June 3, 2021

SUBJECT:

PRAIRIE ISLAND NUCLEAR GENERATING PLANT - BIENNIAL PROBLEM IDENTIFICATION AND RESOLUTION INSPECTION REPORT 05000282/2021011 AND 05000306/2021011

Dear Mr. Domingos:

On April 30, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed a problem identification and resolution inspection at your Prairie Island Nuclear Generating Plant and discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

The NRC inspection team reviewed the stations corrective action program and the stations implementation of the program to evaluate its effectiveness in identifying, prioritizing, evaluating, and correcting problems, and to confirm that the station was complying with NRC regulations and licensee standards for corrective action programs. Based on the samples reviewed, the team determined that your staffs performance in each of these areas adequately supported nuclear safety.

The team also evaluated the stations processes for use of industry and NRC operating experience information and the effectiveness of the stations audits and self-assessments.

Based on the samples reviewed, the team determined that your staffs performance in each of these areas adequately supported nuclear safety.

Finally, the team reviewed the stations programs to establish and maintain a safety-conscious work environment, and interviewed station personnel to evaluate the effectiveness of these programs. Based on the teams observations and the results of these interviews the team found no evidence of challenges to your organizations safety-conscious work environment. Your employees appeared willing to raise nuclear safety concerns through at least one of the several means available.

No findings or violations of more than minor significance were identified during this inspection. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Hironori Peterson, Chief Branch 3 Division of Reactor Projects

Docket Nos. 05000282 and 05000306 License Nos. DPR-42 and DPR-60

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000282 and 05000306

License Numbers:

DPR-42 and DPR-60

Report Numbers:

05000282/2021011 and 05000306/2021011

Enterprise Identifier: I-2021-011-0037

Licensee:

Northern States Power Company, Minnesota

Facility:

Prairie Island Nuclear Generating Plant

Location:

Welch, MN

Inspection Dates:

April 11, 2021 to April 30, 2021

Inspectors:

A. Anderson, Physical Security Inspector

B. Jose, Senior Reactor Inspector

J. Park, Reactor Inspector

K. Pusateri, Resident Inspector

N. Shah, Project Engineer

Approved By:

Hironori Peterson, Chief

Branch 3

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a biennial problem identification and resolution inspection at Prairie Island Nuclear Generating Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the Coronavirus Disease (COVID-19), regional inspectors were directed to begin telework. During this time regional baseline inspections were evaluated to determine if all or portions of the objectives and requirements stated in the IP could be performed remotely. In some cases, portions of an IP were completed remotely and on-site.

The inspection documented below was determined that the objectives and requirements stated in the IP could be completed remotely.

OTHER ACTIVITIES - BASELINE

71152B - Problem Identification and Resolution Biennial Team Inspection (IP Section 02.04)

(1) The inspectors performed a biennial assessment of the licensees corrective action program (CAP), use of operating experience, self-assessments and audits, and safety-conscious work environment.
  • CAP Effectiveness: The inspectors assessed the CAPs effectiveness in identifying, prioritizing, evaluating, and correcting problems. The inspectors also conducted a five-year review of the Unit 1 and 2 emergency diesel generators (EDGs).
  • Operating Experience, Self-Assessments and Audits: The inspectors assessed the effectiveness of the stations processes for use of operating experience, audits and self-assessments.
  • Safety-Conscious Work Environment: The inspectors assessed the effectiveness of the stations programs to establish and maintain a safety-conscious work environment.

INSPECTION RESULTS

Assessment 71152B Review of Corrective Action Program

Based on the samples reviewed, the team determined that the licensee's performance in each of these areas adequately supported nuclear safety.

Effectiveness of Problem Identification

Overall, the station was effective at identifying issues at a low threshold and properly entering them into the CAP as required by station procedures. The team determined that the station was effective at identifying negative trends that could potentially impact nuclear safety. The inspectors interviewed personnel, reviewed documents, walked down portions of the plant, and assessed licensee problem identification.

The team identified that in January 2021, the licensee had missed an opportunity to identify a condition adverse to quality (CAQ) after several safety-related components were affected by ongoing leakage from the A cooling water supply strainers. Several issues were written (CAP items 501000048188, -46948, and -48109) documenting the leakage, but none addressed the wetting of nearby safety-related components. Ironically, barriers had been set up to prevent further wetting, even though no CAP item was written. After the inspectors raised this concern, CAP item 501000049622 was issued by the licensee to address the wetted equipment. The licensee determined that the affected equipment was operable and the inspectors identified no immediate safety concerns.

Effectiveness of Prioritization and Evaluation of Issues:

ln-depth reviews of a risk-informed sampling of CAP items, work orders (WOs), and cause evaluations were completed. Issue identification and screening was generally good, based on a review of CAP documents and observations of CAP screening, Protective Action Review Board, Plant Operating Review Committee and Plant Health Committee meetings. For these meetings, the inspectors observed that the meeting logistics (quorum, etc.) were enforced and that attendees were prepared and asked good questions. The inspectors observed that the issues were generally being appropriately prioritized and evaluated for resolution, and that the corrective actions (CAs) were implemented to mitigate the risk of issues occurring that could affect overall system operability and/or reliability.

The inspectors noted that while issue evaluations were generally sound, there were several examples where additional research was needed to understand the technical basis and final resolution, primarily due to a lack of clear documentation. This issue had previously been identified in past NRC inspections and licensee self-assessments, most recently in the April 2021 licensee self-assessment conducted in preparation for this inspection. The inspectors noted that the licensee had documented this issue in the CAP and was taking corrective actions.

The inspectors also identified several examples where CAP program requirements as stated in FP-PA-ARP-01, "CAP Process," had not been followed; however, these examples did not result in an inappropriate handling of CAQs or other significant CAP issue. These examples included:

  • CAP item 50100023754, "Ground Resistors undersized for EDGs" had four recommendations which were not made into actions under the CAP nor was there any discussion on how they were being addressed. One of these recommendations was later cancelled based on the risk, even though this risk assessment was not documented. The licensee documented this issue as CAP item 501000050714;
  • CAP item 500000303858, which was associated with root cause evaluation 501000035531, "Repetitive Corrosion Induced Failures, was to perform a Snapshot assessment; however, this assessment was not completed. The licensee documented this issue as CAP item 501000050482;
  • Three CAs for CAP item 501000036932, which was associated with a root cause evaluation for an undersized beaker being installed on one of the EDGs, were inappropriately closed to actions taken, instead of remaining open until the actions were verified completed.

The licensee documented this issue as CAP item 501000050896; and

  • CAP item 501000049074 D2 LO STRNR Leak; did not follow the administrative requirements of FP-OP-ACM-01 Adverse Condition Monitoring Plan Process to track an instance of Adverse Condition Monitoring (ACM). The licensee documented this issue as CAP item 501000051144.

As with the documentation issues previously discussed, the inspectors noted that this was also a continuing issue identified in April 2021, and earlier licensee self-assessments, for which CAs had been taken.

Effectiveness of Corrective Actions:

The team concluded that the licensee was generally effective in developing CAs that were appropriately focused to correct the identified problem and to address the root and contributing causes for significant issues in order to preclude repetition. The licensee generally completed CAs in a timely manner and in accordance with procedural requirements commensurate with the safety significance of the issue. For NRC identified issues, the team determined that the licensee generally assigned CAs that were effective and timely.

However, the inspectors noted that there was no clear basis for documenting the risk basis for due date extension. Attachment 8 of CAP procedure FP-PA-ARP-01, "CAP Process,"

required that "an assessment of the risk associated with extending the Activity," be documented as part of the due date extension; however, this procedure did not describe how this requirement should be met. The inspectors identified several examples where the risk assessment was lacking, in that it could not be determined how the assessor concluded that there was no risk. For example, CAP 501000023754 re: an issue with emergency diesel generator grounding resistors had "none" under the risk justification for the due date extension without any further detail. After additional information was provided by the engineering staff, the inspectors were subsequently able to conclude that the justification was supported. The inspectors were concerned with how management approval of the due dates was considered, absent a clearly documented risk basis, and how any future justifications could be properly evaluated, absent the previous documented risk assessment. Although the inspectors were able to determine that the risk assessment was appropriate for the items reviewed, this lack of documentation was a concern as discussed. The licensee documented this concern as CAP item 501000050871.

No violations or findings were identified.

Assessment 71152B The inspectors performed an expanded 5-year review of the Units 1 and 2 EDGs; specifically, by performing system walk-downs and evaluating condition reports, engineering changes, and WOs. Overall, the inspectors determined that the licensee was effectively managing issues associated with this system.

No violations or findings were identified.

Assessment 71152B The inspectors reviewed operating experience (OpE) captured in the CAP and sampled OpE from NRC, industry, vendors, and third-party groups. Overall, for the samples selected, the OpE was appropriately screened and evaluated for applicability, and was effectively used by the station. It was also noted that it was properly considered as a potential precursor in issue evaluations, and during interviews and observations of daily plant meetings, the inspectors concluded that it was seen as a useful learning tool and being used appropriately in daily plant activities.

Nuclear Oversight audits and department self-assessments were generally of good quality, thorough and critical with identified issues being properly dispositioned in the CAP. The audits and assessments were performed in accordance with licensee procedures. Of note, the inspectors observed that the overall conclusions of the licensees self-assessment of the CAP program done prior to this NRC inspection, was consistent with the inspectors observations.

No violations or findings were identified.

Assessment 71152B The inspectors observed various station meetings, including those in which new CAP items were reviewed, and interviewed a representative cross-section of station personnel.

Additionally, the inspectors interviewed the Employee Concerns Program Coordinator, reviewed recent case logs and case files and inquired about the program during interviews with station personnel.

Overall, there is a strong safety culture at the site. Workers felt encouraged to identify issues and felt encouraged to use the CAP. Generally, there was a feeling that issues would be evaluated and corrected. Generally, workers felt that that station management had taken reasonable measures to ensure that focus remained on safe operation and engagement, even given the circumstances due to COVID.

The licensee's 2020 USA safety culture survey identified a potential issue with Knowledge Transfer at the site affecting several departments, including maintenance and engineering.

This issue was captured in the CAP and several actions were underway to address this. The team did not have any issue with the actions proposed, but it is too early to assess their effectiveness.

No violations or findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On April 30, 2021, the inspectors presented the biennial problem identification and resolution inspection results to you and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71152B

Corrective Action

Documents

500000309985

Modify FP-S-FSIP-17: Security Program to Evaluate Need

for Additional Training Evolutions for Strategy Changes

2/23/2020

500001184867

Adverse Trend in 11 Battery Jar/Cover Leakage

06/08/2009

500001192499

Nuclear Safety Advisory Letter RAOC Technical

Specification Actions

08/06/2009

500001227543

MS Snubbers Overloaded - Torsional Acceleration

04/16/2010

500001238619

2" MS Piping Added to High Energy Line

06/23/2010

500001494324

Potential Operable but Non-Conforming D5/D6 Fuel Oil

Day Tank

09/23/2015

500001553539

Issues with the Results Obtained for New Battery

Calculations

03/30/2017

5010000023859

Unit 1 EDG Unavailability Question

05/28/2019

501000007086

Main Steam Valve Maintenance Has AFW MSPI Impact

01/10/2018

501000007811

D2 Lockout During Slow Start Test

01/29/2018

501000011209

Battery 21 Has Misaligned Separator Plate

04/25/2018

501000012189

Identification of Latent OE Trend

05/20/2018

501000012293

Residual Heat Removal Flood Barriers Compensatory

Measures

2/03/2018

501000016536

Unacceptable Void Found in 2RH-11

2/04/2020

501000022183

Fuel Oil Leak on 2EG-9-53 Increased Rate

01/20/2019

501000022281

FW SYS Hanger Snubber Leaking 1-FWH-40B

01/23/2019

501000023141

EEQ DBAI; Motor Operated Valve (MOV) Grease Grading

Criteria in Procedure D70.1

03/07/2019

501000023875

2019 Problem Identification and Resolution Non-CAQ

Items for Rescreening

03/20/2019

501000023915

2019 NRC Ultimate Heat Sink Auxiliary Feedwater Room

UC DP Testing

03/06/2019

501000023925

ACE; 2019 NRC Ultimate Heat Sink (UHS) Inspection:

Auxiliary Feedwater Room Cooler Heat Exchanger

Differential Pressure Testing

04/05/2019

501000024755

Apparent Cause Evaluation (ACE); Breaker 221B-27 A

Phase Will Not Close

06/21/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

501000025116

ACE; 121 Motor Driven Cooling Water Pump (MDCLP) as

Found Condition - Motor Vibration High

05/30/2019

501000025908

1Q2019 Violation - 12 DDCLP Jacket Water

04/19/2019

501000026390

CL Piping Vulnerability - MIC

04/26/2019

501000026633

FW Pump Outboard Oil Leak

05/01/2019

501000027914

Received Multiple Unexpected Alarms

05/29/2019

501000028820

NRC Inspector Observations WC System

06/21/2019

501000028971

Potential U1 RCS Flow Anomaly

05/25/2019

501000029823

CV-31209 Failed PMT

07/20/2019

501000030520

ACE; Potential Diaphragm Degraded on MV-32410

09/16/2019

501000031008

Missing Recommended Actions in LMP

08/21/2019

501000031076

ACE; 2019 AFI ER.1, Equipment Reliability - Emergency

Diesel Generators (EDGs)

10/15/2019

501000031220

Snubber PI-335 Failed As-Found Test

08/26/2019

501000031991

MOVs to Be Rescoped to GL Program

09/16/2019

501000033223

2MS-15-2 Bonnet Sealing Area Degraded

10/13/2019

501000033230

MSSV RS-21-18 Failed as Found Testing

10/12/2019

501000033699

SV-37465 Venting Continuously Post SI Test

10/22/2019

501000034170

SP 1151B Unsat, Stroke Time CV-31654

10/30/2019

501000034334

Fuel Oil Leak at 2EG-9-13 Valve Stem

01/11/2019

501000034334

D5 Fuel Oil Leak at 2EG-9-13 Valve Stem

501000035150

MD AFW Pump Did Not Start

11/26/2019

501000035213

Hole Found in 3" Fuel Oil Supply Line

2/02/2019

501000035531

Repetitive Corrosion Induced Failures

2/10/2019

501000036932

Breaker 26-16 Found Wrong Frame Size

01/24/2020

501000036932

Root Cause Evaluation (RCE); Breaker Removed from

Bus 26, Cubicle 26-16 Was Found to Be a 1200 Ampere

Breaker Instead of 2000 Ampere

01/24/2020

501000037118

CV-31654 Opening Outside of Reference

01/28/2020

501000037475

Cognitive Trend of MIC Comp Beyond RSL

2/07/2020

501000037993

CC PMP Outboard Bearing Oil Leak

2/22/2020

501000038254

2019 AF-2 Off Track

2/29/2021

501000038356

LR Fuel Oil Buried Pipe Inspection Challenge

03/04/2020

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

501000038616

Corrective Action Due Date Extension Not in Accordance

with FP-PA-ARP-01

04/29/2020

501000039650

CC HX Temp CV Failed to Control Temp

04/14/2020

501000039958

PMT UNSAT Due to Leak

04/23/2020

501000040752

DPM Water Drip from 11 TDAFWP CV Stem

05/16/2020

501000041444

Visible Degradation to Auxiliary Feedwater Piping

08/19/2020

501000041819

CV-39409 Stroked Outside the Limit

06/25/2020

501000041863

Ctrl Rod Lifetime Ext Assumptions

05/25/2020

501000041973

Roof Leak in 121 CR Chiller Room

06/30/2020

501000043602

U1 Flux Rate Reactor Trip

08/26/2020

501000043786

20 Problem Identification and Resolution Focused Area

Self-Assessment: A/B Corrective Action Extension

Review

09/02/2020

501000044071

PI&R Focused Area Self-Assessment: Adverse Condition

Monitoring Plan Trending

09/11/2020

501000046312

Fire Extinguisher in D4 Room Degraded

11/03/2020

501000046590

ACE - Players Did Not Respond as Expected - Limited

Scope Drill; Drill Performance

11/19/2020

501000049074

D2 Lube Oil Strainer Leak

03/03/2021

501000049074

D2 Lube Oil Strainer Cover Leakage

501000050432

Security Zones 5 and 6

04/16/2021

501000050460

Security Force Member Annual Physical - Human

Performance

04/16/2021

501000050529

Critical CC Check Valves - No PMs

04/16/2021

50100022183

Prompt Operability for D6 Fuel Oil Leakage

50100023754

Ground/Resistors Undersized for Emergency Diesel

Generators

03/01/2019

50100031909

D5/D6 Fuel Sulfur Additive Nearly Depleted

09/16/2019

50100042597

NSCA General Observation Continuous Learning CL.4

07/24/2020

50130583

ACE; Fuse Blown During CV-31621 Work

09/17/2019

606000000560

10CFR50.65(a)(3) Periodic Assessment

04/01/2020

606000000952

Self-Assessment in Preparation for License Renewal

Phase 4 Inspection

09/12/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

606000001078

Focused Self-Assessment: Problem Identification and

Resolution at Prairie Island Nuclear Generating Plant

04/30/2021

609000001541

Training Revision Request

06/11/2019

60EER1547051

IER L3-16-24 Emergency Diesel Generator

610000000498

ICES 437352 Diesel Generator Air Receiver

610000000632

Westinghouse TB-19-2 Control Rod Drive

05/02/2019

610000001185

OE IRIS 486479; Ultrasonic Inspection on Palisades

Reactor Vessel Head

03/16/2021

610000001211

Operating Experience; Applicability Review of License

Renewal Interim Staff Guidance 2012-02

03/03/2021

61000000691

2168 Diesel Oil Transfer Pump Breaker Failure

06/26/2019

6100000913

501000039063 Monticello Nuclear Generating Plant QIM

Nuclear Oversight: Monticello Programs Audit Technical

Specifications

06/03/2020

610000742

Winter Weather Readiness from NERC

09/05/2019

61000588881

Clearance and Tagging Inspection Report

09/30/2019

A-DES-PINGP-2020-

Nuclear Oversight Audit on Design Control

04/24/2020

QA500000309575

Evaluate Alternate Breaching Simulations

04/15/2021

QA500000311461

Perform Evaluation on T3 IP

04/15/2021

QIM5010000046590

Players Did Not Respond as Expected During NRC FoF

Exercise

11/19/2020

QIM5010000049332

Human Performance Related Security Loggable Events -

Perform Common Cause Evaluation

03/09/2021

QIM5010000050392,

393, 394

Security Deep Dive on Protected Area Barriers

04/10-

2/2021

QIM5010000050463

Security Camera Monitor Malfunction

04/16/2021

QIM5010000050466

AVBS Control Touch Screen

04/16/2021

QIM5010000050481

X-Ray Glass Chipped

04/16/2021

QIM5010000050490

COVID19 Disinfecting Wipes Causing Hand Geometry

Errors

04/14/2021

QIM5010000050498

Thermal Optic Broken Power Switch

04/14/2021

Corrective Action

501000050482

21PIR: Action Not Performed as Written

04/13/2021

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Documents

Resulting from

Inspection

501000050714

CE 500000294364: Recommendations Not Addressed

04/20/2021

501000050871

PI&R Observation: Opportunity for Improvement

04/22/2021

501000051144

Administrative Deficiency via FP-OP-ACM-01

04/27/2021

Engineering

Changes

601000001465

Prairie Island Security Upgrades - Change Request

Report

04/15/2019

601000001947

Repair Fuel Oil Supply Line for 23 D5

60100001947

Repair Fuel Oil Supply Line for 23 D5 FO

2/02/2019

Miscellaneous

Units 1 and 2 4th Quarter Mitigating Systems Performance

Indicator AC Power Submittal

December

20

Emergency Diesel Generator System Health Reports for

D1, D2 and D5

2/01/2021

Procedures

FP-OP-OL-01

Operability

Revision 22

FP-PA-ARP-01

CAP Process

Revision 59

FP-PA-ARP-01

(QF0400)

Issue Report/Change Request Form

Revision 3

FP-PA-OE-01

Operating Experience Program

Revision 29

FP-PA-PAR-01

Performance Assessment Review Board and Performance

Assessment Oversight

Revision 18

FP-PA-RMS-01

Risk Management Screening

Revision 2

FP-S-FSIP-16

Security Training

Revision 14

FP-STND-MTG. 01

Fleet Meeting Standards - Participation

Revision 3

FP-WM-SCH-01

Online Scheduling Process

Revisions 23

and 24

NSPM-1

Quality Assurance Topical Report

Revision 14

Self-

Assessments

500000305009

MM Elevation - Snapshot Assessment

04/14/2020

500000306242

External Surfaces Corrosion SSA

2/24/2021

606000001079

INPO Mid-Cycle FSA Prairie Island

08/21/2020

60600000869

SNAPSHOT Report: Self-Assessment on 71130.04,

Equipment Performance, Testing and Maintenance and

71151, Performance Indicator Verification

06/17/2020

60600000906

SNAPSHOT Report: Self-Assessment on 71130.02,

Access Control

01/20-

24/2020

60600001360

SNAPSHOT Report: Self-Assessment on 71130.02,

03/29-

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Access Control and 71151, Performance Indicator

Verification

04/11/2021

A-INSP/TEST-

PINGP-2020-1

20 Nuclear Oversight Audit of PINGP Inspection and

Testing

06/01/2020

A-MAINT-PINGP-

2019-1

2019 NOS Maintenance Audit

06/10/2019

A-PROG-PINGP-

2019-1

2019 Nuclear Oversight PINGP Audit of Programs

10/01/2019

Nuclear Oversight

(NOS) Audit Report

2019 NOS Audit of PINGP Security (#A-SEC-PING-2019-

1)

07/15-

26/2019

Nuclear Oversight

Audit (NOS) Report

20 NOS Audit of Fleet Security and Cyber Security

(A-SEC-FLT-2020-1)

07/13-

31/2020

Work Orders

700036051

Replace D2 Monal Field Flash dP

01/12/2021

700036053

Replace D1 Shutdown Pushbutton

08/15/2018