IR 05000327/2021002
| ML21209A026 | |
| Person / Time | |
|---|---|
| Site: | Sequoyah |
| Issue date: | 07/27/2021 |
| From: | Tom Stephen NRC/RGN-II/DRP/RPB5 |
| To: | Jim Barstow Tennessee Valley Authority |
| T Francis | |
| References | |
| IR 2021002 | |
| Download: ML21209A026 (16) | |
Text
July 27, 2021
SUBJECT:
SEQUOYAH, UNITS 1 AND 2 - INTEGRATED INSPECTION REPORT 05000327/2021002 AND 05000328/2021002
Dear Mr. Barstow:
On June 30, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Sequoyah, Units 1 and 2. On July 20, 2021, the NRC inspectors discussed the results of this inspection with Mr. Tom Marshall and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA/
Thomas A. Stephen, Chief Reactor Projects Branch #5 Division of Reactor Projects
Docket Nos. 05000327 and 05000328 License Nos. DPR-77 and DPR-79
Enclosure:
As stated
Inspection Report
Docket Numbers:
05000327 and 05000328
License Numbers:
Report Numbers:
05000327/2021002 and 05000328/2021002
Enterprise Identifier: I-2021-002-0018
Licensee:
Tennessee Valley Authority
Facility:
Sequoyah, Units 1 and 2
Location:
Soddy Daisy, TN 37379
Inspection Dates:
April 01, 2021 to June 30, 2021
Inspectors:
N. Childs, Resident Inspector
S. Downey, Senior Reactor Inspector
D. Hardage, Senior Resident Inspector
Approved By:
Thomas A. Stephen, Chief
Reactor Projects Branch #5
Division of Reactor Projects
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Sequoyah, Units 1 and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
PLANT STATUS
Unit 1 began the inspection period at rated thermal power (RTP). On April 5, 2021, the unit entered end of life coast down, and on April 10, 2021, the unit was shutdown from 95 percent RTP for refueling outage 1R24. On May 10, 2021, the reactor was started up and the unit returned to RTP on May 14, 2021. On May 24, 2021, the reactor tripped on power range nuclear instrument negative rate due to a failure of the Control Bank B Group 2 stationary gripper phase control card. The unit was returned to RTP on June 1, 2021 and remained at or near RTP for the remainder of the inspection period.
Unit 2 operated at or near RTP for the entire inspection period.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), resident and regional inspectors were directed to begin telework and to remotely access licensee information using available technology. During this time, the resident inspectors performed periodic site visits each week, increasing the amount of time on site as local COVID-19 conditions permitted.
As part of their onsite activities, resident inspectors conducted plant status activities as described in IMC 2515, Appendix D; observed risk significant activities; and completed on site portions of IPs. In addition, resident and regional baseline inspections were evaluated to determine if all or a portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on site. The inspections documented below met the objectives and requirements for completion of the IP.
REACTOR SAFETY
71111.01 - Adverse Weather Protection
Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)
- (1) The inspectors evaluated readiness for seasonal extreme weather conditions prior to the onset of seasonal summer temperatures including review the material condition of the plants offsite AC power systems and onsite alternate AC power systems including the switchyard and transformers on May 26, 2021.
71111.04 - Equipment Alignment
Partial Walkdown Sample (IP Section 03.01) (4 Samples)
The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:
- (1) Unit 1 residual heat removal system (RHRS) with both trains in service for cooldown in Mode 5 with reactor coolant system (RCS) level below the flange on April 13, 2021
- (2) Unit 1 RHRS with both aligned for low pressure safety injection in Mode 1 following realignment from 1R24 on May 23, 2021
- (3) Unit 1 auxiliary feedwater (AFW) system following replacement of 1B AFW pump on June 11, 2021
- (4) Unit 1 emergency core cooling system pumps and 1A emergency diesel generator (EDG) with 1B-B EDG inoperable due to failure to start on June 28, 2021
71111.05 - Fire Protection
Fire Area Walkdown and Inspection Sample (IP Section 03.01) (5 Samples)
The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:
- (1) Unit 1 Reactor Building, Lower Containment, Elevation 679 on May 3, 2021
- (2) Unit 1 Reactor Building, Upper Containment, Elevation 734 on May 5, 2021
- (3) Unit 2 Auxiliary Building (Non-RCA), Elevation 734 on June 10, 2021
- (4) Unit 1 and Unit 2 Auxiliary Building, Elevation 653 on June 24, 2021
- (5) Unit 1 and Unit 2 Auxiliary Instrument Rooms, Control Building Elevation 685 on June 28, 2021
Fire Brigade Drill Performance Sample (IP Section 03.02) (1 Sample)
- (1) The inspectors evaluated the onsite fire brigade performance in response to a fire in 1B AFW pump on May 27, 2021.
===71111.08P - Inservice Inspection Activities (PWR)
PWR Inservice Inspection Activities Sample (IP Section 03.01)===
- (1) The inspectors evaluated pressurized water reactor non-destructive testing by reviewing the following examinations from May 10 to May 14, 2021:
1. Liquid Penetrant Examination
a. RHRHXH-18-A-2-IA, Integral attachment to Residual Heat Removal Heat Exchanger 1A, ASME Class 2 b. Weld 0-ER-1715A, Pipe to elbow weld, ASME Class 3. This included a review of the associated welding activities.
c. Weld 1-RX-2134A, Transition piece to elbow weld, ASME Class 1.
This included a review of the associated welding activities.
2. Magnetic Particle Examination
a. Weld RFDW-2, Steam Generator 2 Feedwater Nozzle to Shell weld, ASME Class 2
3. Radiographic Examination
a. Weld SIF-196, Pipe to valve Weld, ASME Class 1
4. Ultrasonic Examination
a. Weld AFWF-150, Pipe to reducer weld, ASME Class 2 b. Weld RFDW-2, Steam Generator 2 Feedwater Nozzle to Shell weld, ASME Class 2 c. Weld RCS-032, Pipe to elbow weld, ASME Class 1 d. Weld SI-1693, socket weld, ASME Class 1 e. Weld SIF-196, Pipe to valve weld, ASME Class 1
5. Visual Examination
a. Bare metal visual (remote) examination of Reactor Pressure Vessel Closure Head and penetrations, ASME Class 1
The Inspectors also evaluated the licensees boric acid corrosion control program performance.
71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance
Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)
- (1) The inspectors observed and evaluated licensed operator performance in the main control room during shutdown activities for U1R24 refueling outage on April 9 - 10, 2021.
Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)
- (1) The inspectors observed and evaluated a simulator examination scenario on June 14, 2021.
71111.12 - Maintenance Effectiveness
Maintenance Effectiveness (IP Section 03.01) (2 Samples)
The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:
- (1) Failure of 1-FCV-67-344, essential raw cooling water (ERCW) to 1B-B pipe chase cooler, to open during surveillance testing on November 23, 2020
- (2) Auxiliary building secondary containment enclosure isolation damper 2-FCO-30-272 failed to close on auxiliary building isolation actuation on February 19, 2021
71111.13 - Maintenance Risk Assessments and Emergent Work Control
Risk Assessment and Management Sample (IP Section 03.01) (6 Samples)
The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:
- (1) Unit 1, Yellow shutdown risk week of April 11 - 17, 2021, while RCS level was below Reactor (Rx) flange level and during Rx core offload, including review of defense in depth protected equipment for U1R24.
- (2) Unit 1, Yellow shutdown risk week of April 18 - 23, 2021, during reactor core offload concurrent with maintenance on the A RHR train, including review of defense in depth protected equipment for U1R24.
- (3) Unit 1, Yellow shutdown risk week of May 2-8, 2021, while RCS level was below Rx flange level and RCS heat up from Mode 5 to normal operating temperature including review of defense in depth protected equipment for U1R24.
- (4) Unit 1 and 2, week of May 23-29, 2021, including a reactor trip on Unit 1 and Yellow shutdown risk following a fire in the 1B AFW pump, including protection equipment reviews for emergent maintenance and a conservative operations alert.
- (5) Unit 1 and 2, week of June 6-12, 2021, including protection equipment reviews for planned maintenance on the B auxiliary air compressor and emergent maintenance on D air compressor.
- (6) Unit 1 and 2, week of June 27-30, 2021, including planned replacement of 1B start bus and emergent maintenance on 1B EDG, including protection equipment reviews for the emergent maintenance and a conservative operations alert.
71111.15 - Operability Determinations and Functionality Assessments
Operability Determination or Functionality Assessment (IP Section 03.01) (6 Samples)
The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:
(1)1B Centrifugal Charging Pump Gear Oil Cooler has lower than expect flow on May 5, 2021 (CR 1691745)
- (2) ERCW leak on internal coils of the 2B 669 pipe chase cooler on May 12, 2021 (CR 1693400)
(3)1B motor driven auxiliary feedwater (MDAFW) pump differential pressure below acceptance criteria on May 29, 2021 (CR 1697633)
- (4) Prompt determination of operability request for 1-FCV-68-333 power operated relief valve block valve on April 23, 2021 (CR 1688783)
- (5) Nuts found loose on flange of containment vacuum relief valve 1-VLV-30-47 on April 30, 2021 (CR 1688414)
- (6) Conduit for power range nuclear instrument N41 detector filled with borated water on May 4, 2021 (CR 1690093)
71111.19 - Post-Maintenance Testing
Post-Maintenance Test Sample (IP Section 03.01) (8 Samples)
The inspectors evaluated the following post-maintenance test activities to verify system operability and functionality:
- (1) Work Order (WO) 121287367, ERCW header 1A isolation valve 1-BCTD-3-116A clean square D contactor on April 7, 2021
- (2) WO 121157462, Repack outboard end of Unit 1 turbine driven auxiliary feedwater (TDAFW) pump due to cocked gland on April 9, 2021
- (3) WO 120868165, 1-FCV-74-3, '1A' RHR pump suction valve failed seat leak test, rework valve on April 29, 2021
- (4) WO 122073016, Nuts found loose on bolting surface of 1-VLV-30-46, Containment Vacuum Relief Valve on May 6, 2021
- (5) WO 117818333, Replace unit 1 reactor coolant pump #2 seal on May 8, 2021
- (6) WO 119467102, 1-VLV-1-516 remove valve for testing offsite and replace gaskets on May 8, 2021
- (7) WO 122074616, Replace 1-VLV-063-0559, safety injection loop 2 hot leg check valve, on May 8, 2021
- (8) WO 122153643, Replace 1B-B AFW pump on May 29, 2021
71111.20 - Refueling and Other Outage Activities
Refueling/Other Outage Sample (IP Section 03.01) (1 Sample)
- (1) The inspectors evaluated U1R24 outage activities from April 10 to May 11, 2021.
71111.22 - Surveillance Testing
The inspectors evaluated the following surveillance tests:
Surveillance Tests (other) (IP Section 03.01)
(1)1-SI-SXP-003-202.A, MDAFW 1A-A Comprehensive Performance Test on April 7, 2021 (2)1-SI-OPS-088-001.0, Phase A Isolation Test on April 11, 2021 (3)1-SI-SXP-003-202.S, TDAFW Comprehensive Performance Test on April 9, 2021
Inservice Testing (IP Section 03.01) (2 Samples)
(1)0-SI-SXV-001-859.0, Testing and Setting of Main Steam Safety Valves on April 7, 2021
Containment Isolation Valve Testing (IP Section 03.01) (1 Sample)
(1)0-SI-SLT-043-258.1, Containment Isolation Valve Local Leak Rate Test Post Accident Sampling on April 19, 2021
Ice Condenser Testing (IP Section 03.01) (1 Sample)
(1)0-SI-MIN-061-109.0, Ice Condenser Intermediate and Lower Inlet Doors and Vent Curtains on May 2,
OTHER ACTIVITIES - BASELINE
===71151 - Performance Indicator Verification
The inspectors verified licensee performance indicators submittals listed below:
IE01: Unplanned Scrams per 7000 Critical Hours Sample (IP Section 02.01)===
- (1) Unit 1 (April 2020 - March 2021)
- (2) Unit 2 (April 2020 - March 2021)
IE03: Unplanned Power Changes per 7000 Critical Hours Sample (IP Section 02.02) (2 Samples)
- (1) Unit 1 (April 2020 - March 2021)
- (2) Unit 2 (April 2020 - March 2021)
IE04: Unplanned Scrams with Complications (USwC) Sample (IP Section 02.03) (2 Samples)
- (1) Unit 1 (April 2020 - March 2021)
- (2) Unit 2 (April 2020 - March 2021)
71152 - Problem Identification and Resolution
Semiannual Trend Review (IP Section 02.02) (1 Sample)
- (1) The inspectors reviewed the licensees corrective action program for potential adverse trends related to ice condenser ice baskets being frozen in place which might be indicative of a more significant safety issue.
Annual Follow-up of Selected Issues (IP Section 02.03) (1 Sample)
The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:
- (1) Unit 1 Reactor Vessel Head Vent Degradation
===71153 - Follow Up of Events and Notices of Enforcement Discretion
Event Follow up (IP Section 03.01)===
- (1) The inspectors evaluated licensee performance in response to a fire in 1B-B AFW pump on May 27, 2021.
Personnel Performance (IP Section 03.03) (1 Sample)
- (1) The inspectors evaluated licensee performance in response to Unit 1 reactor trip on May 24,
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On July 20, 2021, the inspectors presented the integrated inspection results to Mr. Tom Marshall and other members of the licensee staff.
- On May 13, 2021, the inspectors presented the ISI Exit Meeting inspection results to Chris Reneau, Plant Manager and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Procedures
0-PI-OPS-000-
006.1
Summer Operation
Revision 9
Degraded Grid or Abnormal Voltage Conditions
Revision 17
NPG-SPP-07.1.6
On Line Work Control Power Systems Alerts/Offsite Power
Revision 8
Miscellaneous
0-PE-2021 / 1-82-
0006
Protected Equipment/Clearance Section for 1B-B D/G
06/28/2021
Procedures
0-SO-74-1
Residual Heat Removal System
Revision 109
1-SO-3-2
Auxiliary Feedwater System
Revision 61
Corrective Action
Documents
CR 1697239
Report of sparks coming from 1B-B MDAFW pump
05/27/2021
CR 1697332
Fire Emergency Response: 1B MDAFW pump
05/27/2021
CR 1700545
Temporary Cat5e Cable routed within the 1-foot boundary of
safety related cable trays and conduit
06/11/2021
Fire Plans
AUX-0-653-00
Pre-Fire Plan Auxiliary Building El 653
Revision 9
AUX-0-734-01
Pre-Fire Plan Auxiliary Building El 734 Unit 1 Side
Revision 10
AUX-0-734-02
Pre-Fire Plan Auxiliary Building El 734 Unit 2 Side
Revision 9
CON-0-685-00
Pre-Fire Plan, Control Building El. 685
Revision 6
RXB-0-679-02
Pre-Fire Plan for Reactor Building (Elevation 679)
Revision 3
RXB-0-734-02
Pre-Fire Plan for Reactor Building (Elevation 734) and
Annulus (Elevation 740, 759, and 778)
Revision 3
Miscellaneous
Standing Order:
SO-21-017
ACMP Fire Watch Camera Monitoring Plan
05/12/2021
Corrective Action
Documents
CRs (by number)
1463750, 1564272, 1580350, 1584849, 1608941, 1685545,
1686073, 1689057, 1689365, 1693829
NDE Reports
R-0478
Ultrasonic Examination Report for RCS-032
04/13/2021
R-0506
Ultrasonic Examination Report for SI-1693
04/20/2021
R-0513
Magnetic Particle Examination Report for RFDW-2
04/21/2021
R-0519
Visual Examination Report for Reactor Pressure Vessel
Closure Head
04/26/2021
R-0524
Ultrasonic Examination Report for RFDW-2
04/26/2021
Procedures
N-GP-18
Ultrasonic Testing Supplements
Revision
23
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
N-MT-6
Magnetic Particle Examination for ASME and ANSI Code
Components and Welds
Revision
0037
N-UT-19
Ultrasonic Examination of Welds in Vessels Greater than 2-
inches in Well Thickness
Revision
20
N-UT-64
Generic Procedure for the Ultrasonic Examination of
Austenitic Pipe Welds
Revision
0018
N-UT-85
Manual Ultrasonic Examination for the Detection of Thermal
Fatigue in Piping and Components within the Material
Reliability Programs
NPG-SPP-09.7.4
Boric Acid Corrosion Control Program
Revision
0006
Work Orders
Work Orders (by
number)
20593669, 121132022
71111.11Q Miscellaneous
SEG
- OPL273E2130
LOR Cycle 21-03 Simulator Exam
06/14/2021
Procedures
1-SI-OPS-082-
26.B
Loss of Offsite Power with Safety Injection D/G 1B-B Test
Revision 56
1-SI-OPS-088-
001.0
Phase A Isolation Test
Revision 24
Corrective Action
Documents
CR 1654164
Failed valve stroke for 1-FCV-67-344
11/23/2020
CR 1660457
Replace packing gland/packing gland follower, gland stud,
gland stud nut and repack valve
2/23/2020
CR 1661050
Failed PMT valve stroke for 1-FCV-67-344
2/29/2021
CR 1663703
1-FSV-67-344-B basic cause determination
01/12/2021
CR 1672837
2-FCO-30-272 did not go closed with a valid auxiliary
building isolation (ABI) signal present
2/19/2021
CR 1684582
Maintenance rule basic cause documentation of 2-FCO-30-
2
04/07/2021
Miscellaneous
CDE 3125
Cause determination evaluation for 1-FCV-67-344 stroke
failure
03/17/2021
CDE 3132
2-FCO-30-272 failed to close on ABI actuation
Revision 1
Procedures
NPG-SPP-03.4
Maintenance Rule Performance Indicator Monitoring,
Trending and Reporting - 10CFR50.65
Revision 4
TI-4, Attachment
Heating, Ventilation, and Air Conditioning - System 030
Revision 31
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
- 7
Work Orders
21941721;
21990076;
2050297
Corrective Action
Documents
CR 1698157
Risk Classification of Works Orders during Forced Outage
06/02/2021
Corrective Action
Documents
Resulting from
Inspection
CR 1704128
Error in online EOOS, 1B EDG not included after failure
06/28/2021
Procedures
0-GO-16
System Operability Checklists
Revision 28
Corrective Action
Documents
CR 1686772
Need Engineering review for 1-FCV-68-333 MOV Test Data.
Test Values exceeded acceptance criteria.
04/15/2021
CR 1690524
No ERCW flow indicated on 1B CCP
04/30/2021
CR 1691051
1B-B CCP speed increaser gearing oil cooler has insufficient
cooling flow
05/03/2021
CR 1691423
Document critical thinking related to CR 1690093 (Insulation
resistance of N41 cable met acceptance criteria).
05/04/2021
Engineering
Evaluations
EWR 21-DEM-
003-075
1B-B MDAFW Pump Replacement total developed head
requirement
05/29/2021
EWR-21-DEM-
067-065
Hydraulic Flow Values Associated with 1B-B Cent. Charging
Pump Gear Oil Cooler
05/05/2021
Operability
Evaluations
Prompt Determination of Operability for PER 732852 (2B
Pipe Chase Cooler Leak)
05/31/2013
Prompt Determination of Operability for CR 1611076 (B-B
EGTS Cooler Leak)
05/29/2020
Corrective Action
Documents
CR 1697633
1B MDAFW Pump DP below acceptance criteria
05/29/2021
Procedures
0-SI-SXT-000-
201.0
ASME Section XI Inservice Pressure Test
Revision 25
0-SI-SXV-003-
266.0
ASME Code Valve Testing
Revision 51
1-SI-SFT-063-
001.0
Safety Injection System Hot Leg and Cold Leg Injection Flow
Test
Revision 12
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
1-SI-SXI-068-
201.0
Leakage Test of the Reactor Coolant System Pressure
Boundary
Revision 16
1-SI-SXP-003-
201.B
Motor Driven Auxiliary Feedwater Pump 1B-B Performance
Test
Revision 18
N-VT-4
System Pressure Test Visual Examination Procedure
Revision 30
Work Orders
1-SI-SXI-068-201.0 Unit 1 leakage test of the reactor coolant
pressure boundary
05/08/2021
Perform Seat Leak Test on 1-FCV-74-003
04/29/2021
Corrective Action
Documents
CR 1685395
CR to document lessons learned from SI-127 performance
(documentation of cooldown rates)
04/11/2021
Corrective Action
Documents
Resulting from
Inspection
CR 1685321
1-VLV-068-0580 has dry boron
04/10/2021
CR 1685322
1-VLV-068-0557 has dry boric acid on stem
04/10/2021
CR 1685323
White powder (boric acid or borax) under RCPs on floor
04/10/2021
CR 1690093
Fluid Coming Out of Conduit with White Residue around
Joints
04/28/2021
CR 1692251
Ice Condenser Drain Pipe leaking on #4 RCP Platform
05/06/2021
Procedures
1-SI-OPS-082-
26.B
Loss of Offsite Power with Safety Injection D/G 1B-B Test
Revision 56
Corrective Action
Documents
CR 1684542
MSSV 1-VLV-001-0516 is suspected of leakage at inlet
04/07/2021
CR 1684653
"B" AFW flow indicator 3-147A is showing zero flow during
comprehensive test
04/07/2021
CR 1697806
MDAFW critical spare exhibited marginal performance
05/31/2021
CR 1697913
06/01/2021
Corrective Action
Documents
Resulting from
Inspection
CR 1690959
Unit 1 Ice Condenser Bay 18 RH Lower Inlet Door Spring
Loose
05/02/2021
Drawings
1-47W881 sheet
Mechanical Flow Drawing Water Quality and Sampling
System
Revision 4
Corrective Action
Documents
CR 1691538
Unit 1 Ice Condenser basket trend
05/04/2021
CR 1691616
U1R24 Ice Condenser Partial Bay Melt Out Lessons
Learned
05/04/2021
Procedures
0-SI-MIN-061-
Ice Condenser - Ice Weighing
Revision 13
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
105.0