IR 05000327/2023011
| ML23286A005 | |
| Person / Time | |
|---|---|
| Site: | Sequoyah |
| Issue date: | 10/16/2023 |
| From: | Daniel Bacon NRC/RGN-II/DRS/EB2 |
| To: | Jim Barstow Tennessee Valley Authority |
| References | |
| IR 2023011 | |
| Download: ML23286A005 (1) | |
Text
SUBJECT:
SEQUOYAH NUCLEAR PLANT - TRIENNIAL FIRE PROTECTION INSPECTION REPORT 05000327/2023011 AND 05000328/2023011
Dear James Barstow:
On October 11, 2023, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Sequoyah Nuclear Plant and discussed the results of this inspection with Meshelle Augustin and other members of your staff. The results of this inspection are documented in the enclosed report.
One finding of very low safety significance (Green) is documented in this report. This finding involved a violation of NRC requirements. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.
If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:
Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region II; the Director, Office of Enforcement; and the NRC Resident Inspector at Sequoyah Nuclear Plant.
October 16, 2023 This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Daniel M. Bacon, Chief Engineering Branch 2 Division of Reactor Safety Docket Nos. 05000327 and 05000328 License Nos. DPR-77 and DPR-79
Enclosure:
As stated
Inspection Report
Docket Numbers:
05000327 and 05000328
License Numbers:
Report Numbers:
05000327/2023011 and 05000328/2023011
Enterprise Identifier:
I-2023-011-0030
Licensee:
Tennessee Valley Authority
Facility:
Sequoyah Nuclear Plant
Location:
Soddy-Daisy, TN
Inspection Dates:
August 14, 2023, to September 01, 2023
Inspectors:
P. Braaten, Senior Reactor Inspector
E. Coffman, Reactor Inspector
J. Montgomery, Senior Reactor Inspector
D. Strickland, Reactor Inspector
Approved By:
Daniel M. Bacon, Chief
Engineering Branch 2
Division of Reactor Safety
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a triennial fire protection inspection at Sequoyah Nuclear Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
Reliance on OMAs In Lieu Of Physical Protection Without Approval or Evaluation Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000327,05000328/2023011-01 Open/Closed None (NPP)71111.21N.
Inspectors identified a Green finding and associated non-cited violation (NCV) of Sequoyah Nuclear Plant (SQN) Operating License Conditions (OLCs) 2.C(16) and 2.C(13), for Units 1 and 2 respectively, for the licensee's reliance on operator manual actions in lieu of protecting cables and equipment to ensure that one train of equipment required for SSD was free of fire damage.
Additional Tracking Items
None.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
REACTOR SAFETY
71111.21N.05 - Fire Protection Team Inspection (FPTI) Structures, Systems, and Components (SSCs) Credited for Fire Prevention, Detection, Suppression, or Post-Fire Safe Shutdown Review (IP Section 03.01)
The inspectors verified that components and/or systems will function as required to support the credited functions stated for each sample. Additional inspection considerations are located in the fire hazards analysis (FHA) or safe shutdown analysis (SSA).
- (1) Automatic preaction sprinkler system in FAA-091 (Auxiliary Control Instrument Room)
- (2) Automatic preaction sprinkler system in FAA-094 (480V Board Room 1A)
- (3) Unit 1 Chemical Volume & Control System
- (4) Unit 1 6.9kV Electrical Distribution System
Fire Protection Program Administrative Controls (IP Section 03.02) (1 Sample)
The inspectors verified that the selected control or process is implemented in accordance with the licensees current licensing basis. If applicable, ensure that the licensees FPP contains adequate procedures to implement the selected administrative control. Verify that the selected administrative control meets the requirements of all committed industry standards.
- (1) Fire Brigade Training Program
Fire Protection Program Changes/Modifications (IP Section 03.03) (2 Samples)
The inspectors verified the following:
a. Changes to the approved FPP do not constitute an adverse effect on the ability to safely shutdown.
b. The adequacy of the design modification, if applicable.
c. Assumptions and performance capability stated in the SSA have not been degraded through changes or modifications.
d. The FPP documents, such as the Updated Final Safety Analysis Report, fire protection report, FHA, and SSA were updated consistent with the FPP or design change.
e. Post-fire SSD operating procedures, such as abnormal operating procedures, affected by the modification were updated.
- (1) SQN-20-1174, Appendix R Concern - RHR Min Flow Valves
- (2) RIS 2005-07 Analysis for WO 120862019 MM/PI/0-PI-FPU-026-101.0 ATT 5 &
12/AUX 734 and 749 A-Train Sprinkler Inspection Sample
INSPECTION RESULTS
Reliance on OMAs In Lieu Of Physical Protection Without Approval or Evaluation Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000327,05000328/2023011-01 Open/Closed None (NPP)71111.21N.0 Inspectors identified a Green finding and associated non-cited violation (NCV) of Sequoyah Nuclear Plant (SQN) Operating License Conditions (OLCs) 2.C(16) and 2.C(13), for Units 1 and 2 respectively, for the licensee's reliance on operator manual actions in lieu of protecting cables and equipment to ensure that one train of equipment required for SSD was free of fire damage.
Description:
For fire safe shutdown, the Chemical Volume & Control System (CVCS) is credited to provide Reactor Coolant Pump seal integrity and Reactor Coolant System inventory control via the seal injection flow path.
During this inspection, the inspectors reviewed credited components in the CVCS for a sample of fire areas and noted, for the main charging flow control valve 1-FCV-062-093, the safe shutdown analysis stated, Resolution record to ensure MOA for local control of RCP seal injection flow can be credited. Inspectors also noted this justification was present for every fire area in the plant. The team questioned the licensing basis for crediting a manual operator action (MOA) (also known as operator manual action [OMA]) in lieu of protecting cables and equipment to ensure that one train of equipment required for safe shutdown (SSD) was free of fire damage. The licensee stated that calculation XDN00000020110001, Operator Manual Actions (OMAs) 10 CFR 50, Appendix R III.G.2 Compliance documented the feasibility, reliability, and defense-in-depth of the action to manually throttle seal injection.
However, after reviewing the plants licensing basis documents, inspectors determined that this action had never been reviewed and approved by the NRC, and that this condition had been noted by a previous inspection team.
In 2012, NRC inspectors issued the licensee a Green non-cited violation (NCV) for relying on OMAs in lieu of protecting cables and equipment to ensure that one train of equipment required for SSD was free of fire damage (Inspection Report 05000327, 328/2012-002). The OMAs that were the subject of the NCV were the following:
1. Disable affected emergency diesel generator (EDG) breakers and energize shutdown
boards from normal feeder within 30 minutes.
2. Place spare vital inverter in service within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />.
3. Restore power to battery charger by transferring 480 Volt vital transfer switch to its
alternate switch position within 45 minutes.
4. Throttle reactor coolant pump seal injection flow to limit pressurizer level rise within 2
hours.
In the 2012 NCV, the inspectors stated "...the licensees methodology of allowing fire damage to occur (in lieu of protecting SSD cables and equipment) and relying on OMAs to achieve post-fire SSD would adversely affect SSD. Thus, adding the new OMAs to the sites fire protection program in 2002 required prior NRC approval because that change adversely affected the ability to achieve and maintain SSD in the event of a fire." The inspection report also stated that the evaluation performed in 2002 for the new OMAs was not adequate to support the conclusion that adding the OMAs did not adversely affect post-fire SSD because the evaluation only addressed OMA feasibility and did not address defense-in-depth.
During this inspection, the team reviewed PER 324757, which was written to address the issue noted above. The team determined that the licensees corrective actions were erroneously focused on re-performing an analysis to address defense-in-depth rather than addressing the fact that reliance on OMAs in lieu of protecting SSD cables and equipment is not allowed by the plants license unless reviewed and approved by the NRC, or the SSD cables and equipment have been demonstrated to not be required for SSD per guidance in NEI 00-01, Guidance for Post Fire Safe Shutdown Circuit Analysis; as partially endorsed by the NRC in RG 1.189, Fire Protection for Nuclear Power Plants.
NEI 00-01 and RG 1.189 describe two classifications of equipment in the plantequipment that is required to achieve and maintain hot-shutdown conditions and equipment that is important to safe shutdown. Equipment that is required to achieve and maintain hot-shutdown conditions must be physically protected to ensure that one train of equipment required for SSD is free of fire damage. Reliance on OMAs is not allowed for this category of equipment, unless reviewed and approved by the NRC. On the other hand, OMAs are an option for equipment that is important to safe shutdown. Licensees must have an analysis to demonstrate that an SSC is important to safe shutdown vice required to achieve and maintain hot-shutdown conditions.
Currently, the plants OMA calculation identifies actions (1), (2), and
- (3) above as being important to safe shutdown. However, the licensee did not have an analysis to support the classification of the actions as being important to safe shutdown vice required for hot shutdown. RG 1.189 states, The information included in Appendix H to NEI 00-01, Revision 4, may be used in classifying components on the success path required for hot shutdown and those important to safe shutdown, when applied in conjunction with this RG. Further, while Appendix G to NEI 00-01, Revision 4, identifies suggested classifications for certain safe shutdown functions and SSCs, each licensee should perform their own plant-specific evaluations.
Additionally, the plants OMA calculation identifies action
- (4) above as being required for safe shutdown. The plant erroneously believed that this action had been approved in a 1988 Safety Evaluation Report (SER). The team determined that this SER documented approval of other OMAs, and each of these OMAs were explicitly discussed. However, the SER did not explicitly discuss or document anything regarding throttling reactor coolant pump seal injection flow.
Corrective Action References: CR 1879011
Performance Assessment:
Performance Deficiency: Inspectors determined the licensee's failure to ensure that one of the redundant trains of equipment necessary to achieve and maintain hot shutdown conditions was free of fire damage was a performance deficiency. Specifically, the licensee relied on OMAs without NRC approval, or proper evaluation, in lieu of protecting cables and equipment.
Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Protection Against External Factors attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the reliance on OMAs without prior NRC approval, or proper evaluation, adversely affected the ability to achieve and maintain safe shutdown in the event of a fire.
Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix F, Fire Protection and Post - Fire Safe Shutdown SDP. The issue was determined to impact Post-Fire Safe Shutdown and was not assigned a low degradation rating. For 3 of the 4 OMAs, the inspectors determined the issue was of very low safety significance (Green)because the finding did not adversely affect the ability to reach and maintain hot shutdown/hot standby conditions using the credited safe shutdown success path (Question 1.4.7-C). For the remaining OMA (throttle reactor coolant pump seal injection flow to limit pressurizer level rise within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />), the NRC utilized the licensee's fire PRA to assess the risk in accordance with section 1.5 of the SDP. The inspectors confirmed that the licensee has a NRC Regulatory Guide 1.200 compliant PRA, which has received a peer review, and all peer review comments have been addressed. The licensee performed a risk-based qualitative analysis because the OMA to throttle reactor coolant pump seal injection flow was not directly modeled in the fire PRA. The licensee's qualitative assessment determined the change in CDF would be zero because, per fire response operating procedures, operators would initiate plant cooldown within one hour of a fire event that necessitates plant shutdown. The reduction in RCS temperature and pressure associated with plant cooldown would alleviate the need to throttle seal injection flow to control RCS level. The SRA reviewed this evaluation and agreed with the licensees conclusion; therefore, inspectors determined the risk associated with the reactor coolant pump seal injection flow OMA was of very low safety significance (Green).
Cross-Cutting Aspect: Not Present Performance. No cross-cutting aspect was assigned to this finding because the inspectors determined the finding did not reflect present licensee performance.
Enforcement:
Violation: Sequoyah OLCs 2.C(16) and 2.C(13) for Units 1 and 2 respectively, state in part, the licensee shall implement and maintain in effect all provisions of the approved fire protection program referenced in the SQN Final Safety Analysis Report (FSAR). Sequoyah FSAR Section 9.5.1, Fire Protection System, states that the fire protection system and fire protection features are described in the SQN Fire Protection Report (FPR), and the FPR should be referred to for a detailed description of the Fire Protection Plan. Section 2.0 of Part II of the SQN FPR states, in part, that the FPR describes the Fire Protection Plan developed for SQN to ensure compliance with the requirements of...10 CFR 50, Appendix R, Sections III.G, J, L, and O. 10 CFR 50, Appendix R, Section III.G.2, states, in part, that where cables or equipment, that could prevent operation or cause mal-operation due to hot shorts, open circuits, or shorts to ground, of redundant trains of systems necessary to achieve and maintain hot shutdown conditions are located within the same fire area outside of primary containment, one of the following means of ensuring that one of the redundant trains is free of fire damage shall be provided:
- (a) separation of cables and equipment by a fire barrier having a 3-hour rating,
- (b) separation of cables and equipment by a horizontal distance of more than 20 feet with no intervening combustibles or fire hazards and with fire detectors and an automatic fire suppression system in the fire area, or
- (c) enclosure of cables and equipment in a fire barrier having a 1-hour rating and with fire detectors and an automatic fire suppression system in the fire area.
Contrary to the above, the licensee failed to use one of the means described in Appendix R,Section III.G.2.a, b, or c to ensure that one of the redundant trains of equipment necessary to achieve and maintain hot shutdown conditions was protected from fire damage.
Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On October 11, 2023, the inspectors presented the triennial fire protection inspection results to Meshelle Augustin and other members of the licensee staff.
- On August 31, 2023, the inspectors presented the primary inspection results to Chris Reneau and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
71111.21N.05
Calculations
26D54EPMABBIMPFHA
Sequoyah Nuclear Plant Fire Hazards Analysis
Calculation
149
71111.21N.05
Calculations
B841029B0036
ACTIONS REQUIRED TO ENSURE PROPER
FLOW TO CENTRIFUGAL CHARGING PUMP
SUCTION DURING AN ONSITE FIRE
71111.21N.05
Calculations
B87190228017
Appendix R - Post Fire RCS Cooldown and
Depressurization
71111.21N.05
Calculations
EDQ0009992017000385FHA
Sequoyah Nuclear Plant - Fire Hazards Analysis
Calculation -FSSD Compliance Mitigation
Strategy
71111.21N.05
Calculations
MDQ000NA2014000101
Sequoyah Nuclear Plant (SQN) Multiple
Spurious Operation Review for Regulatory
Guide 1.189 Revision 2
71111.21N.05
Calculations
XDN00000020110001
Operator Manual Actions (OMAs) for 10 CFR 50, Appendix R III.G.2 Compliance
71111.21N.05
Corrective
Action
Documents
1013894
0-PI-FPU-317-299.W has SQN Fire Operations
currently inspecting HEPA Filter Plenum Room.
The room inspection creates a Safety
Hazard for the inspectors due to D/P across
door.
2/01/2015
71111.21N.05
Corrective
Action
Documents
109269
PER written in response to USNRC Regulatory
Issue Summary (RIS) 2006-10
8/22/2006
71111.21N.05
Corrective
Action
Documents
1440822
Appendix R Control Building Issue for RHR
Pumps
04/03/2023
71111.21N.05
Corrective
Action
Documents
1785063
R014 light failed 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> discharge test
06/27/2022
71111.21N.05
Corrective
Action
Documents
239407
PER written for item identified in Focused Full
Programaitc Self-Assessment for Fire
Protection/
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Appendix R regarding documentation on
Operator Manual Actions (OMAs)
71111.21N.05
Corrective
Action
Documents
24757
NRC Triennial Unresolved issue (URI) Lower
Tier
2/16/2011
71111.21N.05
Corrective
Action
Documents
Resulting from
Inspection
1874456
SQN FPTI 2023011 NRC-identified labeling
deficiency
8/14/2023
71111.21N.05
Corrective
Action
Documents
Resulting from
Inspection
1874643
SQN FPTI 2023011 - HK Trash & Debris in plant
support piping
08/15/2023
71111.21N.05
Corrective
Action
Documents
Resulting from
Inspection
1874934
SQN FPTI 2023011 WO unavailable for
Appendix R Light SI
08/16/2023
71111.21N.05
Corrective
Action
Documents
Resulting from
Inspection
1874987
SQN FPTI 2023011 Non-functional clock in ACR
8/16/2023
71111.21N.05
Corrective
Action
Documents
Resulting from
Inspection
1875160
SQN FPTI 2023011 Lack of Detail in Alternate
Compensatory Evaluation
8/17/2023
71111.21N.05
Corrective
Action
Documents
Resulting from
1875229
SQN FPTI 2023011 Plant Lighting AB 759' U1
Upper Access
08/17/2023
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Inspection
71111.21N.05
Corrective
Action
Documents
Resulting from
Inspection
1875262
SQN FPTI 2023011 FPIP FOR220132 did not
meet OR 14.7.1 Condition B
8/17/2023
71111.21N.05
Corrective
Action
Documents
Resulting from
Inspection
1875795
SQN FPTI 2023011 FPIP FOR220132 did not
meet OR 14.7.1 Condition B
08/21/2023
71111.21N.05
Corrective
Action
Documents
Resulting from
Inspection
1877877
SQN FPTI 2023011 Orange Box OMA
Classification Evaluation
8/30/2023
71111.21N.05
Corrective
Action
Documents
Resulting from
Inspection
1879011
SQN FPTI 2023011 OMA Licensing Basis
9/7/2023
71111.21N.05
Drawings
1, 2-47W491-3-1
Mechanical Service Air, Water, Fire Prot and
Primary Water Makeup
71111.21N.05
Drawings
1, 2-47W812-1
Flow Diagram Containment Spray System
71111.21N.05
Drawings
1, 2-47W850-6
Flow Diagram Fire Protection
71111.21N.05
Drawings
1,2-47W94-1
Fire Prot - Compt - Fire Cells
71111.21N.05
Drawings
1-45E890-103-1
CFR 50 Appendix R RCS Inventory Control
Operational and Spurious CA Keys 1, 2, 4, 5, 6,
and 9
71111.21N.05
Drawings
1-47W491-3
Mechanical Service Air, Water, Fire Prot and
Prim Water Makeup
71111.21N.05
Drawings
1-47W809-1
Flow Diagram Chemical and Volume Control
System
71111.21N.05
Drawings
1-47W811-1
Flow Diagram Safety Injection System
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
71111.21N.05
Engineering
Changes
DCP 100101
Design change that performs multiple scopes of
work in support of the 10CFR50 Appendix R
Program
71111.21N.05
Engineering
Changes
SQN-20-1174
App R Concern - RHR Min Flow Valves
71111.21N.05
Engineering
Evaluations
SQN Fire Protection Report
71111.21N.05
Engineering
Evaluations
6119-RPT-03
SQN Appendix R RCP Seal Injection OMA Risk
Evaluation
71111.21N.05
Engineering
Evaluations
SQN-DC-V-27.2
Chemical and Volume Control System Design
Basis
71111.21N.05
Engineering
Evaluations
SQS40127
EQUIPMENT REQUIRED FOR SAFE
SHUTDOWN PER 10CFR50 APPENDIX R
71111.21N.05
Engineering
Evaluations
T11970512
Watts Bar Nuclear Plant (WBN) - Fire Watch
Time Studies
05/12/1997
71111.21N.05
Fire Plans
PFP NO: AUX-0-734-01
Pre-Fire Plan Aux BLDG 734.0 ELV
71111.21N.05
Fire Plans
PFP NO: AUX-0-734-02
Fire Protection Pre-Fire Plans Auxiliary Building
(EL 734 Unit 2 Side)
71111.21N.05
Fire Plans
PFP NO: AuX-0-734-03
Fire Protection Pre-Fire Plans Auxiliary Building
- EL. 734 (U-X)
71111.21N.05
Fire Plans
PFP NO: AUX-0-749-00
Fire Protection Pre-Fire Plans (Auxiliary Building
- El. 749 & 759)
71111.21N.05
Fire Plans
PFP NO: AUX-0-749-01
Fire Protection Pre-Fire Plans Auxiliary Building
(El. 749 Unit 1 Side)
71111.21N.05
Fire Plans
PFP NO: AUX-0-749-02
Fire Protection Pre-Fire Plans Auxiliary Building
(El. 749 Unit 2 Side)
71111.21N.05
Fire Plans
PFP NO; AUX-0-734-00
Fire Protection Pre-Fire Plans (Auxiliary Building
- EL. 734)
71111.21N.05
Miscellaneous
71111.21N.05
Miscellaneous
DEVIATION REQUESTS FROM APPENDIX R
OF 10 CFR PART 50
06/10/86
71111.21N.05
Miscellaneous
EWR No. 21-DEM-999-118
R1
Document TVA Approval of EPM Fire Watch
Time Study R3615-001-001
9/2/2021
71111.21N.05
Miscellaneous
EWR No.12-COM-999-059
Engineering Work Request to prepare a damage 12/21/2012
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
assessment for selected Appendix R MOV's
required for cold shutdown
71111.21N.05
Miscellaneous
JPM-AOP-C.04 [03]
Transfer Controls to the Auxiliary Mode per
71111.21N.05
Miscellaneous
NRC Inspection Report
05000327, 328/88-24
Inspection conducted in the area of fire
protection and the licensee's actions regarding
implementation of the requirements of 10 CFR 50, Appendix R, Sections III.G, III.J, III.L and
III.O
71111.21N.05
Miscellaneous
NUREG-1232 Vol. 2
Safety Evaluation Report on Tennessee Valley
Authority: Sequoyah Nuclear Performance Plan
May 1988
71111.21N.05
Miscellaneous
TPD-FBT
Fire Brigade Training-Training Program
Description
71111.21N.05
Procedures
0-SI-FPU-247-004.0
Auxiliary Building Appendix R Emergency
Lighting Discharge Test
71111.21N.05
Procedures
Shutdown from Aux Control Room
71111.21N.05
Procedures
Plant Fires
71111.21N.05
Procedures
AOP-N.08 Part 1
Fire Safe Shutdown Part 1
71111.21N.05
Procedures
AOP-N.08 Part 2
Fire Safe Shutdown Part 2
71111.21N.05
Procedures
AOP-N.08 Part 3
Fire Safe Shutdown Part 3
71111.21N.05
Procedures
AOP-N.08 Part 4
Fire Safe Shutdown Part 4
71111.21N.05
Procedures
AOP-N.08 Part 5
Fire Safe Shutdown Part 5
71111.21N.05
Procedures
AOP-N.08 Part 6
Fire Safe Shutdown Appendixes
71111.21N.05
Procedures
AOP-N.08 Part 7
Fire Safe Shutdown Attachments
71111.21N.05
Procedures
EPM-10
AOP-N.08 Manual Action Feasibility and
Reliability Study
71111.21N.05
Procedures
EPM-11
AOP-C.04 Manual Action Feasibility and
Reliability Study
71111.21N.05
Procedures
NPG-SPP-01.3
Housekeeping
71111.21N.05
Procedures
NPG-SPP-18.4.7
Control of Transient Combustibles
06/27/2023
71111.21N.05
Procedures
OPDP-1
Conduct of Operations
71111.21N.05
Procedures
OPDP-3
Administration Of Pre-fire Plans, Fire
Emergency Response, and
Development/Evaluation of Fire Drills
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
71111.21N.05
Procedures
SMI-0-317-18
Appendix R - Casualty Procedures [C.1]
71111.21N.05
Work Orders
20231713
0-PI-OPS-000-004.0 Periodic Validation of Time
Critical Actions (Non-Fire)
08/29/2020
71111.21N.05
Work Orders
20862019
MM/PI/0-PI-FPU-026-101.0 ATT 5 & 12/AUX
734 and 749 A TRAIN SPRINKLER
INSPECTION
SAMPLE
09/15/2020
71111.21N.05
Work Orders
21204888
MM/PI/0-SI-FPU-026-241.R/ AUX BLDG
Authorization to Begin: SRO Date & Time
SPRINKLER INSPECTION
2/10/2021
71111.21N.05
Work Orders
21867352
0-PI-OPS-000-004.1 Periodic Validation of Time
Critical Actions for Fire Safe Shutdown
08/29/2022
71111.21N.05
Work Orders
2266250
1-Pl-OP-000-003.0 Periodic Stroking of Unit I
Time Critical Valves
11/20/2022
71111.21N.05
Work Orders
2415634
MM/PUO-SI-FPU-026-241.R/ AUX BLDG
SPRINKLER INSPECTION
08/11/2022
71111.21N.05
Work Orders
2742894
2-PI-OPS-000-003.0 Periodic Stroking of Unit 2
Time Critical Valves
04/13/2023
71111.21N.05
Work Orders
23002235
R014 Light Failed 8 Hour Discharge Test
09/19/2022
71111.21N.05
Work Orders
23062599
0-SI-FPU-247-001.0 Emergency Lighting (APP
R), Auxiliary Building
07/13/2023
71111.21N.05
Work Orders
23115358
0-Pl-FPU-317-299. W FPU Misc Inspections.
Will require RP Support for HEPA Filter Room
Doors
08/14/2023