IR 05000327/2020012

From kanterella
Jump to navigation Jump to search
Plants - Triennial Fire Protection Inspection Report 05000327/2020012 and 05000328/2020012
ML20294A177
Person / Time
Site: Sequoyah  
Issue date: 10/20/2020
From: Scott Shaeffer
NRC/RGN-II/DRS/EB2
To: Jim Barstow
Tennessee Valley Authority
References
IR 2020012
Download: ML20294A177 (15)


Text

October 20, 2020

SUBJECT:

SEQUOYAH NUCLEAR PLANTS - TRIENNIAL FIRE PROTECTION INSPECTION REPORT 05000327/2020012 AND 05000328/2020012

Dear Mr. Barstow:

On September 9, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Sequoyah Nuclear Plants. On August 31, 2020, the NRC inspectors discussed the results of this inspection with Mr. Scott Hunnewell and other members of your staff. The results of this inspection are documented in the enclosed report.

One finding of very low safety significance (Green) is documented in this report. This finding involved a violation of NRC requirements. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region II; the Director, Office of Enforcement; and the NRC Resident Inspector at Sequoyah Nuclear Plants.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region II; and the NRC Resident Inspector at Sequoyah Nuclear Plants. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Scott M. Shaeffer, Chief Engineering Br 2 Div of Reactor Safety

Docket Nos. 05000327 and 05000328 License Nos. DPR-77 and DPR-79

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000327 and 05000328

License Numbers:

DPR-77 and DPR-79

Report Numbers:

05000327/2020012 and 05000328/2020012

Enterprise Identifier: I-2020-012-0012

Licensee:

Tennessee Valley Authority

Facility:

Sequoyah Nuclear Plants

Location:

Soddy Daisy

Inspection Dates:

June 07, 2020 to August 28, 2020

Inspectors:

P. Braaten, Reactor Inspector

J. Dymek, Reactor Inspector

J. Montgomery, Senior Reactor Inspector

D. Strickland, Reactor Inspector

Approved By:

Scott M. Shaeffer, Chief

Engineering Br 2

Div of Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a triennial fire protection inspection at Sequoyah Nuclear Plants, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Inadequate Surveillance Procedure Allowed Preconditioning of Alternative Safe Shutdown Transfer Switches and Controls Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000328/2020012-01 Open/Closed

[H.1] -

Resources 71111.21N.

The inspectors identified a Green finding and associated Non-cited Violation (NCV) of Sequoyah Unit 2 Operating License Condition 2.C(13) when the licensee failed to comply with procedure NPG-SPP-06.9.2, Surveillance Test Program," by providing operators with inadequate surveillance procedures that preconditioned alternative safe shutdown transfer switches and controls.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

===71111.21N.05 - Fire Protection Team Inspection (FPTI)

Structures, Systems, and Components (SSCs) Credited for Fire Prevention, Detection, Suppression, or Post-Fire Safe Shutdown Review (IP Section 03.01)===

The inspectors verified that the following systems credited in the approved fire protection program could perform their licensing basis function:

a. Review deficiencies or open fire protection impairments for the selected system, including any temporary modifications, operator workarounds, or compensatory measures.

b. Verify that operator actions can be accomplished as assumed in the licensees FHA, or as assumed in the licensees fire probabilistic risk assessment (FPRA)analysis and SSA.

c. Review repetitive or similar maintenance work requests which could be an indicator of a design deficiency and could affect the ability of the components to perform their functions, when needed.

d. Ensure that post maintenance and/or surveillance activities are performed as scheduled.

e. Perform a walkdown inspection to identify equipment alignment discrepancies.

Inspect for deficient conditions such as corrosion, missing fasteners, cracks, and degraded insulation.

f. Ensure the selected SSCs that are subject to aging management review (AMR)pursuant to 10 CFR Part 54 are being managed for aging (e.g., loss of material, cracking, reduction of heat transfer) in accordance with appropriate aging management programs. Verify that the licensees aging management program activities (such as, Fuel Oil Analysis or Selective Leaching Aging Management Program) associated with FP equipment are being implemented.

g. If a review of operating experience issues will be completed for the selected inspection sample, verify that the licensee adequately reviewed and dispositioned the operating experience in accordance with their processes.

The team selected the following SSCs as samples.

  • Unit 1 12v DC Power System
  • Cable Tray Water Spray System in 1B2-B and 2A2-A 480v Shutdown Board Rooms
  • CO2 System in Unit 1 Auxiliary Instrument Room and Required Fire/Smoke Dampers

Fire Protection Program Administrative Controls (IP Section 03.02) (1 Sample)

The inspectors verified that the following fire protection program administrative controls were implemented in accordance with the current licensing basis:

  • Combustible Control Program

Fire Protection Program Changes/Modifications (IP Section 03.03) (1 Sample)

The inspectors reviewed the following changes to ensure that they did not constitute an adverse effect on the ability to safely shutdown post-fire and to verify that fire protection program documents and procedures affected by the changes were updated.

  • Engineering Modification to Replace Unit 1 Pressurizer Power Operated Relief Valves

INSPECTION RESULTS

Inadequate Surveillance Procedure Allowed Preconditioning of Alternative Safe Shutdown Transfer Switches and Controls Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems

Green NCV 05000328/2020012-01 Open/Closed

[H.1] -

Resources 71111.21N.0 The inspectors identified a Green finding and associated Non-cited Violation (NCV) of Sequoyah Unit 2 Operating License Condition 2.C(13) when the licensee failed to comply with procedure NPG-SPP-06.9.2, Surveillance Test Program," by providing operators with inadequate surveillance procedures that preconditioned alternative safe shutdown transfer switches and controls.

Description:

To support inspection of the Unit 2 Pressurizer PORVs and their credit for fire safe shutdown, inspectors reviewed records for the last completion of surveillance test procedure 2-PI-OPS-000-010.D, "Verification of Remote Shutdown Transfer Switches." This test procedure verifies the operation of remote shutdown transfer switches and controls that are credited to meet the alternative shutdown requirements of 10 CFR 50, Appendix R,Section III.G.3. In reviewing this surveillance test procedure, inspectors discovered a sequence of test steps that appeared to constitute preconditioning of the Pressurizer PORVs under surveillance.

For PORV 2-PCV-68-334, after operators receive authorization from the SRO to perform the surveillance, the test directs operators to cycle transfer switch 2-XS-68-334C at least three times to clean contacts. The next step is to cycle control switch 2-HS-68-334C at least three times to clean contacts.

NRC Technical Guidance Part 9900, Maintenance - Preconditioning of Structures, Systems, and Components Before Determining Operability, gives guidance on the acceptability of preconditioning SSCs before the performance of surveillance testing. This document states that the NRC expects surveillance and testing processes of SSCs to be evaluated in an as-found condition. This guidance is echoed in TVA fleet procedure NPG-SPP-06.9.2, Surveillance Test Program. NPG-SPP-06.9.2 states, Surveillance sequences and alignment activities that are implemented prior to a surveillance test should be intended to facilitate testing or prevent unnecessary wear and damage to equipment and/or systems.

Test procedure steps that exercise equipment prior to testing activities are not allowed unless they provide a specific benefit, such as improved safety, reduced wear and tear, or facilitate better test methods. The potential of such activities to unintentionally mask degradation must be considered. Cycling electrical contacts repeatedly to clean them does not specifically facilitate test performance or provide any specific benefit. Further, cleaning the contacts before performing the continuity checks and resistance readings of the surveillance could unintentionally mask degradation of the circuit and the contacts.

Inspectors noted that the steps for PORV 2-PCV-68-340 were structured the same. The last performance of the surveillance for these two valves was November 23, 2018. Inspectors also reviewed the test procedure for other examples of this test sequence, and found that the surveillances for the 4 Main Steam Isolation Valves, the main Charging Header flow control valve (FCV) 62-93, multiple 6.9kV Shutdown Board feeder breakers, and the FCV for RHR Hot Leg injection to loops 1 & 3 (2-FCV-63-172) all contained the same, or similar steps to clean the electrical contacts before performing the continuity checks and resistance readings of the surveillance.

Corrective Action References: CR 1616116

Performance Assessment:

Performance Deficiency: The licensees failure to establish adequate surveillance test instructions in accordance with TVA fleet procedure NPG-SPP-06.9.2 was a performance deficiency. Specifically, surveillance test procedure 2-PI-OPS-000-010.D directed operators to cycle transfer and control switches to clean the contacts before performing the continuity checks and resistance readings to determine whether the surveillance acceptance criteria had been met. Those procedure steps constitute unacceptable preconditioning of the SSCs.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Protection Against External Factors attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the failure to determine the as-found condition of the transfer switches and controls reduced the ability of the licensee to provide reasonable assurance that the licensee's alternative shutdown capability would have been available between tests.

Significance: The inspectors assessed the significance of the finding using Appendix F, Fire Protection and Post - Fire Safe Shutdown SDP. Using IMC 0609, Appendix F, Attachment 1, the inspectors determined the issue was of very low safety significance (Green) because the finding did not adversely affect the ability to reach and maintain hot shutdown/hot standby conditions using the credited safe shutdown success path (Question 1.4.7-C).

Cross-Cutting Aspect: H.1 - Resources: Leaders ensure that personnel, equipment, procedures, and other resources are available and adequate to support nuclear safety.

Specifically, leaders did not ensure that a set of procedures were in place that ensured preconditioning did not take place.

Enforcement:

Violation: Sequoyah Unit 2 Operating License Condition 2.C(13) requires, in part, that TVA shall implement and maintain in effect all provisions of the approved fire protection program referenced in Sequoyah Nuclear Plant's Final Safety Analysis Report (FSAR). Section 9.5.1 of the FSAR states that the Fire Protection System and fire protection features are described in the Fire Protection Report. Part II of the Fire Protection Report is the Fire Protection Plan, and Section 6.0 of the Fire Protection Plan states that the QA program for fire protection uses the applicable parts of the TVA Nuclear Quality Assurance Plan. Fleet procedure NPG-SPP-18.4.5, "Fire Protection QA Program" requires that activities shall be conducted in accordance with the applicable TVA Nuclear Power Group (NPG) programs to provide controls for modification, installation, surveillance, maintenance, operation, and program administration. The NPG Test Program is described in NPG-SPP-06.9, and child procedures.

NPG-SPP-06.9.2, "Surveillance Test Program," requires that Surveillance sequences and alignment activities that are implemented prior to a surveillance test should be intended to facilitate testing or prevent unnecessary wear and damage to equipment and/or systems.

Test procedure steps that exercise equipment prior to testing activities are not allowed unless they provide a specific benefit, such as improved safety, reduced wear and tear, or facilitate better test methods. The potential of such activities to unintentionally mask degradation must be considered.

Contrary to the above, from August 3, 2018 to June 12, 2020, the licensee used a surveillance test procedure that directed operators to exercise equipment prior to surveillance testing activities, without a specific benefit.

Enforcement Action: This violation is being treated as an non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On August 31, 2020, the inspectors presented the triennial fire protection inspection results to Mr. Scott Hunnewell and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21N.05 Calculations

26D54EPMABBIMPFHA

Sequoyah Nuclear Plant - Fire Hazards Analysis

Calculation

Rev. 145

2-92743

Seismic Analysis of 24 Ton CO2 Tank

Rev. 0

APS2068

Appendix R - Post Fire RCS Cooldown and

Depressurization

Rev. 2

B25850329800

Fire Protection Pipe Support Calculation for

Cantilevered 1-inch Pipe

03/27/1985

D2SDJ-P213350

Analysis of the Auxiliary Power System for 10 CFR 50, Appendix R

Rev. 64

EDQ0009992017000385FHA Sequoyah Nuclear Plant - Fire Hazards Analysis

Calculation -

FSSD Compliance Mitigation Strategy

Rev. 3

MDN000NA2019000628

SQN Fire PRA - Fire Risk Quantification

Rev. 1

MDQ0026-97001

Motor Driven Fire Pump Replacement Sprinkler

Calculation

06/25/2018

MDQ0026-97001B

Control Valve(s) 0FCV-26-151 & 0FCV-2066

HPFP Sprinkler Calculation

2/03/2013

MDQ0026-97001D

Flow Testing to Support Pipe Degradation

2/24/1997

MDQ0026-980041

HPFP Sprinkler Calculation, Boric Acid Tank

Room, 690.0' AB, Sprinkler Addition

2/16/1998

SQN-APPR-1

Analysis of AC/DC Instrument & Control (I&C)

Power Systems to Identify Associated Circuits -

CFR 50 Appendix R

Rev. 20

SQN-APS-003

480VAC APS Class 1E Load Coordination

Study

Rev. 108

SQN-DC-V-10.7

Design Criteria Document - 10CFR50, Appendix R, Type I,II, & III Circuits

Rev. 4

SQN-DC-V-24.0

Design Criteria Document - Fire Protection for

Appendix R Requirements

Rev. 10

SQN-DC-V-43.0

Design Criteria Document - High-Pressure Fire

Protection Water Supply System

Rev. 9

SQN-DC-V-7.5

Design Criteria Document - Fire Protection

Rev. 14

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Systems

SQN-DC-V-7.6

Design Criteria Document - Proprietary

Protective Signaling Systems for Fire Alarm and

Supervisory Service

Rev. 4

SQNAPPR10

Appendix R Hot Short Analysis for Non

High/Low RCS Pressure Interfaces and Non-

High Impact Circuits

Rev. 25

XDN00000020110001

OMAs for 10 CFR Appendix R III.G.2

Compliance

1/27/2014

Corrective

Action

Documents

1072726

Appendix R Fire Concern Regarding Smoke

Migration

8/7/2019

1440822

Appendix R Control Building Issue for RHR

Pumps

08/20/2018

1581033

NRC Triennial Fire Protection Inspection (TFPI)

Readiness Self-Assessment

2/24/2020

1610002

Appendix R Lighting Deficiency Created by

Design Change

6/8/2020

27936

Light heads misaimed

8/4/2020

Corrective

Action

Documents

Resulting from

Inspection

1590413

SA-1581033 2020 TFPI Deficiencies in testing

for remote shutdown transfer switches

06/09/2020

1613748

Alternate shutdown transfer switch testing

deficiencies

06/10/2020

1616116

NRC identified issue related to transfer switch

testing

06/12/2020

CR1632843

Fire Door C-22 Missing Screws from Plate on

Door

08/25/2020

CR1632915

Abandon Office Chair Staged in Auxiliary

Building Equipment Room

8/26/2020

Drawings

1,2 45W1699-50

Conduit & Grounding, Floor El.734.0, Details

Sheet 12

Rev. 3

1,2 46W-455-1

Architectural Door Frames and Details

Rev. 1

1,2 46W454-4

Architectural Door and Hardware Schedule

Rev. 1

1,2 46W454-7

Architectural Door and Hardware Schedule

Rev. 0

1,2 47W494-4

Fire Protection Compartmentation-Fire Cells

Rev. 15

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Plan El. 734.0'

1,2 47W494-6

Fire Protection Compartmentation-Fire Cells,

Plan El. 669.0' & 685.0'

Rev. 7

1,2 47W850-27

Flow Diagram-High Pressure Fire Protection

Rev. 11

1,2-45N639-1

Wiring Diagrams CO2 Fire Protection System

Schematic Diagrams Sh-1

Rev. 3

1,2-45N639-2

Wiring Diagrams CO2 Fire Protection System

Schematic Diagrams Sh-2

Rev. 3

1,2-45N639-3

Wiring Diagrams CO2 Fire Protection System

Schematic Diagrams Sh-3

Rev. 15

1,2-45N703-1

Wiring Diagrams - 125V Vital Battery Board I

Single Line Sheet 1

Rev. 85

1,2-45N703-2

Wiring Diagram - 125V Vital Board Battery

Board II Single Line Sheet 2

Rev. 45

1,2-45N703-3

Wiring Diagrams - 125V Vital Battery Board III

Single Line Sheet 3

Rev. 49

1,2-45N703-4

Wiring Diagrams - Vital Battery Board IV Single

Line Sheet 4

Rev. 51

1,2-45N749-1

Wiring Diagrams 480V SD Board 1A1-A Single

Line

Rev. 54

1,2-47W801-1

Flow Diagram - Main & Reheat Steam

Rev. 120

1,2-47W813-1

Flow Diagram-Reactor Cooling System

Rev. 58

1-3591A12

Breaker Setting Sheet 480V S/D Bd 1A1

Rev. 3

1-3591A13

Breaker Setting Sheet 480V Shutdown Board

1A1

Rev. 4

2-47W809-1

Flow Diagram - Chemical & Volume Control

System

Rev. 77

Engineering

Changes

2644

Replace Pressurizer PORVs Due to Current

Valves Being Obsolete and Reaching End of

Life

07/18/2018

Engineering

Evaluations

Fire Protection Report

Rev. 37

Fire Plans

Aux 0-734-02

Fire Protection Pre-Plan, Auxiliary Building El.

734.0

Rev. 9

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

AUX-0-734.00

Fire Protection Pre-Plan Auxiliary Building El.

734.0

Rev. 4

Aux. 0-734-01

Fire Protection Pre-Plan, Auxiliary Building

Elevation 734.0'

Rev. 10

CON 0-685-00

Fire Protection Pre-Plan, Control Building El.

685.0'

Rev. 7

Miscellaneous

FOR 200283

Fire Protection Impairment Permit

7/15/2020

FOR 200302

Fire Protection Impairment Permit

08/03/2020

FOR 202030

Fire Protection Impairment Permit

1/28/2020

QIR-SPQ-SQN-88-182

CO2 Discharge Times Pre-Operational Test

2/11/1988

SQN-VM-4085

Vendor Manual for Protect-O-Wire Special

Hazards Application

Rev. 1

SQN-VM-4534/VD-P115-

4534

Peerless Pump Vendor Manual

Rev. 6

TCE 2020-12

Transient Combustible Permit

05/01/2020

TCE 2020-20

Transient Combustible Permit

10/03/2020

TCE 2020-21

Transient Combustible Permit

10/03/2020

Procedures

0-MI-FPU-000-001

General Maintenance Instructions for Fire

Protection Systems

Rev. 15

0-PI-FPU-317-537.Q

Fire and Medical Emergency Equipment

Inventory

Rev. 23

0-SI-EBT-250-100.1

Vital Battery Quarterly Inspection

4/9/2020

0-SI-EBT-250-100.3

Vital Battery I and Charger Annual Inspection

8/6/2018

0-SI-EBT-250-100.6

U0 Spare 125 v Vital Batt Charger #1

Performance Test

5/24/2016

0-SI-FPU-0026-002.Y

Auxiliary and Diesel Generator Building System

Flow Test

09/26/2019

0-SI-FPU-0026-200R

Diesel Engine RPM Factory Test Settings (2100

RPM)

11/11/2000

0-SI-FPU-0026-201R

Flow Test Surveillance for Motor-Driven Fire

Pump

01/19/2018

0-SI-FPU-013

Fire Detection Panel 0-L-632 Test

Rev. 13

0-SI-FPU-026-201R

Flow Test Surveillance for Motor-Driven Fire

Pump

06/25/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

0-SI-SXV-000-206.0

U2 PMT for Vlvs During Refueling

4/10/2020

0-SI-SXV-068-201.0

U2 Stroke Pzr PORVs

11/2/2018

119684884

0-SI-FPU-026-200.R Diesel Driven Fire Pump B

Month Flow Test

06/22/2019

2-PI-OPS-000-0033.0

Periodic Stroking of U2 Time Critical Valves

10/28/2018

AOP-N.08

Fire Safe Shutdown

NPG-SPP-01.3

Housekeeping

Rev. 8

NPG-SPP-03.6

Fire Protection Program Change Regulatory

Reviews

Rev. 10

NPG-SPP-06.9

Testing Programs

Rev. 2

NPG-SPP-06.9.1

Conduct of Testing

Rev. 12

NPG-SPP-06.9.2

Surveillance Test Program

Rev. 9

NPG-SPP-09.3

Plant Modifications and Engineering Change

Control

Rev. 33

NPG-SPP-18.4.5

Fire Protection Quality Assurance

Rev. 3

SI-237.1

Powerhouse CO2 Fire Protection System Test

09/30/2019

TVA-NQA-PLN89-A

Nuclear Quality Assurance Plan (NQAP)

(Quality Assurance Program Description)

Rev. 38

Self-

Assessments

DCP-SQN-18-011

Fire Protection Program Regulatory Review for

DCN-SQN18-011 (Detection)

Rev. 0

None

Fire Protection Program Health Report

06/30/2020

None

System Health Report (System 26) HPFP

03/31/2020

QA-SQ-19-013

Off-Year Fire Protection Assessment

08/23/2019

Work Orders

115342170

0-PI-FPU-026-122.Y HPFP Yard Flow Test

08.06/14

116401835

2-PI-OPS-000-010.B Verification of Remote

Shutdown Transfer Switches

2/10/2015

117675098

2-PI-OPS-000-010.C Verification of Remote

Shutdown Transfer Switches

05/23/2017

118187526

0-PI-FPU-026-122.Y HPFP Yard Flow Test

06/10/2017

118573914

0-SI-FPU-026-202.R Diesel Fire Pump 18

Month Inspection

05/31/2018

118573915

0-SI-FPU-026-200.R Diesel Driven Fire Pump B

Month Flow Test

07/23/2018

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

119198061

2-PI-OPS-000-010.D Verification Of Remote

Shutdown Transfer Switches

2/04/2019

119684878

0-SI-FPU-026-202.R Diesel Fire Pump 18

Month Inspection

06/14/2019

2027921

0-SI-FPU-026-193.M Motor Driven Fire Pump B

Mini-Flow Test

2/06/2020

203140059

2-PI-OPS-000-010.A Verification of Remote

Shutdown Transfer Switches

05/02/2020

20403941

0-SI-FPU-026-192.M Motor Driven Fire Pump A

Operability Test

03/12/2020

20469066

0-SI-FPU-026-193.M Motor Driven Fire Pump B

Mini-Flow Test

04/09/2020

20501411

0-SI-FPU-026-192.M Motor Driven Fire Pump A

Operability Test

04/16/2020

WO119605602

Power House CO2 Fire Protection System test

WO120314291

Visual Inspection of Fire Dampers for 0-SI-FPU-

031-001R