Sequoyah Nuclear Plant, P.O. Box 2000, Soddy Daisy, Tennessee 37384 November 2, 2023 10 CFR 50.4 ATTN: Document Control Desk U. S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Sequoyah Nuclear Plant, Units 1 and 2 Renewed Facility Operating License Nos. DPR-77 and DPR-79 NRC Docket Nos. 50-327 and 50-328
Subject:
Enforcement Action EA-22-129 Inspection Readiness Notification
Reference:
- 1. TVA letter to NRC dated September 14, 2023, Enforcement Action EA-22-129 Inspection Postponement Request
- 2.
TVA letter to NRC dated August 3, 2023, Enforcement Action EA-22-129 Inspection Readiness Notification
- 3.
NRC Inspection Report dated April 20, 2023, Sequoyah Nuclear Plant, Units 1 & 2 - Final Significance Determination For a Security-Related Greater Than Green Finding, Notice of Violation and Assessment Followup Letter, 05000327/2023441 and 05000328/2023441 By Reference Letter 1, TVA requested a postponement of the NRCs 95001 Inspection at the Sequoyah Nuclear Plant previously scheduled by Reference Letter 2. This 95001 Inspection was identified as a necessary supplemental inspection in Reference Letter 3. Our postponement request was based on time needed to complete additional effectiveness reviews of Fleet corrective actions. The additional effectiveness reviews have not been developed, but also found not to be required prior to the 95001 Inspection based on the outcome of a corrective action program analysis that cleared Sequoyahs corrective actions-to-address the condition for the violation in Reference Letter 3.
This letter serves to notify the NRC that TVA is once again ready for the NRC to schedule the inspection.
U.S. Nuclear Regulatory Commission Page 2 November 2, 2023 There are no regulatory commitments associated with this submittal. Should you have any questions, please contact Rick Medina, Site Licensing Manager at (423) 843-8129 or rmedina4@tva.gov.
Respectfully, Thomas Marshall Site Vice President Sequoyah Nuclear Plant cc:
NRC Regional Administrator - Region II NRC Senior Resident Inspector - Sequoyah Nuclear Plant NRC Project Manager - Sequoyah Nuclear Plant Marshall, Thomas B.
Digitally signed by Marshall, Thomas B.
Date: 2023.11.02 13:40:35 -04'00'