 and MPL-Topical-1 policy 11 paragraph 11.5.7.3.

.

.

._.

_

_. _ _ _. _

._

_

"

,

,e

-

2.

Open Item 416/81-10-02 The action performed in paragraph 7.7.2 does rat provide a means i

for verification of accomplishment as required by Startup Manual chapter 7000 paragraph 4.2.5.13.

3.

Open Item 416/81-10-03 The calculation performed for pump head Vs system flow' is not verified to be within design valves in the acceptance criteria section as required by FSAR paragraph 14.2.12.1. 7(a)(1).

b.

1E22PT01 High Pressure Core Spray, approved 3-24-81

!

1.

Open Item 416/81-10-04 The value for the acceptance criteria in paragraph 10.10 does not agree with the value for HPCS rated flow in FSAR table 6.3-8.

2.

Open Item 416/81-10-05 The value for the acceptance criteria in paragraph 10.11 does not

agree with the value for HPCS beginning flow pressure in FSAR table 6.3-8.

3.

Open Item 416/81-10-06 The diesel generator voltage and speed are not measured and are not verified in the acceptance criteria section of the procedura as required by FSAR paragraph 14.2.12.1.8.

c.

1C41PT01 Standby Liquid Control a pproved 3-24-81 1.

Open Item 416/81-10-07 The prerequisites section does not contain the requirement to have boric acid and barox available as required by FSAR 14.2.12.1.3(b)(6).

2.

Open Item 416/81-10-08 The settings for the storage tank level switch IC41-LS-N600 does not agree with the settings in FSAR 7.4.1.2.5.3.

3.

Open Item 416/81-10-09 The procedure does not specify that the storage tank be filled with demineralized water as required by FSAR 14.2 12.1.3(c)(1).

_ _.- _

_

__

_

__

__ _

_

_

.

.

o

.

c'

_

4.

Open Item 416/81-10-10 Paragraph 7.5.11.13.2 requires a determination to be made that the pump dia.harge piping is not vibrating excessively. It does not provide the acceptance criteria by which this determination can be made. Neither does it provide a definition for " excessive vibration".

Explicit guidance is required by SUM chapter 7000

- paragraph 4.2.5.8.

5.

Open Item 416/81-10-11

.

The criteria for checking pump cavitation in paragraph 7.7.9.1.2 does not agree with the requirement for having low tank level as described in FSAR 14.2.12.1.3(c)(1) (a).

,

6.

Open Item 416/81-10-12 The following sub paratraphs of FSAR 14.2.12.1.3 are not checked or are not adequately c"ecked in the acceptance critieria section of the test procedure; d.1, d.3, d.7, and d.8.

7.

Open Item 416/81-10-13 The heat tracing and freeze protection systems are nat checked as required by FSAR Question and Response 423.12.

6.

System Walkdown The walkdown of the Residual Heat Removal Syster was observed for confor-mance with the requirements of Grand Gulf Startup Manual Chapter 7000 paragraph 4.1.4 and Bechtel Checkout and Turnover Organization Manual chapter 4 section 16.

No violations or deviations were identified.

7.

Quality Assurance Manual Review A review was conducted of the proposed revision to Mississippi Power and Light Company Quality Assurance Manual MPL-Topical-1.

The review was conducted for conformar.ce to 10 CFR 50 Appendix B, and ANSI standard N18.7-1976 and referenced daughter standards. Comments regarding this review have been submitted to the NRC Region II office. They will be forwarded to the NRR QA reviewer for ref olution with the licensee.

8.

Plant Tour

'

The inspector toured portions of the Control Building, Auxiliary Building and the Containment Building.

,

-

y--.,---

,.

i e'-v--

  1. -----,--.

,e e.,,

.,, -,,, - -,. -.. - - -

-

.

...

o

.

Unresolved Item 416/81-10-14

-

The inspector rated that the Standby Liquid Control (SLC) Tank and pumps were located on an elevation of approximately 185'. The components are installed on an open platform with no apparent enclosing protection.

This appears to conflict with the protection requirements as stated in the FSAR

'

chapter 9, paragraph 9.3.5.3.2 which states that the SLC system is located within its own compartment.

This item is considered. unresolved pending review by the licensee to determine if the SLC system is or will be

adequately protected as described in the Final Safety Analysis Report.

?

.