IR 05000327/2021010
| ML21112A344 | |
| Person / Time | |
|---|---|
| Site: | Sequoyah |
| Issue date: | 04/21/2021 |
| From: | James Baptist NRC/RGN-II/DRS/EB1 |
| To: | Jim Barstow Tennessee Valley Authority |
| References | |
| IR 2021010 | |
| Download: ML21112A344 (14) | |
Text
April 21, 2021
SUBJECT:
SEQUOYAH NUCLEAR PLANT, UNITS 1 & 2 - NRC INSPECTION REPORT 05000327/2021010 AND 05000328/2021010
Dear Mr. Barstow:
On March 12, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Sequoyah Nuclear Plant, Units 1 & 2. On April 14, 2021, the NRC inspectors discussed the results of this inspection with Mr. John Taylor - Senior Manager SQN Design Engineering and other members of your staff. The results of this inspection are documented in the enclosed report.
No NRC-identified or self-revealing findings were identified during this inspection.
A licensee-identified violation which was determined to be of very low safety significance and Severity Level IV is documented in this report. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.
If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:
Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region II; the Director, Office of Enforcement; and the NRC Resident Inspector at Sequoyah Nuclear Plant, Units 1 & 2.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA/
James B. Baptist, Chief Engineering Branch 1 Division of Reactor Safety Docket Nos. 05000327 and 05000328 License Nos. DPR-77 and DPR-79
Enclosure:
As stated
Inspection Report
Docket Numbers:
05000327 and 05000328
License Numbers:
Report Numbers:
05000327/2021010 and 05000328/2021010
Enterprise Identifier: I-2021-010-0035
Licensee:
Tennessee Valley Authority
Facility:
Sequoyah Nuclear Plant, Units 1 & 2
Location:
Soddy Daisy, TN
Inspection Dates:
March 08, 2021 to March 12, 2021
Inspectors:
T. Fanelli, Sr. Construction Inspector
M. Greenleaf, Reactor Inspector
N. Morgan, Reactor Inspector
D. Terry-Ward, Construction Inspector
Approved By:
James B. Baptist, Chief
Engineering Branch 1
Division of Reactor Safety
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a NRC inspection at Sequoyah Nuclear Plant, Units 1 & 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information. A licensee-identified non-cited violation is documented in report section: 71111.17T.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), inspectors were directed to begin telework. In addition, regional baseline inspections were evaluated to determine if all or portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on site. The inspections documented below met the objectives and requirements for completion of the IP.
REACTOR SAFETY
71111.17T - Evaluations of Changes, Tests, and Experiments Sample Selection (IP Section 02.01)
The inspectors reviewed the following evaluations, screenings, and/or applicability determinations for 10 CFR 50.59 from [enter dates].
(1)10 CFR 50.59 Evaluation - DCN SQN-19-308, Diesel Generator 2A-A VORD Removal, Rev. 2 (2)10 CFR 50.59 Evaluation - ECP 100098, NIS Time Delay Relay Project, Rev. 2 (3)10 CFR 50.59 Evaluation - DCN 100069, Upgrade the Turbine Driven Auxiliary Feedwater Speed Governor and Flow Controller, Rev. 3 (4)10 CFR 50.59 Evaluation - DCN D23216, 1,2-HS-062-0104C, -108C, -003-0118C, -
0128C, -068-0341AC, -0341DC, Admin. Change #04, Rev. A (5)10 CFR 50.59 Evaluation - D22501, Increase the Capability of 2-FCV-63-72 & -73 to Operate Under Differential Pressure, Rev. A (6)10 CFR 50.59 Evaluation - DCN D23085, Replace Breaker Handle, Breaker Operating Mechanism and Remove Kirk-Key Interlocks, Rev. A (7)10 CFR 50.59 Screen - D23623-01, Charging Flow Isolation Valve 1-FCV-062-0091-B, Rev. A (8)10 CFR 50.59 Screen - EC 23699-03, Change to Allow Flow Element Removal, Rev.
B (9)10 CFR 50.59 Screen - DCN 23885, Issue "Emergency and Abnormal Operating Procedure Setpoints" Calculation SQS20110, Revision 30, Design Output, Rev. 0 (10)10 CFR 50.59 Screen - DCN 22778, Auxiliary Feedwater Min-Flow Protection, Rev. A (11)10 CFR 50.59 Screen - DCN 21892, Install CCUS 2-XC-43-55, -58, -61, and -64 in the Circuit Before Solenoid Valves 2-FSV-43-55, -58, -61, and -64 to Regulate Current And Reduce Heat Rise, Rev. A (12)10 CFR 50.59 Screen - ECP 10068-01, Motor Operated Potentiometers (MOP)
Replacement, Rev. 2 (13)10 CFR 50.59 Screen - ECP SQN-19-785, ECP That Will Eliminate the Need for the Current SBO Diesel Generators by Crediting the FLEX Program, Rev. 1 (14)10 CFR 50.59 Screen - DCN SQN-19-856, Replace Obsolete EQ Transmitter 2-FT-3-163-B, Rev. 1 (15)10 CFR 50.59 Screen - DCN 23813, Replace Steam Generator Blowdown Containment Isolation Sample Valves 1- & 2-FSV-043-0055-B, -0058-A, -0061-B, -
0064-A, Rev. 5 (16)10 CFR 50.59 Screen - DEC SQN-19-699, EQ Binder Revisions for SG Level Transmitter 1-LT-003-0097-G, Rev. 0 (17)10 CFR 50.59 Screen - EDC E21192, WO 09-779231-000, Replace solenoid (per Engineering request), Per MI-10.38 and EDC E21192 with appropriate replacement, acceptance by OPS 6/27/19, Rev. A (18)10 CFR 50.59 Screen - DCN 22346, Replace 480V Board Room Air Conditioners &
Associated Equipment, Rev A (19)10 CFR 50.59 Screen - DEC SQN-18-226, Limit Switch Variation for 2-FCV-67-91, Rev. 1 (20)10 CFR 50.59 Screen - DEC 100075, B Train Shutdown Board Cleaning Maintenance Crosstie, Rev.
INSPECTION RESULTS
Licensee-Identified Non-Cited Violation 71111.17T This violation of very low safety significance was identified by the licensee and has been entered into the licensee corrective action program and is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.
Violation: The licensee performed design change DCN SQN-19-308 which removed the Voltage Overshoot Reduction Device (VORD) from the 2A-A Emergency Diesel Generator (EDG) after the VORD was damaged in 2015. The function of the VORD is to reduce the overvoltage developed by the EDG's voltage regulation system during sequence loading during design basis accidents. The DCN incorrectly determined that the VORD removal was acceptable with respect to their licensing and design bases acceptance criteria.
The station correctly determined that the licensee's commitment to Regulatory Guide (RG)1.9, "Selection, Design, and Qualification of Diesel-Generator Units Used as Onsite Electric Power Systems at Nuclear Power Plants," was a commitment to a Revision 0 of RG 1.9 with the exception of the portion of the RG related to load sequencing. The licensee had been allowed by the NRC to deviate from Rev. 0's 40% load sequence interval acceptance criteria to Rev. 1's acceptance criteria of 60% (as described in NUREG-1232). The licensee determined that they had incorrectly determined that they were allowed to use a provision of RG 1.9 Rev. 1 to exceed the 60% acceptance criteria. To support the modification, the licensee also determined that they had incorrectly altered Section 8.3.1.2.1 of their Updated Final Safety Analysis Report (UFSAR) stating that: "A greater percentage of the time interval may be used if it can be justified by analysis."
10 CFR 50.59(c)(2)(ii) required, in part, that a licensee to obtain a license amendment pursuant to Section 50.90 prior to implementing a proposed change if the change would result in a more than minimal increase in the likelihood of occurrence of a malfunction of a structure, system, or component (SSC) important to safety previously evaluated in the final safety analysis report (as updated).
Contrary to the above, since the completion of DCN SQN-19-308, Diesel Generator 2A-A VORD Removal, in June of 2019, the licensee failed to obtain a license amendment prior to implementing the DCN which allowed the emergency diesel generator to exceed its licensing basis acceptance criteria to which they were committed, thereby resulting in a more than minimal increase in the likelihood of occurrence of a malfunction of the emergency diesel generator 2A-A. Specifically, the licensee was committed to Regulatory Guide (RG) 1.9, Selection, Design, and Qualification of Diesel-Generator Units Used as Onsite Electric Power Systems at Nuclear Power Plants, Rev. 0, with an allowance to exceed 10% of nominal voltage for up to 60% of the load sequence interval, and the licensee inappropriately determined they could apply portions of RG 1.9, Rev. 1, instead of the specific deviation from Rev. 0 criteria that was previously accepted by the NRC without prior approval.
Significance/Severity: Green. Severity Level IV. The inspectors assessed the significance of the finding using SDP Appendix A, The Significance Determination Process (SDP) for Findings At-Power, Exhibit 2 - Mitigating Systems Screening Questions, dated January 1, 2021. The inspectors determined that the finding was of very low safety significance (Green)as the finding was a deficiency affecting the design or qualification of the emergency diesel generator 2A-A, but the emergency diesel generator maintained its operability. In accordance with Section 6.1.d.2 of the NRC Enforcement Policy (dated January 15, 2020) this violation is categorized as Severity Level IV because the resulting changes were evaluated by the SDP as having very low safety significance (i.e., green finding).
Corrective Action References: CR
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On April 14, 2021, the inspectors presented the NRC inspection results to Mr. John Taylor - Senior Manager SQN Design Engineering and other members of the licensee staff.
- On March 12, 2021, the inspectors presented the Onsite Exit inspection results to Thomas Marshall - Site Vice President Sequoyah Nuclear Plant and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
71111.17T Calculations
1-FCV-62-091
Documentation of Design Basis Review, Required
Thrust Cale and Valve and Actuator Capability
Assessment for 1-FCV-62-091 (GL 89-10)
Rev. 6
31C-D053-EPM-RG-
060987
HVAC Equipment Requirements Evaluation: Turbine
Driven Auxiliary Feedwater Pump Room
Rev. 6
DS-M18.2.21
Motor Operated Valve Thrust and Torque Calculations
07/24/2020
ED00009992018000092
Turbine Driven Auxiliary Feedwater Dedication,
Qualification, and Software Verification & Validation
Documentation
Rev. 0
MDQ0000032015000278 Auxiliary Feedwater Pump Alternate Min-flow Relief
Valve Sizing
Rev. 0
N2-62-7A
Summary of Piping Analysis N2-62-7A
NDQ0063980038
RWST and Containment RHR Sump Safety and
Operational Limits, RWST Setpoint Required Accuracy
and LBLOCA, SBLOCA Sump Minimum Levels
Rev. 12
SQN-CPS-051
Circuit Protection Device Evaluation
Rev. 68
SQN-CPS-057
Vital Control Power System Loading Channel I And
Continuous Loading Evaluation of Protective Devices
in the 120v Ac Vital Instrument Power Boards
Rev. 103
SQN-CPS-058
Vital Control Power System Loading Channel II and
Continuous Loading Evaluation of Protective Devices
in the 120v Ac Vital Instrument Power Boards
Rev. 119
SQN-CPS-059
Vital Control Power System Loading Channel III and
Continuous Loading Evaluation of Protective Devices
in the 120v Ac Vital Instrument Power Boards
Rev. 103
SQN-CPS-060
Vital Control Power System Loading Channel IV and
Continuous Loading Evaluation of Protective Devices
in the 120v Ac Vital Instrument Power Boards
Rev. 109
SQN-E3-002
Diesel Generator Loading Analysis
Rev. 63
SQN-E3-011, App. K
Overvoltage Analysis
01/22/1988
SQN-EEB-ETR
Demonstrated Accuracy Calculation ETR
Rev. 2
SQN-MEB-2-FCV-67-
Documentation of Design Basis Review, Required
Rev. 1
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
091
Thrust Call and Valve & Actuator Capability
Assessment For 2-FCV-67-091
SQS20110
Emergency and Abnormal Operating Procedure
Setpoints
Rev. 30
TIECS55
Summary of Harsh Environment Conditions for
Sequoyah Nuclear Plant
Rev. 38
Corrective Action
Documents
0848636
1468371
1380153
283446
1084295
1084294
1076269
1076179
1064785
1064736
1049129
1464713
1192952
260178
0801415
1104481
1641119
Corrective Action
Documents
Resulting from
Inspection
CR 1677990
SQN 50.59 2021010 CRFSAR SQEP-EEB-88-018
Cannot be Found
03/11/2021
CR 1678167
NRC SQN 59.59 2021010 inspection
03/11/2021
Drawings
0-47W610-46-1
Mechanical Control Diagram Feedwater Control
System
04/29/2020
1, 2-45N765-6
Wiring Diagrams, 6900 Shutdown AUX power,
Schematic Diagram
Rev. 6
1,2-45W880-28A
Conduit & Grounding Penetration Sealing
Rev. 8
1,2-88405-2
Forged Bolted Bonnet Primary Nuclear Motor
Operated Gate Valve
Rev. 0
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
1-45N1635
Wiring Diagrams, Local Instrument Panels, Connection
Diagrams, SH 3
Rev. 4
1-47A941-73
Trust Requirements for Motor Operated Valve 1-FCV-
2-091
Rev. 4
2-45W2614-9
Wiring Diagrams Auxiliary Feedwater Pump & Turbine
Connection Diagrams
10/20/2020
2-45W646-6
Wiring Diagrams Feedwater Pump & Turbines
Schematic Diagrams
04/29/2020
Engineering
Changes
DCN 100096
NIS Time Delay Relay Project
Rev. 2
DCN 22346
Replace 480V Board Room Air Conditioners &
Associated Equipment (See attached)
Rev. A
DCN D23085
Replace breaker handle, breaker operating
mechanism and remove Kirk-Key Interlocks
Rev. A
DCN D23216
1,2-HS-062-0104C, -108C, -003-0118C, -0128C, -068-
0341AC, -0341DC, Admin. Change #04
DCN SQN-19-308
2A-A VORD Removal
Rev. 2
DCN SQN-19-856-B
Replace Obsolete EQ Transmitter 2-FT-3-168-
Rev. 1
DCN-D21892
Install CCUS 2-XC-43-55, -58, -61, AND -64 in the
Circuit Before Solenoid Valves 2-FSV-43-55, -58, -61,
and -64 to Regulate Current and Reduce Heat Rise
Rev. A
DEC 10075
B Train Shutdown Board Cleaning Maintenance
Crosstie
Rev. 0
DEC SQN-18-226
Limit Switch Variation for 2-FCV-67-91
Rev. 1
DEC SQN-19-699
EQ Binder revisions for SG Level Transmitter 1-LT-
003-0097-G
Rev. 0
Replace Steam Generator Blowdown Containment
Isolation Sample Valves 1- & 2-FSV-043-0055-B, -
0058-A, -0061-B, -0064-A
Rev. 5
ECP 100068
Motor Operated Potentiometers (MOPs) Replacement
for the Emergency Diesel Generators (EDGs)
Rev. 2
ECP 23085-02
Replace breaker handle, breaker operating
mechanism and remove Kirk-Key Interlocks
06/27/2019
ECP 23085-04
Replace breaker handle, breaker operating
mechanism and remove Kirk-Key Interlocks
06/25/2019
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
ECP SQN-19-785
ECP That Will Eliminate the Need for the Current SBO
Diesel Generators Creating the FLEX Program
Rev. 1
EDC E21195
ASCO has discontinued the production of 206-380 &
206-381
Rev. A
SQN-0-2015-082-001
Functionally Disabling VORD and DC amp meter for
Emergency Diesel 2A-A
Rev. 0
Miscellaneous
NRC Docket Nos. 50-327 and 328, Renewed Facility
Operating License Nos. DPR-77 and DPR-79,
Request to Modify Essential Raw Cooling Water Motor
Control Center Breakers and to Revise the Updated
Final Safety Analysis Report Sequoyah Nuclear Plant
Units 1 and 2 (SQN-TS-17-04)
03/09/2018
Sequoyah Nuclear Plant, Units 1 And 2-Issuance of
Amendments Re: Request To Modify Essential Raw
Cooling Water Motor Control Center Breakers And To
Revise The Updated Final Safety Analysis Report
05/07/2019
White Paper, SQN Auxiliary Feedwater System
Feasibility Study for Min-flow Design Pressure
Increase
11/11/2015
Updated Final Safety Analysis Report, Chapter
10.4.7.2, Auxiliary Feedwater System
Amd. 30
Updated Final Safety Analysis Report, Section 15.4.1,
Major Reactor Coolant System Pipe Ruptures (Loss of
Coolant Accident)
Amd. 30
Sequoyah Nuclear Plant Units 1 and 2 - Nuclear
Steam Supply System Engineering Support Services -
Contract No. 2925 - Letter N10562
09/27/2010
EWR-18-DEC-067-615
Limitorque SMB-000 actuator
11/06/2018
EWR-18-DEE-067-616
Limitorque SMB-000 actuator
Rev. 1
EWR-18-DEM-067-617
Limitorque SMB-000 actuator
11/05/2018
S22 180116 001
Asco Controls, L.P Engineering Report. Rev.3 AQN-
18-226, Limit Switch Variation for 2-FCV-67-91
Rev. 1
SQN FSAR Section 9.3.4 Chemical & Volume Control System
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
10.4.7.2
Auxiliary Feedwater System
SQNEQ-SOL-009
Target Rock Corporation Solenoid Valves
Rev. 31
Procedures
0-TI-OPS-000-004.0
Time Critical Operator Actions
Rev. 10
2-SI-EDC-202-220.A
Setpoint Verification and Calibration for Time Delay
Relays Associated with Automatic Load Sequence
Timers
Rev. 17
Transfer to RHR Containment Sump
Rev. 24
NEDP-2
Design Calculation Process Control
Rev. 18
NEDP-8.0
Evaluations for Procurement of Materials, Items, and
Services
Rev. 7
NEDP-8.2
Technical Evaluation for Procurement of Safety
Related and Quality Related Materials and Items
Rev. 3
NEDP-8.4
Equivalency Evaluation for Procurement and
Replacement of Materials and Items
Rev. 7
NISP-IP-ENG-001
Standard Design Process (EB-17-06)
Rev. 1
NPG-SPP-06.9.3
Post-Modification Testing
Rev. 11
NPG-SPP-09.4
CFR 50.59 Evaluations of Changes, Tests, and
Experiments
Rev. 15
PMTI-100069-001
Turbine Driven Auxiliary Feedwater Governor Upgrade
Rev. 0
TI-28
Curve Book
Rev. 351
TVA-NQA-PLN89-A
Nuclear Quality Assurance Plan (NQAP) (Quality
Assurance Program Description)
Rev. 38
Work Orders
09-779231-000
2729648
115065173
115065174
115065175
115065176
117222626
118765154
119170828
115144038
20757820
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
2485666
20455241