IR 05000327/2020012

From kanterella
Jump to navigation Jump to search
Plants - Triennial Fire Protection Inspection Report 05000327/2020012 and 05000328/2020012
ML20294A177
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 10/20/2020
From: Scott Shaeffer
NRC/RGN-II/DRS/EB2
To: Jim Barstow
Tennessee Valley Authority
References
IR 2020012
Download: ML20294A177 (15)


Text

October 20, 2020

SUBJECT:

SEQUOYAH NUCLEAR PLANTS - TRIENNIAL FIRE PROTECTION INSPECTION REPORT 05000327/2020012 AND 05000328/2020012

Dear Mr. Barstow:

On September 9, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Sequoyah Nuclear Plants. On August 31, 2020, the NRC inspectors discussed the results of this inspection with Mr. Scott Hunnewell and other members of your staff. The results of this inspection are documented in the enclosed report.

One finding of very low safety significance (Green) is documented in this report. This finding involved a violation of NRC requirements. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region II; the Director, Office of Enforcement; and the NRC Resident Inspector at Sequoyah Nuclear Plants.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region II; and the NRC Resident Inspector at Sequoyah Nuclear Plants. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Scott M. Shaeffer, Chief Engineering Br 2 Div of Reactor Safety Docket Nos. 05000327 and 05000328 License Nos. DPR-77 and DPR-79

Enclosure:

As stated

Inspection Report

Docket Numbers: 05000327 and 05000328 License Numbers: DPR-77 and DPR-79 Report Numbers: 05000327/2020012 and 05000328/2020012 Enterprise Identifier: I-2020-012-0012 Licensee: Tennessee Valley Authority Facility: Sequoyah Nuclear Plants Location: Soddy Daisy Inspection Dates: June 07, 2020 to August 28, 2020 Inspectors: P. Braaten, Reactor Inspector J. Dymek, Reactor Inspector J. Montgomery, Senior Reactor Inspector D. Strickland, Reactor Inspector Approved By: Scott M. Shaeffer, Chief Engineering Br 2 Div of Reactor Safety Enclosure

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a triennial fire protection inspection at Sequoyah Nuclear Plants, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Inadequate Surveillance Procedure Allowed Preconditioning of Alternative Safe Shutdown Transfer Switches and Controls Cornerstone Significance Cross-Cutting Report Aspect Section Mitigating Green [H.1] - 71111.21N.

Systems NCV 05000328/2020012-01 Resources 05 Open/Closed The inspectors identified a Green finding and associated Non-cited Violation (NCV) of Sequoyah Unit 2 Operating License Condition 2.C(13) when the licensee failed to comply with procedure NPG-SPP-06.9.2, Surveillance Test Program," by providing operators with inadequate surveillance procedures that preconditioned alternative safe shutdown transfer switches and controls.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.21N.05 - Fire Protection Team Inspection (FPTI) Structures, Systems, and Components (SSCs) Credited for Fire Prevention, Detection, Suppression, or Post-Fire Safe Shutdown Review (IP Section 03.01)

The inspectors verified that the following systems credited in the approved fire protection program could perform their licensing basis function:

a. Review deficiencies or open fire protection impairments for the selected system, including any temporary modifications, operator workarounds, or compensatory measures.

b. Verify that operator actions can be accomplished as assumed in the licensees FHA, or as assumed in the licensees fire probabilistic risk assessment (FPRA)analysis and SSA.

c. Review repetitive or similar maintenance work requests which could be an indicator of a design deficiency and could affect the ability of the components to perform their functions, when needed.

d. Ensure that post maintenance and/or surveillance activities are performed as scheduled.

e. Perform a walkdown inspection to identify equipment alignment discrepancies.

Inspect for deficient conditions such as corrosion, missing fasteners, cracks, and degraded insulation.

f. Ensure the selected SSCs that are subject to aging management review (AMR)pursuant to 10 CFR Part 54 are being managed for aging (e.g., loss of material, cracking, reduction of heat transfer) in accordance with appropriate aging management programs. Verify that the licensees aging management program activities (such as, Fuel Oil Analysis or Selective Leaching Aging Management Program) associated with FP equipment are being implemented.

g. If a review of operating experience issues will be completed for the selected inspection sample, verify that the licensee adequately reviewed and dispositioned the operating experience in accordance with their processes.

The team selected the following SSCs as samples.

  • Unit 1 12v DC Power System
  • Cable Tray Water Spray System in 1B2-B and 2A2-A 480v Shutdown Board Rooms
  • CO2 System in Unit 1 Auxiliary Instrument Room and Required Fire/Smoke

Dampers Fire Protection Program Administrative Controls (IP Section 03.02) (1 Sample)

The inspectors verified that the following fire protection program administrative controls were implemented in accordance with the current licensing basis:

  • Combustible Control Program

Fire Protection Program Changes/Modifications (IP Section 03.03) (1 Sample)

The inspectors reviewed the following changes to ensure that they did not constitute an adverse effect on the ability to safely shutdown post-fire and to verify that fire protection program documents and procedures affected by the changes were updated.

  • Engineering Modification to Replace Unit 1 Pressurizer Power Operated Relief Valves

INSPECTION RESULTS

Inadequate Surveillance Procedure Allowed Preconditioning of Alternative Safe Shutdown Transfer Switches and Controls Cornerstone Significance Cross-Cutting Report Aspect Section Mitigating Green [H.1] - 71111.21N.0 Systems NCV 05000328/2020012-01 Resources 5 Open/Closed The inspectors identified a Green finding and associated Non-cited Violation (NCV) of Sequoyah Unit 2 Operating License Condition 2.C(13) when the licensee failed to comply with procedure NPG-SPP-06.9.2, Surveillance Test Program," by providing operators with inadequate surveillance procedures that preconditioned alternative safe shutdown transfer switches and controls.

Description:

To support inspection of the Unit 2 Pressurizer PORVs and their credit for fire safe shutdown, inspectors reviewed records for the last completion of surveillance test procedure 2-PI-OPS-000-010.D, "Verification of Remote Shutdown Transfer Switches." This test procedure verifies the operation of remote shutdown transfer switches and controls that are credited to meet the alternative shutdown requirements of 10 CFR 50, Appendix R, Section III.G.3. In reviewing this surveillance test procedure, inspectors discovered a sequence of test steps that appeared to constitute preconditioning of the Pressurizer PORVs under surveillance.

For PORV 2-PCV-68-334, after operators receive authorization from the SRO to perform the surveillance, the test directs operators to cycle transfer switch 2-XS-68-334C at least three times to clean contacts. The next step is to cycle control switch 2-HS-68-334C at least three times to clean contacts.

NRC Technical Guidance Part 9900, Maintenance - Preconditioning of Structures, Systems, and Components Before Determining Operability, gives guidance on the acceptability of preconditioning SSCs before the performance of surveillance testing. This document states that the NRC expects surveillance and testing processes of SSCs to be evaluated in an as-found condition. This guidance is echoed in TVA fleet procedure NPG-SPP-06.9.2, Surveillance Test Program. NPG-SPP-06.9.2 states, Surveillance sequences and alignment activities that are implemented prior to a surveillance test should be intended to facilitate testing or prevent unnecessary wear and damage to equipment and/or systems.

Test procedure steps that exercise equipment prior to testing activities are not allowed unless they provide a specific benefit, such as improved safety, reduced wear and tear, or facilitate better test methods. The potential of such activities to unintentionally mask degradation must be considered. Cycling electrical contacts repeatedly to clean them does not specifically facilitate test performance or provide any specific benefit. Further, cleaning the contacts before performing the continuity checks and resistance readings of the surveillance could unintentionally mask degradation of the circuit and the contacts.

Inspectors noted that the steps for PORV 2-PCV-68-340 were structured the same. The last performance of the surveillance for these two valves was November 23, 2018. Inspectors also reviewed the test procedure for other examples of this test sequence, and found that the surveillances for the 4 Main Steam Isolation Valves, the main Charging Header flow control valve (FCV) 62-93, multiple 6.9kV Shutdown Board feeder breakers, and the FCV for RHR Hot Leg injection to loops 1 & 3 (2-FCV-63-172) all contained the same, or similar steps to clean the electrical contacts before performing the continuity checks and resistance readings of the surveillance.

Corrective Action References: CR 1616116

Performance Assessment:

Performance Deficiency: The licensees failure to establish adequate surveillance test instructions in accordance with TVA fleet procedure NPG-SPP-06.9.2 was a performance deficiency. Specifically, surveillance test procedure 2-PI-OPS-000-010.D directed operators to cycle transfer and control switches to clean the contacts before performing the continuity checks and resistance readings to determine whether the surveillance acceptance criteria had been met. Those procedure steps constitute unacceptable preconditioning of the SSCs.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Protection Against External Factors attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the failure to determine the as-found condition of the transfer switches and controls reduced the ability of the licensee to provide reasonable assurance that the licensee's alternative shutdown capability would have been available between tests.

Significance: The inspectors assessed the significance of the finding using Appendix F, Fire Protection and Post - Fire Safe Shutdown SDP. Using IMC 0609, Appendix F, Attachment 1, the inspectors determined the issue was of very low safety significance (Green) because the finding did not adversely affect the ability to reach and maintain hot shutdown/hot standby conditions using the credited safe shutdown success path (Question 1.4.7-C).

Cross-Cutting Aspect: H.1 - Resources: Leaders ensure that personnel, equipment, procedures, and other resources are available and adequate to support nuclear safety.

Specifically, leaders did not ensure that a set of procedures were in place that ensured preconditioning did not take place.

Enforcement:

Violation: Sequoyah Unit 2 Operating License Condition 2.C(13) requires, in part, that TVA shall implement and maintain in effect all provisions of the approved fire protection program referenced in Sequoyah Nuclear Plant's Final Safety Analysis Report (FSAR). Section 9.5.1 of the FSAR states that the Fire Protection System and fire protection features are described in the Fire Protection Report. Part II of the Fire Protection Report is the Fire Protection Plan, and Section 6.0 of the Fire Protection Plan states that the QA program for fire protection uses the applicable parts of the TVA Nuclear Quality Assurance Plan. Fleet procedure NPG-SPP-18.4.5, "Fire Protection QA Program" requires that activities shall be conducted in accordance with the applicable TVA Nuclear Power Group (NPG) programs to provide controls for modification, installation, surveillance, maintenance, operation, and program administration. The NPG Test Program is described in NPG-SPP-06.9, and child procedures.

NPG-SPP-06.9.2, "Surveillance Test Program," requires that Surveillance sequences and alignment activities that are implemented prior to a surveillance test should be intended to facilitate testing or prevent unnecessary wear and damage to equipment and/or systems.

Test procedure steps that exercise equipment prior to testing activities are not allowed unless they provide a specific benefit, such as improved safety, reduced wear and tear, or facilitate better test methods. The potential of such activities to unintentionally mask degradation must be considered.

Contrary to the above, from August 3, 2018 to June 12, 2020, the licensee used a surveillance test procedure that directed operators to exercise equipment prior to surveillance testing activities, without a specific benefit.

Enforcement Action: This violation is being treated as an non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On August 31, 2020, the inspectors presented the triennial fire protection inspection results to Mr. Scott Hunnewell and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection Type Designation Description or Title Revision or

Procedure Date

71111.21N.05 Calculations 26D54EPMABBIMPFHA Sequoyah Nuclear Plant - Fire Hazards Analysis Rev. 145

Calculation

2-92743 Seismic Analysis of 24 Ton CO2 Tank Rev. 0

APS2068 Appendix R - Post Fire RCS Cooldown and Rev. 2

Depressurization

B25850329800 Fire Protection Pipe Support Calculation for 03/27/1985

Cantilevered 1-inch Pipe

D2SDJ-P213350 Analysis of the Auxiliary Power System for 10 Rev. 64

CFR 50, Appendix R

EDQ0009992017000385FHA Sequoyah Nuclear Plant - Fire Hazards Analysis Rev. 3

Calculation -

FSSD Compliance Mitigation Strategy

MDN000NA2019000628 SQN Fire PRA - Fire Risk Quantification Rev. 1

MDQ0026-97001 Motor Driven Fire Pump Replacement Sprinkler 06/25/2018

Calculation

MDQ0026-97001B Control Valve(s) 0FCV-26-151 & 0FCV-2066 12/03/2013

HPFP Sprinkler Calculation

MDQ0026-97001D Flow Testing to Support Pipe Degradation 12/24/1997

MDQ0026-980041 HPFP Sprinkler Calculation, Boric Acid Tank 12/16/1998

Room, 690.0' AB, Sprinkler Addition

SQN-APPR-1 Analysis of AC/DC Instrument & Control (I&C) Rev. 20

Power Systems to Identify Associated Circuits -

CFR 50 Appendix R

SQN-APS-003 480VAC APS Class 1E Load Coordination Rev. 108

Study

SQN-DC-V-10.7 Design Criteria Document - 10CFR50, Appendix Rev. 4

R, Type I,II, & III Circuits

SQN-DC-V-24.0 Design Criteria Document - Fire Protection for Rev. 10

Appendix R Requirements

SQN-DC-V-43.0 Design Criteria Document - High-Pressure Fire Rev. 9

Protection Water Supply System

SQN-DC-V-7.5 Design Criteria Document - Fire Protection Rev. 14

Inspection Type Designation Description or Title Revision or

Procedure Date

Systems

SQN-DC-V-7.6 Design Criteria Document - Proprietary Rev. 4

Protective Signaling Systems for Fire Alarm and

Supervisory Service

SQNAPPR10 Appendix R Hot Short Analysis for Non Rev. 25

High/Low RCS Pressure Interfaces and Non-

High Impact Circuits

XDN00000020110001 OMAs for 10 CFR Appendix R III.G.2 1/27/2014

Compliance

Corrective 1072726 Appendix R Fire Concern Regarding Smoke 8/7/2019

Action Migration

Documents 1440822 Appendix R Control Building Issue for RHR 08/20/2018

Pumps

1581033 NRC Triennial Fire Protection Inspection (TFPI) 02/24/2020

Readiness Self-Assessment

1610002 Appendix R Lighting Deficiency Created by 6/8/2020

Design Change

27936 Light heads misaimed 8/4/2020

Corrective 1590413 SA-1581033 2020 TFPI Deficiencies in testing 06/09/2020

Action for remote shutdown transfer switches

Documents 1613748 Alternate shutdown transfer switch testing 06/10/2020

Resulting from deficiencies

Inspection 1616116 NRC identified issue related to transfer switch 06/12/2020

testing

CR1632843 Fire Door C-22 Missing Screws from Plate on 08/25/2020

Door

CR1632915 Abandon Office Chair Staged in Auxiliary 8/26/2020

Building Equipment Room

Drawings 1,2 45W1699-50 Conduit & Grounding, Floor El.734.0, Details Rev. 3

Sheet 12

1,2 46W-455-1 Architectural Door Frames and Details Rev. 1

1,2 46W454-4 Architectural Door and Hardware Schedule Rev. 1

1,2 46W454-7 Architectural Door and Hardware Schedule Rev. 0

1,2 47W494-4 Fire Protection Compartmentation-Fire Cells Rev. 15

Inspection Type Designation Description or Title Revision or

Procedure Date

Plan El. 734.0'

1,2 47W494-6 Fire Protection Compartmentation-Fire Cells, Rev. 7

Plan El. 669.0' & 685.0'

1,2 47W850-27 Flow Diagram-High Pressure Fire Protection Rev. 11

1,2-45N639-1 Wiring Diagrams CO2 Fire Protection System Rev. 3

Schematic Diagrams Sh-1

1,2-45N639-2 Wiring Diagrams CO2 Fire Protection System Rev. 3

Schematic Diagrams Sh-2

1,2-45N639-3 Wiring Diagrams CO2 Fire Protection System Rev. 15

Schematic Diagrams Sh-3

1,2-45N703-1 Wiring Diagrams - 125V Vital Battery Board I Rev. 85

Single Line Sheet 1

1,2-45N703-2 Wiring Diagram - 125V Vital Board Battery Rev. 45

Board II Single Line Sheet 2

1,2-45N703-3 Wiring Diagrams - 125V Vital Battery Board III Rev. 49

Single Line Sheet 3

1,2-45N703-4 Wiring Diagrams - Vital Battery Board IV Single Rev. 51

Line Sheet 4

1,2-45N749-1 Wiring Diagrams 480V SD Board 1A1-A Single Rev. 54

Line

1,2-47W801-1 Flow Diagram - Main & Reheat Steam Rev. 120

1,2-47W813-1 Flow Diagram-Reactor Cooling System Rev. 58

1-3591A12 Breaker Setting Sheet 480V S/D Bd 1A1 Rev. 3

1-3591A13 Breaker Setting Sheet 480V Shutdown Board Rev. 4

1A1

2-47W809-1 Flow Diagram - Chemical & Volume Control Rev. 77

System

Engineering 22644 Replace Pressurizer PORVs Due to Current 07/18/2018

Changes Valves Being Obsolete and Reaching End of

Life

Engineering Fire Protection Report Rev. 37

Evaluations

Fire Plans Aux 0-734-02 Fire Protection Pre-Plan, Auxiliary Building El. Rev. 9

734.0

Inspection Type Designation Description or Title Revision or

Procedure Date

AUX-0-734.00 Fire Protection Pre-Plan Auxiliary Building El. Rev. 4

734.0

Aux. 0-734-01 Fire Protection Pre-Plan, Auxiliary Building Rev. 10

Elevation 734.0'

CON 0-685-00 Fire Protection Pre-Plan, Control Building El. Rev. 7

685.0'

Miscellaneous FOR 200283 Fire Protection Impairment Permit 7/15/2020

FOR 200302 Fire Protection Impairment Permit 08/03/2020

FOR 202030 Fire Protection Impairment Permit 1/28/2020

QIR-SPQ-SQN-88-182 CO2 Discharge Times Pre-Operational Test 02/11/1988

SQN-VM-4085 Vendor Manual for Protect-O-Wire Special Rev. 1

Hazards Application

SQN-VM-4534/VD-P115- Peerless Pump Vendor Manual Rev. 6

4534

TCE 2020-12 Transient Combustible Permit 05/01/2020

TCE 2020-20 Transient Combustible Permit 10/03/2020

TCE 2020-21 Transient Combustible Permit 10/03/2020

Procedures 0-MI-FPU-000-001 General Maintenance Instructions for Fire Rev. 15

Protection Systems

0-PI-FPU-317-537.Q Fire and Medical Emergency Equipment Rev. 23

Inventory

0-SI-EBT-250-100.1 Vital Battery Quarterly Inspection 4/9/2020

0-SI-EBT-250-100.3 Vital Battery I and Charger Annual Inspection 8/6/2018

0-SI-EBT-250-100.6 U0 Spare 125 v Vital Batt Charger #1 5/24/2016

Performance Test

0-SI-FPU-0026-002.Y Auxiliary and Diesel Generator Building System 09/26/2019

Flow Test

0-SI-FPU-0026-200R Diesel Engine RPM Factory Test Settings (2100 11/11/2000

RPM)

0-SI-FPU-0026-201R Flow Test Surveillance for Motor-Driven Fire 01/19/2018

Pump

0-SI-FPU-013 Fire Detection Panel 0-L-632 Test Rev. 13

0-SI-FPU-026-201R Flow Test Surveillance for Motor-Driven Fire 06/25/2019

Pump

Inspection Type Designation Description or Title Revision or

Procedure Date

0-SI-SXV-000-206.0 U2 PMT for Vlvs During Refueling 4/10/2020

0-SI-SXV-068-201.0 U2 Stroke Pzr PORVs 11/2/2018

119684884 0-SI-FPU-026-200.R Diesel Driven Fire Pump B 06/22/2019

Month Flow Test

2-PI-OPS-000-0033.0 Periodic Stroking of U2 Time Critical Valves 10/28/2018

AOP-N.08 Fire Safe Shutdown

NPG-SPP-01.3 Housekeeping Rev. 8

NPG-SPP-03.6 Fire Protection Program Change Regulatory Rev. 10

Reviews

NPG-SPP-06.9 Testing Programs Rev. 2

NPG-SPP-06.9.1 Conduct of Testing Rev. 12

NPG-SPP-06.9.2 Surveillance Test Program Rev. 9

NPG-SPP-09.3 Plant Modifications and Engineering Change Rev. 33

Control

NPG-SPP-18.4.5 Fire Protection Quality Assurance Rev. 3

SI-237.1 Powerhouse CO2 Fire Protection System Test 09/30/2019

TVA-NQA-PLN89-A Nuclear Quality Assurance Plan (NQAP) Rev. 38

(Quality Assurance Program Description)

Self- DCP-SQN-18-011 Fire Protection Program Regulatory Review for Rev. 0

Assessments DCN-SQN18-011 (Detection)

None Fire Protection Program Health Report 06/30/2020

None System Health Report (System 26) HPFP 03/31/2020

QA-SQ-19-013 Off-Year Fire Protection Assessment 08/23/2019

Work Orders 115342170 0-PI-FPU-026-122.Y HPFP Yard Flow Test 08.06/14

116401835 2-PI-OPS-000-010.B Verification of Remote 12/10/2015

Shutdown Transfer Switches

117675098 2-PI-OPS-000-010.C Verification of Remote 05/23/2017

Shutdown Transfer Switches

118187526 0-PI-FPU-026-122.Y HPFP Yard Flow Test 06/10/2017

118573914 0-SI-FPU-026-202.R Diesel Fire Pump 18 05/31/2018

Month Inspection

118573915 0-SI-FPU-026-200.R Diesel Driven Fire Pump B 07/23/2018

Month Flow Test

Inspection Type Designation Description or Title Revision or

Procedure Date

119198061 2-PI-OPS-000-010.D Verification Of Remote 12/04/2019

Shutdown Transfer Switches

119684878 0-SI-FPU-026-202.R Diesel Fire Pump 18 06/14/2019

Month Inspection

2027921 0-SI-FPU-026-193.M Motor Driven Fire Pump B 02/06/2020

Mini-Flow Test

203140059 2-PI-OPS-000-010.A Verification of Remote 05/02/2020

Shutdown Transfer Switches

20403941 0-SI-FPU-026-192.M Motor Driven Fire Pump A 03/12/2020

Operability Test

20469066 0-SI-FPU-026-193.M Motor Driven Fire Pump B 04/09/2020

Mini-Flow Test

20501411 0-SI-FPU-026-192.M Motor Driven Fire Pump A 04/16/2020

Operability Test

WO119605602 Power House CO2 Fire Protection System test

WO120314291 Visual Inspection of Fire Dampers for 0-SI-FPU-

031-001R

2