IR 05000282/2003004
ML031950512 | |
Person / Time | |
---|---|
Site: | Prairie Island |
Issue date: | 07/11/2003 |
From: | Louden P NRC/RGN-I/DRP/PB5 |
To: | Solymossy J Nuclear Management Co |
References | |
IR-03-004 | |
Download: ML031950512 (60) | |
Text
uly 11, 2003
SUBJECT:
PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNITS 1 AND 2 NRC INTEGRATED INSPECTION REPORT 50-282/03-04; 50-306/03-04
Dear Mr. Solymossy:
On June 30, 2003, the U. S. Nuclear Regulatory Commission (NRC) completed a baseline inspection at your Prairie Island Nuclear Generating Plant, Units 1 and 2. The enclosed report documents the inspection findings which were discussed on June 30, 2003, with you and other members of your staff.
This inspection examined activities conducted under your license as they relate to safety and to compliance with the Commissions rules and regulations and with the conditions of your license.
The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.
Based on the results of this inspection, no findings of significance were identified.
Since the terrorist attacks on September 11, 2001, NRC has issued five Orders and several threat advisories to licensees of commercial power reactors to strengthen licensee capabilities, improve security force readiness, and enhance controls over access authorization. In addition to applicable baseline inspections, the NRC issued Temporary Instruction 2515/148, "Inspection of Nuclear Reactor Safeguards Interim Compensatory Measures," and its subsequent revision, to audit and inspect licensee implementation of the interim compensatory measures required by order. Phase 1 of TI 2515/148 was completed at all commercial power nuclear power plants during calender year 2002 and the remaining inspection activities for Prairie Island are scheduled for completion in June 2003. The NRC will continue to monitor overall safeguards and security controls at Prairie Island. In accordance with 10 CFR 2.790 of the NRC's Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Patrick Louden, Chief Branch 5 Division of Reactor Projects Docket Nos. 50-282; 50-306 License Nos. DPR-42; DPR-60
Enclosure:
Inspection Report 50-282/03-04; 50-306/03-04
REGION III==
Docket Nos: 50-282; 50-306 License Nos: DPR-42; DPR-60 Report No: 50-282/03-04; 50-306/03-04 Licensee: Nuclear Management Company, LLC Facility: Prairie Island Nuclear Generating Plant, Units 1 and 2 Location: 1717 Wakonade Drive East Welch, MN 55089 Dates: April 1 through June 30, 2003 Inspectors: J. Adams, Senior Resident Inspector D. Karjala, Resident Inspector M. Mitchell, Radiation Specialist, DRS J. Creed, Lead Physical Security Inspector G. Pirtle, Physical Security Inspector R. Jickling, Emergency Preparedness Inspector T. Ploski, Emergency Preparedness Inspector Approved by: Patrick Louden, Chief Branch 5 Division of Reactor Projects
SUMMARY OF FINDINGS
IR 05000282/2003-004, 05000306/2003-004; Nuclear Management Company, LLC; 04/01/03 -
06/30/03; Prairie Island Nuclear Generating Plant, Units 1 & 2; Routine Baseline Inspection Report.
This report covers a 3-month period of baseline resident inspection and announced baseline inspection on radiation protection, security, and emergency preparedness. The inspection was conducted by the resident inspectors and inspectors from the Region III office. No findings of significance were identified. The NRCs program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, Reactor Oversight Process,
Revision 3, dated July 2000.
A. Inspector-Identified and Self-Revealed Findings No findings of significance were identified.
Licensee-Identified Violations
A violation of very low safety significance, which was identified by the licensee, has been reviewed by the inspectors. Corrective actions taken or planned by the licensee have been entered into the licensees corrective action program. This violation and corrective action tracking numbers are listed in Section 4OA7 of this report.
REPORT DETAILS
Summary of Plant Status
Unit 1 was operated at or near full power until April 14, 2003, when reactor power was reduced to Mode 2 and the generator was taken off-line to repair an oil leak on the main transformer 1GT. Unit 1 was returned to full power on April 20, 2003, and was operated at that power level until June 16, 2003, when it was discovered that at 100 percent reactor power the steam flow in 11 Steam Generator exceeds 104 percent of design. Reactor power was reduced to approximately 99.5 percent and operated at that power level for the remainder of the inspection period.
Unit 2 was operated at or near full power until April 5, 2003, when power was reduced to 40 percent to conduct quarterly turbine valve testing and to clean condenser water boxes.
Unit 2 was returned to full power on April 6, 2003, and was operated at that power level for the remainder of the inspection period.
REACTOR SAFETY
Cornerstone: Initiating Events, Mitigating Systems, and Barrier Integrity
1R01 Adverse Weather Protection
Hot Weather, Tornado, and High Winds
a. Inspection Scope
On April 25, 2003, the inspectors performed a detailed review of the summer plant operation, high wind, and tornado hazard procedures; Updated Safety Analysis Report (USAR); design basis documents for the alternating current transformers, the switchyard, and engineering safeguards equipment ventilation systems; applicable Technical Specifications (TSs); and the Prairie Island Individual Plant Examination of External Events (IPEEE). During this review, the inspectors verified that the as-found conditions were consistent with the description provided in the above documents.
The inspectors conducted tornado, high winds, and hot weather inspections of the following risk significant mitigating systems:
Tornado and High Winds
- Unit 1 and 2 alternating current power transformers;
- Unit 1 and 2 switchyard; and
- Unit 1 emergency diesel generators.
Hot Weather
- Guardhouse diesel generator
- Unit 1 4160 volt essential switchgear room ventilation for electrical bus 15 and 16; and
- Unit 1 and 2 residual heat removal pump ventilation systems.
The inspectors reviewed the selected systems to verify that the material conditions and system configuration supported the systems availability and operability under adverse weather conditions, and to verify that additional cooling equipment specified in the summer plant operation procedure was available and operating as specified in the procedure. The inspectors conducted walkdowns of the areas specified in the tornado hazards surveillance procedure (SP) to verify that potential missile hazards to transformers and the switchyard had been removed or properly secured.
The inspectors reviewed a number of weather-related corrective action program (CAP)action requests (ARs) that entered problems that, if left uncorrected, could affect the performance of mitigating systems or result in an initiating event. The review was conducted to verify that the licensee entered problems into the corrective action program, identified appropriate corrective actions, and implemented those corrective actions. A detailed list of the documents reviewed during this inspection is included at the end of this report.
b. Findings
No findings of significance were identified.
1R04 Equipment Alignment
a. Inspection Scope
The inspectors performed a partial equipment alignment walkdown of the following risk significant mitigating systems:
- On April 21, 2003, the inspectors conducted an in-plant equipment alignment verification of the D2 emergency diesel generator (EDG) while the D1 EDG was unavailable due to preventative maintenance and testing.
- On May 23, 2003, the inspectors conducted an in-plant equipment alignment verification of the 12 motor-driven auxiliary feedwater (AFW) pump while the 11 turbine-driven AFW pump was unavailable during surveillance testing.
- On May 27, 2003, the inspectors conducted an in-plant equipment alignment verification of the D5 EDG while the D6 EDG was unavailable during surveillance testing.
- On May 28, 2003, the inspectors conducted an in-plant equipment alignment verification of the 21 safety injection pump while the 22 safety injection pump was unavailable for the installation of a plant modification and surveillance testing.
The inspectors utilized the valve and electrical breaker status checklists to verify that system components and support systems were properly configured to support the operability of the available train. The inspectors performed a physical inspection of the available train and reviewed existing outstanding work orders (WOs) and AR CAPs to verify that the available train would be capable to perform its design function as described in the systems design basis. The inspectors also reviewed housekeeping in the proximity of the before mentioned equipment trains to verify that there were no housekeeping issues that could affect the available trains function.
The inspectors reviewed AR CAPs to verify that minor deficiencies identified during these inspections were entered into the licensees corrective action system. A detailed list of the documents reviewed during this inspection is included at the end of this report.
b. Findings
No findings of significance were identified.
1R05 Fire Protection Area Walkdowns
.1 Fire Protection Zone Walkdowns
a. Inspection Scope
The inspectors conducted in-office and in-plant reviews of portions of the licensees Fire Hazards Analysis and Fire Strategies to verify consistency in the documented installed fire protection equipment in the fire protection areas listed below. The inspectors selected fire areas for inspection based on their overall contribution to internal fire risk, as documented in the IPEEE; their potential to impact equipment which could initiate a plant transient; or their impact on the plants ability to respond to a security event. The inspectors assessed the control of transient combustibles and ignition sources, the material and operational condition of fire protection systems and equipment, and the status of fire barriers. The inspectors performed an in-plant walkdown of the following risk significant fire areas:
- Fire Area 20, Unit 1 4160 volt safeguards switchgear room (bus 16), on April 4, 2003;
- Fire Area 41A, screenhouse (diesel-driven cooling water pump area), on April 4, 2003;
- Fire Area 58, Unit 1 auxiliary building ground floor, on April 4, 2003;
- Fire Area 73, Unit 2 auxiliary building ground floor, on April 4, 2003;
- Fire Area 59, Unit 1 auxiliary building mezzanine level, on April 7, 2003;
- Fire Area 74, Unit 2 auxiliary building mezzanine level, on April 7, 2003;
- Fire Area 114, Unit 2 D6 emergency diesel generator fuel oil day tank room, on April 7, 2003; and
- Fire Area 116, Unit 2 D6 emergency diesel generator lubricating oil make-up tank room, on April 27, 2003.
The inspectors also reviewed the AR CAPs listed at the end of this report to verify that the licensee was identifying fire protection issues at an appropriate threshold and entering them into their corrective action program in accordance with station corrective action procedures. The inspectors discussed fire protection issues with the fire protection engineer, operations personnel, and plant management.
b. Findings
No findings of significance were identified.
.2 Annual Fire Drill Observation
a. Inspection Scope
On April 30, 2003, inspectors observed an unannounced fire brigade drill. A large transformer fire was simulated at the Unit 1, 1R transformer. The inspectors observed the fire brigades response at the scene of the simulated fire, at the fire brigade dress out area, and in the control room.
The inspectors verified that the fire brigade donned the appropriate turnout gear and self-contained breathing apparatus; that plant personnel adequately controlled personnel access to the affected area; that the fire brigade made a controlled approach to the simulated fire; that the fire brigade responded with sufficient equipment of the appropriate type to extinguish the fire; that communications between the fire brigade, fire brigade leader, and control room were clear and concise; that fire brigade members checked for victims and for fire propagation into other plant areas; and that the fire brigade correctly used fire fighting pre-plans. Additionally, the inspectors verified that the drill scenario was followed and that drill objectives and acceptance criteria were met.
The inspectors attended the post drill critique and verified that minor weaknesses noted during the drill were discussed with the drill participants.
b. Findings
No findings of significance were identified.
1R06 Flood Protection Measures
.1 External Flood Protection Inspection
a. Inspection Scope
The inspectors performed an in-office review of the most recently completed SP for the inspection of plant flooding barriers and the abnormal procedure for flooding and compared the procedural requirements to the plant flood protection design sections in the USAR and assumption contained in the IPEEE associated with external flooding.
The inspectors performed a physical inspection of all flood protection barriers in the Auxiliary Building, Turbine Building, D5/D6 Building, and the Old Screenhouse during the period of April 2 - 11, 2003, against the acceptance criteria in the SP for the inspection of plant flood barriers. The inspectors also verified that the actions specified in the abnormal procedure for flooding could be performed in a timely manner if required, and the necessary hardware and consumable materials were available and still within their shelf life.
The inspectors reviewed several AR CAPs to verify that minor deficiencies identified during this inspection were entered into the licensees corrective action program, that problems associated with plant equipment relied upon to prevent or minimize flooding were identified at an appropriate threshold, and that corrective actions commensurate with the significance of the issue were identified and implemented. A detailed list of the documents reviewed during this inspection is included at the end of this report.
b. Findings
No findings of significance were identified.
.2 Internal Flood Protection Inspection
a. Inspection Scope
The inspectors reviewed the applicable sections of the USAR and Individual Plant Examination associated with internal flooding in the area of the Unit 1 and Unit 2 Auxiliary Building, elevations 695 feet and 715 feet. The inspectors conducted a physical walkdown of the Unit 1 and Unit 2 Auxiliary Building on April 23, 2003. The inspectors verified that piping systems in these areas were being maintained. The inspectors verified that drain paths from these areas had been maintained and there were no accumulations of loose materials that could plug drain paths. The inspectors reviewed the operator response times assumed in the flood analysis for operator actions and verified that operators could reasonably be expected to complete the required actions in the assumed time.
The inspectors reviewed several AR CAPs to verify that problems associated with plant equipment relied upon to prevent or minimize flooding were identified at an appropriate threshold, and that corrective actions commensurate with the significance of the issue were identified and implemented. A detailed list of the documents reviewed during this inspection is included at the end of this report.
b. Findings
No findings of significance were identified.
1R07 Heat Sink Performance
a. Inspection Scope
On April 21, 2003, the inspectors conducted an as-found inspection of the D1 EDG lubricating oil and jacket water heat exchangers. The inspectors compared the as-found condition of the heat exchangers to the assumed conditions contained in applicable engineering design and performance analyses listed at the end of this report. The inspectors observed conditions as-found heat exchanger for deficiencies such as mussels, clams, tubercles, mud, silt, scale, foreign materials, corrosion, and erosion.
The inspectors also reviewed the licensees performance with respect to the identification and resolution of problems associated with heat sink performance problems. The inspectors focused their evaluation on problems that could result in an initiating event or affect multiple heat exchangers in mitigating systems, thereby increasing risk. A list of corrective action documents reviewed by the inspectors has been included at the end of this report.
b. Findings
No findings of significance were identified.
1R11 Licensed Operator Requalification
a. Inspection Scope
The inspectors observed an operating crew at the simulator during an as-found requalification examination on May 5, 2003. The inspectors evaluated crew performance in the areas of:
- clarity and formality of communications;
- ability to take timely actions in the safe direction;
- prioritization, interpretation, and verification of alarms;
- procedure use;
- control board manipulations;
- oversight and direction from supervisors; and
- group dynamics.
Crew performance in these areas was compared to licensee management expectations identified in the Administrative Work Instruction (AWI) listed at the end of this report.
The inspectors also compared simulator configurations with actual control room board configurations. For any weaknesses identified, the inspectors observed the licensee evaluators to verify that they also noted the issues and discussed them in the critique at the end of the session.
b. Findings
No findings of significance were identified.
1R12 Maintenance Effectiveness
a. Inspection Scope
The inspectors reviewed systems to verify that the licensee properly implemented the maintenance rule for structures, systems, or components (SSCs) with performance problems. This evaluation included the following aspects:
- whether the SSC was scoped in accordance with 10 CFR 50.65;
- whether the performance problems constituted maintenance rule functional failures;
- the proper safety significance classification;
- the proper 10 CFR 50.65(a)(1) or (a)(2) classification for the SSC; and
- the appropriateness of the performance criteria for SSCs classified as (a)(2) or the appropriateness of goals and corrective actions for SSCs classified as (a)(1).
The above aspects were evaluated by using the maintenance rule scoping and report documents listed at the end of this report. For each SSC reviewed, the inspectors also reviewed significant WOs and condition reports listed at the end of this report to verify that failures were properly identified, classified, and corrected and that unavailable time had been properly calculated. The inspectors reviewed documents to verify that minor discrepancies in the licensees maintenance rule reports were corrected.
The inspectors reviewed the licensees implementation of the maintenance rule requirements for the following SSCs:
- Unit 1 and 2 Instrument and Station Air Systems; and
- Cooling Water Pump packing and shaft bearing lubrication.
b. Findings
No findings of significance were identified.
1R13 Maintenance Risk Assessments and Emergent Work Control
a. Inspection Scope
The inspectors reviewed the licensees management of plant risk during emergent maintenance activities and during activities where more than one significant system or train was unavailable. During this review the inspectors compared the licensees risk management actions to those actions specified in the licensees procedures for the assessment and management of risk associated with maintenance activities. The activities were chosen based on their potential impact on increasing the probability of an initiating event or impacting the operation of safety significant equipment. The inspectors verified that evaluation, planning, control, and performance of the work were done in a manner to reduce the risk and minimize the duration where practical, and that contingency plans were in place where appropriate. The licensees daily configuration risk assessment records, observations of shift turnover meetings, observations of daily plant status meetings, observations of shiftly outage meetings, and the documents listed at the end of this report were used by the inspectors to verify that the equipment configurations had been properly listed, that protected equipment had been identified and was being controlled where appropriate, and that significant aspects of plant risk were being communicated to the necessary personnel.
The inspectors reviewed the following planned and emergent maintenance activities:
- planned maintenance on bus ties 1RYBT, 2RYBT, and 4160 volt breakers 14-4, 13-1, 24-9, and 23-9 on April 15, 2003;
- planned maintenance on the 12 diesel-driven cooling water pump, the 11 turbine-driven auxiliary feedwater pump, and the 11 component cooling water pump on April 22, 2003;
- planned maintenance on the D1 EDG and 12 diesel-driven cooling water pump on April 23, 2003;
- emergent failure of the 21 cooling water pump out of service due to excessive heating of the outboard packing gland on May 6, 2003;
- planned maintenance on the 22 safety injection pump, 22 residual heat removal pump, and the unavailability of the residual heat removal pump discharge to safety injection pump suction motor-operated valve MV-32209 on May 28, 2003;
- planned maintenance on the 122 instrument air dryer and the 22 turbine-driven auxiliary feedwater pump on May 30, 2003;
- planned maintenance on the 12 safety injection pump, 12 residual heat removal pump, 122 instrument air compressor, and the unavailability of the residual heat removal pump discharge to safety injection pump suction motor-operated valve MV-32207 on June 5, 2003; and
- emergent failure of the 21 residual heat removal pump due to degraded auxiliary contacts on June 10, 2003.
b. Findings
No findings of significance were identified.
1R15 Operability Evaluations
a. Inspection Scope
The inspectors reviewed six operability determinations the licensee generated that warranted selection on the basis of risk. The inspectors reviewed the following operability determinations:
- prompt operability determination for AR CAP 028899, Inadequate Thread/Bolt Engagement on 12 Safety Injection Pump Seal Water Supply/Return Flanges, March 12, 2003;
- prompt operability determination for AR CAP 029638, Degraded Screen Condition Noted On Safeguards Traveling Screens, April 10, 2003;
- prompt operability determination for AR CAP 029823, Significant Perturbation in 21 RCP [Reactor Coolant Pump] Seal Leakoff, April 19, 2003;
- Operability Recommendation (OPR) 000408, Existence of Three Unsealed Holes in Flood Door 73, May 9, 2003;
- prompt operability determination for AR CAP 030359, 14 Containment Fan Cooling Unit Has High Vibrations in the Danger Range, May 17, 2003; and
- OPR 000415, Breaker 26-10 (22 Safety Injection Pump) Found Puddle of Oil on Cubical Floor Under Charging Motor, May 28, 2003.
The inspectors assessed the accuracy of the evaluations, the use and control of compensatory measures as needed, and compliance with the TSs. The inspectors review included a verification that the operability determinations were made as specified by 5AWI 3.15.5, Operability Determinations. The technical adequacy of the determinations was reviewed and compared to the TSs, Technical Requirements Manual, USAR, and associated design basis documents. A detailed list of the documents reviewed during this inspection is included at the end of this report.
b. Findings
No findings of significance were identified.
1R16 Operator Workarounds (OWAs)
.1 Review of Selected Workarounds
a. Inspection Scope
On May 7, 2003, inspectors conducted an in-office review of an OWA associated with Unit 2, 21 RCP seal leak-off. The RCP seal leak-off started to decrease in January and February 2003, indicating probable seal degradation, which increases the potential for seal failure; an unisolable loss of coolant event. The reduced seal leak-off requires operators to take precautions to prevent further seal degradation. Precautions include smaller and more frequent dilutions, and close monitoring of seal conditions and cooling water temperatures.
The inspectors reviewed the Operating Information for monitoring 21 RCP seal conditions and instructions for responding to normal and transient conditions to determine whether instructions and contingency actions were adequately communicated to and reviewed by on-shift licensed operators. The inspectors reviewed the root cause investigation report and proposed corrective actions to correct and prevent recurrence of the condition. A detailed list of the documents reviewed during this inspection is included at the end of this report.
b. Findings
No findings of significance were identified.
.2 Cumulative Effects of OWAs
a. Inspection Scope
On May 8 - 9, 2003 the inspectors reviewed the cumulative effect of all identified OWAs to determine if there was a significant impact on plant risk or on the operators ability to respond to a transient or an accident. The inspectors reviewed operator logs, AR CAPs, and Operating Information documents to determine if there were OWAs that had not been evaluated. The inspectors used the documents listed at the end of this report to evaluate the list of OWAs.
b. Findings
No findings of significance were identified.
1R17 Permanent Plant Modifications
.1 Permanent Plant Modification Installed On-Line
a. Inspection Scope
The inspectors reviewed design change 01RH01 which removed an interlock from the circuit for motor-operated valve MV-32207 on Unit 1. Motor Operated Valve 32207 is used during the recirculation phase of a small break loss of coolant accident to provide residual heat removal pump discharge to safety injection pump suction. The interlock prevents opening MV-32207 above 210 pounds per square inch gauge to protect from over-pressurization of the safety injection pump suction piping. However, the pressure instrument loops are quality level QIII, while the remainder of the valve circuits are QI.
Administrative and procedural controls were implemented to provide protection against inadvertent over-pressurization of safety injection piping. The inspectors also observed the installation of the modification and the post-modification testing. A detailed list of the documents reviewed during this inspection is included at the end of this report.
b. Findings
No findings of significance were identified.
1R19 Post-Maintenance Testing
a. Inspection Scope
The inspectors conducted in-plant observation and in-office review of post-maintenance testing activities associated with maintenance on important mitigating, barrier integrity, and support systems to ensure that the testing was performed adequately, demonstrated that the maintenance was successful, and that operability was restored.
The inspectors reviewed the appropriate sections of the TSs, USAR, and maintenance documents to determine the systems safety functions and the scope of the maintenance. In addition, the inspectors reviewed ARs to verify that minor deficiencies identified during these inspections were entered into the licensees corrective action system in accordance with station corrective action procedures. A detailed list of the documents reviewed during this inspection is included at the end of this report.
The inspectors observed and evaluated the post-maintenance activities for the following maintenance activities:
- 21 cooling water strainer following annual inspection on April 1, 2003;
- 22 diesel-driven cooling water (DDCL) pump following relay replacement on April 9, 2003;
- D1 EDG 18-month preventive maintenance inspection on April 24, 2003;
- 12 DDCL pump following relay replacement on April 25, 2003;
- 22 containment spray pump following repair of test line drain valve 2CS-25-2 on May 2, 2003;
- 21 pressurizer heaters electrolytic capacitors replacement on May 13, 2003; and
- 11 steam generator power-operated relief valve following replacement of a cable splice on May 15, 2003.
b. Findings
No findings of significance were identified.
1R20 Refueling and Other Outage Activities
a. Inspection Scope
On April 15, 2003, Unit 1 reactor power was reduced to one percent (Mode 2) and the turbine/generator was removed from service because of an unisolable oil leak on main power transformer 1GT. Inspectors observed the unit shutdown and activities related to outage planning, control of risk during plant configuration changes and planned maintenance activities, and return to power operation.
b. Findings
No findings of significance were identified.
1R22 Surveillance Testing
a. Inspection Scope
The inspectors conducted in-plant observation and/or in-office review of selected surveillance tests and test data to verify that the equipment performance met SP acceptance criteria. The inspectors verified that the tested equipment was capable of performing its intended safety functions as described in TSs and the USAR. The inspectors verified that the testing met the required TS frequency; that the tests were conducted in accordance with the applicable procedures; that operators met prerequisites and established the proper plant conditions; and that the results of the tests were properly recorded and reviewed . A detailed list of the documents reviewed during this inspection is included at the end of this report. The following tests were observed or reviewed and evaluated:
- SP 2093, D5 Diesel Generator Monthly Slow Start on April 14, 2003;
- SP 1198, NIS [Nuclear Instrumentation System] Power Range Startup Test on April 15, 2003;
- SP 1295, D1 Diesel Generator 6 Month Fast Start Test on April 24, 2003; and
- SP 1032A, Safeguards Logic Test at Power - Train A, and SP 1035A, Reactor Protection Logic Test at Power - Train A on June 12, 2003.
b. Findings
No findings of significance were identified.
1R23 Temporary Plant Modifications
a. Inspection Scope
The inspectors conducted an in-office review of associated documentation and in-plant walkdowns of the following temporary modifications:
- configuration changes to the 23 charging pump speed control feedback loop; and
- addition of door alarms to the hot chemistry lab doors.
The inspectors reviewed the system design basis requirements in applicable sections of the USAR comparing the as-found configuration to that documented in the USAR. The inspectors reviewed the applicable procedure requirements for control of plant configuration and 50.59 screenings comparing the actions taken by the licensee to the requirements contained in the applicable procedural guidance. A detailed list of the documents reviewed during this inspection is included at the end of this report.
b. Findings
No findings of significance were identified.
Cornerstone: Emergency Preparedness
1EP2 Alert and Notification System (ANS) Testing
a. Inspection Scope
The inspectors discussed with Emergency Preparedness (EP) staff the design, equipment, and periodic testing of the public ANS for the Prairie Island Nuclear Generating Plant (PINGP) reactor facility emergency planning zone to verify that the system was properly tested and maintained. The inspectors also reviewed procedures and records for an 18-month period ending March 2003 related to ANS testing, annual preventive maintenance, and non-scheduled maintenance. The inspectors reviewed the licensees documentation for determining whether each model of siren installed in the emergency planning zone would perform as expected if fully activated. Records used to document and trend component failures for each model of installed siren were also reviewed to ensure that corrective actions were taken for test failures or system anomalies.
b. Findings
No findings of significance were identified.
1EP3 Emergency Response Organization (ERO) Augmentation Testing
a. Inspection Scope
The inspectors reviewed the licensees ERO augmentation testing to verify that the licensee maintained and tested its ability to staff the ERO during an emergency in a timely manner. Specifically, the inspectors reviewed quarterly, off-hours staff augmentation test procedures, related November 6, 2001; January 22, 2002; May 2, 2002; September 18, 2002; November 11, 2002; and February 10, 2003 drill records, primary and backup provisions for off-hours notification of the Prairie Island reactor facility emergency responders, and the current ERO rosters for Prairie Island. The inspectors reviewed and discussed the facility EP staffs provisions for maintaining ERO call out lists.
b. Findings
No findings of significance were identified.
1EP4 Emergency Action Level and Emergency Plan Changes
a. Inspection Scope
The inspectors reviewed Revisions 25, 26, and 27 of the Prairie Island Nuclear Generating Plant Emergency Plan to determine whether changes identified reduced the effectiveness of the licensees emergency planning, pending onsite inspection of the implementation of these changes.
b. Findings
No findings of significance were identified.
1EP5 Correction of Emergency Preparedness Weaknesses and Deficiencies
a. Inspection Scope
The inspectors reviewed the Nuclear Oversight staffs 2002 and 2003 audits to ensure that these audits complied with the requirements of 10 CFR 50.54(t) and that the licensee adequately identified and corrected deficiencies. The inspectors also reviewed the EP staffs 2002 and 2003 self assessments, and critiques to evaluate the EP staffs efforts to identify and correct weaknesses and deficiencies. Additionally, the inspectors reviewed a sample of EP items, condition reports, and action requests related to the facilitys EP program to determine whether corrective actions were acceptably completed.
b. Findings
No findings of significance were identified.
RADIATION SAFETY
Cornerstone: Occupational Radiation Safety
2OS1 Access Control to Radiologically Significant Areas (71121.01)
.1 Plant Walkdowns and Radiological Boundary Verification
a. Inspection Scope
The inspectors conducted walkdowns of selected radiologically controlled areas within the plant to verify the adequacy of radiological boundaries and postings. Specifically, the inspectors walked down areas that were controlled for a resin sluicing to High Integrity Container (HIC) operation. The inspectors observed personnel performing confirmatory radiation measurements to verify that these areas and selected radiation areas were properly posted and controlled in accordance with 10 CFR Part 20, licensee procedures, and the Technical Specifications.
b. Findings
No findings of significance were identified.
.2 Identification and Resolution of Problems
a. Inspection Scope
The inspectors reviewed licensee AR CAPs written since the last inspection (February 2003) to the date of the current inspection, which focused on access control to radiologically significant areas (i.e., problems concerning activities in High Radiation Areas, radiation protection technicians performance, and radiation worker practices). The inspectors reviewed these documents to assess the licensees ability to identify repetitive problems, contributing causes, and the extent of conditions; and then implement corrective actions in order to achieve lasting results.
2OS3 Radiation Monitoring Instrumentation and Protective Equipment (71121.03)
.1 Walkdowns of Radiation Monitoring Instrumentation
a. Inspection Scope
The inspectors reviewed the USAR and performed walkdowns of selected area radiation monitors, small article monitors, and continuous air monitors, in the auxiliary and radwaste buildings. Additionally, the inspectors examined a representative number of portable radiation survey instruments staged throughout the licensees facility to verify that those instruments had current calibrations, were operable, and in good physical condition. The inspectors also reviewed the status of repair or troubleshooting activities associated with selected radiation monitoring instruments to verify that instrumentation problems were being addressed in an appropriate and timely manner. The inspectors performed these walkdowns to verify the instrumentation was:
- (1) optimally positioned (i.e., relative to the potential source(s) of radiation they were intended to monitor),
- (2) in a good material condition, and
- (3) properly indicating area radiation levels.
b. Findings
No findings of significance were identified.
.2 Calibration, Operability, and Alarm Set Points of Radiation Monitoring Instrumentation
a Inspection Scope The inspectors examined calibration and surveillance records for radiological instrumentation associated with monitoring transient high and/or very high radiation areas and instruments used for remote emergency assessment to verify that the calibrations were conducted consistent with industry standards and in accordance with station procedures.
- Spent Fuel Pool Air Radiation Monitor B (R-31)
- Control Room Air Supply Radiation Monitor A and B (R23 and R24)
- New Fuel Pit Criticality Area Radiation Monitor (R-28)
Additionally, the inspectors observed gas calibration and reviewed the licensees alarm set points for the 2R37 Auxiliary Building ventilation monitor to verify that the set points were established consistent with the Technical Specifications. The inspectors also observed calibration of handheld radiation monitors to assure proper calibration using station procedure The inspectors discussed surveillance practices with licensee personnel and reviewed calender year (CY) 2002 calibration records and procedures for the Canberra Fastscan Whole Body Counter used for assessment of internal exposure. The inspectors also reviewed calibration records and procedures associated with the electronic dosimeters utilized for real-time dose tracking of personnel during work in the radiologically controlled area.
The inspectors evaluated the calibration procedures and CY 2001 - 2003 calibration records for selected installed radiation monitoring and portable radiation survey instruments to verify that they had been properly calibrated consistent with the licensees procedures. Specifically, the inspectors observed the calibrations of the MiniRad Monitor Model 3500 and Rados Electronic Dosimeter.
The inspectors also observed Radiation Protection Technicians performing daily functional checks of selected radiation detection instruments to verify that they had been tested consistent with the licensees procedures. Specifically, the inspectors observed the functional testing of the MiniRad Monitor Model 3500.
b. Findings
No findings of significance were identified.
.3 Problem Identification and Resolution
a. Inspection Scope
The inspectors reviewed CY 2002-2003 AR CAPs that addressed radiation monitoring instrument deficiencies to determine if any significant radiological incidents involving instrument deficiencies had occurred. The inspectors examined the results of a self-assessment that focused on the licensees radiation protection instrumentation controls. Additionally, the inspectors reviewed a Nuclear Oversight Observation Report related to radiation monitoring instrumentation accuracy and operability generated during the current assessment period. The inspectors also interviewed plant staff and examined closed AR CAPs to verify that radiological instrumentation and protective equipment related issues were adequately addressed by the licensee. The inspectors evaluated these documents to verify the licensees ability to identify repetitive problems, contributing causes, extent of conditions, and the implementation of corrective actions to achieve lasting results.
b. Findings
No findings of significance were identified.
.4 Self-Contained Breathing Apparatus (SCBA) Program
a. Inspection Scope
The inspectors reviewed the licensees respiratory protection program for compliance with the requirements of Subpart H of 10 CFR Part 20. The inspectors performed walkdowns of the SCBA storage locations and inspected a sampling of the units to verify the material condition of the protective equipment, to ensure that they were properly maintained and stored, and to ensure that SCBAs were properly staged and ready for use. The inspectors evaluated the licensees capability to refill and transport SCBA air bottles throughout the plant in the event of an emergency response. The inspectors examined the licensees shiftly crew staffing (i.e., control room as well as other key emergency response personnel) of SCBA qualified personnel to verify an adequate number of plant personnel could respond in the event of an emergency. The inspectors reviewed the manufacturer-certified training/qualification of personnel allowed to perform maintenance and repairs on SCBA components vital to the units function. The inspectors assessed maintenance procedures governing vital component work and periodic air cylinder hydrostatic testing documentation to verify consistency between licensee procedures and SCBA manufacturers recommended practices. The inspectors reviewed a selection of the CY 2002-2003 monthly testing records for SCBAs located in various areas within the site. Specifically, the inspectors reviewed the licensees current SCBA training and qualification records to verify that control room personnel, fire brigade staff, and other key emergency response organization personnel were properly equipped with necessary protective equipment, currently trained, and qualified for SCBA use (including personal bottle change-out), as required by the Code of Federal Regulations, the licensees Emergency Plan, USAR, and plant procedures.
b. Findings
No findings of significance were identified.
Cornerstone: Public Radiation Safety
2PS3 Radiological Environmental Monitoring and Radioactive Material Control Programs (71122.03)
.1 Review of Environmental Monitoring Reports and Data
a. Inspection Scope
The inspectors reviewed the 2001 Annual Environmental Monitoring Report. Sampling location commitments, monitoring and measurement frequencies, land use census, the vendor laboratorys Interlaboratory Comparison Program, and data analysis were assessed. Anomalous results including data, missed samples, and inoperable or lost equipment were evaluated. The review of the Radiological Environmental Monitoring Program (REMP) was conducted to verify that the REMP was implemented as required by the Radiological Environmental Technical Specifications/Offsite Dose Calculation Manual (RETS/ODCM), and associated Technical Specifications, and that changes, if any, did not affect the licensees ability to monitor the impacts of radioactive effluent releases on the environment. The most recent quality assessment of the licensees REMP vendor was reviewed to verify that the vendor laboratory performance was consistent with licensee and NRC requirements.
b. Findings
No findings of significance were identified.
.2 Walkdowns of Radiological Environmental Monitoring Stations and Meteorological
Tower
a. Inspection Scope
The inspectors conducted a walkdown of selected environmental air, water, and milk sampling stations, and thermoluminescent dosimeters locations to verify that the locations were consistent with their descriptions in the RETS/ODCM and to evaluate the equipment material condition and operability. The inspectors also conducted a walkdown of the primary meteorological monitoring site to validate that sensors were adequately positioned and operable. The inspectors reviewed the 2001 Annual Environmental Monitoring Report to evaluate the onsite meteorological monitoring programs data recovery rates, routine calibration and maintenance activities, and non-scheduled maintenance activities. The review was conducted to verify that the meteorological instrumentation was operable and was calibrated and maintained in accordance with licensee procedures. The inspectors also reviewed indications of wind speed, wind direction, and atmospheric stability measurements to verify that the indications were available in the Control Room and that the instrument indications were operable.
b. Findings
No findings of significance were identified.
.3 Review of REMP Sample Collection and Analysis
a. Inspection Scope
The inspectors accompanied the licensee REMP technician to observe the collection and preparation of air filters, surface and drinking water samples, and milk samples to verify that representative samples were being collected in accordance with procedures and the RETS/ODCM. The inspectors observed the technician perform air sampler field check maintenance to verify that the air samplers were functioning in accordance with procedures. Selected air sampler calibration and maintenance records for 2001 and 2002 were reviewed to verify that the equipment was being maintained as required. The environmental sample collection program was compared with the RETS/ODCM to verify that samples were representative of the licensees release pathways. Additionally, the inspectors reviewed results of the vendor laboratorys Interlaboratory Comparison Program to verify that the vendor was capable of making adequate radio-chemical measurements.
b. Findings
No findings of significance were identified.
.4 Unrestricted Release of Material from the Radiologically Controlled Area
a. Inspection Scope
The inspectors evaluated the licensees controls, procedures, and practices for the unrestricted release of material from radiologically controlled areas and conducted reviews to verify that:
- (1) radiation monitoring instrumentation used to perform surveys for unrestricted release of materials was appropriate;
- (2) instrument sensitivities were consistent with NRC guidance contained in Inspection and Enforcement Circular 81-07 and Health Physics Positions in NUREG/CR-5569 for both surface contaminated and volumetrically contaminated materials;
- (3) criteria for survey and release conformed to NRC requirements;
- (4) licensee procedures were technically sound and provided clear guidance for survey methodologies; and
- (5) radiation protection staff adequately implemented station procedures.
b. Findings
No findings of significance were identified.
.5 Identification and Resolution of Problems
a. Inspection Scope
The inspectors reviewed corrective action process documents addressing issues involving the REMP as well as a Generation Quality Services (GQS) audit of the environmental monitoring program and observation reports addressing the REMP to determine if problems were being identified and entered into the corrective action program for timely resolution.
b. Findings
No findings of significance were identified.
SAFEGUARDS
Cornerstone: Physical Protection
3PP2 Access Control (Identification, Authorization and Search of Personnel and Packages (IP 71130.02)
a. Inspection Scope
The inspectors reviewed the licensees protected area access control equipment testing and maintenance procedures to determine if testing was performance-based, challenged the detection capabilities of the equipment, and was in accordance with security plan requirements. The inspector observed licensee testing of access control equipment to determine if testing and maintenance practices were performance based.
On two occasions, during peak ingress periods, the inspector observed in-processing search of personnel and packages to determine if search practices were conducted in accordance with regulatory requirements, and that sufficient security force staffing was available for the search functions.
The inspectors reviewed a sample of licensee security logged events and other security documents for identification and resolution of problems. In addition, the inspector interviewed security managers to evaluate their knowledge and use of the licensees corrective action system.
b. Findings
No findings of significance were identified.
3PP3 Response to Contingency Events (71130.03)
a. Inspection Scope
The inspectors reviewed the current Plant Protective Strategy. The inspector also conducted a walk down of the protected area boundary and alarm system and observed testing of selected protected area alarm zones. The closed circuit television day light assessment capability was also evaluated. The inspector reviewed licensee drill and exercise critiques pertaining to response to security contingency events.
The inspectors reviewed a sample of licensee security logged events for identification and resolution of problems. In addition, the inspector interviewed security managers to evaluate their knowledge and use of the licensees corrective action system.
b. Findings
No findings of significance were identified.
OTHER ACTIVITIES
4OA1 Performance Indicator Verification
Cornerstones: Initiating Events, Mitigating Systems, Emergency Preparedness, and Occupational Radiation Safety
a. Inspection Scope
The inspectors conducted an in-office review of the performance indicator data submitted by the licensee for completeness and accuracy, and to verify that the licensee had reported data in accordance with the guidance provided by the Nuclear Energy Institute. The inspectors reviewed documents listed at the end of this report for performance indicator data for the mitigating systems cornerstone. The inspectors reviewed safety system unavailability performance indicator for the residual heat removal system for both Unit 1 and Unit 2 from the 2nd quarter 2002 through the 1st quarter 2003.
b. Findings
No findings of significance were identified.
.2 Reactor Scrams and Reactor Scrams with Loss of Normal Heat Removal
a. Inspection Scope
The inspectors conducted an in-office review of the performance indicator data submitted by the licensee for completeness and accuracy, and to verify that the licensee had reported data in accordance with the guidance provided by the Nuclear Energy Institute. The inspectors reviewed documents listed at the end of this report for performance indicator data for the initiating events cornerstone. The inspectors reviewed the following performance indicators from the 2nd quarter 2002 through the 1st quarter 2003:
- Reactor Scrams; and
- Reactor Scrams with Loss of Normal Heat Removal.
b. Findings
No findings of significance were identified.
.3 ANS, ERO Drill Participation, and Drill and Exercise Performance
a. Inspection Scope
The inspectors verified that the licensee had accurately reported these indicators: ANS, ERO Drill Participation, and Drill and Exercise Performance, for the EP cornerstone.
Specifically, the inspectors reviewed the licensees performance indicator records, data reported to the NRC, and condition reports for the period April 2002 through December 2002 to identify any occurrences that were not identified by the licensee. Records of relevant Control Room Simulator training sessions, periodic ANS tests, and excerpts of drill and exercise scenario and evaluations were also reviewed.
b. Findings
No findings of significance were identified.
.4 Occupational Exposure Control Effectiveness
a. Inspection Scope
The inspectors reviewed the licensees determination of performance indicator (PI)for the occupational radiation safety cornerstone (Occupational Exposure Control Effectiveness) to verify that the licensee accurately determined these performance indicators and had identified all occurrences required by these indicators. Specifically, the inspectors reviewed the licensees AR CAPs for CY 2002-2003 Occupational Exposure performance indicator data to ensure that there were no PI occurrences that were not identified by the licensee. Additionally, as part of plant walkdowns (Section 2OS1.1), the inspectors selectively examined the adequacy of posting and controls for locked High Radiation Areas, to verify the current Occupational Exposure Control Effectiveness performance indicator. The inspectors interviewed members of the licensees staff who were responsible for performance indicator data acquisition, verification and reporting, to verify that their review and assessment of the data was adequate.
b. Findings
No findings of significance were identified.
.5 Protected Area Equipment, Personnel Screening Program, FFD/Personnel Reliability
Program
a. Inspection Scope
The inspectors verified that the licensee had accurately reported these indicators: Protected Area Equipment, Personnel Screening Program, FFD/Personnel Reliability Program, for the Physical Protection cornerstone.
Specifically, a sample of plant reports related to security events and other applicable security records were reviewed for the 4th Quarter 2002 and 1st Quarter of 2003.
c. Findings
No findings of significance were identified.
4OA2 Identification and Resolution of Problems
.1 Routine Review of Identification and Resolution of Problems
a. Inspection Scope
Inspectors conducted an in-office review and in-plant walkdown of the corrective actions for previously identified deficiencies in external flood protection barriers and procedures to verify implementation. A detailed list of the documents reviewed during this inspection is included at the end of this report.
b. Findings and Observations
There were no findings identified associated with the sample reviewed. However, the inspectors identified that the implementation of some corrective actions was either incomplete or not thorough. Licensee Event Report (LER) 50-282, 306/01-003-00, Plant in Unanalyzed Condition Due to Flood Panel Deficiencies, was submitted in 2001 as a result of deficiencies in external flood barriers. The LER stated that flood panel inspection/installation procedures would be improved. However the following deficiencies were noted during this inspection period:
- Inspectors identified that Procedure AB-4, Flood, does not include guidance for removing tack welds to open a trap door for egress following installation of a flood seal on door 164 to the Waste Compactor Room;
- An AR CAP documents that Procedure AB-4 instructions regarding use of primer and removal of paint are different than manufacturers instructions.
.2 Routine Review of Identification and Resolution of Problems
a. Inspection Scope
The inspectors selected AR Other (OTH) 023756 for review during the Emergency Preparedness program inspection. The OTH was initiated to evaluate the November 3, 2002, seismic event. The AR OTH was reviewed to ensure the full extent of the issue was identified, appropriate evaluations were performed, and appropriate corrective actions were specified and prioritized. The inspectors evaluated the AR OTH against the requirements of the licensees corrective action program as delineated in 5AWI 16.0.0, Action Request Process.
b. Findings and Observations
There were no findings identified associated with the samples reviewed. However, the inspectors identified one corrective action to revise the emergency plan implementing procedure (EPIP) F3-2, Classification of Emergencies, which could result in a decrease in effectiveness. Revision 32 to EPIP F3-2 was intended to provide operators with better guidance for determining when a seismic event met the emergency classification criteria. The change added a requirement for shift supervisor (SS) or shift manager (SM) or emergency director (ED) opinion, to the Unusual Event classification for the Natural Events condition under the Any Confirmed Earthquake initiating condition. Adding the subjective requirement for the SM to make a judgement call conflicts with Appendix E. IV. B, which states that emergency action levels shall be based on in-plant conditions and instrumentation in addition to onsite and offsite monitoring.
Additionally, guidance in NUREG 0654, Appendix 1-3 states, in part, the rationale for the unusual event and alert classes is to provide early and prompt notification of minor events which could lead to more serious consequences given operator error or equipment failure. The conflicting condition created in this initiating condition could challenge operator consistency in determining emergency classifications as well as providing early and prompt notifications of minor events. The NRC expects the SM or ED to use judgement on all emergency classifications. However, in changing this emergency action level, if the SS or SM or ED declared an emergency using opinion incorrectly, then the change would be a decrease in effectiveness and the licensees PINGP 1239, Emergency Plan 50.54(q) Review Screening, process would be incorrect.
4OA3 Event Followup
.1 Closure of Unresolved Item (URI) 50-306/01-13-02: Potential Failure to Provide
Complete and Accurate Information.
a. Inspection Scope
The inspectors reviewed the circumstances associated with URI 50-306/01-13-02. The inspectors also reviewed Enforcement Action (EA)-01-248 dated December 11, 2001 and EA-02-068 dated December 13, 2002.
b. Findings
URI 50-306/01-13-02 documented an apparent failure of the licensee to provide complete and accurate information to the NRC. After further review, the NRC determined that a violation of NRC requirements occurred. The resolution of this issue is documented in EA-02-068 dated December 13, 2002. URI 50-306/01-13-02 is closed.
.2 (Closed) LER 50-282/03-001-00: Residual Heat Removal Valve CV-31236 Positioner
Linkage Found Broken.
On or about December 4, 2002, a wrench was inappropriately left resting on the positioner for the Unit 1, B train residual heat removal heat exchanger outlet valve CV-31236 by licensee personnel. Subsequently, the wrench fell off the positioner becoming entangled with the positioner feedback linkage causing the linkage to bind and fail. The licensee identified this condition on March 3, 2003, and entered the condition into their corrective action program with AR CAP 028703. The valve was found in its safeguards position and could be opened and closed from the control room allowing the system to perform its safety functions. Upon discovery, the licensee declared the B train of the residual heat removal system inoperable, repaired the valve positioner linkage, and successfully tested the valve.
The inspectors reviewed the licensees root cause investigation, immediate corrective actions, and corrective actions to prevent recurrence to verify that the proposed corrective actions addressed the causes of the event and fully restored the function of CV-31236. The inspectors also assessed the significance of the finding using significance determination process. Because the resulting linkage failure did not cause a loss of safety function of the affected train and the redundant train remained operable, the finding screened out of the phase one worksheets was not more than of very low safety significance (Green). The licensees inappropriate control of tools is being treated as a Non-Cited Violation (see report section 4OA7).
.3 (Closed) LER 50-282, 306/03-002-00: Appendix R Safe Shutdown Analysis Issues.
On March 26, 2003, an evaluation of potential flow diversions was in progress resulting from LER 50-282, 306/98-015-00, Containment to RHR [Residual Heat Removal]
MOVs [Motor-Operated Valve] Appendix R Safe Shutdown Analysis Issues. The evaluation determined that, absent compensatory measures, the ability to safely shut down could have been adversely affected in two cases. In the first case, a postulated fire in certain areas could result in a spurious start of a containment spray pump and spurious opening of its associated discharge motor-operated valve, which would divert the sole credited source of reactor coolant system makeup, the refueling water storage tank, into containment. In the second case, the scavenging and combustion air dampers for the diesel-driven emergency cooling water pumps were found to be vulnerable to postulated fires in certain areas. The licensee entered the condition into their corrective action program with AR CAPs 024537 and 028574. Compensatory measures were added to the plant procedures for control room evacuation fire and fire outside the control room.
The inspectors reviewed the licensees immediate corrective actions, and planned corrective actions to verify implementation. The LER was reviewed by the inspectors and no findings of significance were identified. This LER is closed.
4OA5 Other Activities
The unresolved item pertains to the Security Equipment performance indicator (PI). The Security Equipment PI consists of counting compensatory hours for the perimeter intrusion detection system (IDS) and the closed circuit television (CCTV) system. The PI value is determined by adding the IDS Unavailability Index plus the CCTV Unavailability Index and dividing by 2. At Prairie Island, compensatory measures for the CCTV system are not required except for catastrophic equipment failures that exceed the ability of the on-duty security force to compensate for. Therefore, the current PI value for the Protected Area Security Equipment shows only half the out-of-service time requiring compensatory man-hours for the perimeter detection system. The URI is if Prairie Island should use the part of the PI formula pertaining to CCTV compensatory hours since the security force is not required to routinely compensate for CCTV degradations. This issue is being evaluated by NRC Headquarters and resolution of the issue will be addressed by separate correspondence.
4OA6 Meeting(s)
.1 Interim Exit Meetings
- Emergency Preparedness inspection with Mr. R. Lingle on April 4, 2003;
- Radiation Protection inspection with Mr. Joe Solymossy, Site Vice President on April 11, 2003;
- Access Control to Radiologically Significant Areas, Radiation Monitoring Instrumentation and Protective Equipment, and Performance Indicator Verification for Occupational Exposure Control Effectiveness with Mr. J. Solymossy on June 6, 2003; and
- Temporary Instruction 2515/148, Inspection of Nuclear Reactor Safeguards Interim Compensatory Measures with Mr. J. Solymossy on June 27, 2003.
- Safeguards inspection with Mr. J. Solymossy on June 27, 2003.
.2 Exit Meeting
The resident inspectors presented the inspection results to Mr. M. Werner and other members of licensee management on June 30, 2003. The inspectors asked the licensee whether any materials examined during the inspection should be considered proprietary. No proprietary information was identified.
4OA7 Licensee-Identified Violations
The following violations of very low significance were identified by the licensee and are violations of NRC requirements which meets the criteria of Section VI of the NRC Enforcement Manual, NUREG-1600, for being dispositioned as Non-Cited Violations.
Cornerstone: Mitigating Systems
Failure of the 12 Residual Heat Removal Heat Exchange Outlet Flow Control Valve Prairie Island Technical Specifications, Section 5.4 requires that written procedures recommended in Regulatory Guide 1.33, Revision 2, Appendix A shall be established, implemented and maintained. Administrative Work Instruction 5AWI 8.5.0, Housekeeping and Material Control, Revision 4 establishes requirements for the control of work activities, conditions, and environment that could affect quality.
Section 6.5 requires the control of tools used during maintenance activities be removed upon completion of the work. On or about December 4, 2002, an adjustable wrench was inappropriately left behind at the work site. The wrench was apparently left resting on the positioner for the Unit 1, B train residual heat removal heat exchanger outlet valve CV-31236. The wrench fell off the positioner becoming entangled with the positioner feedback linkage causing the linkage to bind and fail. The licensee entered this condition into their corrective action program with AR CAP 028703. Because the resulting linkage failure did not cause a loss of safety function of the affected train and the redundant train remained operable this violation is not more than of very low safety significance, and is being treated as a Non-Cited Violation.
KEY POINTS OF CONTACT Licensee M. Agen, Emergency Planning Manager T. Allen, Production Planning Manager T. Amundson, Manager Business Support R. Best, Maintenance Rule Coordinator L. Finholm, Emergency Planning Coordinator P. Huffman, Manager of System Engineering A. Johnson, Radiation Protection Manager J. Kivi, Licensing Engineer M. Ladd, General Superintendent Plant Maintenance D. Larimer, Radiochemistry Supervisor R. Lingle, Operations Manager M. McKeown, Manager of Design Engineering M. Nazar, Senior Vice-President S. Northard, Director of Engineering J. Payton, Emergency Planning Coordinator M. Pfeffer, Emergency Planning Trainer J. Solymossy, Site Vice-President A. Qualantone, Superintendent Security M. Werner, Plant Manager P. Wildenborg, Lead Technical Health Physicist R. Womack, Manager of Engineering Programs D. Blaskley, Senior Nuclear Security Consultant J. Corwin, Nuclear Security Consultant C. Glover, Training Coordinator (The Wackenhut Corporation)
T. Qualentone, Security Manager LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED Opened None.
Closed 50-282, 306/00-10-02 URI Calculation Method of IDS Unavailability Index 50-306/01-13-02 URI Potential Failure to Provide Complete and Accurate Information 50-282/03-001-00 LER Residual Heat Removal Valve CV-31236 Positioner Linkage Found Broken 50-282, 306/03-002-00 LER Appendix R Safe Shutdown Analysis Issues Discussed None.
LIST OF
DOCUMENTS REVIEWED
1R01 Adverse Weather
SP 1039; Tornado Hazard Monthly Site Inspection; Revision 7
Test Procedure 1636; Summer Plant Operation; Revision 14
Abnormal Procedure AB-2; Tornado/Severe Thunderstorm; Revision 20
Operating Procedure C18.1; Engineered Safeguards Equipment Support Systems;
Revision 12
Design Basis Document TOP-05; Hazards; Revision 2W
AR CAP 029758; Screenhouse Doghouse Wall Louver Screens Significantly
Obstructed; April 16, 2003
AR CAP 029893; Number of Test Procedure 1636 Fans in the Plant Exceeds
50.59 Screening # 1476 Total; April 23, 2003
AR CAP 030029; Residual Heat Removal Unit Cooler Safety Evaluation Out of Date;
April 30, 2003
1R04 Equipment Alignment
Integrated Checklist C1.1.20.7-5; D2 Diesel Generator Valve Status; Revision 17
Integrated Checklist C1.1.20.7-6; D2 Diesel Generator Auxiliaries and Room Cooling
Local Panels; Revision 8
Integrated Checklist C1.1.20.7-7; D2 Diesel Generator Main Control Room Switch and
Indicating Light Status; Revision 12
Integrated Checklist C1.1.20.7-8; D2 Diesel Generator Circuit Breakers and Panel
Switches; Revision 16
Motor-Driven AFW Pump
System Prestart Checklist C28-15; 12 Motor-Driven Auxiliary Feedwater Pump;
Revision 2
Integrated Checklist C1.1.20.7-9; D5 Diesel Generator Valve Status; Revision 10
Integrated Checklist C1.1.20.7-10; D5 Diesel Generator Auxiliaries and Room Cooling
Local Panels; Revision 6
Integrated Checklist C1.1.20.7-11; D5 Diesel Generator Main Control Room Switch and
Indicating Light Status; Revision 4
Integrated Checklist C1.1.20.7-12; D5 Diesel Generator Circuit Breakers and Panel
Switches; Revision 8W
Safety Injection Pump
Integrated Checklist C1.1.18-2; Safety Injection, Containment Spray, Caustic Addition,
and Hydrogen Control System Checklist, Unit 2; Revision 35
Design Basis Document 18A; Design Basis Document for the Safety Injection System;
Revision 4
System Alignment Problem Identification and Resolution Reviews
AR CAP 030515; Switch Positions Different Between Logic Diagram and Label Plate;
May 28, 2003
AR CAP 030521; Unlabeled Drain Valve in Fire Protection Line; May 28, 2003
AR CAP 030524; Safety Injection Recirculation Pump-Isolation Valve Discrepancy;
May 28, 2003
1R05 Fire Protection
Fire Zone Walkdowns
Plant Safety Procedure F5, Appendix A; Fire Strategies for Fire Areas 20, 41A, 58, 59,
73, 74, 114, and 116; Revision 13
Plant Safety Procedure F5, Appendix F; Fire Hazard Analysis for Fire Areas 20, 41A, 58,
59, 73, 74, 114, and 116; Revision 17
IPEEE NSPLMI-96001, Appendix B; Internal Fires Analysis; Revision 2
Annual Fire Drill
Plant Safety Procedure F5; Fire Fighting; Revision 27
Plant Safety Procedure F5, Appendix A; Fire Strategies for Fire Area 62; Revision 11
Plant Safety Procedure F5, Appendix F; Fire Hazard Analysis for Fire Area 62;
Revision 17
Plant Safety Procedure F5, Appendix J; Fire Drills; Revision 9
Fire Protection Problem Identification and Resolution Reviews
AR CAP 026351; Structural Columns Sprayed with Fireproofing Need Periodic
Inspection; November 16, 2002
AR CA 003024; Structural Columns Sprayed with Fireproofing Need Periodic Inspection;
November 19, 2002
AR CAP 027629; Fire Detection Zone #4 Was Found in Alarm Without Causing an
Annunciator Alarm; January 13, 2003
AR CAP 030250; Welding Carts Not Meeting Minimum Separation Criteria;
May 12, 2003
AR CAP 030297; Polyethylene Tanks on 695 Aux Building for ZX [Containment
Cooling] Project; May 14, 2003
1R06 Flood Protection Measures (External)
USAR 2.4.3.5; Floods; Revision 24
Calculation ENG-ME-529; Flood Barrier Leakage Criteria; Revision 0
SP 1293; Inspection of Flood Control Measures; Revision 11
AB-4; Flood; Revision 22
AR CAP 029164; All Flood Control Sealant On Site is 22 Months Old; March 21, 2003
AR Condition Evaluation (CE) 002374; Evaluate Why Sealant Is Not Included in Shelf
Life Program; March 25, 2003
AR CAP 029197; Bottom Anchor Bolts for Door 257 & 258 Flood Panels Corroded
and/or Dirty; March 24, 2003
AR CAP 029207; Contents of Flood Panel Storage Boxes Not Checked During Recent
SP 1293; March 24, 2003
AR CAP 029215; AB-4 Flood Sealant Application Process Differs from Manufacturers
Process; March 24, 2003
AR CE 002386; AB-4 Flood Sealant Application Process Differs from Manufacturers
Process; March 27, 2003
AR CAP 029332; Flood Control Gasket Inspection Not Completed Per SP 1293
Expectations; March 28, 2003
AR CA 005152; Inadequate Guidance in AB-4 Regarding Caulking of Flood Door 164;
April 15, 2003
AR CAP 029800; Corrective Action (CA 005152) Issued Instead of CAP Resulting in
Orphan CA; April 18, 2003
AR CAP 029815; Inadequate Guidance in AB-4 Regarding Caulking of Flood Door 164;
April 18, 2003
1R06 Flood Protection Measures (Internal)
NSPLMI-94001; Prairie Island Nuclear Generating Plant Individual Plant Examination;
Revision 0
Design Basis Document TOP-05; Design Bases Document for in Hazards; Revision 2
Plant Procedure H36; Plant Flooding; Revision 0
5AWI 8.9.0; Internal Flooding Drainage Control; Revision 1
1R07 Heat Sink Performance
Inspection of D1 EDG Lubricating Oil and Jacket Water Heat Exchangers
Prairie Island Nuclear Generating Plant Form 1066; Cooling Water Heat Exchanger
Internal Inspection for the D1 Diesel Generator Jacket Water Heat Exchanger; April 21,
2003
Prairie Island Nuclear Generating Plant Form 1066; Cooling Water Heat Exchanger
Internal Inspection for the D1 Diesel Generator Lubricating Oil Heat Exchanger; April 21,
2003
Engineering Analysis ENG-ME-409; Unit 1 Emergency Diesel Generator Heat
Exchanger Performance with Reduced Cooling Water Flow; Revision 0
Engineering Analysis ENG-ME-479; Tube Plugging Criteria for Unit 1 Diesel Generator
Heat Exchangers; Revision 0
Engineering Analysis ENG-ME-480; Operability Determination for Unit 1 Diesel
Generator Heat Exchangers with Tubes Plugged and 85 °F Cooling Water; Revision 0
Heat Sink Problem Identification and Resolution Reviews
AR CAP 025841; 124 Air Compressor Cooling Jacket Full of Mud; October 17, 2002
AR CA 002659; 124 Air Compressor Cooling Jacket Full of Mud; October 22, 2002
AR CAP 030899; Inadequate Formal Guidance to Ensure Flushing of Station Air
Compressors; June 17, 2003
1R11 Licensed Operator Requalification Program
5AWI 3.15.0; Plant Operation; Revision 13
1R12 Maintenance Rule Implementation
Unit 1 and 2 Instrument and Station Air Systems
USAR Section 10.3.10; Compressed Air System; Revision 23
Plant Procedure B34; Instrument and Station Air; Revision 4
Top 10 Equipment Issues List; April 23, 2003
Maintenance Rule System Specific Basis Document; Revision 5
Maintenance Rule Monthly Equipment Performance Report; January 2003
Summary of PINGP Maintenance Rule Scope Determination and Performance Criteria;
May 1, 2003
AR CAP 008161; Air Compressor Required Rework After Valved Back Into Service;
May 31, 2001
AR CAP 023021; Degradation of Pipe On Discharge of 121 Air Compressor;
April 3, 2002
AR CAP 023544; Instrument Air System Improper Operation; May 17, 2002
AR CAP 024485; Needed to Reisolate 124 Air Compressor Due to Loose Belts;
August 6, 2002
AR CAP 024564; Air Compressors Inclusion On Top 10 Equipment List; August 8, 2002
AR CAP 024623; Replacement of CV31191 Does Not Correct Problem with Unloader
Leaking Air; August 13, 2002
AR CAP 025841; 124 Air Compressor Cooling Jacket Full of Mud; October 17, 2002
AR CAP 026355; Potential Silting/Sediment Concerns with Plant Equipment and
Systems; November 16, 2002
AR CAP 027805; CV-39194 Has an Air Leak; January 23, 2003
AR CAP 028600; 123 Instrument Air Compressor Had to Be Shut Down Due to Lack of
Cooling Water; February 27, 2003
AR CAP 029180; Failure of 124 Station Air Compressor to Start; March 23, 2003
Cooling Water Pump Packing and Shaft Bearing Lubrication
AR CAP 030128; 21 Cooling Water Pump; May 5, 2003
AR MRE 000158; Maintenance Rule Evaluation; May 6, 2003
AR Apparent Cause Evaluation (ACE) 008704; 21 Cooling Water Pump; May 6 2003
Maintenance Rule A(1) Action Plan; Cooling Water System; Revision 1
SP 1845; Test Three-Way Valve Actuation to Cooling Water Supply for 12 DDCLP
[Diesel-Driven Cooling Water Pump] Bearing Water; Revision 0; May 19, 2003
SP 1846; Test Three-Way Valve Actuation to Cooling Water Supply for 12 DDCLP
Bearing Water; Revision 0; May 1, 2003 and May 20, 2003
SP 1847; Test Three-Way Valve Actuation to Cooling Water Supply for 12 DDCLP
Bearing Water; Revision 0; May 4, 2003
Operator Work Arounds; June 13, 2003
AR CAP 030227; Well Water Restoration Did Not Resolve CL [Cooling Water] Pump
Seal Filter Operator Burden; May 11, 2003
1R13 Maintenance Risk Assessments and Emergent Work Control
Planned Maintenance on 1RYBT, 2RYBT, and Breakers 14-4,13-1, 24-9, and 23-9
Plant Status Report; April 15, 2003
Risk Assessment for Proposed Work for Week of 3205A; April 15, 2003
Operations Log Entries; April 14 -15, 2003
Section Work Instruction O-59; Protected Equipment Program; Revision 1
Plant Procedure H24.1; Assessment and Management of Risk Associated with
Maintenance Activities; Revision 5
Planned Maintenance 12 Diesel-Driven Cooling Water Pump, the 11 Turbine-Driven
Auxiliary Feedwater Pump, and the 11 Component Cooling Water Pump
Plant Status Report; April 22, 2003
Risk Assessment for Proposed Work for Week of 3206A; April 20, 2003
Operations Log Entries; April 21-22, 2003
Plant Procedure H24.1; Assessment and Management of Risk Associated with
Maintenance Activities; Revision 5
Planned Maintenance on the D1 EDG and 12 Diesel-Driven Cooling Water Pump
Plant Status Report; April 23, 2003
Risk Assessment for Proposed Work for Week of 3206A; April 20, 2003
Operations Log Entries; April 22-23, 2003
Plant Procedure H24.1; Assessment and Management of Risk Associated with
Maintenance Activities; Revision 5
Emergent Work on 21 Cooling Water Pump
Plant Status Report; May 6, 2003
Risk Assessment for Proposed Work for Week of 3208B; May 6, 2003
Operations Log Entries; May 5 - 6, 2003
Plant Procedure H24.1; Assessment and Management of Risk Associated with
Maintenance Activities; Revision 5
Planned Maintenance on the 22 Safety Injection Pump, 22 Residual Heat Removal
Pump, and the Unavailability of the Residual Heat Removal Pump Discharge to Safety
Injection Pump Suction Motor-Operated Valve MV-32209
Plant Status Report; May 28, 2003
Risk Assessment for Proposed Work for Week of 3211B; May 27, 2003
Operations Log Entries; May 27 - 28, 2003
Plant Procedure H24.1; Assessment and Management of Risk Associated with
Maintenance Activities; Revision 5
Planned Maintenance on the 122 Instrument Air Dryer and the 22 Turbine-Driven
Auxiliary Feedwater Pump
Plant Status Report; May 30, 2003
Risk Assessment for Proposed Work for Week of 3211B; May 27, 2003
Operations Log Entries; May 29 - 30, 2003
Plant Procedure H24.1; Assessment and Management of Risk Associated with
Maintenance Activities; Revision 5
Planned Maintenance on the 12 Safety Injection Pump, 12 Residual Heat Removal
Pump, 122 Instrument Air Compressor, and the Unavailability of the Residual Heat
Removal Pump Discharge to Safety Injection Pump Suction Motor-Operated Valve
MV-32207
Plant Status Report; June 5, 2003
Risk Assessment for Proposed Work for Week of 3212B; June 3, 2003
Operations Log Entries; June 4 - 5, 2003
Plant Procedure H24.1; Assessment and Management of Risk Associated with
Maintenance Activities; Revision 5
Emergent Work on 21 Residual Heat Removal Pump
Prairie Island Work Week 3301A; High Level Summary
Risk Assessment for Proposed Work for Week of 3301A; June 9, 2003
Operations Log Entries; June 10 - 11, 2003
Plant Procedure H24.1; Assessment and Management of Risk Associated with
Maintenance Activities; Revision 5
AR CAP 030769; Unplanned Limiting Condition for Operation Not Met Due to 21
Residual Heat Removal Pump Out-of-Service
Risk Assessment Problem Identification and Resolution Reviews
AR CAP 024708; Protected Equipment Signs Continue to be Ineffective; August 17,
2002
ACE 008536; Protected Equipment Signs Continue to be Ineffective; August 20, 2002
AR CAP 024726; Signs; August 19, 2002
AR CA 001982; Signs; August 20, 2002
AR CAP 030128; 21 Cooling Water Pump; May 5, 2003
AR CAP 030772; 21 RHR [Residual Heat Removal] Pump Removed from Service and
No Reevaluation of Risk was Performed
1R15 Operability Evaluations
Inadequate Thread Engagement on the 12 Safety Injection Pump
AR CAP 028899; Inadequate Thread Engagement on 12 Safety Injection Pump Seal
Water Supply and Return Flanges; March 12, 2003
Maintenance Procedure D63; Installation Guidelines for Threaded Fasteners;
Revision 11
AR CAP 029432; Flange on 11 Feedwater Pump Discharge Line Has Inadequate
Thread Engagement on One Stud; April 1, 2003
AR CAP 029535; Concerns with the Adequacy of Thread Engagement Corrective
Actions; April 6, 2003
AR CAP 029534; Weakness in Calculation ENG-CS-080, Acceptable Thread
Engagement; April 6, 2003
AR CAP 029624; Inadequate Thread Engagement on Body-to-Bonnet Studs on Motor
Valves MV-32335 and MV-32336; April 10, 2003
AR 029655029655 Degraded Studs on Two Safety Injection Valves; April 10, 2003
Degraded 122 Safeguards Traveling Screen
AR CAP 029638; Degraded Screen Condition Noted On Safeguard Traveling Screen;
April 10, 2003
Design Basis Document System 35; Cooling Water System; Revision 4W
Prairie Island Drawing NF-38607-2B; Circulating Water System Emergency Cooling
Water Intake Crib Details; Revision B
AR CAP 030789; Issues with Operability Evaluations in CAPs; June 11, 2003
AR CAP 030825; 122 Safeguard Traveling Screen Degraded Due to Enlargement of
Holes in the Mesh; June 12, 2003
RCP Seal Leakoff
AR CAP 029823; Significant Perturbation in 21 RCP Seal Leakoff; April 19, 2003
AR CE 002513; Significant Perturbation in 21 RCP Seal Leakoff; April 19, 2003
Temporary Change Notice 2003-0459; Component Cooling Heat Exchanger Quarterly
Test; May 9, 2003
Operator Log Entries; April 19, 2003
Emergency Response Computer System Trend Display; 21 RCP; April 18 - 21, 2003
Abnormal Operating Procedure 1C3AOP3; Failure of a Reactor Coolant Pump Seal;
Revision 11
Operating Information No. 03-74; 21 RCP; April 17, 2003
Three Holes in Flood Door 73
AR CAP 030191; Existence of Three Small Holes in Flood Door 73; May 9, 2003
OPR 000408; Existence of Three Small Holes in Flood Door 73; May 9, 2003
AR CAP 030217; Inadequate Operability Review for Flood Door 73; May 9, 2003
Containment Fan Cooler Unit High Vibrations
AR CAP 030359; 14 Containment Fan Cooler Unit Has High Vibrations in the Danger
Range; May 17, 2003
CE 002701; 14 Containment Fan Cooler Unit Has High Vibrations in the Danger Range;
May 19, 2003
AR CAP 030789; Issues with Operability Evaluations in CAPs; June 11, 2003
Breaker 26-10, 22 Safety Injection Pump Oil Leak
AR CAP 030519; Breaker 26-10 (22 Safety Injection Pump) Found Puddle of Oil on
Cubicle Floor Under Charging Motor; May 28, 2003
OPR 000415; Breaker 26-10 (22 Safety Injection Pump) Found Puddle of Oil on Cubicle
Floor Under Charging Motor; May 28, 2003
1R16 OWAs
RCP Seal Leak-Off
Operator Workarounds List; May 1, 2003
AR CAP 028083; 21 RCP Number 1 Seal Leak-Off Decreased to Less Than 1.5 GPM;
February 5, 2003
AR CAP 030223; Swapped 11 and 121 Cooling Water Pumps for SP 1106C; May 10,
2003
Root Cause Evaluation 000182; 21 RCP Number 1 Seal Leak-Off Decreased to Less
Than 1.5 GPM; April 17, 2003
Operating Information No. 03-74; 21 Reactor Coolant Pump; April 17, 2003
Cumulative Effects of OWAs
5AWI 3.10.8; Equipment Problem Resolution Process; Revision 3
PINGP List of Operator Workarounds; May 8, 2003
Operator Work Around Aggregate Impact; First Quarter; May 1, 2003
Operating Information No. 03-83; 13 Charging Pump; May 7, 2003
1R17 Permanent Plant Modifications
Design Change 01RH01; RHR Discharge Pressure Loop 1E/Non-1E Separation;
Revision 1
WO 0113782; Remove Interlock & PreOp 1P-628 and MV-32207; June 4, 2003
Plant Procedure 1ES-1.2; Transfer to Recirculation; Revision 16; Temporary Change
Notice 2003-0293; March 26, 2003
Plant Procedure 1ES-1.3; Transfer to Recirculation with One Safeguard Train Out of
Service; Revision 11; Temporary Change Notice 2003-0294; March 26, 2003
Alarm Response Procedure C47016; 12 RHR Pump Hi Press; Revision 37; Temporary
Change Notice 2003-0566; June 5, 2003
AR CAP 004995; Information from Kewaunee Questions Quality Requirements of RHR
Discharge Pressure Loops; May 18, 2000
AR CAP 030713; LCO Times for B Train ECCS [Emergency Core Cooling System]
During WO 0113782 and 0107579; June 6, 2003
AR CAP 030744; Some Reactor Protection and Safeguards Racks are Missing Hinge
Bolts; June 8, 2003
1R19 Post-Maintenance Testing
Cooling Water Strainer
WO 0209509; 21 Cooling Water Strainer Annual Inspection; March 30, 2003
Preventive Maintenance Procedure PM 3109-1-21; 21 Cooling Water Strainer Annual
Inspection Equipment I.D. 258-011; Revision 9
Plant Procedure B35; Cooling Water System; Revision 6
Diesel-Driven Cooling Water Pump
WO 0209135; Test Relays/Circuit Logic for 10 Year Relay Replacement; April 6, 2003
SP 1106B; 22 Diesel-Driven Cooling Water Pump Monthly Test; Revision 60
AR CAP 029637; Poor Work Package for WO 0209135; April 10, 2003
AR CAP 029641; Headset Communications Seriously Degraded; April 10, 2003
AR CAP 029701; 22 DDCLP Post Job Comments/Concerns; April 14, 2003
WO 0208525; Correct Air-Coolant Water Leakage at 4 Inch Slip-Joint
WO 0204450; Correct Cause of Oscillating Turbocharger to Blower Air Inlet Check
Valve
WO 0211329; Replace Engine Driven Jacket Water Coolant Pump
WO 0114131; Replace Damaged Jacket Water Sensing Line
WO 0202328; Correct Oil Leakage at Pipe and Tubing Connections
WO 0115719; 1DG-20 Valve and Pipe Have External Lubricating Oil Leakage
WO 0210728; Packing Leak on CV-31954, Adjust Valve Packing
WO 0201648; Repair Air Leak at 1DG-26
WO 0212021; Replace Pipe and Tubing on D1 Starting Air Compressor
WO 0212020; Replace D1 Air Compressor Valve Unloaders
Preventive Maintenance Procedure PM 3001-2-D1; D1 Diesel Generator 18 Month
Inspection; Revision 18
SP 1295; D1 Diesel Generator 6 Month Fast Start Test; Revision 31
SP 1334; D1 Diesel Generator 18 Month 24 Hour Load Test; Revision 7
AR CAP 029905; Starting Air Valve Leaking By During D1 Restoration; April 24, 2003
Diesel-Driven Cooling Water Pump
WO 0209497; 12 DDCLP Annual Electrical Inspection; April 16, 2003
SP 1106A; 12 Diesel-Driven Cooling Water Pump Monthly Test; Revision 62
AR CAP 028246; Spare Governor for DDCL Pump Leaking Oil; February 12, 2003
AR CA 004284; Spare Governor for DDCL Pump Leaking Oil; April 7, 2003
AR CAP 028320; New Allen Bradley Relays for 12 and 22 DDCLPs Are Not in Same As
in Installed; February 15, 2003
AR CA 004332; New Allen Bradley Relays for 12 and 22 DDCLPs Are Not in Same As
in Installed; April 18, 2003
AR CAP 029917; Moisture and Corrosion Products Found in 12 DDCLP SA Line During
AR CAP 029930; 12 DDCLP Starting Air Compressor Replacement; April 24, 2003
AR CAP 030123; 12 DDCLP Post-Job Critique Comments from Electrical Maintenance;
May 5, 2003
AR CAP 03124; Post-Job Critique Comments from Electrical Maintenance; May 5, 2003
Containment Spray Pump
WO 0300594; Repair 2CS-25-2
SP 2090B; 22 Containment Spray Pump Test Quarterly Test; Revision 3
AR CAP 030096; Overtime Incurred in an Attempt to Complete Scheduled Work; May 2,
2003
AR CAP 030097; Resource Load Inadequate; May 2, 2003
AR CAP 030088; Work Delayed to Next Day on 22 CS [Containment Spray] Pump;
May 2, 2003
Pressurizer Heaters
WO 0206118; Replace 480 Volt Capacitors and Test
Steam Generator Power-Operated Relief Valve
WO 0213214; Replace Splice for CV-31084
SP 1111A; Train A Monthly Main Steam Power-Operated Relief Valve Test; Revision 4
1R22 Surveillance Testing
Turbine-Driven Auxiliary Feedwater Pump
WO 0212440; SP 2102 22 Turbine-Driven AFW Pump Monthly Test; April 4, 2003
SP 2102; 22 Turbine-Driven AFW Pump Monthly Test; Revision 71
Plant Procedure B28B; Auxiliary Feedwater System; Revision 6
WO 0214650; SP 2093 D5 Diesel Generator Monthly Slow Start; April 14, 2003
SP 2093; D5 Diesel Generator Monthly Slow Start Test; Revision 72
NIS Power Range Startup Test
WO 0302065; SP 1198 Nuclear Power Range Startup Test; April 15, 2003
Operations Log Entries; April 15, 2003
AR CAP 029805; Missed Surveillance After Unit Mode Change; April 18, 2003
TS Surveillance Requirement 3.3.1.8; Reactor Trip System (RTS) Instrumentation
Surveillance; Amendment No. 158
TS Surveillance Requirement 3.0.3; Surveillance Requirement Applicability; Amendment
No. 158
D1 EDG Fast Start Test
SP 1295; D1 Diesel Generator 6 Month Fast Start Test; Revision 31
Safeguards Logic Test and Reactor Protection Logic Test
SP 1032A; Safeguards Logic Test at Power - Train A; Revision 22
SP 1035A; Reactor Protection Logic Test at Power - Train A; Revision 29
Temporary Modification O3T155, Hot Chemistry Lab Door Alarms
Temporary Modification O3T155; Addition of Hot Chemistry Lab Door Alarms
5AWI 6.5.0; Temporary Modifications; Revision 12
50.59 Screening # 1739; Addition of Hot Chemistry Lab Door Alarms
5AWI 3.3.5; 50.59 Screenings; Revision 11
AR CAP 024185; Auxiliary Building Special Ventilation Zone Boundary at Hot Chemistry
Lab; July 16, 2002
OPR 000324; Auxiliary Building Special Ventilation Zone Boundary at Hot Chemistry
Lab; July 16, 2002
Charging Pump Speed Control Feedback Loop
AR CAP 030038; 23 Charging Pump Speed Feedback Loop Bypassed Without T-Mod;
April 30, 2003
USAR 10.2.3; Chemical and Volume Control System; Revision 25
Plant Procedure B12A; Chemical and Volume Control; Revision 7
5AWI 3.9.0; Bypass Control; Revision 6
5AWI 6.5.0; Temporary Modifications; Revision 12
5AWI 15.5.1; Plant Equipment Control and Clearance Process; Revision 9
1EP2 Alert and Notification System (ANS) Testing
PINGP 1120; ANS Monthly Trend Reports; October 2001 through February 2002
SP 1397; Emergency Plan Fixed Siren Test; Revision 1
Sirens Forms; Failure Matrix; November 2001 though March 2002
Nelcom Procedure; Siren Post Maintenance and Post Service Operability
5AWI 6.1.4; Emergency Siren Replacement Project/Design Change 01NS03; Revision 0
NATEK Inc. Letter to Federal Emergency Management Agency; Technical Review of
Prairie Island Design Change #01NS03, Update and Replacement of the Public Alert
and Notification System; March 19, 2003
Dakota County Emergency Response Plan; Annex A: Warning and Notification;
Revision 2
1EP3 Emergency Response Organization (ERO) Augmentation Testing
Sections 5.3 and 8.1; Prairie Island Nuclear Generating Plant; Revision 24
PINGP 581; Emergency Organization Call List; Revision 73
PINGP 948; Switchboard Operator Call List; Revision 55
PINGP 1334; Implementing ERO Duty Roster Change Management Plan
SP 1744; Semi-Annual Emergency Organization Augmentation Response Test;
Revision 25
SP 1744; Semi-Annual Emergency Organization Augmentation Response Test;
November 6, 2001
SP 1744; Semi-Annual Emergency Organization Augmentation Response Test;
January 22, 2002
SP 1744; Semi-Annual Emergency Organization Augmentation Response Test;
May 2, 2002
SP 1744; Semi-Annual Emergency Organization Augmentation Response Test;
September 18, 2002
SP 1744; Semi-Annual Emergency Organization Augmentation Response Test;
November 11, 2002
SP 1744; Semi-Annual Emergency Organization Augmentation Response Test;
February 10, 2003
1EP4 Emergency Action Level and Emergency Plan Changes
PINGP Emergency Plan; Revisions 24, 25, 26, and 27
1EP5 Correction of Emergency Preparedness Weaknesses and Deficiencies
5AWI 16.0.0; Action Request Process; Revision 3
PINGP SA021240; Emergency Preparedness Focused Self-Assessment;
October 29, 2002
PINPG 1239; Emergency Plan 50.54(q) Review Screening Form; February 9, 2003
2002-001-6-040; Nuclear Oversight Observation Report; April 17, 2002
2002-004-6-030; Nuclear Oversight Observation Report; December 5, 2002
2002-004-6-031; Nuclear Oversight Observation Report; November 18, 2002
2003-001-6-009; Nuclear Oversight Observation Report; January 28, 2003
2003-001-6-021; Nuclear Oversight Observation Report; February 6, 2003
EPIP F3-2; Emergency Classification; Revisions 32 and 33
AR ACE 008644; Drill - Radiation Protection Group Failed to Recognize General
Emergency EAL [Emergency Action Level] Met in a Timely Manner; January 31, 2003
AR OTH 023756; Evaluate the Emergency Plan Results of the November 3, 2002
Seismic Abnormal Event; January 9, 2003
AR OTH 024673; Review the February 2003 EP Self Assessment for Minor Issues that
Need Follow-up; February 20, 2003
AR CAP 023528; Classification Problems During 2002 Emergency Plan Exercise;
May 17, 2002
AR CAP 023723; Potentially >30% of Sirens Not Functional During Test; June 5, 2002
AR CAP 023826; Install a Plant Public Address Speaker in the OCA [Owner Controlled
Area] Gate House; June 13, 2002
AR CAP 023853; 2002 Exercise OSC [Operational Support Center]-Plant Page Quality
Poor in Turbine Building; June 14, 2002
AR CAP 024049; Unreliable Meteorological Information for Emergency Notification;
July 2, 2002
AR CAP 024409; One Question on F3-2 Classification Exercise #2 Was Frequently
Missed; July 31, 2002
AR CAP 024638; Semi-Annual ERO Augmentation Test Position Substitution
Assessment; August 13, 2002
AR CAP 024965; Shield Building High Range Stack Gas Monitor Out of Service;
August 30, 2002
AR CAP 025646; F3-2 Classification for Fires Per 11A Need to Re-evaluate;
October 8, 2002
AR CAP 025712; Emergency Classification Opportunity Missed on Simulator;
October 11, 2002
AR CAP 025952; 2002 EP Fall Drill - Plant Evacuation Ordered in an Untimely Manner;
October 24, 2002
AR CAP 027943; Drill - Radiation Protection Group Failed to Recognize General
Emergency EAL Met in a Timely Manner; January 29, 2003
AR CAP 028116; 2002 Emergency Plan Exercise CAPs (Not Closed & No Indication of
Screening Results; February 6, 2003
AR CAP 029222; 60 Meter B Wind Direction Sticking; March 25, 2003
AR CAP 029512; NRC Observation Made During April 4, 2003 Emergency Plan
Inspection Exit Regarding Potential Decrease in Effectiveness for EAL Change;
April 4, 2003
AR CE 001283; 2002 EP Fall Drill - Plant Evacuation Ordered in an Untimely Manner;
October 30, 2002
2OS1 Access Control to Radiologically Significant Areas
Radiation Work Permit 138; Sluice Resin from Spent Resin Tank to HIC; Revision 0
AR CAP 029837; No Follow-up on Positive Entrance Wholebody Count; April 21, 2003
AR CAP 029945; Radiation Dose Caused by 1000 mr/hr [millirem per hour] Drum on
Next Floor Above Work Area; April 25, 2003
AR CAP 030240; Dose Rates on Ion Exchangers; May 12, 2003
AR CAP 030256; Timekeeping Was Not Required for TWP for Resin Liner
Disconnecting of Hoses; May 12, 2003
CAP 0300266; Worker Reached Across Boundary; May 13, 2003
AR CAP 030263; No Procedure for Set-up and Removal of High Level Liner Manifold;
May 13, 2003
Radiation Protection Implementing Procedure (RPIP) 1104; Neutron TLD Monitoring;
Revision 8
2OS3 Radiation Monitoring Instrumentation and Protective Equipment
AR CAP 002803; Manufacturer Notice on Potential SCBA Alarm Proble; November 4,
2002
AR CAP 003894; Prairie Island Management Should Consider Revising Expectation for
Use of SCBA During Fire Drills to Conform with Current Norms; January 13, 2000
AR CAP 004090; Manufacturer Recommended SCBA Air Flow Test was Not Performed;
February 6, 2003
AR CAP 024729; Control Room Breathing Air System - Low Outlet Pressure;
August 19, 2002
AR CAP 025817; Sensitivities of Radiation Monitors Providing Leak Detection Indication;
October 16, 2002
AR CAP 025136; Control Room Breathing Air Outlet Pressures Below Specification;
September 10, 2002
AR CAP 028337; Operations Required Lens Program Outdated and Inaccurate;
February 17, 2003
AR CAP 029307; RWST [Refueling Water Storage Tank] High Level Alarms, Should
Consider Revising Alarm Setpoints or Drain RWSTs; March 27, 2003
AR CAP 030693; Non-SCBA Materials Placed in OSC Cabinet Designated for SCBAs;
June 5, 2003
AR CAP 030694; Control Room Operator with Goatee Not Meeting Expectations for Fit
Test; June 5, 2003
AR CAP 030695; Expected Air Volume Not Immediately Available from CR [Control
Room] Breathing Air System; June 5, 2003
AR CAP 030696; Control Room Operator Respirator Fit Test Expired; June 5, 2003
AR ACE 006818; Converted Issue 20010862, Personnel that Maybe Assigned to
Emergency Repair Teams are Not Qualified to Wear Respirators and/or SCBA;
March 30, 2002
AR Root Cause Evaluation 000169; PINGP Root Cause Evaluation Report -
Deficiencies in Respirator Protection Qualifications; June 24, 2002
Observation Report 2002-002-6-022; Nuclear Oversight Observation Report - Radiation
Protection - Radiation Monitoring Instrumentation Accuracy and Operability; May 24,
2002
Self-Assessment of Radiation Protection Instrumentation Control; October 9, 2001
SP 1783.1; Westinghouse Radiation Monitor Electronic Calibration; Revision 5
SP 1783.2; Nuclear Management Company Radiation Monitor Electronic Calibration;
Revision 7
SP 1783.4; High Range Radiation Monitor Electronic Calibration; Revision 4
RPIP 1704; Eddy Current Testing and SG [Steam Generator] Primary Side Repair;
Revision 15
RPIP 1701; Underwater Diving Operations; Revision 7
RPIP 1210; Charging SCBA Air Cylinders; Revision 7
RPIP 1223; Fastscan Stand Up Whole Body Counting; Revision 8
RPIP 1224; Calibration and Manager Menu Operations for the Fastscan WBC [Whole
Body Count]; Revision 3
RPIP 1617; Minirad Monitor Model 3500 Description and Calibration; Revision 8
RPIP 1667; Electron Dosimeter Description and Calibration; Revision 9
CSDS-076; Confined Space Data Sheet Report - Steam Generator Primary Manways;
April 30, 2003
RPIP 4650; Gas Calibration of R22, R30, R35, and R37; Revision 0
Revision 13
Updated Safety Analysis Report, Section 7; Revision 24
2PS3 Radiological Environmental Monitoring and Radioactive Material Control Programs
GQS Observation Report 2001082; REMP/Radioactive Waste and Sealed Sources
Self-Assessment; June 27, 2001
GQS 2001088; REMP Program Implementation; July 10, 2001
SA021240; Self-Assessment of Emergency Preparedness; August 8, 2002
AR CAP 024566; REMP Air Sampler P-4 had Approximately 45 Hours Lost Time Week
of August 4, 2002; August 8, 2002
AR CAP 026787; REMP Air Sampler P-2 Found with no Flow; November 27, 2002
AR CAP 027688; REMP Air Sampler P-4 Indicated 16 Hours Less Than Expected;
January 16, 2003
AR CAP 029623; REMP Shipment Delayed Due to Missing Label; April 10, 2003
AR 20017964; REMP Air Sampler at P1 Found Running but no Air Flow; Weekly
Sample Missed; November 26, 2001
Test Procedure 1676; Meteorological Instruments Calibration; Revision 8
Test Procedure 1677; Meteorological Instrumentation Monthly Test; Revision 14
2001 Annual Radiological Environmental Monitoring Report; May 15, 2002
Annual Review of MIDAS Meteorological Data 2002
NUPIC [Nuclear Utilities Procurement Issues Committee] Audit Number 17795; NUPIC
Joint Audit of Environmental, Inc. Northbrook, IL; August 13, 2001
Radiation Protection Implementing Procedure 1302; Unconditional Release of Materials;
Revision 15
3PP2 Access Control
SP 1620, Quarterly Metal Detector Calibration; Rev 12, January 23, 2003
SP 1621, Explosive Vapor Detector Annual Test; Rev 14, August 16, 2002
SP 1653, X-Ray Machine Quarterly Test; Rev 7, January 23, 2003
Loggable Security Events from June 11, 2002 to June 15, 2003
PINGP Security Shift Activity Reports from June 11, 2002 to June 15, 2003
3PP3 Response to Contingency Events
SIP 3.5, Protective Strategy and Response Procedure, January 17, 2003
SP 1651, Weekly Perimeter Intrusion Detection System (PIDS) Functional Test; Rev 22,
October 22, 2002
4OA1 Performance Indicator Verification
Calculated Performance Indicator Data for the Unit 1 and Unit 2 Safety System
Unavailability of the Residual Heat Removal System for the 2nd Quarter 2002, 3rd
Quarter 2002, 4th Quarter 2002, and the 1st Quarter 2003
Calculated Performance Indicator Data for the Unit 1 and Unit 2 Reactor Scrams for the
2nd Quarter 2002, 3rd Quarter 2002, 4th Quarter 2002, and the 1st Quarter 2003
Calculated Performance Indicator Data for the Unit 1 and Unit 2 Reactor Scrams with
Loss of Normal Heat Removal for the 2nd Quarter 2002, 3rd Quarter 2002, 4th Quarter
2002, and the 1st Quarter 2003
Unit 1 Operating Logs from April 1, 2002 through March 31, 2003
Unit 2 Operating Logs from April 1, 2002 through March 31, 2003
Plant Procedure H33.2; Mitigating Systems Cornerstone Unavailability Performance
Indicator Reporting Instructions; Revision 6
Plant Procedure H33.1; Performance Indicator Reporting Instructions; Revision 5
Plant Procedure H33; Performance Indicator Reporting; Revision 5
AR CAP 029671; Performance Indicator Unavailability Tracking Improvements Needed;
April 11, 2003
H33.4; Emergency Preparedness Performance Indicators Reporting Instructions;
Revision 3
Section Work Instruction EP-620; Monthly Fixed Siren Alert Test; Revision 0
Memo: PANS Fixed Siren Trend Report; April 11, 2002
PINGP 1120; Monthly Trend Report 2002 Failure Matrix; May through
December 2002
PINGP NRC Emergency Plan Participation Performance Indicator Data Sheets; April
through December 2002
PINGP 577; Emergency Notification Report Form; Second Quarter 2002 - Fourth
Quarter 2002
PINGP 580; Emergency Notification Call List for an Alert, Site Area, or General
Emergency; Second Quarter 2002 - Fourth Quarter 2002
PINGP 1326; PINGP EP Performance Record; Second Quarter 2002 - Fourth Quarter
2002
PINGP 1385; Emergency Response Organization Activation for Security Event;
June 28, 2002
Drill and Exercise Performance Data Form; Prairie Island Nuclear Generating Plant NRC
Emergency Plant Performance Indicator; April through December 2002
NPM 2003-0005; NRC Occupational Exposure Performance Indicator data for
December 2002; January 6, 2003
H33, Performance Indicator reporting; Rev 3, June 19, 2001
SAP 2.8, Quarterly Security Reports, Rev 2, March 28, 2000
PING Security Shift Activity reports for October 2002 and February 2003
Loggable Security Events from October 2002 to March 30, 2003
FFD Personnel Reliability, Personnel Screening, and Security Equipment Performance
Indicator Data worksheets FOR 4TH Quarter 2002 and 1st Quarter 2003.
4OA2 Identification and Resolution of Problems
4OA3 Event Followup
Failure of the 12 Residual Heat Removal Heat Exchange Outlet Flow Control Valve
LER 50-282/03-001-00; Residual Heat Removal Valve CV-31236 Positioner Linkage
Found Broken; Revision 0
Appendix R Safe Shutdown Analysis Issues
LER 50-282, 306/03-002-00; Appendix R Safe Shutdown Analysis Issues; Revision 0
AR CAP 024537; Appendix R Commitment Closed Prematurely; August 7, 2002
AR CAP 028574; Issues Arising from Completion of Appendix R Flow Diversion
Analysis; February 26, 2003
Plant Safety Procedure F5, Appendix B; Control Room Evacuation (Fire); Revision 27
Plant Safety Procedure F5, Appendix B; Impact of Fire Outside Control/Relay Room;
Revision 11
4OA5 Other Activities
4OA7 Licensee-Identified Violation
Failure of the 12 Residual Heat Removal Heat Exchange Outlet Flow Control Valve
Root Cause Report 000183; 12 Residual Heat Removal Heat Exchange Outlet Flow
Control Valve Positioner Found with Broken Linkage; Revision 1
AR CAP 028703; Valve Positioner Feedback Linkage Found Disconnected on
CV-31236, 12 Residual Heat Removal Heat Exchange Outlet; March 3, 2003
CE 002363; Valve Positioner Feedback Linkage Found Disconnected on CV-31236,
Residual Heat Removal Heat Exchange Outlet; March 24, 2003
Design Basis Document 15; Residual Heat Removal System; Revision 3W
5AWI 8.5.0; Housekeeping and Materiel Condition; Revision 4
LER 50-282/03-001-00; Residual Heat Removal Valve CV-31236 Positioner Linkage
Found Broken; Revision 0
LIST OF ACRONYMS USED
ACE Apparent Cause Evaluation
ADAMS Agencywide Documents Access and Management System
ANS Alert and Notification System
AR Action Request
AWI Administrative Work Instruction
CA Corrective Action
CAP Corrective Action Program
CCTV Closed Circuit Television
CE Condition Evaluation
CFR Code of Federal Regulations
CL Cooling Water
CR Control Room
CY Calendar Year
DDCL Diesel-Driven Cooling Water
DDCLP Diesel-Driven Cooling Water Pump
DRP Division of Reactor Projects
DRS Division of Reactor Safety
EA Enforcement Action
EAL Emergency Action Level
ECCS Emergency Core Cooling System
ED Emergency Director
EDG Emergency Diesel Generator
EPIP Emergency Plan Implementing Procedure
ERO Emergency Response Organization
GQS Generation Quality Services
HIC High Integrity Container
ICM Interim Compensatory Measure
IDS Intrusion Detection System
IMC Inspection Manual Chapter
IPEEE Individual Plant Examination of External Events
IR Inspection Report
LER Licensee Event Report
mr/hr Millirem Per Hour
MOV Motor-Operated Valve
MRE Maintenance Rule Evaluation
NIS Nuclear Instrumentation System
NRC U.S. Nuclear Regulatory Commission
NUPIC Nuclear Utilities Procurement Issues Committee
OCA Owner Controlled Area
OTH Other
OPR Operability Recommendation
OSC Operational Support Center
OWA Operator Workaround
PARS Publicly Available Records
PI Performance Indicator
PINGP Prairie Island Nuclear Generating Plant
RCP Reactor Coolant Pump
REMP Radiological Environmental Monitoring Program
RETS/ODCM Radiological Environmental Technical Specifications/Offsite Dose
Calculation Manual
RPIP Radiation Protection Implementing Procedure
RTS Reactor Trip System
RWST Refueling Water Storage Tank
SCBA Self-Contained Breathing Apparatus
SM Shift Manager
SP Surveillance Procedure
SS Shift Supervisor
SSC Structure, System, or Component
TS Technical Specification
URI Unresolved Item
USAR Updated Safety Analysis Report
WBC Whole Body Count
WO Work Order
ZX Containment Cooling
55