Inspection/Activity Plan - Sequoyah Nuclear Plant (NRC Inspection Report 05000327/2006001, 05000328/2006001)
ML060610560
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 03/02/2006
From: Widmann M
Reactor Projects Region 2 Branch 6
To:
Shared Package
ML060610530 List:
References
IR-06-001
Download: ML060610560 (2)


Text

Page 1 of 2 Sequoyah 03/02/2006 11:55:43 Inspection / Activity Plan Report 22 03/01/2006 - 09/30/2007 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type EB3-ISI - U1 INSERVICE INSPECTION 1 1 IP 7111108P Inservice Inspection Activities - PWR 04/17/2006 04/21/2006 Baseline Inspections PSB1-RP - RP PUBLIC PREINSP VISIT/ ISFSI 1 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 05/15/2006 05/17/2006 Baseline Inspections PSB1-RP - RP PUBLIC BASELINE 4 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 06/05/2006 06/09/2006 Baseline Inspections 1, 2 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 06/05/2006 06/09/2006 Baseline Inspections 1, 2 IP 7112201 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems 06/05/2006 06/09/2006 Baseline Inspections 1, 2 IP 7112203 Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control P 06/05/2006 06/09/2006 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 06/05/2006 06/09/2006 Baseline Inspections ISFSI-O - 60855.1 - OPERATION OF AN ISFSI 1 1 IP 6085 Operation of an Independent Spent Fuel Storage Installation at Operating Plants 07/03/2006 07/07/2006 Other Routine EB3-MR - MR EFFECTIVENESS 2 1, 2 IP 7111112B Maintenance Effectiveness 08/14/2006 08/18/2006 Baseline Inspections PS2-EP - EP EXERCISE 3 1, 2 IP 7111401 Exercise Evaluation 08/28/2006 09/01/2006 Baseline Inspections 1, 2 IP 7111404 Emergency Action Level and Emergency Plan Changes 08/28/2006 09/01/2006 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 08/28/2006 09/01/2006 Baseline Inspections OL RQ - REQUAL INSPECTION 2 1, 2 IP 7111111B Licensed Operator Requalification Program 10/16/2006 10/20/2006 Baseline Inspections EB1-MODS - MODIFICATIONS/10CFR50.59 3 1, 2 IP 7111102 Evaluation of Changes, Tests, or Experiments 11/13/2006 11/17/2006 Baseline Inspections 1, 2 IP 7111117B Permanent Plant Modifications 11/13/2006 11/17/2006 Baseline Inspections EB3-ISI - U2-INSERVICE INSPECTION 1 2 IP 7111108P Inservice Inspection Activities - PWR 12/04/2006 12/08/2006 Baseline Inspections EB3TI150 - 2515/150 U-2: RPV & VHP NOZZLES 1 2 IP 2515/150 Reactor Pressure Vessel Head and Vessel Head Penetration Nozzles (NRC ORDER EA-03- 12/04/2006 12/08/2006 Safety Issues EB3SGISI - U2 STEAM GENERATOR ISI 1 2 IP 7111108P Inservice Inspection Activities - PWR 12/11/2006 12/15/2006 Baseline Inspections EB1-SUMP - PWR CONTAINMENT SUMP BLOCKAGE TI (U-2) 2 2 IP 71111 Reactor Safety-Initiating Events, Mitigating Systems, Barrier Integrity 12/17/2006 12/22/2006 Baseline Inspections OL PREP - INITIAL EXAM PREP 3 1 V23243 SEQUOYAH/APRIL 2007 EXAM AT POWER FACILITIES 03/19/2007 03/23/2007 Not Applicable EB3-HS - HEAT SINK 1 1, 2 IP 7111107B Heat Sink Performance 03/26/2007 03/30/2007 Baseline Inspections This report does not include INPO and OUTAGE activitie This report shows only on-site and announced inspection procedure Enclosure

Page 2 of 2 Sequoyah 03/02/2006 11:55:43 Inspection / Activity Plan Report 22 03/01/2006 - 09/30/2007 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type OL EXAM - INITIAL EXAM WEEK 1 3 1 V23243 SEQUOYAH/APRIL 2007 EXAM AT POWER FACILITIES 04/09/2007 04/13/2007 Not Applicable OL EXAM - INITIAL EXAM WEEK 2 3 1 V23243 SEQUOYAH/APRIL 2007 EXAM AT POWER FACILITIES 04/23/2007 04/27/2007 Not Applicable EB1-CDB - COMPONENT DESIGN BASES INSPECTION 5 1, 2 IP 7111121 Component Design Bases Inspection 05/14/2007 05/18/2007 Baseline Inspections 1, 2 IP 7111121 Component Design Bases Inspection 06/04/2007 06/08/2007 Baseline Inspections 1, 2 IP 7111121 Component Design Bases Inspection 06/18/2007 06/22/2007 Baseline Inspections 1, 2 IP 7111121 Component Design Bases Inspection 07/09/2007 07/13/2007 Baseline Inspections PS2-EP - EP INSP 1 1, 2 IP 7111402 Alert and Notification System Testing 05/21/2007 05/25/2007 Baseline Inspections 1, 2 IP 7111403 Emergency Response Organization Augmentation Testing 05/21/2007 05/25/2007 Baseline Inspections 1, 2 IP 7111404 Emergency Action Level and Emergency Plan Changes 05/21/2007 05/25/2007 Baseline Inspections 1, 2 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 05/21/2007 05/25/2007 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 05/21/2007 05/25/2007 Baseline Inspections RPB6-PIR - BIENNIAL PI&R INSPECTION 4 1, 2 IP 71152B Identification and Resolution of Problems 05/21/2007 05/25/2007 Baseline Inspections 1, 2 IP 71152B Identification and Resolution of Problems 06/04/2007 06/08/2007 Baseline Inspections PSB1-RP - RP OCCUPATIONAL PRE-INSP VISIT/ISFSI 1 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 09/04/2007 09/06/2007 Baseline Inspections This report does not include INPO and OUTAGE activitie This report shows only on-site and announced inspection procedures.