MONTHYEARIR 05000416/20240052024-08-21021 August 2024 Updated Inspection Plan for Grand Gulf Nuclear Station (Report 05000416/2024005) ML24204A2432024-07-23023 July 2024 Notification of Cyber Security Baseline Inspection and Request for Information (05000416/2024403) ML24108A1142024-04-17017 April 2024 June 2024 Emergency Preparedness Program Inspection - Request for Information IR 05000416/20230062024-02-28028 February 2024 Annual Assessment Letter for Grand Gulf Nuclear Station - Report 05000416/2023006 ML24023A3242024-01-23023 January 2024 Inservice Inspection Request for Information ML23348A3712023-12-14014 December 2023 Notification of an NRC Fire Protection Baseline Inspection (NRC Inspection Report (05000416/2024011) and Request for Information IR 05000416/20230052023-08-21021 August 2023 Updated Inspection Plan for Grand Gulf Nuclear Station (Report 05000416/2023005) IR 05000416/20220062023-03-0101 March 2023 Annual Assessment Letter for Grand Gulf Nuclear Station Report 05000416/2022006 ML22312A5832022-11-0808 November 2022 Notification of Cyber Security Baseline Inspection and Request for Information 05000416/2023401 IR 05000416/20220052022-08-18018 August 2022 Updated Inspection Plan for Grand Gulf Nuclear Station (Report 05000416/2022005) ML22110A1172022-04-19019 April 2022 (GG) 2022 Emergency Preparedness (EP) Program Inspection RFI Sdh 041922 IR 05000416/20210062022-03-0202 March 2022 Annual Assessment Letter for Grand Gulf Nuclear Station (Report 05000416/2021006) ML22075A3682022-02-14014 February 2022 2022 PIR Request for Information.Pdf ML21327A0842021-11-22022 November 2021 ISI RFI IR 05000416/20210052021-09-0101 September 2021 Mid-Cycle Inspection Plan Transmittal Letter for Grand Gulf Nuclear Station (Report 05000416/2021005) ML21179A1202021-06-28028 June 2021 Notification of NRC Supplemental Inspection of Action Matrix Column 3 (Degraded Performance) Inputs and Request for Information ML21158A0822021-06-0707 June 2021 Notification of Inspection (NRC Inspection Report 05000416/2021003) and Request for Information ML21106A2232021-04-16016 April 2021 IR 2021402 Document Request List ML21074A0822021-03-15015 March 2021 Notification of Evaluations of Changes, Tests, and Experiments Inspection (Inspection Report 05000416/2021002) and Request for Information ML21061A3352021-02-25025 February 2021 Request for Information: Grand Gulf Nuclear Station, Dated December 4, 2020; Inspection Report 05000416-2021001, Occupational Radiation Safety Inspection-2, 4 ML20363A1462020-12-22022 December 2020 Request for Information: Grand Gulf EP Exercise Inspection - March 2021 ML20258A0202020-09-0909 September 2020 EP Program Inspection RFI, Request for Information to Support and Prepare for Emergency Preparedness (EP) Program Inspection Scheduled to Occur the Week of November 16, 2020 ML20199M2352020-07-17017 July 2020 Notification of NRC Design Bases Assurance Inspection (Teams) (Inspection Report 05000416/2020012) and Initial Request for Information ML20155K7172020-06-0303 June 2020 Notification of NRC Fire Protection Baseline Inspection (NRC Inspection Report 05000416/2020013) and Request for Information ML20125A3802020-05-0404 May 2020 Request for Information, Inspection Date: July 20-24, 2020 ML20055E1562020-03-0303 March 2020 GG2019006 Annual Assessment Letter ML19346E2892019-12-11011 December 2019 ISI Request for Information ML19302E1082019-10-29029 October 2019 Document Request - GG 95001 - August 2 2019 ML19302E1102019-10-29029 October 2019 Document Request - GG 95001 - July 15 2019 IR 05000416/20190052019-08-30030 August 2019 Updated Inspection Plan for Grand Gulf Nuclear Station, Report 05000416/2019005 ML19148A5252019-05-28028 May 2019 Notification of Nrc Design Bases Assurance Inspection (Programs) ((05000416/2019010) and Initial Request for Information IR 05000416/20180062019-03-0404 March 2019 Annual Assessment Letter for Grand Gulf Nuclear Station (Report 05000416/2018006) ML19063B4882019-03-0404 March 2019 Notification of NRC Triennial Heat Sink Performance Inspection (05000416/2019002) and Request for Information ML19003A3812018-12-31031 December 2018 Notification of Cyber Security Inspection Report 05000416/2019410, and Request for Information ML18283A0622018-10-10010 October 2018 Notification of Evaluations of Changes, Tests, and Experiments Inspection (05000416/2018004) and Request for Information IR 05000416/20180052018-08-31031 August 2018 Updated Inspection Plan for Grand Gulf Nuclear Station (Report 05000416/2018005) IR 05000416/20170062018-03-0101 March 2018 Annual Assessment Letter for Grand Gulf Nuclear Station (Report 05000416/2017006) IR 05000416/20170052017-08-28028 August 2017 Updated Inspection Plan for Grand Gulf Nuclear Station (Report 05000416/2017005) ML17243A3062017-08-28028 August 2017 Updated Non-Public Security Inspection Plan for Grand Gulf Nuclear Station, Unit 1 IR 05000416/20160062017-03-0101 March 2017 Annual Assessment Letter for Grand Gulf Nuclear Station (Report 05000416/2016006) ML16320A2082016-11-14014 November 2016 Notification of an NRC Triennial Fire Protection Baseline Inspection (NRC Inspection Report 05000416/2017008) and Request for Information IR 05000416/20160052016-09-12012 September 2016 Errata for Mid-Cycle Assessment Letter for Grand Gulf Nuclear Station (Report 05000416/2016005) ML16242A3352016-08-31031 August 2016 Mid-Cycle Assessment Letter for Grand Gulf Nuclear Station (Report 05000416/2016005) IR 05000416/20164012016-08-31031 August 2016 Non-Public Security Inspection Plan for Grand Gulf Nuclear Station (NRC Physical Security Inspection Report Number 05000416/2016401) IR 05000416/20150062016-03-0202 March 2016 Annual Assessment Letter for Grand Gulf Nuclear Station (Report 05000416/2015006) IR 05000416/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Grand Gulf Nuclear Station (Report 05000416/2015005) ML15132A7112015-05-11011 May 2015 Notification of NRC Component Design Bases Inspection (05000416/2015007) and Initial Request for Information IR 05000416/20140062014-09-0202 September 2014 Mid-Cycle Assessment Letter for Grand Gulf Nuclear Station (Report 05000416/2014006) IR 05000416/20144022014-09-0202 September 2014 Non-Public Security Inspection Plan for Grand Gulf Nuclear Station (NRC Physical Security Inspection Report Number 05000416/2014402) IR 05000416/20130012014-03-0404 March 2014 IR 05000416-13-001, 02/11/2014, Grand Gulf, Annual Assessment Letter 2024-08-21
[Table view] Category:Letter
MONTHYEARML24289A0312024-11-0808 November 2024 – Issuance of Amendments Related to the Removal of License Condition 2.F as Part of the Consolidated Line-Item Improvement Process (CLIIP) IR 05000416/20240032024-11-0606 November 2024 Integrated Inspection Report 05000416/2024003 IR 05000416/20240112024-10-16016 October 2024 – Fire Protection Team Inspection Report 05000416/2024011 ML24263A2712024-09-19019 September 2024 Application to Revise Technical Specifications to Adopt TSTF-592, Revise Automatic Depressurization System (ADS) Instrumentation Requirements IR 05000416/20240122024-09-17017 September 2024 License Renewal Post Approval Phase 2 Inspection Report 05000416/2024012 ML24257A0172024-09-17017 September 2024 Request for Withholding Information from Public Disclosure Unit 1 ML24254A3602024-09-10010 September 2024 Pre-Submittal Slides for License Amendment Request, Criticality Safety Analysis, Technical Specification 4.3.1, Criticality and Technical Specification 5.5.14, Spent Fuel Storage Rack Neutron Absorber Monitoring Program IR 05000416/20244022024-09-0909 September 2024 Security Baseline Inspection Report 05000416/2024402 05000416/LER-2024-003, Feedwater Inlet Check Valve Incorrectly Determined Operable2024-08-26026 August 2024 Feedwater Inlet Check Valve Incorrectly Determined Operable ML24235A0832024-08-22022 August 2024 Evaluations Performed in Accordance with 10 CFR 50.54(q) for Changes to Emergency Planning Documents IR 05000416/20240052024-08-21021 August 2024 Updated Inspection Plan for Grand Gulf Nuclear Station (Report 05000416/2024005) ML24220A2642024-08-20020 August 2024 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment ML24185A1522024-08-13013 August 2024 Issuance of Amendment Nos. 334, 235, and 215, Respectively, to Revise TSs to Adopt TSTF-205 ML24176A1202024-07-29029 July 2024 Issuance of Amendment 234 Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times – RITSTF Initiative 4b IR 05000416/20240022024-07-29029 July 2024 Integrated Inspection Report 05000416/2024002 ML24172A2502024-07-29029 July 2024 – Issuance of Amendment No. 233 Adoption of 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors ML24204A2432024-07-23023 July 2024 Notification of Cyber Security Baseline Inspection and Request for Information (05000416/2024403) ML24191A2432024-07-0909 July 2024 Completion of License Renewal Activities Prior to Entering the Period of Extended Operations IR 05000416/20240102024-06-27027 June 2024 Biennial Problem Identification and Resolution Inspection Report 05000416/2024010 ML24156A1762024-06-24024 June 2024 Regulatory Audit Summary in Support of License Amendment Requests to Adopt TSTF-505, Revision 2 and 10 CFR 50.69 (Epids L-2023-LLA-0081 and L-2023-LLA-0080) ML24165A1512024-06-13013 June 2024 Second Supplement to License Amendment Request to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times – RITSTF Initiative 4b and Application to Adopt 10 CFR 50.69, Risk-Informe ML24163A2652024-06-11011 June 2024 Inservice Inspection Summary Report ML24060A2192024-05-30030 May 2024 Authorization of Alternative to Use EN-RR-01 Concerning Proposed Alternative to Adopt Code Case N-752 05000416/LER-2024-002, Automatic Actuation of Reactor Protection System2024-05-28028 May 2024 Automatic Actuation of Reactor Protection System ML24130A0912024-05-0909 May 2024 Request for Information Letter License Renewal Phase 2 Inspection ML24128A1512024-05-0909 May 2024 Project Manager Assignment ML24128A0422024-05-0707 May 2024 License Amendment Request to Remove Obsolete License Conditions IR 05000416/20240012024-05-0202 May 2024 Integrated Inspection Report 05000416 2024001 ML24122C6112024-05-0101 May 2024 Supplement to License Amendment Request to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - Ritstf. ML24116A0372024-04-25025 April 2024 Report of Technical Specification Bases Changes ML24113A0952024-04-22022 April 2024 Annual Radioactive Effluent Release Report for 2023 ML24113A0972024-04-22022 April 2024 Annual Report of Individual Monitoring - NRC Form 5 for 2023 Per 1 0 CFR 20.2206 ML24107B0402024-04-16016 April 2024 Notification by Entergy Operations, Inc., of Proposed Economic Performance Incentive and Reliance on Post-Event Improvements in Plant Procedures And/Or Methods of Operation in FERC ML24107A8872024-04-16016 April 2024 2023 Annual Radiological Environmental Operating Report (AREOR) ML24101A3882024-04-10010 April 2024 Response to Request for Confirmation of Information by the Office of Nuclear Reactor Regulation Proposed Alternative Request EN-RR-22-001 Risk-Informed Categorization and Treatment for Repair ML24100A0692024-04-0909 April 2024 Report of Changes or Errors to 10 CFR 50.46 Analysis ML24094A0992024-04-0303 April 2024 (GGNS) Core Operating Limits Report (COLR) Cycle 25, Revision O ML24089A2262024-03-29029 March 2024 Entergy Response to Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Exams 05000416/LER-2024-001, High Pressure Core Spray Inoperable Due to Minimum Flow Valve Failure to Close2024-03-27027 March 2024 High Pressure Core Spray Inoperable Due to Minimum Flow Valve Failure to Close ML24075A1712024-03-15015 March 2024 Nuclear Onsite Property Damage Insurance (10 CFR 50.54(w)(3)) ML24074A2892024-03-14014 March 2024 Proof of Financial Protection (10 CFR 140.15) ML24058A3512024-02-28028 February 2024 Notification of Biennial Problem Identification and Resolution Inspection and Request for Information IR 05000416/20230062024-02-28028 February 2024 Annual Assessment Letter for Grand Gulf Nuclear Station - Report 05000416/2023006 IR 05000416/20233012024-02-26026 February 2024 NRC Examination Report 05000416-2023301 05000416/LER-2023-002, Reactor Scram Due to Generator Stator Fault to Ground2024-02-13013 February 2024 Reactor Scram Due to Generator Stator Fault to Ground ML24043A1892024-02-12012 February 2024 Spent Fuel Storage Radioactive Effluent Release Report for 2023 ML24012A1422024-01-31031 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0051 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML24043A0732024-01-29029 January 2024 2024-01 Post Examination Comments IR 05000416/20230042024-01-25025 January 2024 Integrated Inspection Report 5000416/2023004 ML24018A0222024-01-18018 January 2024 Core Operating Limits Report (COLR) Cycle 24, Revision 2 2024-09-09
[Table view] |
Text
arch 4, 2014
SUBJECT:
ANNUAL ASSESSMENT LETTER FOR THE GRAND GULF NUCLEAR STATION (REPORT 05000416/2013001)
Dear Mr. Mulligan:
On February 11, 2014, the NRC completed its end-of-cycle performance review of the Grand Gulf Nuclear Station. The NRC reviewed the most recent quarterly performance indicators (Pis)
in addition to inspection results and enforcement actions from January 1, 2013 through December 31, 2013. This letter informs you of the NRC's assessment of your facility during this period and its plans for future inspections at your facility.
The NRC determined the performance at the Grand Gulf Nuclear Station during the most recent quarter was within the Regulatory Response Column of the NRC's Reactor Oversight Process (ROP) Action Matrix because, as discussed in our letter to you dated May 13, 2013 (ML13133A197), and in our Mid-Cycle letter to you dated September 3, 2013 (ML13246A404),
the PI for Unplanned Scrams per 7000 Critical Hours was reported as White for the first quarter of 2013. In addition, this PI was reported as White again in the third quarter of 2013.
These letters informed you that the NRC planned to conduct a supplemental inspection, in accordance with Inspection Procedure 95001, "Supplemental Inspection for One or Two White Inputs in a Strategic Performance Area," once you inform the NRC of your readiness for inspection. Because you have not yet informed the NRC of your readiness for this inspection, the Grand Gulf Nuclear Station will remain within the Regulatory Response Column until the NRC completes the inspection with satisfactory results.
The enclosed inspection plan lists the inspections scheduled through June 30, 2015. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the mid-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence. From January 1 to December 31 , 2013, the NRC issued three Severity Level IV traditional enforcement violations associated with impeding the regulatory process. Therefore, the NRC plans to conduct Inspection Procedure 92723, "Follow-up Inspection for Three or More Severity Level IV Traditional Enforcement Violations in the Same Area in a 12-Month Period," to follow-up on these violations. The purpose of this inspection is to provide assurance that you understand the cause of these violations, and that the extent of condition and extent of cause of these multiple Severity Level IV violations are also identified.
As a result of the Safety Culture Common Language Initiative, the terminology and coding of cross-cutting aspects were revised effective January 1, 2014. New cross-cutting aspects will be coded in accordance with the latest revision to NRC Inspection Manual Chapter (IMC) 0310, dated December 19, 2013. Cross-cutting aspects identified in the last six months of 2013 using the previous terminology will be converted to the revised language in accordance with the cross-reference in IMC 0310. The revised cross-cutting aspects will be evaluated for cross-cutting themes and potential substantive cross-cutting issues in accordance with IMC 0305 starting with the calendar year 2014 mid-cycle assessment.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/readinq-rm/adams.html (the Public Electronic Reading Room).
Please contact Don Allen at (817) 200-1144 with any questions you have regarding this letter.
57_/n_
~~. Kennedy, Director Division of Reactor Projects Docket No. 50-416 License No. NPF-29 Enclosure: Grand Gulf Nuclear Station Inspection/Activity Plan cc w/enclosure: Electronic Distribution
Page 1 of1 Grand Gulf 03/03/2014 16:32:56 Inspection I Activity Plan Report 22 03/01/2014 - 06/30/2015 09/22/2014 09/26/2014 X02530 INITIAL EXAM- GRAND GULF (12131/14)
10/20/2014 10/29/2014 X02530 INITIAL EXAM- GRAND GULF (12/31/14)
EB2-05T - TRIENNIAL FIRE PROTECTION INSPECTION 4 04/14/2014 04/18/2014 IP 7111105T Fire Protection [TrienniaQ 04/28/2014 05/02/2014 IP "/111105T Fire Protection [Trienniaij ISFSI - ROUTINE INSPECTION (1 WEEK IN THE MONTH) 1 09/01/2014 09/3012014 IP 60855.1 Operation of an Independent Spent Fuel Storage Installation at Operating Plants EP-1 - EP PERFORMANCE INDICATORS 1 10/20/2014 10/24/2014 IP 71151-EP01 Drill/Exercise Performance 10/20/2014 10/24/2014 IP 71151-EP02 ERO Drill Participation 10/20/2014 10/24/2014 IP 71151-EP03 Alert & Notification System EP-2 - BIENNIAL EP PROGRAM INSPECTION 1 1 10/20/2014 10/24/2014 IP 7111402 Alert and Notification System Testing 1 10/20/2014 10/2412014 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 10/20/2014 10/2412014 IP 7111404 Emergency Action Level and Emergency Plan Changes 10/20/2014 10/24/2014 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies RS24 - RADIATION SAFETY 2 11/17/2014 11/21/2014 IP 71124.02 Occupational ALARA Planning and Controls 11/17/2014 11/21/2014 IP 71124.04 Occupational Dose Assessment RS5678 - RADIATION SAFETY- TEAM 4 03/30/2015 04/03/2015 IP 71124.05 Radiation Monitoring Instrumentation 03/30/2015 04/03/2015 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment 03/30/2015 04/03/2015 IP 71124.07 Radiological Environmental Monitoring Program 03/30/2015 04/03/2015 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation is report does not include IN PO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.