IR 05000282/2022004

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000282/2022004 and 05000306/2022004
ML23025A401
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 01/26/2023
From: Hironori Peterson
NRC/RGN-III/DORS/RPB3
To: Domingos C
Northern States Power Company, Minnesota
References
IR 2022004
Preceding documents:
Download: ML23025A401 (1)


Text

SUBJECT:

PRAIRIE ISLAND NUCLEAR GENERATING PLANT - INTEGRATED INSPECTION REPORT 05000282/2022004 AND 05000306/2022004

Dear Christopher Domingos:

On December 31, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Prairie Island Nuclear Generating Plant. On January 13, 2023, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Hironori Peterson, Chief Reactor Projects Branch 3 Division of Operating Reactor Safety Docket Nos. 05000282 and 05000306 License Nos. DPR-42 and DPR-60

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000282 and 05000306

License Numbers:

DPR-42 and DPR-60

Report Numbers:

05000282/2022004 and 05000306/2022004

Enterprise Identifier:

I-2022-004-0053

Licensee:

Northern States Power Company

Facility:

Prairie Island Nuclear Generating Plant

Location:

Welch, MN

Inspection Dates:

October 01, 2022, to December 31, 2022

Inspectors:

S. Bell, Health Physicist

J. Bozga, Senior Reactor Inspector

A. Demeter, Project Engineer

T. Iskierka-Boggs, Senior Operations Engineer

V. Myers, Senior Health Physicist

K. Pusateri, Resident Inspector

D. Tesar, Senior Resident Inspector

Approved By:

Hironori Peterson, Chief

Reactor Projects Branch 3

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Prairie Island Nuclear Generating Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

Type Issue Number Title Report Section Status URI 05000282/2022004-

Bus 15 Failure to Meet Acceptance Criteria 71111.15 Open URI 05000306,05000282

/2018-011-02 Potential Failure to Protect Class I Structures, Systems, and Components from Tornado Generated Missiles 71111.21M Closed LER 05000282,05000306

/2022-001-00 LER 2022-001-00 for Prairie Island Nuclear Generating Plant, Units 1 and 2, Fuel Assemblies Incorrectly Placed in Spent Fuel Pool 71153 Closed

PLANT STATUS

Unit 1 began the inspection period at rated thermal power. On September 20, 2022, at 09:27, the unit entered coast down to the refueling outage. On October 14, 2022, at 10:45, unit 1 was shut down from 84 percent power, starting the 1R33 refueling outage (RFO). The unit was taken critical on November 7, 2022, at 22:23, and was synched to the grid on November 9, 2022, at 10:21, ending the 1R33 RFO. The unit was returned to full-rated thermal power on November 12, 2022, at 15:35, and remained at or near rated thermal power for the remainder of the inspection period except for brief power reductions to perform surveillance testing or flexible power operations.

Unit 2 operated at or near rated thermal power for the entire inspection period with the exception of brief power reductions to perform surveillance testing or flexible power operations.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, appendix D, Plant Status, observed risk-significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated readiness for seasonal extreme weather conditions prior to the onset, inspectors reviewed implementation of TP 1637, Revision 58, "Annual Winter Plant Operation," on September 26, 2022.

Impending Severe Weather Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the adequacy of the overall preparations to protect risk-significant systems from impending severe weather freeze/thaw/snow cycles on susceptible risk-significant components on November 21, 2022.

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Unit 1 auxiliary feedwater system following integrated safety injection testing on October 17, 2022
(2) Unit 1 4.16kV 'B' train electrical walkdown during Yellow risk on October 19, 2022
(3) Unit 1 4.16kV system following restoration of bus 15 on October 26, 2022

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated system configurations during a complete walkdown of the spent fuel pool cooling during unit 1 refueling outage system on October 18, 2022.

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Unit 1 containment reactor coolant pump vaults fire walkdown on October 15, 2022
(2) Spent fuel pool during fuel moves fire walkdown on October 21, 2022
(3) Unit 1 containment general areas for 715', 735', and 755' elevations on October 25, 2022
(4) Walkdown of screenwash pump with motor-driven and diesel-driven fire pumps out of service on October 24, 2022

71111.06 - Flood Protection Measures

Inspection Activities - Internal Flooding (IP Section 03.01) (1 Sample)

The inspectors evaluated internal flooding mitigation protections in the:

(1) Auxiliary feedwater pump and hot shutdown panel room

71111.07A - Heat Exchanger/Sink Performance

Annual Review (IP Section 03.01) (1 Sample)

The inspectors evaluated readiness and performance of:

(1) Work Order (WO) 700077322, "SP 1424 unit 1 Five
(5) Year Containment Fan Coil Unit Performance Test"

71111.08P - Inservice Inspection Activities (PWR) PWR Inservice Inspection Activities Sample (IP Section 03.01)

(1) The inspectors verified that the reactor coolant system boundary, steam generator tubes, reactor vessel internals, risk-significant piping system boundaries, and containment boundary are appropriately monitored for degradation and that repairs and replacements were appropriately fabricated, examined and accepted by reviewing the following activities from October 17 to October 28, 2022:

03.01.a - Nondestructive Examination and Welding Activities

ultrasonic testing (UT) exam of reactor coolant (RC) pipe-to-pipe weld for component W-5

UT exam of RC elbow-to-pipe weld for component W-4

magnetic particle examination of 11 steam generator feedwater nozzle-to-shell weld component N-1

visual examination (VT-3) of 11 component cooling heat exchanger support

11 RC pump support indication evaluation

welds 1 thru 12 for cooling water piping replacement 24-CL-13 (WO 700072740-0340)03.01.b - Pressurized-Water Reactor Vessel Upper Head Penetration Examination Activities

bare metal visual examination (VE) of the unit 2 reactor vessel upper head penetrations nozzles 03.01.c - Pressurized-Water Reactor Boric Acid Corrosion Control Activities

boric acid leakage evaluation on component ID SI-14-1 (Issue Report 501000054481)

boric acid leakage evaluation on component ID CV-31201 (Issue Report 501000049320)

boric acid leakage evaluation on component ID CV-31200 (Issue Report 501000045188)

71111.11A - Licensed Operator Requalification Program and Licensed Operator Performance

Requalification Examination Results (IP Section 03.03) (1 Sample)

(1) The inspectors reviewed and evaluated the licensed operator examination failure rates for the requalification annual operating tests administered from April 25 thru June 6, 2022. One licensed operator that was unable to take the 2021 licensed operator examinations due to medical restrictions, has since been remediated, and was administered a makeup biennial written examination and applicable annual operating test to meet CFR requirements for standing watch as a senior reactor operator.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during the unit 1 cooldown operations on October 15, 2022.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (2 Samples)

(1) The inspectors observed and evaluated licensed operator requalification simulator sessions on December 5, 2022.
(2) The inspectors observed and evaluated simulator scenarios on November 14, 2022.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (2 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) 'A' train cooling water header valve replacements on October 20, 2022
(2) RS-19-1 Furmanite found on December 7, 2022

Aging Management (IP Section 03.03) (1 Sample)

The inspectors evaluated the effectiveness of the aging management program for the following SSCs that did not meet their inspection or test acceptance criteria:

(1) Bus 15 maintenance during outage - aging management on November 1, 2022

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Risk evaluation for reactor vessel drain down evolution to 1' below flange on October 17, 2022
(2) WO 700098197, "Zebra Mussel Treatment"
(3) WO 700107193-23, "Inverter Corrective Maintenance"
(4) RICT implementation on Unit 2 during unit 1 outage on October 24, 2022
(5) Risk assessment during Yellow risk due to reduced inventory and single train of decay heat removal period on October 18, 2022

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (7 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1)1N32 operability evaluation Technical Specification (TS) 3.3.1

(2) Cooling water header RTO and 22 diesel-driven cooling water pump (DDCLP)relief lifting (3)12 DDCLP speed switch timing, as documented in CAP 501000067737
(4) CAP 501000068275, "N35 Operability in Mode 2 Above P6"
(5) Makeup air handling unit (MUAH) post-maintenance SP's
(6) D5 rack differential detector
(7) Bus 15 following maintenance on November 1, 2022

71111.18 - Plant Modifications

Severe Accident Management Guidelines (SAMG) Update (IP Section 03.03) (1 Sample)

(1) The inspectors verified the site SAMG were updated in accordance with the PWR generic severe accident technical guidelines and validated in accordance with Nuclear Energy Institute (NEI) 14-01, Emergency Response Procedures and Guidelines for Beyond Design Basis Events and Severe Accidents, revision 1 on November 1, 2022.

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (7 Samples)

The inspectors evaluated the following post-maintenance testing (PMT) activities to verify system operability and/or functionality:

(1) WOs 700094054-02, -04, -06, -08, "Power Range Detector Bypass Modification Installation for NIs 41, 42, 43, and 44"
(2) WO 700114928, "Inspect and Test 22 DDCLP Jacket HX Relief"
(3) Breaker 15-2 PMT via D1 emergency diesel generator slow start on October 26, 2022
(4) SP 1373, "RS-19-1 U1 Loop A MSIV Non-Return Check Valve IST Test," on October 31, 2022 (5)11TDAFW, "Testing Post Refueling Maintenance," on November 10, 2022
(6) SP 1070, "RCS Integrity Test," on November 3, 2022
(7) SP 1106A, "12 DDCLP PMT Following Maintenance," on December 15, 2022

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated RFO 1R33 activities from October 14, 2022, thru November 9, 2022.

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance testing activities to verify system operability and/or functionality:

Surveillance Tests (other) (IP Section 03.01) (4 Samples)

(1) SP 1155A/ST, "1155A 11 Component Cooling (CC) Water Pump"
(2) SP 1083, "Integrated Safety Injection Test," on October 16, 2022
(3) SP 1092B, "Safety Injection Check Valve Test (Head Off) part B," on October 19, 2022
(4) SP 1092A, "Safety Injection Check Valve Test (Head Off) part A," on October 28, 2022

Inservice Testing (IP Section 03.01) (1 Sample)

(1) SP 1090B, "Containment Spray Pump Quarterly IST Test," on December 15, 2022

RCS Leakage Detection Testing (IP Section 03.01) (2 Samples)

(1) SP 1168.1, "RCS Pressure Test," on November 6, 2022
(2) SP 1070, "RCS Integrity Test," on November 3, 2022

71114.04 - Emergency Action Level and Emergency Plan Changes

Inspection Review (IP Section 02.01-02.03) (1 Sample)

(1) The inspectors evaluated the following submitted Emergency Action Level and Emergency Plan changes:

FT-2021-756, FP-S-FSIP-07 Revision, 10/27/2021

PI-2021-753, F3-17 Revision, 11/20/2021

PI-2021-754, EDCM 300 Revision, 08/30/2021

PI-2021-757, F3-13.3 Revision, 11/08/2021

PI-2021-758, F3-23-1C and F3-23-2C Revisions, 11/10/2021

PI-2022-764, PING 580 Revision, 01/27/2022 This evaluation does not constitute NRC approval.

71114.06 - Drill Evaluation

Drill/Training Evolution Observation (IP Section 03.02) (1 Sample)

The inspectors evaluated:

(1) Emergency preparedness exercise walkthrough with drill and exercise performance on December 13,

RADIATION SAFETY

71124.01 - Radiological Hazard Assessment and Exposure Controls

Radiological Hazard Assessment (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated how the licensee identifies the magnitude and extent of radiation levels and the concentrations and quantities of radioactive materials and how the licensee assesses radiological hazards.

Instructions to Workers (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated how the licensee instructs workers on plant-related radiological hazards and the radiation protection requirements intended to protect workers from those hazards.

Contamination and Radioactive Material Control (IP Section 03.03) (3 Samples)

The inspectors observed/evaluated the following licensee processes for monitoring and controlling contamination and radioactive material:

(1) Licensee surveys of potentially contaminated material leaving the radiologically controlled area
(2) Workers exiting the radiologically controlled area
(3) Workers exiting unit 1 containment

Radiological Hazards Control and Work Coverage (IP Section 03.04) (3 Samples)

The inspectors evaluated the licensee's control of radiological hazards for the following radiological work:

(1) RC pump motor replacement under RWP 221020
(2) Valve maintenance in the regenerative heat exchanger room under RWP 221007
(3) Reactor head O-ring removal under RWP 221042 High Radiation Area and Very High Radiation Area Controls (IP Section 03.05) (4 Samples)

The inspectors evaluated licensee controls of the following High Radiation Areas and Very High Radiation Areas:

(1) Regenerative heat exchanger area
(2) Spent fuel pool skimmer pump room
(3) Reactor head stand
(4) Reactor cavity sump 'C' Radiation Worker Performance and Radiation Protection Technician Proficiency (IP Section 03.06) (1 Sample)
(1) The inspectors evaluated radiation worker and radiation protection technician performance as it pertains to radiation protection requirements.

71124.03 - In-Plant Airborne Radioactivity Control and Mitigation

Temporary Ventilation Systems (IP Section 03.02) (1 Sample)

The inspectors evaluated the configuration of the following temporary ventilation systems:

(1) Auxiliary building sump pit

71124.05 - Radiation Monitoring Instrumentation

Walkdowns and Observations (IP Section 03.01) (6 Samples)

The inspectors evaluated the following radiation detection instrumentation during plant walkdowns:

(1) Portable ion chambers survey instruments stored ready for use at the radiologically controlled area exit facility
(2) Observed the calibration of the Raddos personnel contamination monitor, Serial Number 479902
(3) Observed the operation of the Hopewell Designs gamma irradiator
(4) Observed the calibration of the MG Telepole, Serial Number 6605-075
(5) Observed the performance of source checks on the Canberra Fastscan whole body counter
(6) Portable GM contamination survey instruments stored and ready for use at the radiologically controlled area exit facility

Calibration and Testing Program (IP Section 03.02) (13 Samples)

The inspectors evaluated the calibration and testing of the following radiation detection instruments:

(1) Canberra Fastscan whole body counter
(2) JL Shepherd Model 89 gamma irradiator
(3) Hopewell Designs Model G10-2-2600-2SR gamma irradiator
(4) MGP DMC 3000 electronic dosimeter, serial number 100511
(5) MGP IRD 2000 gamma calibrator (6)1/2 R-48 containment high range monitor
(7) Thermo Scientific SAM 12 small article monitor, serial number 537597
(8) Rados personnel contamination monitor, serial number 479900
(9) Control room ventilation system train A
(10) Ludlum Model 2241-4/42-31H, serial numbers 279858/PR296854
(11) Area radiation monitor 2R53, SI pump area
(12) Eberline AMS4 air sampler, serial number 1289
(13) Gamma spectroscopy system #13 Effluent Monitoring Calibration and Testing Program Sample (IP Sample 03.03) (2 Samples)

The inspectors evaluated the calibration and maintenance of the following radioactive effluent monitoring and measurement instrumentation:

(1) Unit 1 steam generator blowdown liquid effluent monitor (1R-19)
(2) Unit 1 shield building ventilation monitor (1R-22)

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

MS07: High Pressure Injection Systems (IP Section 02.06)===

(1) Unit 1 (October 1, 2021, through September 30, 2022)
(2) Unit 2 (October 1, 2021, through September 30, 2022)

MS08: Heat Removal Systems (IP Section 02.07) (2 Samples)

(1) Unit 1 (October 1, 2021, through September 30, 2022)
(2) Unit 2 (October 1, 2021, through September 30, 2022)

MS09: Residual Heat Removal Systems (IP Section 02.08) (2 Samples)

(1) Unit 1 (October 1, 2021, through September 30, 2022)
(2) Unit 2 (October 1, 2021, through September 30, 2022)

MS10: Cooling Water Support Systems (IP Section 02.09) (2 Samples)

(1) Unit 1 (October 1, 2021, through September 30, 2022)
(2) Unit 2 (October 1, 2021, through September 30, 2022)

BI01: Reactor Coolant System (RCS) Specific Activity Sample (IP Section 02.10) (2 Samples)

(1) Unit 1 (April 1, 2021, through September 30, 2022)
(2) Unit 2 (April 1, 2021, through September 30, 2022)

OR01: Occupational Exposure Control Effectiveness Sample (IP Section 02.15) (1 Sample)

(1) April 1, 2021, through September 30, 2022 PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample (IP Section 02.16) (1 Sample)
(1) April 1, 2021, through September 30, 2022

71153 - Follow Up of Events and Notices of Enforcement Discretion Event Report (IP Section 03.02)

The inspectors evaluated the following licensee event reports (LERs):

(1) LER 2022-001-00 Fuel Assemblies Incorrectly Placed in Spent Fuel Pool (ADAMS Accession No. ML22290A172). The inspection conclusions associated with this LER are documented in Inspection Report 05000282/2022003 and 05000306/2022003 (ADAMS Accession No. ML22300A183) under Inspection Results Section

INSPECTION RESULTS

Unresolved Item (Open)

Bus 15 Failure to Meet Acceptance Criteria URI 05000282/2022004-01 71111.15

Description:

During maintenance on safety-related safeguards bus 15, the resistance values obtained failed to meet acceptance criteria. The licensee took additional actions to disassemble, clean, and reassemble the bus bars in an attempt to improve the resistance readings. However, the as-left values were higher than the as-found values. Engineering performed an evaluation to disposition the as-left data not meeting acceptance criteria. Upon reviewing the documents associated with this activity, the inspectors had several questions regarding the work performed, documentation of work performed, and technical justification for the engineering evaluation.

Planned Closure Actions: Inspectors need to evaluate the adequacy of the work performed and/or work order documentation for compliance with 10 CFR 50, appendix B, criterion V requirements as well as the licensee quality assurance program and implementing procedures. In addition, inspectors will need to assess and evaluate the technical justification in the licensee's engineering evaluation to determine reasonable assurance that the safeguards bus will continue to perform its specified safety function until the next performance of the maintenance which is scheduled in 4 years.

Licensee Actions: Based upon the data not meeting the acceptance criteria, the licensee disassembled at least some of the connections, cleaned, and reassembled the bus bar connections. In addition, they reduced the period between inspections from 8 years to 4 years per the EPRI recommendations. Since the licensee had restored the bus bar to operable condition, the inspectors have no immediate safety concerns.

Corrective Action References: 501000054247, "PE 009 Acceptance Criteria Change-Update" 501000068630, "PE 0009 In Need of Update" 501000067574, "Over-Limit High Cubicle-to-Cubicle Res" 501000067578, "Hi Stab Resist: Bus 15 Cub 7 Hi Side" 501000067646, "Relay Testing Failure - Sol. Coil" Very Low Safety Significance Issue Resolution Process: Closure of Unresolved Item 05000282/2018011-02 and 05000306/2018011-02 - Potential Failure to Protect Class 1 Structures, Systems and Components from Tornado Generated Missiles 71111.21M This issue is a current licensing basis question and inspection effort is being discontinued in accordance with the Very Low Safety Significance Issue Resolution (VLSSIR) process. No further evaluation is required.

Description:

Prairie Island Nuclear Generating Plant Design Basis Assurance Inspection Report 05000282/2018011 and 05000306/2018011 identified an unresolved item regarding the potential failure to protect class I structures, systems and components from tornado generated missiles as described in chapters 1 and 12 of the Updated Safety Analysis Report.

Specifically, the team postulated the design basis tornado missile (either a 4x12x12 plank traveling end on at 300 miles per hour or a 4,000 pound automobile flying through the air at 50 miles per hour and not more than 25 feet above ground level) could impact one of the following combinations of equipment rendering the equipment non-functional during a tornado:

-

the D1 and D2 EDG engine exhaust piping

-

the D1 and D2 EDGs fuel oil day tank vent piping

-

the D1 and D2 EDGs fuel oil storage tank vent piping

-

the 12 and 22 DDCLP fuel oil day tank vent piping

-

the 12 and 22 DDCLP fuel oil storage tank vent piping

-

the 12 and 22 DDCLP engine exhaust piping

-

the 12 and 22 DDCLP room ventilation intake and exhaust equipment Licensing Basis: The licensees position is that the site has always met the licensing basis based on the following:

-

a tornado event is not concurrent with any other event or accident

-

no single failure is taken during a tornado event

-

only one tornado missile is required to be assumed per tornado event

-

tornado missile protection is provided via separation and redundancy

-

susceptible vents and exhausts are stacks (Class III components) and do not require tornado missile protection The inspectors, using the resource estimate in the applicable inspection procedure as a guideline and involvement with NRC headquarters support, have not been able to conclude whether adequate tornado missile protection is provided via separation and redundancy. In addition, the inspectors have not been able to determine whether the vents and exhausts listed above are class I (require protection) or class III (do not require protection)components.

Significance: Initiating events, hypothetical situations, and other failures, including multiple equipment failures are treated probabilistically in the probabilistic risk assessment itself. If an SSC is the subject of a performance deficiency and is degraded only under a very specific set of hypothetical circumstances, then it is likely to be of very low safety significance. To the VLSSIR process, a February 28, 2019, letter from Ho Nieh, Office of Nuclear Reactor Regulation Director, to the Nuclear Energy Institute (ADAMS Accession Number ML18338A085), also indicated that based upon information gathered during post-compliance inspections at each plant, and considering the additional defense-in-depth benefits of mitigating strategies implemented at each U.S. nuclear plant as part of NRC Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, the NRC has confidence the safety significance of tornado missiles is very low. Based upon the significance evaluation discussed above and the information provided in the February 28, 2019, letter, the NRC does not plan to expend additional resources to determine whether the components listed above are adequately protected from a tornado missile via separation and redundancy, nor does the NRC plan to determine whether the vents and exhausts listed above are class I or class III components. Unresolved Item 05000282/2018011-02 and 05000306/2018011-02 is closed.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On January 13, 2023, the inspectors presented the integrated inspection results to C. Domingos, Site Vice President, and other members of the licensee staff.

On October 11, 2022, the inspectors presented the licensed operator requalification program annual operating test inspection results to F. Collins, Operator License Program Manager, and other members of the licensee staff.

On October 27, 2022, the inspectors presented the radiation protection inspection results to H. Hanson, Plant Manager, and other members of the licensee staff.

On October 28, 2022, the inspectors presented the Unit 1 inservice inspection results to C. Turner, Director of Site Performance, and other members of the licensee staff.

On November 30, 2022, the inspectors presented the emergency action level and emergency plan changes inspection results to J. Bremer, Regulatory Assurance Manager, and other members of the licensee staff.

On December 1, 2022, the inspectors presented the radiation protection baseline inspection results to H. Hanson, Plant Manager, and other members of the licensee staff.

On December 15, 2022, the inspectors presented the closure of unresolved item 05000282/2018011-02 and 05000306/2018011-02 inspection results to J. Bremer, Regulatory Assurance Manager, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

C1.1.20.5-1

Unit 1 4.16kV System Switches and Indication Checklist

C1.1.20.5-1

Unit 1 4.16 kV System Switches and Indication Checklist

C16-1

Spent Fuel Pool Cooling

71111.04

Procedures

C28-17

Turbine Driven Auxiliary Feedwater Pump

Procedures

SP 1424

Unit 1 Five (5) Year Containment Fan Coil Unit Performance

Test

WO 700077322

SP 1424 CTMT Fan Coil Unit Perf Test

10/24/2022

71111.07A

Work Orders

WO 700077322

SP 1424 CTMT Fan Coil Unit Perf Test

09/29/2022

501000044650

ISI Indications On 11 RCP Support

09/25/2020

501000059447

Relief Request Rx Vessel Fluence Error

01/04/2022

501000067456

1R33 ISI Indication 11 CC HX Support

10/17/2022

501000067641

RV Closure Head 157-051 Inspection 1R33

10/22/2022

501000067694

Late Response to NRC Questions

10/24/2022

Corrective Action

Documents

610000000561

OEER: NRC RIS 2018-06 PWR UH Visual Exam

2/11/2018

PI-1R33-MT-001

Steam Generator Feedwater Nozzle to Shell Weld

Component N-1

10/22/2022

PI-1R33-UT-002

Pipe to Pipe Weld Component W-5

10/22/2022

PI-1R33-UT-003

Elbow to Pipe Weld Component W-4

10/22/2022

PI-1R33-VT-020

Reactor Vessel Closure Head Bare Metal Visual Examination

10/25/2022

NDE Reports

PI*1R33*VT*008

CC HX Support

10/20/2022

FP-PE-NDE-300

Dry Magnetic Particle Examination - Yoke/Coil

FP-PE-NDE-402

Ultrasonic Examination of Austenitic Pipe Welds -

Supplement 2

FP-PE-NDE-530

Visual Examination, VT-3

H-2

Boric Acid Corrosion Control Program

Procedures

SWI NDE-VT-6.0

Visual Examination for Leakage on Reactor Vessel

Penetrations (VT-2)

71111.08P

Work Orders

WO 700072740-

0340

Cl Hdr Pipe Replace on 24-CL -13 & -16

2/09/2021

71111.11A

Miscellaneous

22 LOR NRC

Annual Op Test

Prairie Island 2022 Licensed Operator Requalification Exam

Summary Which Provides the Exam Results for the Annual

10/01/2022

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Summary

Operating Tests and a Make-up Biennial Written Examination

Administered from 04/25/2022 - 06/06/2022

Calculations

ENG-ME-185

Unit 1 - 4160V Switchgear Rm Ventilation Sys Design

501000067574

Over-Limit High Cubicle-to-Cubicle Res.

10/22/2022

501000067578

Hi Stab Resist: Bus 15 Cub 7 Hi Side

10/22/2022

Corrective Action

Documents

501000067646

Relay Testing Failure - Sol. Coil

10/23/2022

EC 0000023197

Develop Construction Standard for Bolting 4kV and 480V Bus

Bar Connections

000

EC 23197

Develop Construction Standard for Bolting 4kV and 480V Bus

Bar Connections

EC-0441

EC-0441 EC Closeout Package Report (Rev. 4)

Engineering

Changes

ENG-E-185

EC 25112, Cable Reroute Heat Load Affects

0C

Engineering

Evaluations

EA

608000000492

PE 0009 Bus Contact Resistance Acceptance Criteria Update

10/15/2019

ANSI/NETA ATS-

2009

Standard for Acceptance Testing Specifications for Electrical

Power Equipment and Systems

ASME NQA-1-

1994 Edition

Quality Assurance Requirements for Nuclear Facility

Applications

07/29/1994

EM 4.3.1-B.3

Bolting Standard for Electrical Bus Connections

EM 4.3.1-T.1

Termination

NSPM-1

Quality Assurance Topical Report

NSPM-1

Quality Assurance Topical Report

QF0739, Request

Number 240

EPRI TR 104213, Section 7 Has Temperature Limitations

Associated With the Torque Tables Contained With This

Section.

11/16/2022

Miscellaneous

QF0739, Request

Number 268

EC 608000000896, Was the Engineering Recommendation

for Additional Work Completed and What Work Was Done and

What Were the Results?

11/02/2022

FP-NO-QC-02

Inspection Planning

FSG-25

Isolation and Repower Bus 25 During ELAP

H65

License Renewal Implementation and Aging Management

Programs

H65.2.6

Bolting Integrity Aging Management Program

71111.12

Procedures

H65.2.6

Bolting Integrity Aging Management Program

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

MSIP 3026

Bolting Standard for Electrical Bus Connections

MSIP 3026

Bolting Standard for Electrical Bus Connections

PE 0009

4kV Switchgear Preventive Maintenance

PE 0009

4kV Switchgear Preventive Maintenance

PE 0009

4kV Switchgear Preventative Maintenance

WO 700061067

PE-B15-2BUS 15 Inspection/Doble

09/01/2022

WO 700061067

PE-B15-2BUS 15 INSPECTION/DOBLE

10/27/2022

Work Orders

WO 700061067

PE-B15-2BUS 15 INSPECTION/DOBLE

10/27/2022

71111.13

Procedures

B20.8

Instrument AC Distribution System

501000054247

PE 0009 Acceptance Criteria Change/Update

07/21/2021

501000067737

DDCLP Speed Switch 7030037

10/25/2022

Corrective Action

Documents

501000068630

PE 0009 in Need of Update

11/17/2022

608000000492

PE 0009 Bus Contact Resistance Acceptance Criteria Update

10/15/2019

608000000614

Evaluate Contact Resistance for Bus 16

608000000896

Bus 15 Contact Resistance Evaluation

608000000896

Bus 15 Contact Resistance Evaluation

608000000896

Bus 15 Contact Resistance Evaluation

10/24/2022

Engineering

Evaluations

608000000896,

Rev. 2

Bus 15 Contact Resistance Evaluation

11/03/2022

LER 05000282;

01-05-00

Fault and Fire in Non-Safeguards Circuit Breaker Results in

Reactor Trip

10/02/2001

QF0739, Request

Number 241

In EC Eval 896, Why Do We Not Consider All the Heat Load

Above the Design Bases?

11/16/2022

QF0739, Request

Number 242

The Engineering Evaluation 608000000896 Says the Current

Heat Load is Acceptable, However the Maintenance is

Performed Every 4 years. Based on the Upward Trend, is That

Acceptable?

11/16/2022

QF0739, Request

Number 264

EC 608000000896, PE 0009 Acceptance Criteria for Each

Phase Is Determined by 50% Deviation From a Three Data

Set Rolling Average From Previous Readings.

11/02/2022

71111.15

Miscellaneous

QF0739, Request

Number 265

EC 608000000896 Did Not Evaluate the High Stab Resistance

as Identified in QI 501000067578, for the Potential Impact for

Fire Based on the High Resistance as Left Value Being Higher

than the As Found

11/02/2022

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

QF0739, Request

Number 266

EC 608000000896 Attachment 6 is the decision tree to work

through to Address Potential High Resistance

11/02/2022

QF0739, Request

Number 267

EC 608000000896; The Increase Documented in the

Engineering Evaluation is Greater Than the Margin in

ENG-ME-185, Why is a Calculation Update Not Required?

11/02/2022

B35

Cooling Water System

C18.1

Engineered Safeguards Equipment Support Systems

FSG-20

Cooling Water Management Following a Loss of AC Power

PE 0009

4kV Switchgear Preventive Maintenance

PM 3002-2-12

DDCLP Diesel Minor Periodic Maintenance

PM 4910

Thermographic Inspection of Prairie Island Components

Procedures

SP 1106A

Diesel Cooling Water Pump Monthly Test

103

LP P9112L-0902

EDMG/SAMG Review

P7480L-001

SAMG Overview

PI-BEP-CNT-

005F

SAMG Overview

Miscellaneous

PINGP 1237

SAMG Evaluation Team Leader Checklist

1DPG

Diagnostic Process Guideline

1SAG-1

Main Control Room Severe Accident Guideline Initial

Response

1SAG-2

Main Control Room Severe Accident Guideline TSC

Recommending Strategies

1SAG-3

Inject Into the Steam Generators

1SAG-4

Depressurize the RCS

1SAG-5

Inject Into the RCS

1SAG-6

Inject Into Containment

1SAG-7

Reduce Containment Hydrogen

1SAG-8

Control Containment Pressure

1SAG-9

Mitigate Fission Product Releases

1TSG-1

Instrumentation

1TSG-3

Site Capabilities

2DPG

Diagnostic Process Guideline

71111.18

Procedures

2SAG-1

Main Control Room Severe Accident Guideline Initial

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Response

2SAG-2

Main Control Room Severe Accident Guideline TSC

Recommending Strategies

2SAG-3

Inject Into the Steam Generators

2SAG-4

Depressurize the RCS

2SAG-5

Inject Into the RCS

2SAG-6

Inject Into Containment

2SAG-7

Reduce Containment Hydrogen

2SAG-8

Control Containment Pressure

2SAG-9

Mitigate Fission Product Releases

2TSG-1

Instrumentation

2TSG-3

Site Capabilities

CD 10.2

Severe Accident Management Guidelines (SAMGs) Program

SAG-10

Control Spent Fuel Pool Level

TSG-2

Ultimate Decision Maker

TSG-4

Benefit Consequence

TSG-5

Computational Aids

Drawings

XH-112-1

Main Steam Isolation Valve and Check Valve

2C20.7

D5/D6 Diesel Generators

D72

Check Valve Disassembly and Inspection Procedures

D72 ATT R

Schutte and Koerting Check Valves

MSIP 6004

Rigging from Grating

SP 1070

Reactor Coolant System Integrity Test

SP 1072

Local Leakage Rate Test of Containment Penetrations

SP 1072.41A

Local Leakage Rate Test of Penetration 41A No. 11 Vacuum

Breaker

SP 1072.41B

Local Leakage Rate Test of Penetration 41B No. 12 Vacuum

Breaker

SP 1373

RS-19-1 Unit 1 Loop A MSIV Non-Return Check Valve IST

Test

Procedures

SP 2295

D5 Diesel Generator 6 Month Fast Start Test

WO 700080770

SP 1072.41A - LLRT 11 Vacuum Breaker

10/04/2022

71111.19

Work Orders

WO 700080822

SP 1072.41B - LLRT 12 Vacuum Breaker

10/04/2022

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

WO 700081344

SP 1072 - LLRT OF CNTMT PENET

10/04/2022

WO 700094054-

U1 Westnghse NIS Pwr Range BTI Panels

06/06/2022

WO 700094054-

U1 Westnghse NIS Pwr Range BTI Panels

06/07/2022

WO 700094054-

U1 Westnghse NIS Pwr Range BTI Panels

06/07/2022

WO 700094054-

U1 Westnghse NIS Pwr Range BTI Panels

06/07/2022

WO 700097178

Replace D5 Low Voltage/Low Current RLYS

08/23/2022

WO 700115103

RS-19-1 Disassembly and Inspection

10/31/2022

501000067235

1N32 CPS Did Not Come on Scale

10/14/2022

501000067253

CV-31095 Leaks By

10/14/2022

501000067257

FM in Containment

10/14/2022

501000067261

1N32 Did Not Come on Scale With 1N31

10/14/2022

501000067270

Oil Leak On 11 Turb Oil Cooler End Bell

10/14/2022

501000067271

Unit 1 Turbine Stop Valve SV-1 Leaks By

10/15/2022

501000067288

DEHC Micronet Modules Contain Capacitors

10/17/2022

501000067290

Both A and B Door Can Open at Same Time

10/15/2022

501000067296

Fault on Relay Room Incipient Detector

10/15/2022

501000067310

CV-31255 Timed Out of Limiting Stroke

10/15/2022

501000067311

SP 1168.3, RHR Pit Pressure Test Missed

10/16/2022

501000067312

Valve Stem in Containment Leak Level 696'

10/16/2022

501000067327

CV-31423 Partially Open

10/17/2022

501000067328

Rifle Round Found in Sec. Search Train

10/17/2022

501000067342

SP 1083A Table 20 Data

10/16/2022

501000067345

Security Radio and Communication Checks

10/17/2022

501000067346

Temp Designated Hot Work Area

10/17/2022

501000067352

SP 1083A Expected Lights not Received

10/16/2022

501000067357

AMP Requirements for Diving Activities

10/17/2022

501000067360

Containment Spray Pump Run Time

10/17/2022

501000067368

Boric Acid Around Reactor Vessel Studs

10/17/2022

71111.20

Corrective Action

Documents

501000067539

1R33 ISI Indication SP 1392 Bolted Conn

10/21/2022

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

501000067562

Place 5 to 4 Mode Hold for Sump C Repair

10/20/2022

501000067572

CST Tmod Cold Weather Effectiveness

10/21/2022

501000067580

MV-32072: Packing Leak Identified

10/21/2022

501000067589

Bus 112 Undervoltage Relay Failed

10/21/2022

501000067591

Anonymous CAP-Anonymous Condition Report

10/21/2022

501000067597

Unable to Verify Closed

10/23/2022

501000067598

Valve Testing Open Outside Ref Range

10/23/2022

501000067600

Damaged Thrusts Bearing on 11 CC PMP

10/21/2022

501000067616

Traveling Screen Broken Sheer Pin

10/21/2022

501000067629

APP J: CV-31929 Leak Rate Exceeded Admin

10/23/2022

501000067635

Indications of T/C Inst. Ports

10/22/2022

501000067652

PENC 17 Potential Rock UP With BA

10/23/2022

501000067658

Solenoid Failed Open

10/25/2022

501000067665

RCP Motor Oil Drain Not Identified

10/23/2022

501000067698

Cont Plan/Prot Equip Misalignment

10/24/2022

501000067746

CV-31637 Stroked Outside of Band

10/25/2022

501000067750

MV-32165 Running Load High

10/25/2022

501000067814

CV-31369 High Friction

10/27/2022

501000067817

As Found Readings Below Range Cycle

10/27/2022

501000067824

Minor Leakage from Dome of CV-31224

10/27/2022

501000067829

I/P Trending QIM

10/28/2022

501000067843

RCP Terminal Bar Issue

10/28/2022

501000067848

1R33 ISI Indication SP 1168.3 RHR Pits

10/28/2022

501000067862

VC-2-1, 11 VCT OUT CHECK VLV Leak By

10/27/2022

501000067863

U1 Incipient Detector 2 LED Fault

10/28/2022

501000067868

Possible Charging Pmp Suct Overpressure

10/28/2022

501000067879

CV-31622 Is Leaking

10/28/2022

501000067885

I/P Would Not Calibrate to Tolerance

10/29/2022

501000068034

Inverter, North Fan Not Running

11/01/2022

501000068061

MV-32016 Low Packing Load

11/02/2022

501000068071

Contractor RP Staffing

11/02/2022

501000068118

1R33 LLRT Nitrogen Blanket Bleed Off

11/03/2022

501000068128

Unterminated Cable

11/05/2022

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

501000068141

Uncontrolled Badges in the PA

11/03/2022

501000068151

MV-32027 Running Load High

11/03/2022

501000068188

Mode 4 Dose Equivalent Xenon-133

11/06/2022

501000068189

1R33 ISI Indication SP 1168.1 RCS Press

11/06/2022

501000068195

Air Leak From Tubing for CV-31637

11/06/2022

501000068197

CV-39426

11/06/2022

501000068237

MD AFW PMP Inner Seal Pck Leakage >60

11/07/2022

501000068237

MD AFW PMP Inner Seal Pck Leakage >60

11/07/2022

501000068238

Suspected Leakby On CV-31998

11/07/2022

501000068244

Existing 86B/105 Relay Did Not Function

11/06/2022

501000068261

Flammable Storage Locker Does Not Latch

11/06/2022

501000068357

Unable to Close or Reposition 2HS-21-15

11/10/2022

501000068358

New B Kernel Power Supply Failed

11/10/2022

501000068361

Flux Trace Deviation Outside Guidance

11/10/2022

501000068361

Flux Trace Deviation Outside Guidance

11/10/2022

501000068375

22 PIR FSA CAP Not Rescreened

11/10/2022

501000068376

RCP Stator High Temps

11/10/2022

501000068377

TP 1626 90% Rectifiers Op Not Met

11/10/2022

501000068381

GAMP: Acceptable Voids in RHR Suction

11/09/2022

501000068391

PMT Packing Leak

11/10/2022

501000068393

ASME Post Work Review for WO 700108241

11/10/2022

501000068405

Failed 1N-44 Bistable

11/10/2022

501000068413

Camera 45 Fail

11/11/2022

501000068415

U1 Incore Drive A & C Erratic Behavior

11/11/2022

501000068446

D5 Rack Diff >1.5mm (.258V) When Stopped

11/14/2022

501000068461

Xcel Energy TD Oversight

11/13/2022

501000068500

NRC Red Phone in CR not Working

11/15/2022

Corrective Action

Documents

Resulting from

Inspection

501000068093

Sr. Resident Questions about EC Eval

11/02/2022

Miscellaneous

ASME NQA-1-

22

SUBPART 2.18 Quality Assurance Requirements for

Maintenance of Nuclear Facilities

1994

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CS Resource

NRC

1R33 Unit 1 Refueling Outage (TRN A)

10/11/2022

Schedule Critical

Path

1R33 Unit 1 Refueling Outage (TRN A)

10/11/2022

D30

Post Refueling Startup Testing

D58.1.9

Unit 1 Reactor Vessel Head Removal

H10.1

ASME Inservice Testing Program

SP 1136.2

Volumetric Leakage Rate Test of Containment Maintenance

Airlock

SP 1168.1

Unit 1 Reactor Coolant System Pressure Test

SP 1177

Core Inventory Verification

Procedures

SP 1750

Post Outage Containment Close-Out Inspection

WO 700080382

SP 1177 - RFL Core Inventory Verif

10/27/2022

WO 700094054-

U1 Westnghse NIS Pwr Range BTI Panels

06/06/2022

WO 700094054-

U1 Westnghse NIS Pwr Range BTI Panels

06/07/2022

WO 700094054-

U1 Westnghse NIS Pwr Range BTI Panels

06/07/2022

Work Orders

WO 700094054-

U1 Westnghse NIS Pwr Range BTI Panels

06/07/2022

Corrective Action

Documents

501000012997

2018 DBAI: FOST Vent Line Classification

06/06/2018

NF-38550

Architectural Screen House Plan Elevation 695'-0" and

Elevations

NF-39232

Flow Diagram Fuel and Diesel System Unit 1 and 2

Drawings

NF-39601

HVAC Flow Diagram Turbine Building-Diesel Generator Unit 1

and 2

APC 18-04

NEI Position on Tornado-Generated Missile Analysis

Considerations for Single Missile and Single Failure Criterion

2/16/2018

71111.21M

Miscellaneous

White Paper

Response to NRC Question on Fuel Oil Storage Tank Vents

unknown

SP 1070

Reactor Coolant System Integrity Test

71111.22

Procedures

SP 1092A

SI Check Valve Test (Head Off) Part A: High Head SI Flow

Path Verification

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

SP 1092B

Safety Injection Check Valve Test (Head Off) Part B: RWST to

RHR Flow Path Verification

SP 1111A

Train A Main Steam Power Operated Relief Valve Test

09/06/2022

SP 2155B

CC System Quarterly Test Train B

WO 700081726

SP 1168.1 - U1 RX Coolant Sys Press Test

11/06/2022

WO 700101564

SP 1111A TRN A POWER OPER RLF VLV TEST

09/17/2022

Work Orders

WO 700102757

SP 2155BCC SYS QTR TEST TRN B

09/28/2022

FT-2021-756

FP-S-FSIP-07 Revision

10/27/2021

PI-2021-753

F3-17 Revision

11/20/2021

PI-2021-754

EDCM 300 Revision

08/30/2021

PI-2021-757

F3-13.3

11/08/2021

PI-2021-758

F3-23-1C and F3-23-2C Revisions

11/10/2021

Miscellaneous

PI-2022-764

PING 580 Revision

01/27/2022

EDCM 300

Liquid Release to River Dose Calculation

EPlan

Emergency Plan

EPlan

Emergency Plan

F3-13.3

Manual Dose Calculations

F3-17

Core Damage Assessment

71114.04

Procedures

F8-3

Activation and Operation of the Emergency Operations Facility

Miscellaneous

Prairie Island Plant Alpha Characterization Study

07/26/2022

FP-RP-AM-01

Alpha Monitoring Program

FP-RP-NISP-02

Radiation and Contamination Surveys

FP-RP-NISP-05

Access Controls for High Radiation Areas

PING 1560

Posting Changes for Fuel Handling

Procedures

PINGP 1236

Reactor Coolant System and Draindown Radiation Protection

Requirements

Air Sample Report

10/22/2022

PI-M-20221015-

Regen Room Initial Entry

10/15/2022

PI-M-20221015-

Regen Room Post Shielding

10/16/2022

PI-M-20221018-5

Regen Room Insulation Removal

10/16/2022

71124.01

Radiation Surveys

PI-M-20221019-

Chemical Volume Control System Passageway Down Posting

10/19/2022

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

PI-M-20221019-

Down Posting Internals Lift Rig Area

10/19/2022

PI-M-20221022-

Reactor Head O-Ring Removal

10/22/2022

PI-M-20221022-

  1. 12 Steam Generator Secondary Side

10/22/2022

RWP 221007

1R33 Regenerative Heat Exchanger Room Work

RWP 221020

1R33 Reactor Coolant Pump Work

Radiation Work

Permits (RWPs)

RWP 221042

1R33 - Reactor Head Disassembly/Reassembly Work

Thermo Scientific SAM-12 Small Article Monitor, Serial

Number 537597

09/02/2021

Rados Personnel Contamination Monitor, Serial Number

479900

05/25/2020

JL Shepherd Model 89 Gamma Irradiator Calibration

2/07/2021

Daily and Weekly Portal Monitor Checks

11/20/2022

MGP DMC 3000 Electronic Dosimeter, Serial Number 100511

09/08/2022

MGP IRD 2000 Gamma Calibrator

08/24/2021

Ludlum Model 2241-4/42-31H Serial Numbers

279858/PR296854

01/18/2022

Eberline AMS-4 Air Sampler Serial Number 1289

08/03/2022

Chemistry Gamma Spectroscopy System #13

09/30/2022 -

10/04/2022

Mirion/Canberra Whole Body Counter Calibration

08/10/2022

2-0067-03673

Hopewell Designs Gamma Irradiator Calibration

07/26/2022

WO 700411531

1R19 Liquid Calibration

08/25/2010

WO 700057522

Area Radiation Monitor Calibrations

04/03/2020

WO 700076794

Control Room Ventilation System Train A

07/22/2021

WO 700109283

1R-22 Shield Building Radiation Monitor

10/05/2022

WO700089639

1/2 R-48 Containment High Range Monitor Electronic

Calibration

05/17/2022

Calibration

Records

WO 700098730

SP 1027.4 High Range Radiation Monitor

08/17/2022

71124.05

Corrective Action

501000050540

Aging Rados RCA Exit Monitors

04/15/2021

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

501000058741

2R-48 Containment Hi Range Area Radiation Meter B

2/01/2021

501000061995

M-177 Frisker Failed Function Check

04/06/2022

501000062414

Weld Break on JL Shepherd

04/19/2022

Documents

501000062547

As Found Calibration Failure

04/26/2022

Radiochemistry Cross Check Performance Data Fourth

Quarter 2020 through Third Quarter 2022

Various

NSPM RP Instrument Response Investigation Report for

Instrument Model 2241-4, Serial Number 600072

06/25/2022

Miscellaneous

National Source Tracking System Annual Inventory

Reconciliation Report

01/05/2022

Procedures

FP-RP-EDC-01

DMC 2000S/DMC3000SOR Electronic Dosimeter and IRD

2000 Calibration

Corrective Action

Documents

501000069038

MSPI Coefficients Not Revised Timely

2/08/2022

MSPI Indicator

Margin Remaining

in Green

Prairie Island Unit 1, System ROP-MSPI-CWS MSPI Cooling

Water System, P/E March 2022

March 2022

MSPI Indicator

Margin Remaining

in Green

Prairie Island Unit 1, System ROP-MSPI-CWS MSPI Cooling

Water System, P/E June 2022

June 2022

MSPI Indicator

Margin Remaining

in Green

Prairie Island Unit 2, System ROP-MSPI-CWS MSPI Cooling

Water System, P/E December 2021

December

21

MSPI Indicator

Margin Remaining

in Green

Prairie Island Unit 2, System ROP-MSPI-CWS MSPI Cooling

Water System, P/E March 2022

March 2022

MSPI Indicator

Margin Remaining

in Green

Prairie Island, Unit 2, System ROP-MSPI-CWS MSPI Cooling

Water System, P/E June 2022

June 2022

71151

Miscellaneous

QF0739, Request

Number 244

For the Performance Indicator MSPI 10 (Cooling Water), Why

Is There a Difference Between the NRC Website Numbers

and the INPO Reports?

2/07/2022

501000051933

DBAI - OM 2017-06 Not Fully Evaluated

05/12/2021

71152A

Corrective Action

Documents

2000013088

QF2900, Fire Protection Program Impact Screen, IN 2017-06

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CR

610000000170

OEER-NRC IN 2017-06 BATTERY & BATTERY CH

05/08/2019

OEE AR

501000051933

DBAI - IN 2017-06 Not Fully Evaluated

08/13/2021

OEE AR

501000051933

Revise IN 2017-06 Response

2/25/2022

Corrective Action

Documents

Resulting from

Inspection

501000062449

NRC Question on Updates to PRA for OE

04/21/2022

Change Number:

PI-22-0014 (FP)

IN 2017-06 Battery Charger Fault Current Could Trip DC

Output Breaker

2/22/2022

Miscellaneous

QF0739

Provide Response to the Item of Interest Regarding

Information Notice 2017-06 as It Pertains to Coordination

Between the Battery Charger Output Breaker and

Downstream Fusing.

05/26/2021