IR 05000416/2017001
ML17135A406 | |
Person / Time | |
---|---|
Site: | Grand Gulf |
Issue date: | 05/15/2017 |
From: | Greg Warnick NRC/RGN-IV/DRP/RPB-C |
To: | Emily Larson Entergy Operations |
Greg Warnick | |
References | |
IR 2017001 | |
Download: ML17135A406 (43) | |
Text
May 15, 2017
SUBJECT:
GRAND GULF NUCLEAR STATION - NRC INTEGRATED INSPECTION REPORT 05000416/2017001
Dear Mr. Larson:
On March 31, 2017, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Grand Gulf Nuclear Station. On April 11, 2017, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.
NRC inspectors documented one finding of very low safety significance (Green) in this report.
This finding involved a violation of NRC requirements. The NRC is treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2.a of the Enforcement Policy.
Further, inspectors documented three licensee-identified violations, which were determined to be of very low safety significance (Green), in this report. The NRC is treating these violations as NCVs consistent with Section 2.3.2.a of the Enforcement Policy.
If you contest the violations or significance of these NCVs, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement; and the NRC resident inspector at the Grand Gulf Nuclear Station.
If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; and the NRC resident inspector at the Grand Gulf Nuclear Station. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA/
Greg Warnick, Branch Chief Project Branch C Division of Reactor Projects Docket No. 50-416 License No. NPF-29
Enclosure:
Inspection Report 05000416/2017001 w/ Attachments:
1. Supplemental Information 2. Request for Information for the O
REGION IV==
Docket: 05000416 License: NPF-29 Report: 05000416/2017001 Licensee: Entergy Operations, Inc.
Facility: Grand Gulf Nuclear Station, Unit 1 Location: 7003 Baldhill Road Port Gibson, MS 39150 Dates: January 1 through March 31, 2017 Inspectors: M. Young, Senior Resident Inspector N. Day, Resident Inspector L. Carson II, Senior Health Physicist M. Phalen, Senior Health Physicist P. Elkmann, Senior Emergency Preparedness Inspector S. Hedger, Emergency Preparedness Inspector E. Uribe, Project Engineer Approved Greg Warnick By: Chief, Project Branch C Division of Reactor Projects 1 Enclosure
SUMMARY
IR 05000416/2017001; 01/01/2017 - 03/31/2017; Grand Gulf Nuclear Station; Maintenance of
The inspection activities described in this report were performed between January 1 and March 31, 2017, by the resident inspectors at Grand Gulf Nuclear Station and inspectors from the NRCs Region IV office. One finding of very low safety significance (Green) is documented in this report. This finding involved a violation of NRC requirements. Additionally, NRC inspectors documented in this report three licensee-identified violations of very low safety significance (Green). The significance of inspection findings is indicated by their color (i.e.,
Green, greater than Green, White, Yellow, or Red), determined using Inspection Manual Chapter 0609, Significance Determination Process, dated April 29, 2015. Their cross-cutting aspects are determined using Inspection Manual Chapter 0310, Aspects within the Cross-Cutting Areas, dated December 4, 2014. Violations of NRC requirements are dispositioned in accordance with the NRC Enforcement Policy. The NRCs program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, Reactor Oversight Process, dated July 2016.
Cornerstone: Emergency Preparedness
- Green.
The inspectors identified a non-cited violation of 10 CFR 50.54(q)(2) associated with the licensees failure to conduct a drill required by the site emergency plan in 2014. The licensee was required to conduct a drill involving both the site first-aid team and a local hospital. This violation is not an immediate safety concern because drills were conducted involving the site first-aid team and other drills were conducted at local hospitals. This issue has been entered into the licensees corrective action program as Condition Report CR-GGN-2017-00311.
The performance deficiency was more than minor, and therefore a finding, because it was associated with the emergency response organization performance (drills and exercises)cornerstone attribute and adversely affected the Emergency Preparedness Cornerstone objective of being capable of implementing adequate measures to protect the health and safety of the public in the event of a radiological emergency. The finding was evaluated using Inspection Manual Chapter 0609, Appendix B, Emergency Preparedness Significance Determination Process, dated September 22, 2015. The finding was determined to be of very low safety significance (Green) because it was a failure to comply with NRC requirements, was not associated with the risk-significant planning standards, and was not a degraded planning standard function. The finding had a cross-cutting aspect in the area of human performance associated with training because the licensee did not maintain a workforce knowledgeable about the requirements of the emergency plan [H.9].
(Section 1EP5)
Licensee-Identified Violations
Violations of very low safety significance (Green) that were identified by the licensee have been reviewed by the inspectors. Corrective actions taken or planned by the licensee have been entered into the licensees corrective action program. These violations and associated corrective action tracking numbers are listed in Section 4OA7 of this report.
PLANT STATUS
The Grand Gulf Nuclear Station began the inspection period in Mode 4.
On January 31, 2017, operations personnel commenced power ascension, and on February 9, 2017, Grand Gulf Nuclear Station reached 100 percent power.
On February 10, 2017, operations personnel reduced power to 74 percent power due to an issue with the condensate booster pump B outboard mechanical seal.
On February 13, 2017, operations personnel commenced power ascension and reached 100 percent power.
On February 24, 2017, operations personnel reduced power to 74 percent power to perform planned maintenance and testing, and remained at that power level to support troubleshooting a problem with the condensate booster pump C outboard mechanical seal.
On March 9, 2017, operations personnel commenced power ascension to 100 percent power following replacement of condensate booster pump A and C outboard mechanical seals.
The Grand Gulf Nuclear Station finished the inspection period at 100 percent power.
REPORT DETAILS
REACTOR SAFETY
Cornerstones: Initiating Events, Mitigating Systems, and Barrier Integrity
1R01 Adverse Weather Protection
a. Inspection Scope
On February 7, 2017, the inspectors completed an inspection of the stations readiness for impending adverse weather conditions. The inspectors reviewed plant design features, the licensees procedures to respond to tornadoes and high winds, and the licensees implementation of these procedures. The inspectors evaluated operator staffing and accessibility of controls and indications for those systems required to control the plant.
These activities constituted one sample of readiness for impending adverse weather conditions, as defined in Inspection Procedure 71111.01.
b. Findings
No findings were identified.
1R04 Equipment Alignment
a. Inspection Scope
One January 29, 2017, inspectors performed a partial system walk-down of the reactor core isolation cooling system following a valve operability test. The inspectors reviewed the licensees procedures and system design information to determine the correct lineup for the system. They visually verified that critical portions of the system were correctly aligned for the existing plant configuration.
These activities constituted one partial system walk-down sample, as defined in Inspection Procedure 71111.04.
b. Findings
No findings were identified.
1R05 Fire Protection
Quarterly Inspection
a. Inspection Scope
The inspectors evaluated the licensees fire protection program for operational status and material condition. The inspectors focused their inspection on four plant areas important to safety:
- January 6, 2017, northeast auxiliary building passage, 166 feet elevation, Fire Area 8, Zone 1A401
- January 24, 2017, auxiliary building corridors and passages, 93 feet and 103 feet elevations, Fire Areas 7 and 8, Zones 1A101, 1A117, 1A121, and 1A123
- March 3, 2017, Unit 1, turbine building, 93 feet elevation, Fire Area TB1, Zone TB1-01
- March 3, 2017, Unit 2, auxiliary building, 119 feet and 139 feet elevations, Fire Area AB2, Zones AB2-01 and AB2-02 For each area, the inspectors evaluated the fire plan against defined hazards and defense-in-depth features in the licensees fire protection program. The inspectors evaluated control of transient combustibles and ignition sources, fire detection and suppression systems, manual firefighting equipment and capability, passive fire protection features, and compensatory measures for degraded conditions.
These activities constituted four quarterly inspection samples, as defined in Inspection Procedure 71111.05.
b. Findings
No findings were identified.
1R06 Flood Protection Measures
a. Inspection Scope
From January 31, 2017, to February 14, 2017, the inspectors completed inspections of underground bunkers susceptible to flooding. The inspectors selected three underground vaults that contained risk-significant or multiple-train cables whose failure could disable risk-significant equipment:
- SP45MH01
- SP45MH02
- SP45MH03 The inspectors observed the material condition of the cables and splices contained in the vaults and looked for evidence of cable degradation due to water intrusion. The inspectors verified that the cables and vaults met design requirements.
These activities constituted completion of one bunker/manhole sample, as defined in Inspection Procedure 71111.06.
b. Findings
No findings were identified.
1R13 Maintenance Risk Assessments and Emergent Work Control
a. Inspection Scope
The inspectors reviewed three risk assessments performed by the licensee prior to changes in plant configuration and the risk management actions taken by the licensee in response to elevated risk:
- January 6, 2017, operation with a potential for draining the reactor vessel during control rod exercising and control rod drive vent valve manipulations
- February 17, 2017, risk associated with preventative maintenance of fuel pool cooling and cleanup pump A, with fuel pool time to 200 degrees Fahrenheit less than 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />
- March 6 - 7, 2017, Division 2 emergency diesel generator verification of extended allowed outage time risk management actions required by technical specifications The inspectors verified that these risk assessments were performed timely and in accordance with the requirements of 10 CFR 50.65 (the Maintenance Rule) and plant procedures. The inspectors reviewed the accuracy and completeness of the licensees risk assessments and verified that the licensee implemented appropriate risk management actions based on the results of the assessments.
The inspectors also observed portions of two emergent work activities that had the potential to cause an initiating event:
- February 10, 2017, secured condensate booster pump B and subsequent downpower due to elevated temperatures on the pumps outboard mechanical seal
- February 28, 2017, following a downpower for testing, secured condensate booster pump C due to elevated temperatures on the pumps outboard mechanical seal The inspectors verified that the licensee appropriately developed and followed a work plan for these activities. The inspectors verified that the licensee took precautions to minimize the impact of the work activities on unaffected structures, systems, and components (SSCs).
These activities constituted completion of five maintenance risk assessments and emergent work control inspection samples, as defined in Inspection Procedure 71111.13.
b. Findings
No findings were identified.
1R15 Operability Determinations and Functionality Assessments
a. Inspection Scope
The inspectors reviewed five operability determinations and functionality assessments that the licensee performed for degraded or nonconforming structures, systems, or components (SSCs):
- January 12, 2017, operability determination of high pressure core spray following restricting orifice leakage
- January 28, 2017, operability determination of the high pressure core spray cables due to being wetted
- March 23, 2017, functionality assessment for FLEX debris removal equipment (1FLEXE001 and 1FLEXE002) unable to be started due to dead batteries
- March 23, 2017, functionality assessment of the fire brigade during the time two operators were locked on top of the standby service water basin and during times when brigade members performed walk-downs in the switchyard
- March 24, 2017, operability determination of the Division 1 and 2 emergency diesel generators due to potential crankcase pressure trip condition The inspectors reviewed the timeliness and technical adequacy of the licensees evaluations. Where the licensee determined the degraded SSC to be operable or functional, the inspectors verified that the licensees compensatory measures were appropriate to provide reasonable assurance of operability or functionality. The inspectors verified that the licensee had considered the effect of other degraded conditions on the operability or functionality of the degraded SSC.
These activities constituted completion of five operability and functionality review samples, as defined in Inspection Procedure 71111.15.
b. Findings
No Findings were identified.
1R18 Plant Modifications
a. Inspection Scope
The inspectors reviewed two temporary plant modifications that affected SSCs:
- January 31, 2017, installation and removal of the autostart feature for standby service water pumps A and B only when a manual start of residual heat removal system occurred during the outage
- February 24, 2017, modification to remove the linear velocity transducer for flow control valve B The inspectors verified that the licensee had installed these temporary modifications in accordance with technically adequate design documents. The inspectors verified that these modifications did not adversely impact the operability or availability of affected SSCs. The inspectors reviewed design documentation and plant procedures affected by the modifications to verify the licensee maintained configuration control.
These activities constituted completion of two samples of temporary modifications, as defined in Inspection Procedure 71111.18.
b. Findings
No findings were identified.
1R19 Post-Maintenance Testing
a. Inspection Scope
The inspectors reviewed three post-maintenance testing activities that affected risk-significant SSCs:
- February 28, 2017, control room air conditioning A following replacement of the compressor seal
- March 6, 2017, condensate booster pump A following replacement of the outboard mechanical seal and orifice installation
- March 12, 2017, Division 2 emergency diesel generator following an extended maintenance outage The inspectors reviewed licensing- and design-basis documents for the SSCs and the maintenance and post-maintenance test procedures. The inspectors observed the performance of the post-maintenance tests to verify that the licensee performed the tests in accordance with approved procedures, satisfied the established acceptance criteria, and restored the operability of the affected SSCs.
These activities constituted completion of three post-maintenance testing inspection samples, as defined in Inspection Procedure 71111.19.
b. Findings
No findings were identified.
1R22 Surveillance Testing
a. Inspection Scope
The inspectors observed two risk-significant surveillance tests and reviewed test results to verify that these tests adequately demonstrated that the SSCs were capable of performing their safety functions:
In-service tests:
- February 13, 2017, standby service water pump A quarterly surveillance test Other surveillance tests:
- January 29, 2017, intermediate-range monitor E surveillance test The inspectors verified that these tests met technical specification requirements, that the licensee performed the tests in accordance with their procedures, and that the results of the test satisfied appropriate acceptance criteria. The inspectors verified that the licensee restored the operability of the affected SSCs following testing.
These activities constituted completion of two surveillance testing inspection samples, as defined in Inspection Procedure 71111.22.
b. Findings
No findings were identified.
Cornerstone: Emergency Preparedness
1EP3 Emergency Response Organization Staffing and Augmentation System
a. Inspection Scope
The inspectors verified that the licensees emergency response organization on-shift and augmentation staffing levels were in accordance with the licensees emergency plan commitments. The inspectors reviewed documentation and discussed with licensee staff the operability of primary and backup systems for augmenting the on-shift emergency response staff to verify the adequacy of the licensees methods for staffing emergency response facilities, including the licensees ability to staff pre-planned alternate facilities.
The inspectors also reviewed records of emergency response organization augmentation tests and events to determine whether the licensee had maintained a capability to staff emergency response facilities within emergency plan timeliness commitments.
These activities constituted completion of one emergency response organization staffing and augmentation testing sample, as defined in Inspection Procedure 71114.03.
b. Findings
No findings were identified.
1EP5 Maintenance of Emergency Preparedness
a. Inspection Scope
The inspectors reviewed the following documents for the period November 2014 through December 2016:
- After-action reports for emergency classifications and events
- After-action evaluation reports for licensee drills and exercises
- Independent audits and surveillances of the licensees emergency preparedness program
- Self-assessments of the emergency preparedness program conducted by the licensee
- Licensee evaluations of changes made to the emergency plan and emergency plan implementing procedures
- Drill and exercise performance issues entered into the licensees corrective action program
- Emergency preparedness program issues entered into the licensees corrective action program
- Maintenance records for equipment supporting the emergency preparedness program
- Emergency response organization and emergency planner training records The inspectors reviewed summaries of 161 corrective action program reports associated with emergency preparedness, and selected 30 to review against program requirements to determine the licensees ability to identify, evaluate, and correct problems in accordance with planning standard 10 CFR 50.47(b)(14) and 10 CFR Part 50, Appendix E, IV.F. The inspectors verified that the licensee accurately and appropriately identified and corrected emergency preparedness weaknesses during critiques and assessments.
The inspectors reviewed summaries of 91 licensee evaluations of the impact of changes to the emergency plan and implementing procedures, and selected 14 to review against program requirements to determine the licensees ability to identify reductions in the effectiveness of the emergency plan in accordance with the requirements of 10 CFR 50.54(q)(3) and 50.54(q)(4). The inspectors verified that evaluations of proposed changes to the licensee emergency plan appropriately identified the impact of the changes prior to being implemented.
The inspectors reviewed summaries of records pertaining to the maintenance of equipment and facilities used to implement the emergency plan to determine the licensees ability to maintain equipment in accordance with the requirements of 10 CFR 50.47(b)(8) and 10 CFR Part 50, Appendix E, IV.E. The inspectors verified that equipment and facilities were maintained in accordance with the commitments of the licensees emergency plan.
These activities constituted completion of one sample of the maintenance of the licensees emergency preparedness program, as defined in Inspection Procedure 71114.05.
b. Findings
Introduction.
The inspectors identified a Green, non-cited violation of 10 CFR 50.54(q)(2) associated with the licensees failure to follow their emergency plan. Specifically, the licensee failed to follow Emergency Plan, Revision 72, Section 8.3.2(d), which requires that a drill involving the first-aid team and local support hospital(s) be conducted on an annual basis. The licensee failed to conduct a drill involving the first-aid team and local support hospitals during 2014.
Description.
The inspectors reviewed drills and exercises conducted by the licensee between July 2014 and December 2016, and compared the drill and exercise evaluation reports to the requirements of the licensee Emergency Plan.
The inspectors determined that Emergency Plan, Revisions 70 through 72, Section 8.3.2(d), required that a drill involving the first-aid team and local support hospital(s) be conducted on an annual basis. The inspectors identified that an on-site drill involving the site first-aid team was conducted in August 2014 and that a Medical Service - 1 (MS-1) drill simulating a contaminated and injured person was conducted on April 16, 2014, involving Northeast Louisiana Ambulance Service and Riverland Medical Center, Ferriday, Louisiana. The inspectors reviewed the post drill evaluation report(s)for the Riverland Medical Center and determined that licensee staff did not materially participate in this drill. Specifically, licensee staff were only present as observers.
The inspectors determined, from a review of letters of agreement between the licensee and offsite hospitals, that the hospitals relied upon by the licensee to treat contaminated and injured individuals originating at the licensees site were Claiborne County Hospital, River Region Medical Center, and Ochsner Clinic. The inspectors determined that the April 2014 drill was not conducted at a hospital credited in the site emergency plan as being relied upon to treat contaminated and injured employees from the licensees site.
The inspectors found that licensee Document 2014/00183, 2014 Annual Site Medical Drill, dated September 2, 2014, reported that although hospital response was not observed, hospital response, was demonstrated during the FEMA-evaluated MS-1 drill earlier this year. However, the inspectors concluded the licensee was required to drill with a hospital relied upon to treat contaminated and injured employees from the licensees site to ensure that proficiency was maintained for rarely-performed tasks that directly affect the radiological protection of site employees.
The inspectors reviewed site implementation procedures and conducted licensee staff interviews. Emergency preparedness staff explained that they believed they were in compliance with the emergency plan because, although the site first-aid team and local hospitals were not evaluated at the same time, the direction of the site drill and exercise procedure was met. Procedure EN-EP-306, Drills and Exercises, Revisions 5 through 8, Attachment 9.1, stated for drill/exercise, Type 6, that the annual Medical Emergency Drill, contains provisions for participation by the local medical support service agencies. While the site procedure stated this, the procedure also contained a site-specific emergency plan commitment list (Section 8.0). This list documented that the text in Attachment 9.1 was subject to site commitments in the Emergency Plan, Section 8.3.2. Licensee emergency preparedness staff failed to recognize that the wording of the site emergency plan commitment required the site to complete the drill requirement in a manner different than the general description in the site procedure.
The inspectors determined that the licensee did not conduct a drill in which both the site first-aid team and a hospital participated. Therefore, the inspectors concluded that the licensee did not follow the requirements of the site emergency plan.
Analysis.
The failure to conduct a drill required by the licensees emergency plan is a performance deficiency within the licensees ability to foresee and correct. The performance deficiency was more than minor, and therefore a finding, because it was associated with the emergency response organization performance (drills and exercises)cornerstone attribute and adversely affected the Emergency Preparedness Cornerstone objective of being capable of implementing adequate measures to protect the health and safety of the public in the event of a radiological emergency. The licensees ability to take adequate measures to protect the health and safety of the public is degraded when the licensee does not perform drills and exercises to ensure emergency response organization proficiency. The finding was evaluated using Inspection Manual Chapter 0609, Appendix B, Emergency Preparedness Significance Determination Process, dated September 22, 2015. The finding was determined to be of very low safety significance (Green) because it was a failure to comply with NRC requirements, was not associated with the risk significant planning standards, and was not a loss of planning standard function. The planning standard function was not lost because the licensee conducted other required drills during 2014, including drills involving the first-aid team.
The finding had a cross-cutting aspect in the area of human performance associated with training because the licensee did not maintain a workforce knowledgeable about the requirements of the emergency plan. Specifically, the review of drill reports text and responses in licensee interviews showed examples of insufficient knowledge of content of the site emergency plan by emergency preparedness staff. This contributed to the misconception by the licensee that their actions were in compliance with the plan [H.9].
Enforcement.
Title 10 CFR 50.54(q)(2) requires, in part, that a power reactor licensee follow an emergency plan which meets the requirements of Appendix E to 10 CFR Part 50 and the standards of 10 CFR 50.47(b). Planning standard 10 CFR 50.47(b)(14) requires, in part, that the licensee conduct periodic drills to maintain key skills. Emergency Plan, Revisions 70 through 72, Section 8.3.2(d),requires, in part, that, [a] drill involving the first-aid team and local support hospitals is conducted on an annual basis. Contrary to the above, between December 31, 2014, and January 13, 2017, Grand Gulf Nuclear Station failed to follow an emergency plan which met the requirements of Appendix E and the standards of 10 CFR 50.47(b).
Specifically, the licensee failed to conduct an annual drill involving the first-aid team and local support hospital(s) as required by Emergency Plan, Revisions 70 through 72, Section 8.3.2(d), to maintain key emergency response organization skills. The licensees ability to take adequate measures to protect the health and safety of the public is degraded when the licensee does not perform drills and exercises to ensure emergency response organization proficiency. The inspectors determined that all drills required to be conducted by the emergency plan were conducted in 2015 and 2016.
This issue has been entered into the licensees corrective action program as Condition Report CR-GGN-2017-00311. Because this violation has been determined to be of very low safety significance (Green) and has been entered into the licensees corrective action program, this violation is being treated as a non-cited violation, consistent with Section 2.3.2.a of the Enforcement Policy. (NCV 05000416/2017001-01, Failure to Conduct a Drill Required by the Site Emergency Plan in 2014)
1EP6 Drill Evaluation
a. Inspection Scope
The inspectors observed an emergency preparedness drill on February 22, 2017, to verify the adequacy and capability of the licensees assessment of drill performance.
The inspectors reviewed the drill scenario, observed the drill from the Technical Support Center and the simulator, and attended the post-drill critique. The inspectors verified that the licensees emergency classifications, off-site notifications, and protective action recommendations were appropriate and timely. The inspectors verified that any emergency preparedness weaknesses were appropriately identified by the licensee in the post-drill critique and entered into the corrective action program for resolution.
These activities constituted completion of one emergency preparedness drill observation sample, as defined in Inspection Procedure 71114.06.
b. Findings
No findings were identified.
RADIATION SAFETY
Cornerstones: Public Radiation Safety and Occupational Radiation Safety
2RS1 Radiological Hazard Assessment and Exposure Controls
a. Inspection Scope
The inspectors evaluated the licensees performance in assessing the radiological hazards in the workplace associated with licensed activities. The inspectors assessed the licensees implementation of appropriate radiation monitoring and exposure control measures for both individual and collective exposures. During the inspection, the inspectors interviewed licensee personnel, walked down various areas in the plant, performed independent radiation dose rate measurements, and observed postings and physical controls. The inspectors reviewed licensee performance in the following areas:
- Radiological hazard assessment, including a review of the plants radiological source terms and associated radiological hazards. The inspectors also reviewed the licensees radiological survey program to determine whether radiological hazards were properly identified for routine and nonroutine activities and assessed for changes in plant operations.
- Instructions to workers, including radiation work permit requirements and restrictions, actions for electronic dosimeter alarms, changing radiological condition, and radioactive material container labeling.
- Contamination and radioactive material control, including release of potentially contaminated material from the radiologically controlled area, radiological survey performance, radiation instrument sensitivities, material control and release criteria, and control and accountability of sealed radioactive sources.
- Radiological hazards control and work coverage. During walk-downs of the facility and job performance observations, the inspectors evaluated ambient radiological conditions, radiological postings, adequacy of radiological controls, radiation protection job coverage, and contamination controls. The inspectors also evaluated dosimetry selection and placement as well as the use of dosimetry in areas with significant dose rate gradients. The inspectors examined the licensees controls for items stored in the spent fuel pool and evaluated airborne radioactivity controls and monitoring.
- High radiation area and very high radiation area controls. During plant walk-downs, the inspectors verified the adequacy of posting and physical controls, including areas of the plant with the potential to become risk-significant high radiation areas.
- Radiation worker performance and radiation protection technician proficiency with respect to radiation protection work requirements. The inspectors determined if workers were aware of significant radiological conditions in their workplace, radiation work permit controls/limits in place, and electronic dosimeter dose and dose rate set points. The inspectors observed radiation protection technician job performance, including the performance of radiation surveys.
- Problem identification and resolution for radiological hazard assessment and exposure controls. The inspectors reviewed audits, self-assessments, and corrective action program documents to verify problems were being identified and properly addressed for resolution.
These activities constituted completion of the seven required samples of radiological hazard assessment and exposure control program, as defined in Inspection Procedure 71124.01.
b. Findings
No findings were identified.
2RS3 In-Plant Airborne Radioactivity Control and Mitigation
a. Inspection Scope
The inspectors evaluated whether the licensee controlled in-plant airborne radioactivity concentrations are consistent with ALARA principles, and that the use of respiratory protection devices did not pose an undue risk to the wearer. During the inspection, the inspectors interviewed licensee personnel, walked down various areas in the plant, and reviewed licensee performance in the following areas:
- Engineering controls, including the use of permanent and temporary ventilation systems to control airborne radioactivity. The inspectors evaluated installed ventilation systems, including review of procedural guidance, verification the systems were used during high-risk activities, and verification of airflow capacity, flow path, and filter/charcoal unit efficiencies. The inspectors also reviewed the use of temporary ventilation systems used to support work in contaminated areas such as high efficiency particulate air (HEPA)/charcoal negative pressure units.
Additionally, the inspectors evaluated the licensees airborne monitoring protocols, including verification that alarms and set points were appropriate.
- Use of respiratory protection devices, including an evaluation of the licensees respiratory protection program for use, storage, maintenance, and quality assurance of National Institute for Occupational Safety and Health (NIOSH)certified equipment, air quality and quantity for supplied air devices and self-contained breathing apparatus (SCBA) bottles, qualification and training of personnel, and user performance.
- Self-contained breathing apparatus for emergency use, including the licensees capability for refilling and transporting SCBA air bottles to and from the control room and operations support center during emergency conditions, hydrostatic testing of SCBA bottles, status of SCBA staged and ready for use in the plant including vision correction, mask sizes, etc., SCBA surveillance and maintenance records, and personnel qualification, training, and readiness.
- Problem identification and resolution for airborne radioactivity control and mitigation. The inspectors reviewed audits, self-assessments, and corrective action documents to verify problems were being identified and properly addressed for resolution.
These activities constituted completion of the four required samples of in-plant airborne radioactivity control and mitigation program, as defined in Inspection Procedure 71124.03.
b. Findings
No findings were identified.
OTHER ACTIVITIES
Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity, Emergency Preparedness, Public Radiation Safety, Occupational Radiation Safety, and Security
4OA1 Performance Indicator Verification
.1 Unplanned Scrams per 7000 Critical Hours (IE01)
a. Inspection Scope
The inspectors reviewed licensee event reports (LERs) for the period of January 1, 2016, through December 31, 2016, to determine the number of scrams that occurred. The inspectors compared the number of scrams reported in these LERs to the number reported for the performance indicator. Additionally, the inspectors sampled monthly operating logs to verify the number of critical hours during the period. The inspectors used definitions and guidance contained in Nuclear Energy Institute Document 99-02, Regulatory Assessment Performance Indicator Guideline, Revision 7, to determine the accuracy of the data reported.
These activities constituted verification of the unplanned scrams per 7000 critical hours performance indicator, as defined in Inspection Procedure 71151.
b. Findings
No findings were identified.
.2 Unplanned Power Changes per 7000 Critical Hours (IE03)
a. Inspection Scope
The inspectors reviewed operating logs, corrective action program records, and monthly operating power reports for the period of January 1, 2016, through December 31, 2016, to determine the number of unplanned power changes that occurred. The inspectors compared the number of unplanned power changes documented to the number reported for the performance indicator. Additionally, the inspectors sampled monthly operating logs to verify the number of critical hours during the period. The inspectors used definitions and guidance contained in Nuclear Energy Institute Document 99-02, Regulatory Assessment Performance Indicator Guideline, Revision 7, to determine the accuracy of the data reported.
These activities constituted verification of the unplanned power changes per 7000 critical hours performance indicator, as defined in Inspection Procedure 71151.
b. Findings
(Opened) Unresolved Item (URI)05000416/2017001-02, Grand Gulf Unplanned Power Changes per 7000 Critical Hours Performance Indicator
Introduction.
The inspectors identified an URI associated with the unplanned power changes per 7000 critical hours performance indicator related to events that occurred on June 17, 2016.
Description.
On June 17, 2016, during turbine stop valve testing, stop valve B was to be cycled closed. Upon performing that action, stop valve B closed as expected; however, stop valve D unexpectedly closed. In response to the unexpected valve closure, the electro-hydraulic control trip fluid pressure fluctuated at an increased rate which caused the turbine control valves to cycle. This valve cycling resulted in numerous unplanned reactor pressure and power changes for approximately 42 minutes. During this time, operations personnel repeatedly performed troubleshooting activities by attempting to reset the stop valves, which caused additional system instability and increased the magnitude of the power oscillations. Ultimately, operations personnel decided to insert control rods in an attempt to stabilize the power and pressure oscillations. The operator action to insert control rods failed to stabilize the power and pressure oscillations, and approximately 1 minute later, an automatic reactor scram occurred due to a valid oscillating power range monitor input to the reactor protection system. This event was documented in Licensee Event Report 05000416/2016004-00, and NRC Inspection Reports 05000416/2016002 and 05000416/2016003.
The unplanned power changes per 7000 critical hours performance indicator measures the rate of unplanned power changes per year of operation at power and provides an indication of initiating event frequency. The licensee did not include any unplanned power changes as inputs into this performance indicator for the second quarter of 2016.
The inspectors questioned whether any unplanned power changes should have been reported with this performance indicator, and the licensee submitted a frequently asked question (FAQ) to the NRC reactor oversight process working group (ADAMS Accession No. ML17100A235, 03/23/2017 Reactor Oversight Process Working Group Public Meeting). This FAQ (FAQ 17-01) is currently under review to determine whether the above events should be captured as inputs to the unplanned power changes performance indicator.
The inspectors concluded that additional inspection would be required to assess whether the unplanned power changes should have been reported in the unplanned power changes per 7000 critical hours performance indicator. This issue was identified as URI 05000416/2017001-02, Grand Gulf Unplanned Power Changes per 7000 Critical Hours Performance Indicator.
.3 Unplanned Scrams with Complications (IE04)
a. Inspection Scope
The inspectors reviewed the licensees basis for including or excluding in this performance indicator each scram that occurred from January 1, 2016, through December 31, 2016. The inspectors used definitions and guidance contained in Nuclear Energy Institute Document 99-02, Regulatory Assessment Performance Indicator Guideline, Revision 7, to determine the accuracy of the data reported.
These activities constituted verification of the unplanned scrams with complications performance indicator, as defined in Inspection Procedure 71151.
b. Findings
No findings were identified.
.4 Occupational Exposure Control Effectiveness (OR01)
a. Inspection Scope
The inspectors reviewed corrective action program records documenting unplanned exposures and losses of radiological control over locked high radiation areas and very high radiation areas during the period of January 1, 2016, to December 31, 2016. The inspectors reviewed a sample of radiologically controlled area exit transactions showing exposures greater than 100 millirem. The inspectors used definitions and guidance contained in Nuclear Energy Institute Document 99-02, Regulatory Assessment Performance Indicator Guideline, Revision 7, to determine the accuracy of the reported data.
These activities constituted verification of the occupational exposure control effectiveness performance indicator, as defined in Inspection Procedure 71151.
b. Findings
No findings were identified.
.5 Radiological Effluent Technical Specifications (RETS)/Offsite Dose Calculation Manual
(ODCM) Radiological Effluent Occurrences (PR01)
a. Inspection Scope
The inspectors reviewed corrective action program records for liquid and gaseous effluent releases, and leaks and spills that occurred between January 1, 2016, and December 31, 2016, to verify the performance indicator data. The inspectors used definitions and guidance contained in Nuclear Energy Institute Document 99-02, Regulatory Assessment Performance Indicator Guideline, Revision 7, to determine the accuracy of the reported data.
These activities constituted verification of the RETS/ODCM radiological effluent occurrences performance indicator, as defined in Inspection Procedure 71151.
b. Findings
No findings were identified.
4OA2 Problem Identification and Resolution
Routine Review
a. Inspection Scope
Throughout the inspection period, the inspectors performed daily reviews of items entered into the licensees corrective action program and periodically attended the licensees condition report screening meetings. The inspectors verified that licensee personnel were identifying problems at an appropriate threshold and entering these problems into the corrective action program for resolution. The inspectors verified that the licensee developed and implemented corrective actions commensurate with the significance of the problems identified. The inspectors also reviewed the licensees problem identification and resolution activities during the performance of the other inspection activities documented in this report.
b. Findings
No findings were identified.
4OA5 Other Activities
(Closed) Temporary Instruction (TI) 2515/192, Inspection of the Licensees Interim Compensatory Measures Associated with the Open Phase Condition Design Vulnerabilities in Electric Power Systems
a. Inspection Scope
The objective of this performance based temporary instruction is to verify implementation of interim compensatory measures associated with an open phase condition design vulnerability in electric power systems for operating reactors. The inspectors conducted an inspection to determine if the licensee had implemented the following interim compensatory measures. These compensatory measures are to remain in place until permanent automatic detection and protection schemes are installed and declared operable for the open phase condition design vulnerability. The inspectors verified the following:
- The licensee identified and discussed with plant staff the lessons learned from the open phase condition events at the United States operating plants, including the Byron Station open phase condition and its consequences. This included conducting operator training for promptly diagnosing, recognizing consequences, and responding to an open phase condition.
- The licensee updated plant operating procedures to help operators promptly diagnose and respond to open phase conditions on off-site power sources credited for safe shutdown of the plant.
- The licensee established and implemented periodic walk-down activities to inspect switchyard equipment such as insulators, disconnect switches, and transmission line and transformer connections associated with the off-site power circuits to detect a visible open phase condition.
- The licensee ensured that routine maintenance and testing activities on switchyard components have been implemented and maintained. As part of the maintenance and testing activities, the licensee assessed and managed plant risk in accordance with 10 CFR 50.65(a)(4) requirements.
b. Findings and Observations
No findings were identified.
The inspector identified that the licensee did not implement any operator training focused on the changes to operating procedures related to the open phase condition vulnerability. The licensee documented this feedback in the corrective action program as Condition Report CR-GGN-2017-03246.
4OA6 Meetings, Including Exit
Exit Meeting Summary
On January 13, 2017, the inspectors presented the emergency preparedness program inspection results to Mr. V. Fallacara, Acting Site Vice President, and other members of the licensee staff. The licensee acknowledged the issues presented. The licensee confirmed that any proprietary information reviewed by the inspectors had been returned or destroyed.
On February 22, 2017, the inspectors presented the radiation safety inspection results via teleconference, to Mr. T. Coutu, Director, Regulatory and Performance Improvement, and other members of the licensee staff. The licensee acknowledged the issues presented. The licensee confirmed that any proprietary information reviewed by the inspectors had been returned or destroyed.
On March 30, 2017, the inspectors presented the open phase temporary instruction inspection results via teleconference, to Mr. E. Larson, Site Vice President, and other members of the licensee staff. The licensee acknowledged the issues presented. The licensee confirmed that any proprietary information reviewed by the inspectors had been returned or destroyed.
On April 11, 2017, the inspectors presented the quarterly baseline inspection results to Mr. E. Larson, Site Vice President, and other members of the licensee staff. The licensee acknowledged the issues presented. The licensee confirmed that any proprietary information reviewed by the inspectors had been returned or destroyed.
4OA7 Licensee-Identified Violations
The following licensee-identified violations of NRC requirements were determined to be of very low safety significance (Green) and meet the NRC Enforcement Policy criteria for being dispositioned as non-cited violations:
- Title 10 CFR 50.54(q)(2) requires, in part, that a power reactor licensee follow an emergency plan which meets the requirements of Appendix E to 10 CFR Part 50 and the standards of 10 CFR 50.47(b). Planning Standard 10 CFR 50.47(b)(4) requires, in part, that a standard emergency classification and action level scheme is in use by the licensee. Contrary to the above, on June 7, 2015, Grand Gulf Nuclear Station failed to follow an emergency plan which met the requirements of Appendix E and the standards of 10 CFR 50.47(b). Specifically, the licensee failed to accurately classify a Notification of Unusual Event in accordance with the licensees emergency action level scheme.
The licensee declared the emergency based on a fire condition, which did not exist, as identified in the licensees after-action report dated July 13, 2015. The finding was evaluated using Inspection Manual Chapter 0609, Appendix B, Emergency Preparedness Significance Determination Process, dated September 22, 2015, and was determined to be of very low safety significance (Green) because it was a failure to comply with NRC requirements, was associated with a risk-significant planning standard, and was not a lost or degraded planning standard function. The licensee entered this issue into the corrective action program as Condition Reports CR-GGN-2015-03345 and CR-GGN-2017-00288.
- Technical Specification 5.7.1 states, in part, that each high radiation area, as defined in 10 CFR Part 20, shall be barricaded and conspicuously posted as a high radiation area.
Contrary to the above, on April 20, 2016, an accessible area of the auxiliary building 185 feet south, new fuel pool heat exchanger room, was a high radiation area as defined in 10 CFR Part 20 and was not barricaded or conspicuously posted. This finding was determined to be of very low safety significance (Green) because the finding was not an ALARA planning issue, there was no overexposure or potential for overexposure, and the licensees ability to assess dose was not compromised. The licensee entered this issue into the corrective action program as Condition Report CR-GGN-2016-03482.
- Technical Specification 5.7.2 states, in part, that in addition to the requirements of Specification 5.7.1, areas with radiation levels greater than 1000 mrem/hr shall be provided with locked or continuously guarded doors to prevent unauthorized entry.
Contrary to the above, on April 6, 2016, the reactor water cleanup pump B room had accessible areas with radiation levels greater than 1000 mrem/hr and was not locked or continuously guarded to prevent unauthorized entry. This finding was determined to be of very low safety significance (Green) because the finding was not an ALARA planning issue, there was no overexposure or potential for overexposure, and the licensees ability to assess dose was not compromised. The licensee entered this issue into the corrective action program as Condition Report CR-GGN-2016-03146.
SUPPLEMENTAL INFORMATION
KEY POINTS OF CONTACT
Licensee Personnel
- R. Benson, Manager (Acting), Radiation Protection
- A. Burks, Supervisor, Radiation Protection
- D. Burnett, Director, Emergency Preparedness, Entergy South
- T. Coutu, Director, Regulatory Assurance and Performance Improvement
- J. Dorsey, Manager, Security
- V. Fallacara, Acting Site Vice President
- E. Garrison, Manager, Training
- J. Keir, Manager, Nuclear Oversight
- R. Meister, Regulatory Assurance
- J. Nadeau, Manager, Regulatory Assurance
- K. Petersen, Manager, Recovery
- J. Seiter, Manager, Emergency Preparedness
- P. Stokes, Supervisor, Radiation Protection
- S. Sweet, Licensing Specialist
- P. Williams, Director, Engineering
- E. G. Wright, Supervisor, Radiation Protection
- R. Young, Auditor
LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED
Opened
Grand Gulf Unplanned Power Changes per 7000 Critical Hours
- 05000416/2017001-02 URI Performance Indicator (Section 4OA1)
Opened and Closed
Failure to Conduct a Drill Required by the Site Emergency Plan
- 05000416/2017001-01 NCV in 2014 (Section 1EP5)
Closed
Inspection of the Licensees Interim Compensatory Measures 2515/192 TI Associated with the Open Phase Condition Design Vulnerabilities in Electric Power Systems (Section 4OA5)
Attachment 1