IR 05000327/2022010

From kanterella
Jump to navigation Jump to search
Design Basis Assurance Inspection (Teams) Inspection Report 05000327/2022010 and 05000328/2022010
ML22115A161
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 04/25/2022
From: James Baptist
NRC/RGN-II/DRS/EB1
To: Jim Barstow
Tennessee Valley Authority
Shared Package
ML22115A162 List:
References
IR 2022010
Download: ML22115A161 (14)


Text

SUBJECT:

SEQUOYAH NUCLEAR PLANT - DESIGN BASIS ASSURANCE INSPECTION (TEAMS) INSPECTION REPORT 05000327/2022010 AND 05000328/2022010

Dear Mr. Barstow:

On March 17, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Sequoyah Nuclear Plant and discussed the results of this inspection with Mr. Tom Marshall, Site Vice President and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, James B. Baptist, Chief Engineering Br 1 Division of Reactor Safety Docket Nos. 05000327 and 05000328 License Nos. DPR-77 and DPR-79

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000327 and 05000328

License Numbers:

DPR-77 and DPR-79

Report Numbers:

05000327/2022010 and 05000328/2022010

Enterprise Identifier:

I-2022-010-0023

Licensee:

Tennessee Valley Authority

Facility:

Sequoyah Nuclear Plant

Location:

Soddy Daisy, TN 37379

Inspection Dates:

February 28, 2022 to March 18, 2022

Inspectors:

C. Baron, Contractor

J. Braisted, Reactor Inspector

P. Braxton, Reactor Inspector

R. Fanner, Reactor Inspector

C. Franklin, Reactor Inspector

P. Meier, Senior Resident Inspector

R. Patterson, Senior Reactor Inspector

S. Sandal, Senior Reactor Analyst

T. Su, Reactor Inspector

Approved By:

James B. Baptist, Chief

Engineering Branch 1

Division of Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a design basis assurance inspection (teams) inspection at Sequoyah Nuclear Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

===71111.21M - Design Bases Assurance Inspection (Teams) The inspectors evaluated the following components and listed applicable attributes, permanent modifications, and operating experience:

Design Review - Risk-Significant/Low Design Margin Components (IP Section 02.02) (5 Samples)

(1) Unit 1 residual heat removal pump 1B-B

Compliance with the Update Final Safety Analysis Report and the Technical Specifications

Material condition and configuration

Surveillance test procedures and recent results

System health report

Normal and emergency operating procedures

Corrective action history (2)480V Shutdown Boards 1A1-A,1B1-B, 1B2-B

Compliance with UFSAR, TS and TS Bases

Material Condition and Configuration

Design Requirements

Environmental Conditions

Protective relay setting and calibration

Overcurrent protection and coordination

System Health Report (3)1B EDG - Mechanical/Electrical

Surveillance Test Procedures and Recent Results

Corrective maintenance records

Normal and Emergency Operating Procedures

Vendor Manuals for battery chargers

Condition Report history

Alarm Response Procedures

Design Procedures and Guides review

Environmental Qualification Documents

(4) Unit 1 Motor Driven Auxiliary Feedwater Pump 1B

Normal and Emergency Operating Procedures

Surveillance Test Procedures and Recent Results

Inservice Test Procedures and Recent Results

Basis for Pump Test Acceptance Criteria, Including Instrument Uncertainty

Validation of Time Critical Action Associated with Isolating AFW Flow

Safety and Seismic Classification of Piping Associated with AFW Pumps

Potential Backleakage of Hot Fluid Through AFW Check Valves

Potential Clogging of AFW Control Valves

Material Condition of Pumps and Associated Equipment

Corrective Action History

(5) Unit 1 Pressurizer Power Operated Relief Valves (PORVs) SQN-1-PCV-068-0340A-A

& SQN-1-PCV-068-0334-B

Normal and Emergency Operating Procedures

Surveillance Test Procedures and Recent Results

Time Critical Action Associated with PORVs Design Review - Large Early Release Frequency (LERFs) (IP Section 02.02)===

(1) Unit 1 Containment Purge/Relief Valves 1-FCV-30-46, -47, -48, -56, -57

Surveillance Test Procedures and Recent Results

Appendix J Test Procedures and Recent Results

Air-Operated Valve and Inservice Testing Program Documents

Setpoint Control Calculations

Valve and Actuator Vendor Manuals

Environmental Qualification Documents

Wiring, Logic, Control, and Flow Diagrams

Preventive Maintenance History

Corrective Action History

Modification Review - Permanent Mods (IP Section 02.03) (5 Samples)

(1) DCN 22703, Replace Unit 1 TDAFW Governor Valve Controller w/Digital Controller
(2) SCN 23632-5, Replace MSIV Actuator Springs on Unit 2 MSIV 2-FCV-1-4
(3) D23623, Degraded non-conforming motor-operated valve (MOV) modification for the gear replacement of the refueling water storage tank to residual heat removal pump control valve SQN-1-FCV-063-0001-A
(4) DCN 23680, 480V Shutdown Board Transformer 1A1-A
(5) D22644, Replace Pressurizer PORVs due to Current Valves Being Obsolete and Reaching End of Life

Review of Operating Experience Issues (IP Section 02.06) (4 Samples)

(1) IN 2010-25 Inadequate Electrical Connections
(2) IN 2019-08 Flow-Accelerated Corrosion Events
(3) IN 2004-01: Auxiliary Feedwater Pump Recirculation Line Orifice Fouling - Potential Common Cause Failure
(4) IN 84-06: Steam Binding of Auxiliary Feedwater Pumps

INSPECTION RESULTS

Very Low Safety Significance Issue Resolution Process: Safety Classification of Piping Associated with Auxiliary Feedwater Pump Suctions 71111.21 M

This issue is a current licensing basis question and inspection effort is being discontinued in accordance with the Very Low Safety Significance Issue Resolution (VLSSIR) process. No further evaluation is required.

Description:

The inspectors identified a concern with the safety classification of a section of piping in the auxiliary feedwater (AFW) system. The water supply for the AFW pumps of both units is normally aligned from the two non-safety related, non-seismic condensate storage tanks (CSTs) through a common 16-inch header. The piping from the CSTs up to the auxiliary building wall is classified as TVA Class H. The Class H piping is not safety related, not seismically qualified, and not protected from external events.

The portion of piping from the auxiliary building wall to the check valves located adjacent to the six AFW pump suctions is classified as TVA Class G and Seismic Category I(L)A as defined in TVA Design Criteria Document SQN-DC-V-3.0, Classification of Piping, Pumps, Valves, and Vessels, Revision 23. The Class G piping is quality related, but not safety related, and is designed to designed to maintain pressure retention in the event of a safe shutdown earthquake (SSE). In accordance with SQN-DC-V-3.0, Category I(L)A seismic qualification may be accomplished without meeting the full extent of the design, construction, quality assurance, and other regulatory requirements normally specified for Seismic Category I structures, systems, or components wherein a quality related function must be assured. The remainder of the AFW system is classified as TVA Classes C and B.

The inspectors reviewed calculation CAD530HCGLCS110882, Auxiliary Feedwater System Pressure Switch Analytical Limits, Revision 18, which evaluated the automatic transfer of the AFW pumps suction supply from the CSTs to the safety related essential raw cooling water (ERCW) system. This transfer would be automatically initiated by low pressure switches in the CST supply header after a time delay. The AFW pumps would continue to operate during the transfer. The calculation took credit for the volume of water contained in a portion of the Class G piping after a seismic event; this volume was required to prevent air ingestion to the pump suctions during the time required to complete the transfer, less than one minute. If the Class G piping was not available, the transfer would not be successful without damaging the AFW pumps.

Based on these reviews, the inspectors were concerned with the classification of the Class G piping required to support the suction transfer. This portion of AFW system would be required to maintain pressure retention until the pump suction transfer was completed. SQN-DC-V-3.0, Table 3.1-1a addresses the classification of systems. Regarding AFW, it states that condensate supply and other piping not required after a seismic event but in Seismic Category I structures are TVA Class G, Seismic Category I(L). It also states that portions of the system not in SC-2a but required after a seismic event are TVA Class C, Seismic Category I. Based on calculation CAD530HCGLCS110882, the inspectors determined that this portion of piping would be required after a seismic event and should be TVA Class C, Seismic Category I in accordance with SQN-DC-V-3.0. The inspectors also observed that TVA Design Criteria Document SQN-DC-V-3.0 referenced NRC Regulatory Guide 1.26, Quality Group Classifications and Standards for Water,Steam and Radioactive Waste Containing Components of Nuclear Power Plants, Revision 3, February, 1976; and that the design criteria document was consistent with the regulatory guide regarding safety classifications.

In response to this concern, the licensee stated that the classification of this piping was consistent with the licensing basis, was designed to maintain pressure retention in the event of a safe shutdown earthquake (SSE), was located within a safety related building, and was subject to periodic visual inspections in accordance with the Aging Management Program. They stated that this portion of the piping was only required to perform a secondary, not primary, safety function as discussed in Position 2 of NRC Regulatory Guide 1.29, Seismic Design Classification, Revision 2, February 1976.

After extensive discussions with licensee personnel and NRC staff, the inspectors concluded that there was very low safety significance associated with the difference between classifying this section of piping as TVA Class C, Seismic Category I and TVA Class G, Seismic Category I(L)A. The inspectors also concluded that the current licensing basis was not clear and significant resources would be required to fully resolve this issue.

Licensing Basis: UFSAR Table 10.4.7-5 states that AFW system components were classified in accordance with the draft version of ANS 18.2 issued August 1970 and that a point-by-point comparison with RG 1.26 quality groups shows no significant differences for the AFW.

UFSAR Section 3.7.3.6, Seismic Analysis of System Piping, states All piping systems important to safety that have been designed to remain functional in the event of a safe shutdown earthquake (SSE) are designated as Category I.

Those portions of structures, systems, or components which perform secondary safety functions and which are not essential to safe shutdown and isolation of the reactor but whose failure could jeopardize, to an unacceptable extent, the achievement of a primary safety function are considered Category I(L) safety related.

Where pressure boundary integrity is required, the piping is classified as Category I(L)A. For Category I(L)A, all piping and tubing shall be analyzed to meet the requirements for Category I except that ASME Section III subsection NC Equation 9 needs not to be evaluated for the upset condition.

UFSAR Table 10.4.7-6, Responses to Short-and Long-Term Recommendations Resulting From a General NRC Investigation of AFWS, states that pump damage is prevented by the automatic transfer to the alternate water source which is essential raw cooling water.

Significance: This potential issue would Phase 1 screen to GREEN in question 1 of exhibit 2 (for mitigating systems - AFW) of IMC 0609 App A because there is no increased likelihood of failure of the pipe due to the qualification in question (i.e., no change in PRA likelihood of failure between the nominal and conditional case).

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On March 17, 2022, the inspectors presented the design basis assurance inspection (teams) inspection results to Mr. Tom Marshall, Site Vice President and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

03D53EPMGLC031193

Condensate Storage Tank (CST) Usable Volume for

Aux Feedwater Use

Rev. 10

03D53EPMWLL063094

AFW Hydraulic Analysis

Rev. 17

219280000

Minimum Head Required for the Turbine-Driven and

Motor Driven Auxiliary Feedwater (AFW) Pumps

Rev. 26

219280000A

Flow to Steam Generator During Main Steam Line

Break for Various Single Component Failures

Rev. 15

3BD53HCGHCM090486

Auxiliary Feedwater System Maximum Operating

Pressures

Rev. 18

B25861217301

7-Day Fuel Oil Tank Volume & Setpoints Calculation -

Diesel Generators

Rev. 7

B87 890810 003

SQN Diesel Generator Fuel Oil Consumption 7 Day

Supply Calculation

Rev. 3

CAD0530HCGLCS032384

Auxiliary Feedwater System Instrument/Process Safety

Limits

Rev. 24

CAD530HCGLCS110882

Auxiliary Feedwater System Pressure Switch Analytical

Limits

Rev. 20

ED00009992018000092

Turbine Driven Auxiliary Feedwater Dedication,

Qualification, and Software Verification &

Validation Documentation

Rev. 0

MDQ00000120020128

System Level Review for Sequoyah Main Steam

Supply System (MSSS) Air Operated Valves (AOV)

Rev. 0

MDQ00000120020133

Evaluation of Required Thrust for MSIVs and SG-

PORVs (Pilot-Operated Balanced Disk Globe AOVs) At

Sequoyah Nuclear Power Station

Rev. 1

MDQ00000120020134

Component Level Review Calculation for SQN Main

Steam Supply (MSS) System Pilot-Operated Balanced

Disk Globe Air Operated Valves (AOVs)

Rev. 5

MDQ00099920040148

Set Point Controls Parameters Review Calculation for

Sequoyah Category 2 Air Operated Valves (AOVs)

Rev. 10

71111.21M

Calculations

SCG-4M-00976

Seismic Qualification of 32" Main Steam Isolation

Valve

Rev. 4

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

SQN-APS-003

480VAC APS Class 1E Load Coordination Study

Rev. 115

SQN-CPS-051

Circuit Protection Device Evaluation

Rev. 74

SQNETAPAC

Auxiliary Power System

Rev. 111

SQS20110

Emergency and Abnormal Operating Procedure

Setpoints

Rev. 40

SQTP-003

ASME Section XI ln-service and Augmented Valve

Identification for the Second and Third Ten

Year Interval

Rev. 042

Corrective Action

Documents

Condition Report (CR)

210327, 1494201, 1557491, 1560137, 1561929,

1687020, 1697239, PER 20333

1758304

Administrative Drawing Discrepancies Were Identified

When Responding to an NRC Question

1758706

Procedure Weakness Was Identified When

Responding to a Question Asked By an NRC Inspector

1759019

SQN DBAI 2022010 / DWG 1-47W610-30-1

Discrepancy

03/03/2022

1759352

5/28/21 performance of 1-SI-SXP-003-202.B, Motor

Driven Auxiliary Feedwater Pump 1B-B

Comprehensive Performance Test

1759354

11/8/21 performance of 1-SI-SXP-003-201.B, Motor

Driven Auxiliary Feedwater Pump 1B-B Performance

Test

1759382

During Extent of Condition Review, an EOP Weakness

Was Identified

1759385

During the Extent of Condition Review, Additional

Deficiencies In PI-4 Were Identified

1760059

SQN DBAI 2022010 / Revise 0-MI-MVV-000-022.0 and

MMTP-152

03/07/2022

1760945

NRC Asked Whether If It Necessary to Consider Flow

As Part Of The Overall Uncertainty For The IST Pump

Flow Tests

Corrective Action

Documents

Resulting from

Inspection

1762821

SQN Should Consider Using AFW Discharge Header

Temperature Elements to Monitor for Backleakage

Through AFW Check Valves

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CR 1761999

ECP 22703 TDAFW flow controller dead time not

exeplicity discussed in 50.59

03/14/2022

1,2 45N749-4

Wiring Diagram 480V shutdown Board 1B2-B Single

Line

Rev. 63

1,2-45N749-1

Wiring Diagrams 480 V SD Board 1A1-A Single Line

Rev. 54

1,2-45N749-3

Wiring Diagram 480V Shutdown Board 1B1-B Single

Line

Rev. 58

1,2-45N630-11, Sht. 11

Wiring Diagrams, Ventilation System Schematic

Rev. 9

1,2-47W611-30-1

Mechanical Logic Diagram, Ventilation System

Rev. 4

1,2-47W801-1

Flow Diagram, Main & Reheat Steam

Rev. 122

1,2-47W866-3

Auxiliary Building -Flow Diagram Heating Vent & Air

Cond Air Flow

Rev. 20

1-3591A16

Breaker Setting Sheet 480V Shutdown BD 1B1

Rev. 5

1-3591A17

Breaker Setting Sheet 480V Shutdown BD 1B1-B

Rev. 5

1-47W610-30-1

Mechanical Control Diagram, Cntmt Ventilation Sys

Rev. 23

1-47W866-1

Flow Diagram, Heating and Ventilating Air Flow

Rev. 43

SQN-0-45N779-23

Wiring Diagram - 480V Shutdown Aux Power

Schematic Diagram SH-23

Rev. 44

SQN-0-45N779-49

Wiring Diagram - 480V Shutdown Aux Power

Schematic Diagram SH-49

Rev. 4

SQN-0-47W427-3

Mechanical Auxiliary Feedwater Piping

Rev. 5

SQN-0-47W427-4

Mechanical Auxiliary Feedwater Piping

Rev. 12

SQN-0-47W611-3-3

Mechanical Logic Diagram - Auxiliary Feedwater

System

Rev. 44

SQN-0-47W803-2

Flow Diagram - Auxiliary Feedwater

Rev. 78

SQN-0-47W813-1

Flow Diagram - Reactor Coolant System

Rev. 59

SQN-1-47W610-3-3

Mechanical Control Diagram - Auxiliary Feedwater

System

Rev. 32

Drawings

SQN-2-47K427-59

N2-03-10A Isometric - Auxiliary Feedwater Piping

Rev. 4

Engineering

Changes

DC 22703

Upgrade the Turbine Driven Auxiliary Feedwater

Speed Governor and Flow Controller

Rev. 2

Miscellaneous

Equipment Failure Investigation Checklist - Unit 1, B

Train Motor Driven Auxiliary Feed Water Pump Failure

dated

08/20/21

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Sequoyah Nuclear Plant Updated Final Safety Analysis

Report

Amend. 29

0-GO-14-1

Daily Logsheet

Rev. 55

0-TI-SXI-000-100.0

Inservice Testing Program Bases Document

Rev. 6

0-TI-SXI-000-200.0

Inservice Testing Program

Rev. 7

Amendment No. 61

Deletion of Reference to Motor-Operated Valves

(MOVs) With Bypassed Thermal Overload Devices and

Other MOVs

dated

10/22/87

Part 21, Event Number 54095

INTROL POSITIONERS POTENTIAL LATENT

DEFECT

05/31/2019

SO-22-007

Standing Order - Isolation of AFW to a Faulted S/G

dated

03/02/22

SQN-DC-V-13.9.5

Reactor Building Environmental Control System

Rev. 9

SQN-DC-V-21.0

Environmental Design

Rev.29

SQN-DC-V-4.1.1

Main Steam System

Rev. 19

SQN-VTD-A585-0020

Instruction Manual for 32 Main Steam Isolation Valves

Rev. 10

SQN-VTD-B237-0020

General Operating and Maintenance Instructions

Double Acting and Spring Return Series Pneumatic

Rotary Valve Actuators

Rev. 1

SQN-VTD-B237-0030

General Operating and Maintenance Instructions for

Nuclear Series Actuators

Rev. 1

SQN-VTD-B237-0070

Operating and Maintenance Instructions Disassembly

and Assembly Spring Return Series Actuators

Rev. 2

SQN-VTD-F130-1300

Fisher Controls 67C Series Instrument Supply

Regulators

Rev. 1

SQN-VTD-W120-7457

MPH-DS Breaker (MARCH, 1999) Maintenance

Program Manual for Safety Related Type DS Low

Voltage Metal Enclosed Switchgear

Rev. 5

0-PI-DXX-000-100.06.2

Uninsulated Components External Surfaces Inspection

Rev. 5

0-PI-OPS-000-004.0

Periodic Validation of Time Critical Actions Using

Simulator

Rev. 15

0-SI-SLT-030-258.3

Containment Isolation Valve Local Leak Rate Test

Containment Vacuum Relief

Rev. 12

Procedures

0-SI-SXV-068-201.0

Pressurizer PORV Operability Test

Rev. 2

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

0-TI-DXX-000-016.0

Erosive Wear Degradation Monitoring Program

Rev. 3

0-TI-OPS-000-004.0

Time Critical Operator Actions

Rev. 11

0-TI-OPS-000-004.0

Time Critical Operator Actions

Rev. 11

0-TI-SXI-000-200.0

Inservice Testing Program

Rev. 7

0-TPP-DXX-000-100.06

License Renewal Aging Management Program Basis

Document External Surfaces Monitoring Program

Rev. 2

1-SI-ICC-003-144.0

Calibration of Condensate Storage Tank Suction

Header Pressure Switches to Auxiliary Feedwater

System (1-PS-3-144A, -144B & -144D)

Rev. 14

1-SI-ICC-003-144.0

Calibration of Condensate Storage Tank Suction

Header Pressure Switches to Auxiliary Feedwater

System

Rev. 14

1-SI-OPS-003-118.0

Auxiliary Feedwater Pump and Valve Automatic

Actuation

Rev. 38

1-SI-SXP-003-201.B

Motor Driven Auxiliary Feedwater Pump 1B-B

Performance Test

dated

2/08/22

1-SI-SXP-003-202.B

Motor Driven Auxiliary Feedwater Pump 1B-B

Comprehensive Performance Test

dated

05/28/21

1-SI-SXV-000-201.0

Full Stroking of Category A and B Valves During

Operation

Rev. 28

1-SO-3-2

Auxiliary Feedwater System

Rev. 62

DS-M4.2.1

Flow Accelerated Corrosion Program Methods

Rev. 10

E-0

Reactor Trip or Safety Injection

Rev. 43

E-0

Reactor Trip or Safety Injection

Rev. 43

E-1

Loss of Reactor or Secondary Coolant

Rev. 32

E-3

Steam Generator Tube Rupture

Rev. 28

EA-202-2

Operating Equipment from 6.9KV Shutdown Board

Rev. 0

EA-3-10

Establishing Motor Driven AFW Flow

Rev. 5

EA-3-11

Local Isolation of MD and TD AFW

Rev. 2

ECA-0.0

Loss of All AC Power

Rev. 37

ES-1.3

Transfer to RHR Containment Sump

Rev. 24

ES-1.4

Transfer to Hot Leg Recirculation

Rev. 7

NPG-SPP-09.18.1

Vulnerability Identification and

Rev. 10

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Management

NPG-SPP-09.26.13

Air Operated Valve Program

Rev. 1

NPG-SPP-09.7.2

Flow Accelerated Corrosion Control Program

Rev. 5

NPG-SPP-09.7.5

Erosion Program

Rev. 1

SAR Change 20-27

Increased Operator Action Times for a SGTR

dated

06/02/06

SQN-DC-V-13.9.8

Auxiliary Feedwater System

Rev. 30

SQN-DC-V-27.4

Reactor Coolant System

Rev. 26

SQN-DC-V-3.0

The Classification of Piping, Pumps, Valves, and

Vessels

Rev. 23

Work Orders

Work Order (WO)

111338695, 119443478, 119446769, 119746807,

20281971, 120440234, 120792667, 120883320,

21401831, 121135517, 121135880, 121446977,

21721612, 121881329, 121912740, 121919585,

21982107, 122040836, 122062181, 118860328,

118860343, 120231713,

21719840, 120573157