UPDATED INSPECTION PLAN FOR PRAIRIE ISLAND NUCLEAR GENERATING PLANT (REPORT 05000282/2023005 AND 05000306/2023005)

Dear Thomas Conboy:

The enclosed inspection plan lists the inspections scheduled through June 30, 2025 for Prairie Island Nuclear Generating Plant. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

August 30, 2023 Please contact Hironori Peterson at 630-829-9707 with any questions you have regarding this letter.

Sincerely, Hironori Peterson, Chief Reactor Projects Branch 3 Division of Operating Reactor Safety Docket Nos. 05000282; 05000306; 07200010 License Nos. DPR-42; DPR-60; SNM-2506 Enclosure:

Inspection Plan cc: Distribution via LISTSERV Signed by Peterson, Hironori on 08/30/23