IR 05000282/2024002

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000282/2024002 and 05000306/2024002
ML24211A170
Person / Time
Site: Prairie Island  
Issue date: 07/30/2024
From: Richard Skokowski
NRC/RGN-III/DORS/RPB3
To: Conboy T
Northern States Power Company, Minnesota
References
IR 2024002
Download: ML24211A170 (1)


Text

SUBJECT:

PRAIRIE ISLAND NUCLEAR GENERATING PLANT - INTEGRATED INSPECTION REPORT 05000282/2024002 AND 05000306/2024002

Dear Thomas Conboy:

On June 30, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Prairie Island Nuclear Generating Plant. On July 15, 2024, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more-than-minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Richard A. Skokowski, Chief Reactor Projects Branch 3 Division of Operating Reactor Safety Docket Nos. 05000282 and 05000306 License Nos. DPR-42 and DPR-60

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000282 and 05000306

License Numbers:

DPR-42 and DPR-60

Report Numbers:

05000282/2024002 and 05000306/2024002

Enterprise Identifier:

I-2024-002-0065

Licensee:

Northern States Power Company

Facility:

Prairie Island Nuclear Generating Plant

Location:

Welch, MN

Inspection Dates:

April 01, 2024, to June 30, 2024

Inspectors:

T. McGowan, Resident Inspector

K. Poolman, Project Engineer

K. Pusateri, Resident Inspector

J. Reed, Health Physicist

D. Tesar, Senior Resident Inspector

Approved By:

Richard A. Skokowski, Chief

Reactor Projects Branch 3

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Prairie Island Nuclear Generating Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more-than-minor significance were identified.

Additional Tracking Items

Type Issue Number Title Report Section Status URI 05000306/2024001-01 Unresolved Item Associated with Modifications to Motor-Operated Valve Limit Switch 71111.18 Closed

PLANT STATUS

Unit 1 entered the inspection period operating at full-rated thermal power (RTP), except for brief power reductions to perform surveillance testing, or flexible power operations.

On June 12, 2024, at 0930, Unit 1 power commenced an unplanned downpower to approximately 42 percent of RTP for maintenance. On June 20, 2024, at 0100, Unit 1 returned to full RTP where it operated at or near full RTP for the remainder of the inspection period.

Unit 2 entered the inspection period operating at full RTP, except for brief power reductions to perform surveillance testing, or flexible power operations. On May 5, 2024, Unit 2 briefly lowered power to approximately 50 percent RTP for maintenance. On May 8, 2024, at 2000, Unit 2 power was lowered to approximately 42 percent of RTP for maintenance. On May 12, 2024, from 1500 to 1900, Unit 2 power was further lowered to approximately 8 percent RTP for equipment recovery following maintenance, and then returned to approximately 42 percent RTP. On May 15, 2024, at 1240, Unit 2 returned to full RTP where it operated at or near full RTP for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated readiness for seasonal extreme weather conditions prior to the onset of severe weather in the area for the following systems:

entry into AB-2, Severe Weather, on June 17, 2024

Impending Severe Weather Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the adequacy of the overall preparations to protect risk-significant systems from an impending 3-day severe weather event on May 20, 2024.

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) D6 emergency diesel generator standby lineup on April 1, 2024 (2)122 bus rooms during 122 control room chiller maintenance on April 22, 2024
(3) D1 emergency diesel generator standby lineup on May 10, 2024 (4)121 spent fuel pool cooling system (protected train) on May 30, 2024

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated system configurations during a complete walkdown of the 22 turbine-driven auxiliary feedwater (AFW) system on May 21, 2024.

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Fire Detection Zone (FDZ) 4, turbine building Unit 1, elevation 679' and 695' on April 1, 2024
(2) FDZ 74, screenhouse ground floor, elevation 670' on April 9, 2024
(3) FDZ 75, plant screen house, elevation 695' on April 11, 2024
(4) FDZ 6, elevation 695', level D2 diesel room on May 6, 2024
(5) FDZ 46, elevation 715', auxiliary building Unit 2 on May 20, 2024

71111.06 - Flood Protection Measures

Flooding Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated external flooding mitigation protections in the external flood barriers and underground cables.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during Unit 2 down power (100 percent to 40 percent) on May 8, 2024.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated a licensed operator NRC requalification exam on May 21, 2024.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (2 Samples, 1 Partial)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1)

(Partial)main steam isolation valve maintenance procedure evaluation on March 6, 2024 (2)maintenance rule and in-service testing requirements review on May 1, 2024 (3)motor-driven auxiliary feedwater pump (MDAFWP) suction and discharge pressure calibrations on May 29, 2024

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1)123 instrument air compressor failure on April 15, 2024

(2) SP 1159, Failure of MV-32018 Valve Position Indication (IST Failure), on April 29, 2024 (3)auxiliary building crane failure with loaded cask suspended on May 21, 2024 (4)122 instrument air compressor failure with 121 and 122 out of service on June 10, 2024 (5)emergent downpower on Unit 1 to repair circulation water pump leak on June 14, 2024

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (6 Samples)

The inspectors evaluated the licensees justifications and actions associated with the following operability determinations and functionality assessments:

(1)prompt operability determination for MV-32019 on April 9, 2024 (2)auxiliary building special ventilation system operability and PMT 21 auxiliary building exhaust fan on April 18, 2024

(3) C18.1 evaluation of temperature for operability of 122 bus room on April 22, 2024 (4)21 cooling water strainer failure to backwash for Corrective Action Program (CAP)

===501000084343 on April 22, 2024 (5)cooling water system operability post Surveillance Procedure (SP) 1159 on April 29, 2024 (6)operability review for CAP 501000085115 MV-32038 high running torque on May 9, 2024

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02)

=

The inspectors evaluated the following temporary or permanent modifications:

(1)limit switch modifications for MV-32019 on January 6, 2024 (2)bus 25 feed to bus 27, setpoint change for Bkr 25-1 for Engineering Change (EC)

===601000004855 on May 7, 2024

(3) D5 engine 1 fan 1 mods on June 5, 2024

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01)===

(1) Work Order (WO) 700119556, 21 Aux Bldg Exhaust Fan PMT, on April 18, 2024
(2) WO 700128733, SP 1089A 11 RHR [residual heat removal] Pump Qtrly Run, on May 9, 2024
(3) WO 7000095073, MV-32128 Bkr Roll PMT 21 RHR HX [heat exchanger]

CC [component cooling] Inlt MV-32128, on May 14, 2024

(4) WO 700129256, SP 2102 22 Turbine-Driven AFW Pump Qtrly Test PMT, on May 21, 2024
(5) WO 700125627, PMT and RTS MD-32428 with New Positioner, on May 22, 2024
(6) WO 700139187, PMT 22 CC Pump, on May 31, 2024 (7)122 auxiliary building special ventilation PMT on May 31, 2024
(8) WO 700129846, SP 1101 12 MDAFWP Qtr Flow & Vlv Test, on May 29, 2024
(9) SP 1295 D1 emergency diesel generator pump following maintenance on June 12, 2024

Surveillance Testing (IP Section 03.01) (5 Samples)

(1) WO 700127266, SP 2101 21 Motor Driven Auxiliary Feedwater Pump Quarterly Flow and Valve Test, on April 1, 2024
(2) WO 700130624, SP 1106A 12 Diesel CL [cooling water] Pmp Mnthly, on April 15, 2024
(3) WO 700127468, SP 1090A 11 Containment Spray Pump Quarterly Test, on May 3, 2024
(4) WO 700126441, SP 2295 D5 Diesel Generator 6 Month Fast Start Test, on May 13, 2024
(5) WO 700129945, SP 1090B 12 Containment Spray Pump Quarterly Test on May 24, 2024

Diverse and Flexible Coping Strategies (FLEX) Testing (IP Section 03.02) (1 Sample)

(1) WO 700128442, TP 1870A 121 FLEX DS DRIVEN SG-SFP M-U PMP SEMI-ANN, on May 16, 2024

71114.06 - Drill Evaluation

Required Emergency Preparedness Drill (1 Sample)

(1)emergency preparedness drill with Drill and Exercise Performance (DEP) and ERO evaluation on May 14,

RADIATION SAFETY

71124.03 - In-Plant Airborne Radioactivity Control and Mitigation

Permanent Ventilation Systems (IP Section 03.01) (1 Sample)

The inspectors evaluated the configuration of the following permanently installed ventilation systems:

(1) Unit 1 auxiliary building ventilation particulate and charcoal filtration system

Self-Contained Breathing Apparatus for Emergency Use (IP Section 03.04) (1 Sample)

(1) The inspectors evaluated the licensees use and maintenance of self-contained breathing apparatuses.

71124.04 - Occupational Dose Assessment

Source Term Characterization (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated licensee performance as it pertains to radioactive source term characterization.

External Dosimetry (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated how the licensee processes, stores, and uses external dosimetry.

Internal Dosimetry (IP Section 03.03) (2 Samples)

The inspectors evaluated the following internal dose assessments:

(1) internal dose assessment for ID# N128502 (2)internal dose assessment for ID# 301529

Special Dosimetric Situations (IP Section 03.04) (2 Samples)

The inspectors evaluated the following special dosimetric situations:

(1) skin exposure evaluation for ID# 226834 (2)declared pregnant worker evaluation for ID#

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

MS05: Safety System Functional Failures (SSFFs) Sample (IP Section 02.04)===

(1) Unit 1 (January 1, 2023, through December 31, 2023)
(2) Unit 2 (January 1, 2023, through December 31, 2023)

MS08: Heat Removal Systems (IP Section 02.07) (2 Samples)

(1) Unit 1 (January 1, 2023, through December 31, 2023)
(2) Unit 2 (January 1, 2023, through December 31, 2023)

BI02: RCS Leak Rate Sample (IP Section 02.11) (2 Samples)

(1) Unit 1 (January 1, 2023, through December 31, 2023)
(2) Unit 2 (January 1, 2023, through December 31, 2023)

71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1)follow up of CAP 50100078473 CV-31116 as-found condition on April 22, 2024 (2)follow up of CAP 50100077533 hourly firewatch round missed on June 26, 2024

71152S - Semiannual Trend Problem Identification and Resolution Semiannual Trend Review (Section 03.02)

(1) The inspectors reviewed the licensees corrective action program to identify potential trends in backlog reduction meeting effectiveness on April 16, 2024, that might be indicative of a more significant safety issue.
(2) The inspectors reviewed the licensees corrective action program to identify potential trends in instrument air compressor failures on June 20, 2024, that might be indicative of a more significant safety issue.

71153 - Follow Up of Events and Notices of Enforcement Discretion Event Report (IP Section 03.02) (2 Partials)

The inspectors evaluated the following licensees event reporting determinations to ensure it complied with reporting requirements.

(1)

(Partial)05000306/2024-001-00; LER 2024-001-00 for Prairie Island Nuclear Generating Plant, Unit 2, Reactor Trip and Auto-Start Actuation of Auxiliary Feedwater due to Loss of Suction to the 22 Main Feedwater Pump (2)

(Partial)05000306/2024-001-01; LER 2024-001-01 for Prairie Island Nuclear Generating Plant, Unit 2, Reactor Trip and Auto-Start Actuation of Auxiliary Feedwater due to Loss of Suction to the 22 Main Feedwater Pump

INSPECTION RESULTS

Unresolved Item (Closed)

Unresolved Item Associated with Modifications to Motor Operated Valve Limit Switch URI 05000306/2024001-01 71111.18

Description:

A minor violation was identified and documented in Section 71111.18 of this report.

This unresolved Item (URI) is being closed to that minor violation.

Corrective Action References:

501000079553, Bkr 211J-13 Tripped During PMT/RTS 501000079667, Manually Operated MV-32019 per COO-17 501000081027, MOV [motor-operated valve] Limit Switch Grease Related Failures 501000081105, MV-32019 Thermals Tripped D 501000083170, LEGACY: MV-32019 Limit Switch Material 501000083626, MV-32019 Limit Switch Minor Violation 71111.18 Minor Violation Associated with Modifications to Motor-Operated Valve Limit Switch Minor Violation: During refueling outage 2R33, modifications were made to the safety-related limit switch installed on motor-operated valve, MV-32019, 21 steam generator main steam supply to the 22 turbine-driven auxiliary feedwater pump. Specifically, the gears inside the replacement switch were stainless steel rather than bronze (not like-for-like), and the licensee drilled an additional hole through the intermittent shaft perpendicular to the manufacturer-provided hole, and then changed the orientation of the rotor from that provided by the vendor, in order for the rotor to work correctly.

Title 10 of the Code of Federal Regulations (CFR) Part 50, Appendix B, Criteria XV, Nonconforming Materials, Parts, or Components, requires, in part, Measures shall be established to control materials, parts, or components which do not conform to requirements in order to prevent their inadvertent use or installation. These measures shall include, as appropriate, procedures for identification, documentation, segregation, disposition, and notification to affected organizations. Nonconforming items shall be reviewed and accepted, rejected, repaired or reworked in accordance with documented procedures.

Contrary to the above, between December 5, 2023, and January 29, 2024, the licensee failed to control nonconforming items, such that they were reviewed and accepted, rejected, repaired or reworked in accordance with documented procedures. Specifically, nonconforming parts were modified and installed without coordination with affected organizations in accordance with plant procedures FP-SC-PE-02, Item Equivalency Evaluations, and FP-E-MOD-02, Engineering Change Control.

Screening: The inspectors determined the performance deficiency was minor. This violation aligns with the minor case of IMC 0612, Appendix E, Examples of Minor Violations, example 4.m: The inspector identified a motor-operated valve (MOV) torque switch was not installed properly. Specifically, the licensees procedure to re-install MOV RH-6833 did not include a step to reset the MOV torque switch to previously installed torque switch settings.

Once identified, the licensee had to enter an unplanned maintenance window to reset the toque switch.

This performance deficiency did not adversely affect the mitigating systems cornerstone objective because the inadequate adherence to procedure would not have resulted in equipment failure. Specifically, the licensee analysis confirmed the change in material was authorized by the vendor and the modification to the shaft and rotor would not prevent the limit switch from performing its safety function, and therefore the limit switch and the motor-operated valve remained operable.

Enforcement:

This failure to comply with 10 CFR 50, Appendix B, Criteria XV constitutes a minor violation that is not subject to enforcement action in accordance with the NRCs Enforcement Policy.

Observation: Follow-up of CAP 501000077533 Hourly Firewatch Round Missed on F5 APP 71152A Inspectors selected CAP 501000077533 for follow-up based upon the risk significance of fire as an external event, especially during higher risk evolutions (HRE). On October 8, 2023, at 1535, Operations entered a fire impairment for Unit 2 establishing hourly fire watches for areas listed in F5 Appendix K, Attachment 4, per procedure 2C1.3-M5. The 1800 round was not completed for the safety-related bus 15 room. The individual performing the fire watch round for 1900 realized that the incorrect room had been checked on the 1800 round and reported the condition to supervision. The licensee entered the issue into the corrective action program (CAP) and performed a human performance event investigation. Corrective actions included review of other rounds which determined no other spaces were missed, re-training staff to arrest knowledge gaps, and the bus 15 room was verified to have functional fire detection. Inspectors reviewed the corrective action database and noted that corrective actions appeared to be effective since no further issues have been identified.

No more-than-minor findings or violations were identified during this inspection.

Observation: Review of Actions Taken for CAP 501000078473 CV-31116 As-Found Condition 71152A Inspectors reviewed actions taken for CAP 501000078473, CV-31116 As-Found Condition, based upon risk significance. This CAP documented the following: foreign material (FM) on top of the actuating cylinder pistons, binding of the actuator disk, and scoring at the bottom of the air cylinders (full closed position). The FM was determined to be pipe scale from the upstream air system. The CAP was then closed to WO 700038835-0010 which completed PM 3170-1-21, CV-31116 Loop A MSIV Refueling Inspection. Inspectors reviewed the WO and determined that actions were taken to correct or disposition the conditions identified in CAP 501000078473 and the WO documented that the valve moved freely following maintenance. In addition, the PMT was completed satisfactorily, ensuring the valve was capable of performing its designed safety function. Inspectors did not identify any issues of concern associated with the actions taken to correct the condition(s) adverse to quality identified in the CAP. The inspectors did not identify any more-than-minor findings or violations during this review.

Observation: Trend Review of Aggregate Risk Impact of Low Safety Significant Systems 71152S Based upon a cognitive trend, inspectors performed a trend review of how the licensee was assessing the aggregate risk associated with deficiencies in low safety significant systems.

The inspectors identified that the licensee had not recently performed backlog reduction meetings in accordance with fleet procedure FP-WM-WOI-01, Work Identification, Screening, Validation, and Cancelation, Attachment 7. The purpose of these meetings was to determine the aggregate risk impact of multiple deficiencies in a particular system and elevating the priority of the repairs as needed based upon the results of that review.

Inspectors determined that the failure to conduct the meetings was due to individuals new in role who were unfamiliar with the procedural requirements. Once identified, the licensee entered this issue into their corrective action program (CAP) and initiated monthly meetings as required. Inspectors determined that the action taken has corrected the condition adverse to quality. No more-than-minor findings or violations were identified during this review.

Observation: Trend of Instrument Air Compressor Failures 71152S Inspectors selected a cognitive trend of instrument air compressor (IAC) failures for a semi-annual review. Twenty corrective action documents were reviewed, where nine maintenance rule evaluations identified condition monitoring events across multiple functions. On May 1, 2024, the licensee determined that the condition monitoring threshold for 123 instrument air compressor had been exceeded, and 123 instrument air compressor was later (on June 27, 2024) placed in (a)(1) monitoring status per 10 CFR 50.65 Maintenance Rule. On June 8, 2024, QIM 501000086471 titled, Instrument Air System Health, was written to identify the condition of all three IACs degraded or non-functional. Immediate corrective actions included the senior leadership team meeting, staffing the outage control center, and prioritizing IAC troubleshooting and corrective maintenance. This led to restoration of the three instrument air compressors and associated support equipment. Planned corrective actions include re-evaluating upcoming preventive maintenance work windows in an attempt to avoid the need for future corrective maintenance. Inspectors noted that the condition adverse to quality had been corrected with the restoration of all three instrument air compressors. Additional actions are planned to evaluate for trends or commonalities associated with instrument air equipment failures to provide increased reliability moving forward. No more-than-minor findings or violations were identified during the semi-annual trend review.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On July 15, 2024, the inspectors presented the integrated inspection results to Thomas Conboy, Site Vice President, and other members of the licensee staff.
  • On May 3, 2024, the inspectors presented the radiation protection baseline inspection results to Timothy Borgen, Plant Manager, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.01

Procedures

AB-2

Severe Weather

NF-39223

Flow Diagram Feedwater & Aux Feedwater Unit 2

Drawings

XH-1-29

Flow Diagram Spent Fuel Cooling System Units 1 & 2

1C20.7

D1/D2 Diesel Generators

C16

Spent Fuel Cooling System

C28-18

Turbine Driven Auxiliary Feedwater Pump

C28-7

Auxiliary Feedwater System Unit 2

71111.04

Procedures

Operating

Procedure 2C20.7

D5/D6 Diesel Generators

Fire Detection

Zone 1

695' Level Turbine Building, Battery Room 11 & 12

Fire Detection

Zone 2

Aux Feedwater Pump Rooms, El 695'

Fire Detection

Zone 35

Battery Room 21 & 22, El 695'

Fire Detection

Zone 4

Fire Area 69; Turbine Building Unit 1, Elevation 679' and 695'

Fire Detection

Zone 6

Fire Area 26; Level D2 Diesel Room, Elevation 695'

Fire Detection

Zone 74

Fire Area 41B; Screenhouse Ground Floor, Elevation 670'

Fire Detection

Zone 75

Fire Areas 41 & 41A; Plant Screen House, Elevation 695'

71111.05

Fire Plans

Fire Detection

Zone 82

D1 Diesel Room, El 695'

71111.06

Procedures

AB-4

Flood

Corrective Action

Documents

5010000860002

SP 1234B Procedure Issues

05/29/2024

Engineering

Changes

IEE-2024-054-00

Limitorque 4-Train Limit Switch Assembly, P/N 10120 to P/N

10160, MID # KLT13G-1, SR

608000001135

Come-along Usage on MSIV

71111.12

Engineering

Evaluations

QF0739, Request

Approval 602000017241, Chain-Falls for Closing the MSIVs

04/01/2024

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Number 355

as Part of Operating the Plant

Prairie Island

Maintenance Rule

Basis Document

Various Functions

Various

Dates

QF0739, Request

Number 362

Should the Testing Of CV-31741 be Adjusted to Account for

the Max Containment Pressure Of 46 Psig?

05/02/2024

Miscellaneous

QF0739, Request

Number 363

What is the Credited Fail Position for SV-33133, Cooling

Water to 121 Safeguards Traveling Screens Solenoid Valve?

05/02/2024

PM 3122-3

Shield Bldg, Category 1 Vent Zone, Fire and Security Door

Inspection

Procedures

SP 1234B

Aux Feedwater Pump Suction and Discharge Pressure

Switches Calibration

Corrective Action

Documents

501000083626

MV-32019 - 21 SG Steam Supply Valve

Engineering

Evaluations

POR

501000085115

Satisfactorily Completed SP 1159, COOLING WATER

VALVES QUARTERLY TEST per WO-000700122604-0010.

01/04/2024

71111.15

Procedures

SP 1159

Cooling Water Valves Quarterly Test

501000080988

PICETI Bus 27 Coordination Not Assured

01/18/2024

501000084375

Breaker Opening Times: ENG-EE-162

04/22/2024

501000084967

PMT Issues for Setpoint Change Bus 27 Relay

05/07/2024

Corrective Action

Documents

501000085005

Perform BKR Setpoint Chg: As Found

05/07/2024

NE-116785,

Sheet 12

Prairie Island Nuclear Generating Plant

NF-120705-0

Internal Wiring Diagram 4kV Switchgear Bus 25

Cub. 1 - Sh. 2

Drawings

NF-239270

Prairie Island Plant and Substation Operating One Line

Diagram

Engineering

Changes

601000004855

601000005066

D5 ENG1 MTR Cooling Fan New Keyway EC

Miscellaneous

EPRI Report

Summary

Technical Repair Guidelines for Limitorque Model SMB-OO

Valve Actuators

June 1995

71111.18

Work Orders

WO 700134076

Perform BKR 25-1 Setpoint Change

05/07/2024

71111.24

Procedures

SP 1074A

Train A Auxiliary Building Special Vent System

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Quarterly Test

SP 1074B

Train B Auxiliary Building Special Vent System

Quarterly Test

SP 1089A

Train A RHR Pump and Suction Valve from RWST

Quarterly Test

SP 1090A

Containment Spray Pump Quarterly Test

SP 1090B

Containment Spray Pump Quarterly Test

SP 1101

Motor-Driven Auxiliary Feedwater Pump Quarterly

Flow and Valve Test

SP 1106A

Diesel Cooling Water Pump Monthly Test

106

SP 1295

D1 Diesel Generator 6 Month Fast Start Test

SP 2101

Motor-Driven Auxiliary Feedwater Pump Quarterly

Flow and Valve Test

TP 2296B

D6 Radiator Fans Weekly Run Test & 2ZG System Weekly

Damper Cycling

WO 700127468

SP 1090A 11 CNTMT SPRAY PMPQTR

05/03/2023

WO 700078684

Troubleshoot BKR 211J-13 and MV-32019

WO 700095073

(BKR 211J-11) 21 RHR HX CC INLT MV-32128

04/28/2022

WO 700119556

QIM 501000070722

WO 700125627

D6 RM RECIRC AIR MD REPL POSNR

05/22/2024

WO 700128733

SP 1089A-1A RHR PMP & SUCT VLV FROM RWST

05/29/2024

WO 700129456

SP 1090B 12 CNTMT SPRAY PMP QTR

06/13/2024

WO 700129846

SP 1101 12 MDAFWP WTR FLOW & VLV TEST

05/30/2024

WO 700130624

SP 1106A 12 DIESEL CL PMP MNTHLY

Work Orders

WO 700137489

SP 1074A TRN A ABSV SYS QTR TEST

Annual SCBA

Flow Test for

LAD090894

MSA SCBA Annual Flow Test

07/13/2023

Calibration

Records

Annual SCBA

Flow Test for Unit

PI-FB-112

Scott SCBA Annual Flow Testing

07/12/2023

501000065032

SCBA Breathing Air Supply

07/27/2022

71124.03

Corrective Action

Documents

501000080448

CR Breathing Air System is Degrading

01/03/2024

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

501000084450

Fit Test Monitored Evolution Comment

04/23/2024

Corrective Action

Documents

Resulting from

Inspection

501000084455

NRC Health Physics Observations

04/24/2024

Grade D Testing

Grade D Testing for Plant Air and SCBA Compressors

2/27/2023

Miscellaneous

PINGP 252

(RPIP 1214)

Respirator Inspections for the Month of December 2023

FP-RP-RPP-02

Respirator Fit Testing and Portacount Fit Tester Operation

RPIP 1211

Charging MSA or Scott SCBA Air Cylinders

RPIP 1214

Respiratory Protection Equipment Testing

Procedures

RPIP 1216

MAX Air 2000-800 Respiratory Protection

Self-Assessments Snapshot Self-

Assessment for

71124.03

Program Self-Assessment for Inspection Procedure 71124.03

Work Orders

700102048

Control Room Clean-up Ventilation Efficiency Test

03/09/2023

Calculations

SSA

606000001914

Prairie Island 2023 Isotopic Mix Report

501000074108

DLR Vendor Failed to Detect SDE

06/01/2023

Corrective Action

Documents

501000082610

Dose Discrepancies for Period 2, 2023

03/06/2024

Engineering

Evaluations

Technical Basis

Document#

20-001

SRD Bias

APEX / In-Vivo

Logbook

Summary

Whole Body Counter Log for January 2024 and

February 2024

03/07/2024

APEX / In-Vivo

Logbook

Summary

Whole Body Counter Log for May 2023 to December 2023

01/02/2024

Declared

Pregnant Worker

Evaluation for ID#

231460

PINGP 656 Prairie Island Fetal Protection Program

Evaluation

10/18/2022

71124.04

Miscellaneous

Dosimetry

Discrepancy

Primary to Secondary Dose Discrepancy Review for 2023

04/22/2024

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Review for 2023

Exposure

Correction

Radiation

Occurrence

Report for ID#

313426

Primary to Secondary Dosimetry Investigation Per QF3008

03/06/2024

Exposure

Correction

Radiation

Occurrence

Report for ID#

N151793

Primary to Secondary Dosimetry Investigation Per QF3008

03/05/2024

NLVAP

Accreditation for

Mirion

Technologies

NVLAP Accreditation for 10/03/2023-06/30/2024

10/03/2023

Personnel

Contamination

Event Review for

ID# 226834

PCE Evaluation Form QF1282

11/27/2023

FP-RP-DR-01

Sentinel DLR Issue & Managing Dose Records

FP-RP-IDA-01

Internal Dose Assessment

Procedures

FP-RP-WBC-01

Whole Body Counter Use and Functional Check

23 Annual Area

TLD Trending

Area Dosimetry Results and Trending

01/30/2024

Radioactive

Intake Screening

for ID# 301529

Internal Dose Evaluation Per QF1282

10/16/2023

Radioactive

Intake Screening

for ID# N128502

Internal Dose Evaluation Per QF1282

10/16/2023

Radiation

Surveys

Technical Basis

Document No. 17-

Prospective Dose Evaluation and Dose Reporting Threshold

Summary

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

001

Self-Assessments Snapshot Self-

Assessment

71124.04

Program Self-Assessment for Inspection Procedure 71124.04

PI Summary

Report

Prairie Island Unit 1, Initiating Events, IE01 - Unplanned

Scams per 7,000 Critical Hours

06/2023 -

05/2024

71151

Miscellaneous

PI Summary

Report

Prairie Island Unit 2, Initiating Events, 1E01 - Unplanned

Scrams per 7,000 Critical Hours

06/2023 -

05/2024

Corrective Action

Documents

501000077533

Hourly Firewatch Round Missed on F5 APP

10/09/2023

71152A

Work Orders

WO 700038835

INSP CV-31116 Valve Internals

10/30/2023

501000078473

CV-31116 As-Found Condition

11/01/2023

501000079065

2R33 ISI Indication CV-31116

11/16/2023

501000084473

Roll Up CAP for IA/SA Sys Issues

04/24/2024

71152S

Corrective Action

Documents

501000086471

Instrument Air System Health

06/08/2024

Corrective Action

Documents

501000082488

Unit 1 Reactor Trip

585121

Automatic Reactor Trip Due to a Loss of Suction in Main

Feedwater Pump

03/03/2024

71153

Miscellaneous

QF0739, Request

Number 1

What Is the Difference in CCDP Between a Normal Reactor

Trip from 100% Power and a Normal Reactor Trip from

100% Power with Main Feedwater Pumps Failed (Unit 1)?

06/06/2024