Sequoyah Nuclear Plant, P.O. Box 2000, Soddy Daisy, Tennessee 37384 August 3, 2023 10 CFR 50.4 ATTN: Document Control Desk U. S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Sequoyah Nuclear Plant, Units 1 and 2 Renewed Facility Operating License Nos. DPR-77 and DPR-79 NRC Docket Nos. 50-327 and 50-328

Subject:

Enforcement Action EA-22-129 Inspection Readiness Notification

Reference:

NRC Inspection Report dated April 20, 2023, Sequoyah Nuclear Plant, Units 1 & 2 - Final Significance Determination For a Security-Related Greater Than Green Finding, Notice of Violation and Assessment Followup Letter, 05000327/2023441 and 05000328/2023441 By the Reference letter, the NRC determined the performance at Sequoyah Nuclear Plant, Units 1 & 2, to be in the Regulatory Response Column of the Regulatory Oversight Program Action Matrix beginning the Fourth Quarter of 2022. The NRC also therein notified TVA of its plan to perform an additional inspection after TVA notifies the NRC of TVAs readiness. This letter serves to notify the NRC of TVAs readiness for the NRC to schedule the inspection.

There are no regulatory commitments associated with this submittal. Should you have any questions, please contact Rick Medina, Site Licensing Manager at (423) 843-8129.

Respectfully, Marshall, Thomas Digitally signed by Marshall, Thomas B.

B. Date: 2023.08.03 13:44:30 -04'00' Thomas Marshall Site Vice President Sequoyah Nuclear Plant cc: