Integrated Inspection Report 05000282/2023002 and 05000306/2023002
ML23215A177
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 08/03/2023
From: Hironori Peterson
NRC/RGN-III/DORS/RPB3
To: Conboy T
Northern States Power Company, Minnesota
References
IR 2023002
Download: ML23215A177 (1)


Text

SUBJECT:

PRAIRIE ISLAND NUCLEAR GENERATING PLANT - INTEGRATED INSPECTION REPORT 05000282/2023002 AND 05000306/2023002

Dear Thomas Conboy:

On June 30, 2023, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Prairie Island Nuclear Generating Plant. On July 21, 2023, the NRC inspectors discussed the results of this inspection with Thomas Conboy, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Hironori Peterson, Chief Reactor Projects Branch 3 Division of Operating Reactor Safety Docket Nos. 05000282 and 05000306 License Nos. DPR-42 and DPR-60

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000282 and 05000306

License Numbers:

DPR-42 and DPR-60

Report Numbers:

05000282/2023002 and 05000306/2023002

Enterprise Identifier:

I-2023-002-0059

Licensee:

Northern States Power Company

Facility:

Prairie Island Nuclear Generating Plant

Location:

Welch, MN

Inspection Dates:

April 01, 2023 to June 30, 2023

Inspectors:

R. Baker, Senior Operations Engineer

G. Hansen, Sr. Emergency Preparedness Inspector

J. Kutlesa, Emergency Preparedness Inspector

K. Pusateri, Resident Inspector

D. Tesar, Senior Resident Inspector

T. Wingfield, Senior Operations Engineer

Approved By:

Hironori Peterson, Chief

Reactor Projects Branch 3

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Prairie Island Nuclear Generating Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors.

Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

Unit 1 operated at or near rated thermal power for the entire inspection period with the exception of brief power reductions to perform surveillance testing or flexible power operations.

Unit 2 began the inspection period at rated thermal power. On May 27, 2023 at 6:19 p.m., the Unit 2 turbine generator and reactor tripped. The unit was taken critical on June 1, 2023 at 2:43 p.m., and was synched to the grid on June 2, 2023 at 7:50 a.m., ending the Unit 2 forced outage. The unit was raised to approximately 50 percent rated thermal power on June 3, 2023 at 3:36 a.m. and remained there. On June 7, 2023 at 1:00 a.m., Unit 2 commenced shutdown from approximately 50 percent power and the reactor was tripped at 3:33 a.m. Unit 2 reactor was taken critical on June 16, 2023 at 3:48 a.m. The unit was returned to full-rated thermal power on June 17, 2023 at 12:32 p.m., and remained at or near rated thermal power for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)

(1) On April 11, 2023 the inspectors evaluated readiness for seasonal extreme weather conditions per SP 1293, "Review of Seasonal Flood Preparations," for the following systems: the cooling water system, auxiliary feedwater system, and the emergency diesel generators.

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1)cooling water system walkdown in screenhouse and turbine building on April 19, 2023

(2) Unit 1 charging system after through-wall leak identified on May 2, 2023 (3)121 spent fuel pool cooling heat exchanger restoration on May 16, 2023
(4) Unit 2 nuclear instrumentation pre-startup from forced outage on June 12, 2023

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated system configurations during a complete walkdown of the Unit 2 4.16kV system on June 13, 2023.

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Fire Area (FA) 37, Unit 1 normal switchgear room, bus 150/160, elevation 695' on April 24, 2023
(2) FA 38, Unit 2 normal switchgear room, bus 250/260, elevation 695' on April 27, 2023
(3) FA 21, Unit 1 normal switchgear room bus 13 and 14, elevation 715' on May 1, 2023
(4) FA 23, Unit 2 normal switchgear room, bus 23 and 24, elevation 715' on May 1, 2023
(5) FA 66, D3 storage/construction room, elevation 695', detection on April 27, 2023
(6) FA 57, elevation 695', gas house on May 8, 2023

Fire Brigade Drill Performance Sample (IP Section 03.02) (2 Samples)

(1) The inspectors evaluated the onsite fire brigade training and performance during an announced Unit 2 2M transformer fire drill for detection zone 61 on June 20, 2023.
(2) The inspectors evaluated the onsite fire brigade training and performance during un-announced drill at the heating boiler, elevation 695', Unit 1 turbine building on June 26, 2023.

71111.06 - Flood Protection Measures

Flooding Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated external flooding upon entry into AB-4 flood, abnormal operating procedure for flooding mitigation protections on April 10, 2023.

71111.11A - Licensed Operator Requalification Program and Licensed Operator Performance

Requalification Examination Results (IP Section 03.03) (1 Sample)

(1) The inspectors reviewed and evaluated the licensed operator examination failure rates for the requalification annual operating tests and biennial written examinations administered from May 8, 2023 through June 16, 2023.

71111.11B - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Requalification Program (IP Section 03.04) (1 Sample)

(1) Biennial Requalification Written Examinations The inspectors evaluated the quality of the licensed operator biennial requalification written examination administered on May 18, 2023.

Annual Requalification Operating Tests The inspectors evaluated the adequacy of the facility licensees annual requalification operating test administered the week of May 15, 2023.

Administration of an Annual Requalification Operating Test The inspectors evaluated the effectiveness of the facility licensee in administering requalification operating tests required by 10 CFR 55.59(a)(2) and that the facility licensee is effectively evaluating their licensed operators for mastery of training objectives.

Requalification Examination Security The inspectors evaluated the ability of the facility licensee to safeguard examination material, such that the examination is not compromised.

Remedial Training and Re-examinations The inspectors evaluated the effectiveness of remedial training conducted by the licensee, and reviewed the adequacy of re-examinations for licensed operators who did not pass a required requalification examination.

Operator License Conditions The inspectors evaluated the licensees program for ensuring that licensed operators meet the conditions of their licenses.

Control Room Simulator The inspectors evaluated the adequacy of the facility licensees control room simulator in modeling the actual plant, and for meeting the requirements contained in 10 CFR 55.46.

Problem Identification and Resolution The inspectors evaluated the licensees ability to identify and resolve problems associated with licensed operator performance.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (3 Samples)

(1) The inspectors observed and evaluated licensed operator performance in the control room during 1A MSR reheater cooldown and heat up on April 17, 2023.
(2) The inspectors observed and evaluated licensed operator performance in the control room during Unit 2 startup from forced outage on June 1, 2023.
(3) The inspectors observed and evaluated licensed operator performance in the control room during Unit 2 shutdown for 22 main feed pump repairs on June 7, 2023.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated licensed operator requalification observation as-found evaluation on April 25, 2023.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (3 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) SV-37467, "Failure to Operate," on April 18, 2023
(2) CV-39423, "21/23 FCU Wtr Rtn CV Failed IST LST," on April 18, 2023
(3) CD-34085, "Failed to Open during SP 2091," on April 18, 2023

Quality Control (IP Section 03.02) (1 Sample)

The inspectors evaluated the effectiveness of maintenance and quality control activities to ensure the following SSC remains capable of performing its intended function:

(1)quality control maintenance review on May 1, 2023

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Work Order (WO) 700103068, "Megger Motor Control Center 1AB Bus 1"
(2) WO 700122454, "Replace Diaphragm VC-15-37" (3)12 EHC pump O-ring failure and replacement online on April 20, 2023
(4) WO 700063902, "SFP Transfer Canal Draindown"
(5) Unit 2 forced outage and bus failure to transfer 'M' to 'R' on June 1, 2023
(6) Unit 1B train component cooling water inservice testing comprehensive test failure on June 21, 2023

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (7 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Corrective Action Plan (CAP) 501000072239, "AFW [auxiliary feedwater] Pump Room Cooler Flow OOB"
(2) CAP 501000072050, "Low Oil Level 21 MDAFW [motor-driven auxiliary feedwater]

Pump"

(3) CAP 501000073498, "1R-50 Shield Building Vent Gas Rad Detector" (4)bus 21 underfrequency relay test light lit on May 24, 2023
(5) CAP 501000072054, "D1 Voltage Readings Out of Acceptance"
(6) CAP 501000073010, "13 Charging Pump Suction Side Leak"
(7) CAP 501000074231, "Elevated Temps in the Aux Building"

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (2 Samples)

The inspectors evaluated the following temporary or permanent modifications:

(1)cooling water artificial load modification on April 20, 2023 (2)121 control room chiller regulator on June 20, 2023

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (2 Samples)

(1) The inspectors evaluated the Unit 2 forced outage for the 'A' phase lightning arrestor failure on May 27, 2023.
(2) The inspectors evaluated Unit 2 forced outage for the 22 main feed pump repairs on June 7, 2023.

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (6 Samples)

(1) ICPM 0-047B, "122 Safeguards Traveling Screen DPS (7038605) Blowdown,"

on April 26, 2023

(2) PMT/return to service (RTS) of BKR 112G-9 on May 8, 2023
(3) PMT of spent fuel pool cooling system valve maintenance on May 15, 2023
(4) SP 1055.2, "122 Control Room Filter Efficiency Test," on May 22, 2023 (5)22 turbine-driven auxiliary feedwater pump PMT on May 23, 2023
(6) PMT following 2N32 nuclear instrument replacement on May 31, 2023

Surveillance Testing (IP Section 03.01) (3 Samples)

(1) SP 1106A, "12 Diesel Cooling Water Pump Monthly Test," on April 13, 2023
(2) SP 1258A, "Bus 15 Sequencer Load Rejection and Restoration of 121 CR Chiller,"

on May 9, 2023

(3) D2 emergency diesel generator fast start surveillance on May 22, 2023

Inservice Testing (IST) (IP Section 03.01) (1 Sample)

(1) SP 1155A, "CC System Quarterly Test Train A," on May 10, 2023

71114.02 - Alert and Notification System Testing

Inspection Review (IP Section 02.01-02.04) (1 Sample)

(1) The inspectors evaluated the following maintenance and testing of the alert and notification system:

annual siren inspection and maintenance records for the period from May 2021 to May 2023

monthly alert notification system (siren) tests for the period from May 2021 to May 2023

71114.03 - Emergency Response Organization Staffing and Augmentation System

Inspection Review (IP Section 02.01-02.02) (1 Sample)

(1) The inspectors evaluated the readiness of the emergency response organization.

71114.05 - Maintenance of Emergency Preparedness

Inspection Review (IP Section 02.01 - 02.11) (1 Sample)

(1) The inspectors evaluated the maintenance of the emergency preparedness program.

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

BI02: RCS Leak Rate Sample (IP Section 02.11)===

(1) Unit 1 (April 1, 2022, through March 31, 2023)
(2) Unit 2 (April 1, 2022, through March 31, 2023)

EP01: Drill/Exercise Performance (DEP) Sample (IP Section 02.12) (1 Sample)

(1) April 1, 2022, through March 31, 2023 EP02: Emergency Response Organization (ERO) Drill Participation (IP Section 02.13) (1 Sample)
(1) April 1, 2022, through March 31, 2023 EP03: Alert and Notification System (ANS) Reliability Sample (IP Section 02.14) (1 Sample)
(1) April 1, 2022, through March 31, 2023

71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1)follow-up of D5/D6 Fuel Oil Storage Tank (FOST) vault tank and piping condition on June 20, 2023

71152S - Semiannual Trend Problem Identification and Resolution Semiannual Trend Review (Section 03.02)

(1)semi-annual trend of ES4 detectors out of service on April 24, 2023 (2)cognitive trend - security behaviors on June 13, 2023 71153 - Follow Up of Events and Notices of Enforcement Discretion Event Report (IP section 03.02) (1 Partial)

The inspectors evaluated the following licensee event reports (LERs):

(1)

(Partial)10 CFR 50.72 Report for Auto Start of Aux Feedwater Pumps. Inspectors have reviewed the circumstances surrounding the event and will review the LER once it has been submitted.

INSPECTION RESULTS

Observation: Annual Follow-up D5/D6 Storage Vault Tank and Piping Material Condition 71152A Inspectors performed an annual follow-up sample of CAPs 501000054198, 501000054985, 500000317360, 501000064012, and 501000064279, associated with the material condition of the D5/D6 fuel oil storage tank (FOST) vaults and piping. These CAPs were associated with material issues and a non-cited violation identified in August of 2021. In 2019, a hole was discovered in the 23 FOST suction line due to exterior corrosion. A temporary modification (T-mod) was put into place as a compensatory measure. In 2021, based upon questions from the NRC, the T-mod was removed, and the section of piping was replaced. During the work in the vaults and subsequent inspections, additional degradation of the vaults, tanks, and the piping was identified. Subsequent preventive maintenance activities completed since August of 2021 have resulted in unmet acceptance criteria. Inspectors did not identify any substantive actions which have been taken to correct these issues to date. However, piping repairs are currently scheduled to occur during the upcoming refueling outage starting October 6, 2023. The licensee has recently conducted challenge meetings to ensure readiness to complete the corrective maintenance activities. In addition, high impact team (HIT) meetings are being conducted weekly to ensure alignment and preparedness to complete the work. The inspectors did not identify any more-than-minor findings or violations during this review.

Observation: Trend Review - Security Behaviors 71152S Inspectors assessed a cognitive trend they observed regarding security behaviors of site personnel. Based upon personal observations and recent CAPs, inspectors questioned if site personnel were ensuring strict compliance with security policies and procedures. Inspectors discussed their observations with the security manager and site supervision.

CAP 501000074816, NRC Observation - Security Gate Use Trend, was initiated by the licensee. Following CAP initiation, the issue was discussed at the 6:30 a.m.

plan-of-the-day (POD) meeting. In addition, on June 27, 2023 and June 29, 2023, the plant manager update videos featured discussions of poor security behaviors and delay gate standards messaging to all site personnel. Although not fully affective in curbing the potential adverse trend, the inspectors did note marked improvements of personnel security behaviors.

Discussions with the security manager indicated that additional actions were planned to correct the observed behaviors as well. The NRC-identified trend CAP has an ongoing action which is due on August 28, 2023. The inspectors did not identify any more-than-minor findings or violations during this review.

Observation: Semi-annual Trend of ES4 Detectors Out of Service 71152S The inspectors selected the security equipment reliability trend of ES4 detectors for a semi-annual review to identify potential trends that might indicate the existence of a more significant issue. Inspectors reviewed corrective action documents related to repetitive issues with equipment which caused operational burden on the security and instrumentation and control departments. Inspectors reviewed procedures and conducted interviews with security department personnel concerning the potential negative equipment trend. Inspectors also interviewed instrumentation and control department personnel with respect to the assessment of operating experience related to the new detectors. Additionally, inspectors reviewed the corrective actions taken in response to the repetitive issues associated with the security equipment and did not identify any new issues. One notable observation was that it was not clear to some individuals closing corrective action documents that there is a process for documenting objective evidence for CAP closure of safeguard-related CAPs in the safeguard computer systems at the site. The inspectors did not identify any findings or violations of more-than-minor significance.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On July 21, 2023, the inspectors presented the integrated inspection results to Thomas Conboy, Site Vice President, and other members of the licensee staff.

On May 19, 2023, the inspectors presented the biennial licensed operator requalification inspection results to Timothy Borgen, Plant Manager, and other members of the licensee staff.

On June 22, 2023, the inspectors presented the emergency preparedness baseline inspection results to Timothy Borgen, Plant Manager, and other members of the licensee staff.

On June 23, 2023, the inspectors presented the annual licensed operator requalification program summary testing inspection results to Fredrick Collins, Operator Licensing Program Manager, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.01

Procedures

SP 1293

Review of Seasonal Flood Preparations

NF-39217-1

Flow Diagram Cooling Water - Turbine Building, Unit 2

Drawings

XH-1-29

Flow Diagram Spent Fuel Cooling System Unit 1 & 2

C1.1.20.5-2

Unit 2 4.16kV System Switches and Indication Checklist

71111.04

Procedures

C22.3

Turbine Lube Oil System and Turning Gear Operation

71111.06

Procedures

AB-4

Flood

71111.11A

Miscellaneous

Requalification

Program Annual

Testing Summary

Results

Licensed Operator Annual Examination Performance Records

for 2023

06/23/2023

501000051468

PITC [Prairie Island Training Center] Sim Computer Rm Temp

Above Set Pt

05/02/2021

501000054881

Trend in Low Level Simulator Events

08/08/2021

501000055373

PITC Sim 1R-11/12 RAM606 Failed

08/23/2021

501000055443

W-2 Control Switch Spring Retainer Broke

08/25/2021

501000060764

Acrid odor in the PITC Simulator

2/20/2022

501000063495

PITC Sim 1R-11/12 RAM606 Failed

05/30/2022

501000064286

PITC Sim Cmptr Rm HVAC ACU-3 Fail

06/26/2022

501000064666

Simulator Floor Drain Clogged

07/13/2022

501000067386

Sim Computer Room HVAC Failed MCU-2

10/17/2022

501000068912

Simulator HVAC MCU-1 degraded

11/30/2022

501000069232

PITC Simulator Roof Leak, Behind Pnl A

2/14/2022

501000070055

PITC Simulator Computer Room Roof Leak

01/20/2023

501000070502

Sim Elector Switch Series 20 Shaft Broke

2/06/2023

501000070976

Sin NUS/C-W Contr Dev Meter Failed

2/28/2023

501000071353

PITC Roof Leak, VCR-GPS

03/12/2023

Corrective Action

Documents

501000073082

Simulator Hardware Failure, Erratic Aos

05/01/2023

eSOMS Credit for Standing Watch-All Crew 6 RO and SRO

Licensees Active for 1st Quarter 2023

04/23/2023

71111.11B

Miscellaneous

Remediation Training Form - 208623 Failure to Correctly

Complete PINGP 577, Emergency Notification Report Form

01/25/2022

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Remediation Training Form - THMT22 Failure to Correctly

Complete PINGP 577, Emergency Notification Report Form

07/14/2022

Remediation Training Form - FVRB01 Failure to Correctly

Complete PINGP 577, Emergency Notification Report Form

07/13/2022

Job Performance

Measure

ADMIN-147

Job Performance

Measure

WS-1F

Job Performance

Measure

ADMIN-142

Job Performance

Measure

ADMIN-145

Job Performance

Measure

ADMIN-141

Job Performance

Measure

RC-26SF-2

Job Performance

Measure

RD-6SF-2

Job Performance

Measure

EG-25S

Job Performance

Measure

RC-27S

Job Performance

Measure

BD-2

PINGP 1568

Licensed Operator Return to Duty Checklist - PTRA32 dated

03/30/2022

PINGP 1568

Licensed Operator Return to Duty Checklist - 207676 dated

06/14/2022

PINGP 1568

Licensed Operator Return to Duty Checklist - MRTR07 dated

06/15/2022

QF 107302

Crew Simulator Examination Summary (Week 2/Crew 6-Group

and 2)

05/16/2023

QF 107303

Individual Operator Simulator Examination Summary (Week

2/Crew 6-10 Individuals)

05/16/2023

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

QF 107304

SE/STA Simulator Examination Summary (Week 4/Crew 6-1

Individual)

05/16/2023

QF-1081-01

Simulator Performance Test Procedure Cycle 32 Core Testing

11/15/2020

QF-1081-01 S01

Steady State (Cycle 32)

05/11/2022

QF-1081-01 T01

Manual Reactor Trip (Cycle 32)

10/29/2020

QF-1081-01 T02

Simultaneous Trip of Both Main Feedwater Pumps (Cycle 32)

10/01/2020

QF-1081-01 T03

Simultaneous Closure of All MSIVs (Cycle 32)

10/03/2020

QF-1081-01 T04

Simultaneous Trip of All RCPs (Cycle 32)

10/03/2020

QF-1081-01 T05

Trip of Single RCP (Cycle 32)

10/03/2020

QF-1081-01 T06

Manual Turbine Trip W/O Rx Scram (Cycle 32)

09/14/2022

QF-1081-01 T07

Power Change (100% to 75% to 100%) (Cycle 32)

09/29/2020

QF-1081-01 T08

Loss of Coolant Accident (LOCA) with Loss of Offsite Power

(LOOP) (Cycle 32)

10/01/2020

QF-1081-01 T09

Max Size Unisolable Main Steam Line Rupture (Cycle 32)

10/05/2020

QF-1081-01 T10

Slow Primary System Depressurization (Cycle 32)

10/05/2020

QF-1081-01 T11

Maximum Design Load Rejection (Cycle 32)

10/03/2020

SDA [Simulator

Deviation

Assessment]

SDA-15

Lead Operator LAN Workstation ERCS Display Capability

05/28/2009

SDA-17

Manual vs. Motorized T-Bar

03/03/2010

SDA-23

LED Bulb Replacement in Simulator (Incandescent in Plant)

09/08/2010

SDA-29

SRNI Response

2/05/2011

SDA-45

Control Room Annunciator Replacement (ECRs 24410 &

24412)

04/10/2017

SDA-47

Minor Labeling Differences

03/12/2018

SDA-53

Refueling Water Level Meter 41018 (ECR 602000013545)

2/07/2020

SDA-55

Rev. 1 HD Pump VFD Software (ECR 601000003237)

03/01/2023

SDA-56

CS-46952, BKR 26-15 BUS 26 FEED TO 222M XFMR

2/06/2023

Simulator

Exercise Guide

PI-LOR-NRC-2301S

Simulator

Exercise Guide

PI-LOR-NRC-2304S

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Simulator

Exercise Guide

PI-LOR-NRC-2306S

Simulator

Exercise Guide

PI-LOR-NRC-2308S

Written

Examination

23 LOR-NRC-BRE-Week 2 RO/SRO

05/18/2023

FP-T-SAT-60

Systematic Approach to Training (SAT) Overview

FP-T-SAT-71

NRC Exam Security Requirements

FP-T-SAT-73

Licensed Operator Requalification Program Examinations

FP-T-SAT-75

Job Performance Measure and Simulator Exercise Guide

Development

FP-T-SAT-80

Simulator Configuration Management

FP-T-SAT-81

Simulator Testing and Documentation

Periodic Test

Procedure (TP)

1850

Quarterly Watchstander Verification

QF1081-01

Simulator Performance Test Procedure

Procedures

Section Work

Instruction (SWO)

O-43

Operator Qualification Program

A-TRN-FL-2022-1

22 Nuclear Oversight Audit of Training (TRN)

09/07/2022

Self-Assessments

607000000834

Pre-IP 71111.11B Licensed Operator Requalification Program

Inspection Assessment

03/20/2023

SWO [Simulator

Work Order] C0M-

21

Add artificial load line CL header, EC-601000000677

11/18/2020

SWO C1D-021

ERCS High Stm F Alarm, Engr Limits MLB/HR

05/18/2021

SWO C1D-031

Loss of IA to U1 CNTMT Impact on U2 and AB/CNTMT

Chillers

06/10/2021

SWO C1M-010

ERCS Update 2021-01

06/06/2021

SWO C1M-017

Annunciator Green Dots Removal (Additional)

11/23/2021

SWO C2D-003

Gen Motoring Modeling

01/24/2022

SWO C2D-027

Letdown CV Stroke Times Update

05/05/2022

Work Orders

SWO C2D-036

FWP Aux Oil Pump Low Pressure Alarm Logic (47010-0102)

06/09/2022

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

SWO C2M-020

ERCS Update 2022-02

09/15/2022

SWO C3D-013

Install New CS-46952, Bus 26 Feed to 222M Xfmr

2/16/2023

SWO C3D-027

Panel B1 Analog Outputs Erratic

05/03/2023

501000070651

Document Bus 15 Lessons Learned

2/13/2023

Corrective Action

Documents

501000071608

RTS Trips May Be Subject to SR 3.3.1.16

03/23/2023

QC Inspection

Log

QC Inspection Logs from 05/05/2022 thru 05/01/2023

05/01/2023

QF 1113,

Revision 6 (FP-

PA-HU-05)

Type 2 - Operational Decision-Making Risk Matrix

05/31/2023

71111.12

Miscellaneous

WOs Request

NRC Request for WOs with QC ASME XI ANI IST ASME

Review Hold Codes

05/02/2023

Corrective Action

Documents

501000071986

FCU NORM DISCH TO GAP & STRUCT CD

04/05/2023

Drawings

NF-39245-1

Flow Diagram Component Cooling System, Unit 1

Engineering

Evaluations

2000020872

During 2GT Lockout Event and U2 Rx Trip the M to R Auto

Transfer did not Occur Leaving Buses 21, 23, & 24

Deenergized

05/31/2023

Miscellaneous

QF1113, Revision

(FP-PA-HU-05)

Type 2 - Operational Decision-Making Risk Matrix

05/31/2023

PE 6033

2GT Transformer Maintenance

PE XFMR-1

Transformer Gas-In-Oil Samples

Procedures

SP 1155B

CC System Quarterly Test Train B

WO 505323

EC 21255: Assemble and Test New 2GT XFMR at Temp Pad

07/09/2014

WO 700005081

PE-6033 - 2GT Transformer Refueling Main

10/31/2017

WO 700031246

PE-6033 - 2GT XFMR REFL MAIN INSP

07/27/2022

WO 700031246

PE-6033 - 2GT XFMR REFL MAIN INSP

10/25/2021

WO 700063902-

0040

SFP Transfer Canal Draindown

71111.13

Work Orders

WO 700063902-

0040

SFP Transfer Canal Draindown

71111.15

Corrective Action

Documents

501000073010

Charging Pump - Suction Side Leak

04/30/2023

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Engineering

Evaluations

EA

608000000953

Bus 15 Contact Resistance Evaluation

03/14/2023

Work Orders

WO 700123764-

0010

Replace 1R-50 Sample Pump Motor

CR

601000002437

Replace Line 2 1/2-CL-106

71111.18

Engineering

Changes

EC

601000000677

Cooling Water (CL) Line Artificial Load

Drawings

NF-39603-1

Admin Bldg Screenhouse & Control Rm Flow Diagram

D35.1

NIS Source and Intermediate Range Detector Replacement

SP 1055.2

2 Control Room Clean Up Ventilation System Filter Removal

Efficiency Test

SP 1106A

Diesel Cooling Water Pump Monthly Test

105

SP 1258A

Bus 15 Sequencer Load Rejection and Restoration of 121 CR

Chiller

Procedures

SP 1307

D2 Diesel Generator 6 Month Fast Start Test

WO 700090330-

0030

PMT/RTS BKR 112G-9

WO 700112715

SP 2102 22 TDAFW PMP WTR TEST

05/23/2023

71111.24

Work Orders

WO 700119703

Contingency Replace 2N32 Detector

05/31/2023

501000057506

Siren Back-up Monitoring System

10/21/2021

Corrective Action

Documents

501000068073

SP 1397 Weekly Siren Test

11/02/2022

Annual Siren Maintenance Records

01/01/2021 -

2/31/2022

Weekly Siren Testing Records

06/01/2021 -

05/31/2023

Miscellaneous

ANS

Alert and Notification System Design Report

71114.02

Procedures

SP 1397

Emergency Plan Fixed Siren Test

501000065188

EP Drill - Lack of Qualified Individuals

08/02/2022

501000070808

Initial training - EM position

2/22/2023

501000071426

Trend in ERO Drill Participation

03/16/2023

501000073989

PINGP 1843 Off Site Notification 5/27/23

05/28/2023

71114.03

Corrective Action

Documents

501000073997

NUE Contact with ECC/EMT not IAW Stand.

05/29/2023

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

501000074004

NUE ERO Activation Shortfall

05/29/2023

501000074023

NUE TSC Activation Time

05/29/2023

Miscellaneous

ERO Augmentation Drill Reports (Semi-annual)

01/01/2021 -

03/31/2023

F-8.3

Activation and Operation of the EOF

F3-1.1

On-shift Staffing Analysis Report

F3-6

Activation and Operation of the Technical Support Center

F3-7

Activation and Operation of the Operational Support Center

FG-EP-WI-23

Augmentation Test Maintenance Evaluation

PI-BEP-TPD

Prairie Island Nuclear Generating Plant

Emergency Plan Training Program

Procedures

SP 1744

Semi-Annual Emergency Organization Augmentation

Response Drill

501000064921

Exercise Binder Loss of Accountability

07/21/2022

Corrective Action

Documents

501000073939

NUE Event Investigation

05/28/2023

23 Prairie Island Emergency Planning Guide

01/01/2023

Emergency Exercise and Drill Reports (Sample)

06/01/2021 -

05/31/2023

Emergency Response Facilities Equipment Test Records

06/01/2021 -

05/30/2023

Emergency Preparedness Program Letters of Agreement

(Off-site Support Organizations)

06/01/2021 -

05/31/2023

Emergency Response Facilities Inventory Records

06/01/2021 -

05/31/2023

20000011857

Nuclear Oversight Emergency Preparedness Annual

Evaluation Report

2/17/2021

A-EP-FLT-2023-1

23 Nuclear Oversight Fleet Audit of Emergency

Preparedness (EP)

03/02/2023

Miscellaneous

KLD-TR-1262

Prairie Island Nuclear Generating Plant Development of

Evacuation Time Estimates

August 12,

22

EAL-RM

Prairie Island Nuclear Plant EAL Reference Manual

71114.05

Procedures

EPLAN

Emergency Plan

71151

Miscellaneous

NRC Performance Indicator Data; Emergency Preparedness -

Drill/Exercise Performance;

04/01/2022 -

03/31/2023

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

NRC Performance Indicator Data; Emergency Preparedness -

ERO Readiness

04/01/2022 -

03/31/2023

NRC Performance Indicator Data; Emergency Preparedness -

Alert and Notification System Reliability

04/01/2022 -

03/31/2023

603000007423

2Q2022 NRC PI Submittal - Prairie Island

06/24/2022

603000007662

3Q2022 NRC PI Submittal - Prairie Island

09/27/2022

Maintenance Rule

Functional and

MSPI Failure

Evaluation

CAP QIM 501000071986, 23 FCU NORM DISCH TO GAP &

STRUCT CD

04/05/2023

501000065316

NRC Observation of Security Delay Gate

08/04/2022

501000066334

Human Performance Shortfall (Gate Usage)

09/13/2022

501000071836

23PIR Door 286 Sign Blocking Flow Path

03/30/2023

Corrective Action

Documents

AR 1391945

Sign On Door 286 Partially Blocking Flow Path

07/30/2013

71152A

Work Orders

WO 700099442

RPIP 5001 D5/D6 FO STORAGE TK INSP

09/26/2022

71152S

Corrective Action

Documents

501000071147

Explosive Detector Reliability

03/05/2023