IR 05000275/2018003

From kanterella
Jump to navigation Jump to search
NRC Inspection Report 05000275/2018003 and 05000323/2018003 and Independent Spent Fuel Installation Inspection Report 07200026/2018002
ML18304A467
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 10/31/2018
From: Mark Haire
NRC/RGN-IV/DRP
To: Welsch J
Pacific Gas & Electric Co
References
IR 2018002, IR 2018003
Download: ML18304A467 (47)


Text

October 31, 2018

SUBJECT:

DIABLO CANYON POWER PLANT - NRC INSPECTION REPORT 05000275/2018003 AND 05000323/2018003 AND INDEPENDENT SPENT FUEL INSTALLATION INSPECTION REPORT 07200026/2018002

Dear Mr. Welsch:

On September 30, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Diablo Canyon Power Plant, Units 1 and 2. On October 9, 2018, the NRC inspectors discussed the results of this inspection with you and other members of your staff.

The results of this inspection are documented in the enclosed report.

NRC inspectors documented two findings of very low safety significance (Green) in this report.

Both of these findings involved a violation of NRC requirements. The NRC is treating these violations as non-cited violations (NCVs) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violations or significance of these NCVs, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement; and the NRC resident inspector at the Diablo Canyon Power Plant.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; and the NRC resident inspector at the Diablo Canyon Power Plant. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Mark S. Haire, Chief Project Branch A Division of Reactor Projects

Docket Nos. 50-275, 50-323, and 72-026 License Nos. DPR-80, DPR-82, and SNM-2511

Enclosure:

Inspection Report 05000275/2018003, 05000323/2018003, and 07200026/2018002 w/ Attachments:

1. Documents Reviewed 2. RFI for Resident Inspection - 3rd Quarter 3. RFI Public Radiation Safety Inspection

Enclosure U.S. NUCLEAR REGULATORY COMMISSION

Inspection Report

Docket Numbers:

05000275, 05000323, and 07200026

License Numbers:

DPR-80, DPR-82, and SNM-2511

Report Numbers:

05000275/2018003, 05000323/2018003, and 07200026/2018002

Enterprise Identifier: I-2018-003-0001 and I-2018-002-0101

Licensee:

Pacific Gas and Electric Company

Facility:

Diablo Canyon Power Plant, Units 1 and 2, and associated Independent

Spent Fuel Storage Installation (ISFSI)

Location:

Avila Beach, California

Inspection Dates:

July 1, 2018 to September 30, 2018

Inspectors:

C. Newport, Senior Resident Inspector

J. Reynoso, Resident Inspector

R. Alexander, Senior Project Engineer

L. Carson II, Senior Health Physicist

N. Greene, PhD, Senior Health Physicist

P. Hernandez, Health Physicist

E. Simpson, CHP, Health Physicist, FCDB

L. Brookhart, Senior ISFSI inspector, FCDB

C. Osterholtz, Senior Operations Engineer

Approved By:

Mark S. Haire, Chief

Project Branch A

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Diablo Canyon Power Plant, Units 1 and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors.

Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

NRC-identified and self-revealed findings, violations, and additional items are summarized in the table below. Licensee-identified non-cited violations are documented in the Inspection Results at the end of this report.

List of Findings and Violations

Multiple Examples of Scaffolding in Place Greater Than 90 Days Without Required Evaluation Cornerstone Significance Cross-cutting Aspect Inspection Procedure Mitigating Systems

Green NCV 05000275/2018003-01 and 05000323/2018003-01 Closed P.2 - Problem Identification and Resolution-Evaluation 71111.05Q -

Fire Protection Annual/Quarterly The inspectors identified a Green, non-cited violation of 10 CFR 50, Appendix B, Criterion V,

Procedures, because PG&E personnel failed to follow the requirements of AD7.ID5, Scaffold Material Structure. Specifically, 20 instances of scaffold structures installed in the plant were identified that had been in place for greater than 90 days without required 10 CFR 50.59 reviews being completed.

kV Vital Switchgear Room Ventilation Degraded or Non-Conforming Condition and Associated Compensatory Measure Not Corrected in a Timely Manner Cornerstone Significance Cross-cutting Aspect Inspection Procedure Mitigating Systems Green NCV 05000275/2018003-02 and 05000323/2018003-02 Closed H.1 - Human Performance-Resources 71152 - Problem Identification and Resolution The inspectors identified a Green, non-cited violation of 10 CFR 50, Appendix B, Criterion XVI,

Corrective Action, because PG&E personnel failed to promptly correct a degraded or non-conforming condition associated with an open operability condition. Specifically, PG&E personnel did not promptly correct a degraded condition associated with an open operability determination and corresponding compensatory measure related to Unit 1 and Unit 2, 4 kV vital switchgear ventilation for a period of over 4 years. This time period included two refueling outages for Unit 1 and three refueling outages for Unit 2.

PLANT STATUS

Units 1 and 2 began the inspection period at full power.

Unit 2 reduced power to 50 percent on September 15, 2018, to clean water boxes and condensers. Unit 2 returned to full power on September 16, 2018.

Units 1 and 2 operated at full power for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/

reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed plant status activities described in IMC 2515 Appendix D, Plant Status, and conducted routine reviews using IP 71152, Problem Identification and Resolution. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather (1 Sample)

The inspectors evaluated readiness for seasonal extreme weather conditions prior to the onset of seasonal hot and extreme drought due to dry weather.

External Flooding (1 Sample)

The inspectors evaluated readiness to cope with external flooding on August 16, 2018.

71111.04 - Equipment Alignment

Partial Walkdown (2 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Unit 2, turbine driven auxiliary feedwater pump 2-1 on July 5, 2018
(2) Unit 1, emergency diesel generator 1-2 air start system on July 10, 2018

Complete Walkdown (1 Samples)

The inspectors evaluated system configurations during a complete walkdown of the Unit 1, emergency diesel generator 1-1 on September 12, 2018.

71111.05AQ - Fire Protection Annual/Quarterly

Quarterly Inspection (5 Samples)

The inspectors evaluated fire protection program implementation in the following selected areas:

(1) Unit 1, H block 100 foot elevation on July 6, 2018
(2) Units 1 and 2, radiological control areas in the auxiliary building 115 foot elevation on August 16, 2018
(3) Unit 1, diesel fuel oil transfer pump vault 0-1 on September 4, 2018
(4) Units 1 and 2, emergency diesel generator rooms 114 and 85 foot elevations on September 19, 2018
(5) Units 1 and 2, radiological control areas in the auxiliary building 140 foot elevation on September 26, 2018

Annual Inspection (1 Samples)

The inspectors evaluated fire brigade performance on September 20, 2018.

71111.06 - Flood Protection Measures

Internal Flooding (1 Samples)

The inspectors evaluated internal flooding mitigation protections associated with the Units 1 and 2 emergency diesel generator rooms on August 22, 2018.

71111.11 - Licensed Operator Requalification Program and Licensed Operator Performance

Operator Requalification (1 Sample)

The inspectors observed and evaluated a crew of licensed operators in the plants simulator during an emergency preparedness exercise on August 29, 2018.

Operator Performance (1 Sample)

The inspectors observed and evaluated operator performance during the following activities:

(1) Units 1 and 2, heavy lift and spent fuel activities as part of planned ISFSI transport campaign on July 28, 2018
(2) Units 1 and 2, routine activities and under-instruction licensed operator training on August 30, 2018

Operator Exams (1 Sample)

The inspectors reviewed and evaluated requalification examination results on September 17, 2018.

71111.12 - Maintenance Effectiveness

Routine Maintenance Effectiveness (2 Samples)

The inspectors evaluated the effectiveness of routine maintenance activities associated with the following equipment and/or safety significant functions:

(1) Units 1 and 2, review of annual periodic evaluation of maintenance rule requirements per 10 CFR 50.65(a)(3)
(2) Units 1 and 2, emergency diesel generators

71111.13 - Maintenance Risk Assessments and Emergent Work Control

The inspectors evaluated the risk assessments for the following planned and emergent work activities:

(1) Unit 2, elevated risk due to auxiliary building ventilation exhaust fan S-33 out of service for maintenance on July 23-24, 2018
(2) Unit 1, elevated risk due to emergency diesel generator 1-2 out of service for maintenance on August 14, 2018
(3) Unit 2, elevated risk due to centrifugal charging pump 2-2 out of service for inboard bearing troubleshooting on August 14-16, 2018
(4) Unit 2, elevated risk due to component cooling water heat exchanger 2-2 out of service for maintenance on August 16, 2018
(5) Unit 1, elevated risk due to emergency diesel generator 1-1 major maintenance outage on September 24, 2018

71111.15 - Operability Determinations and Functionality Assessments

The inspectors evaluated the following operability determinations and functionality assessments:

(1) Unit 2, emergency diesel generator 2-1 crankcase exhauster motor alignment, Notification 50953506, on July 10-11, 2018
(2) Units 1 and 2, residual heat removal, quick disconnect vents seismic configuration, Notification 50986728, on July 11, 2018
(3) Unit 2, vital battery 2-2, cell 37 adverse voltage trend, Notification 50989078, on July 29, 2018
(4) Unit 2, centrifugal charging pump 2-2, inboard bearing degradation, Notification 50992967, on August 15, 2018
(5) Units 1 and 2, main turbine, overspeed trip testing frequency change, Notification 50975752, on September 6, 2018

71111.18 - Plant Modifications

The inspectors evaluated the following temporary or permanent modifications:

(1) Unit 1, emergency diesel generator air intake wind barrier installation on August 23, 2018
(2) Units 1 and 2, control rod drive mechanism fuse upgrade on August 23, 2018

71111.19 - Post Maintenance Testing

The inspectors evaluated the following post maintenance tests:

(1) Unit 1, reactor coolant pump 1-3, seal leak-off flow instrumentation backfill, Work Order 60112240, on July 19, 2018
(2) Unit 2, auxiliary saltwater pump 2-1, discharge header cross-tie valve FCV-496 maintenance, Work Order 64147202, on July 24, 2018
(3) Unit 2, auxiliary building ventilation system, fan S-33 belt replacement, Work Order 64169308, on July 31, 2018
(4) Unit 2, emergency diesel generator 2-2, lube oil temperature instrument TIS-92 replacement, Work Order 60094511, on August 8, 2018
(5) Unit 2, containment isolation valve reactor coolant drain train, Work Order 60113365, on September 13, 2018
(6) Unit 1, emergency diesel generator 1-1, routine surveillance test after repairs to flex coupling and jacket water system maintenance, Work Order 60098911, on September 27, 2018

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Routine

(1) Unit 1, emergency diesel generator 1-1, diesel engine analysis and routine surveillance test per procedure STP M-9A1 on July 10, 2018
(2) Unit 2, emergency diesel generator 2-3, 4 kV vital bus under-voltage relay testing, per procedure STP M-75F, on August 21, 2018
(3) Unit 1, emergency diesel generator 1-1, 4 kV vital bus under-voltage relay calibration, per procedure STP M-75H, on September 25, 2018

In-service (1 Samples)

(1) Unit 2, exercising residual heat removal pump suction valve 8700A, per procedure STP V-3M4A, on September 11, 2018

71114.06 - Drill Evaluation

Emergency Planning Drill (1 Sample)

The inspectors evaluated an emergency preparedness drill on August 29,

RADIATION SAFETY

71124.05 - Radiation Monitoring Instrumentation

Walk Downs and Observations (1 Sample)

The inspectors evaluated radiation monitoring instrumentation during plant walkdowns.

Calibration and Testing Program (1 Sample)

The inspectors evaluated the licensees calibration and testing program.

71124.06 - Radioactive Gaseous and Liquid Effluent Treatment

Walk Downs and Observations (1 Sample)

The inspectors evaluated the licensees radioactive gaseous and liquid effluent treatment systems during plant walkdowns.

Calibration and Testing Program (Process and Effluent Monitors) (1 Sample)

The inspectors evaluated the licensees gaseous and liquid effluent monitor instrument calibration and testing.

Sampling and Analyses (1 Sample)

The inspectors evaluated radioactive effluent sampling and analysis activities.

Instrumentation and Equipment (1 Sample)

The inspectors evaluated radioactive effluent instrumentation and equipment.

Dose Calculations (1 Sample)

The inspectors evaluated dose calculations.

71124.07 - Radiological Environmental Monitoring Program

Site Inspection (1 Sample)

The inspectors evaluated the licensees radiological environmental monitoring program.

Groundwater Protection Initiative Implementation (1 Sample)

The inspectors evaluated the licensees groundwater monitoring program.

71124.08 - Radioactive Solid Waste Processing and Radioactive Material Handling, Storage,

and Transportation

Radioactive Material Storage

The inspectors evaluated the licensees radioactive material storage.

Radioactive Waste System Walk down (1 Sample)

The inspectors evaluated the licensees radioactive waste processing facility during plant walkdowns.

Waste Characterization and Classification (1 Sample)

The inspectors evaluated the licensees radioactive waste characterization and classification.

Shipment Preparations (1 Sample)

The inspectors evaluated the licensees radioactive material shipment preparation processes.

Shipment Records (1 Sample)

The inspectors evaluated the licensees non-excepted package shipment records.

OTHER ACTIVITIES - BASELINE

71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

(1) MS08: Units 1 and 2, Heat Removal Systems [07/2017-06/2018]
(2) MS09: Units 1 and 2, Residual Heat Removal Systems [07/2017-06/2018]
(3) MS10: Units 1 and 2, Cooling Water Support Systems [07/2017-06/2018]

71152 - Problem Identification and Resolution

Annual Follow-up of Selected Issues (2 Samples)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) Diablo Canyon Power Plants implementation of preventative maintenance scope and frequency optimization of all plant-related preventative maintenance activities on September 10-21, 2018
(2) Evaluation and corrective actions related to compensatory measures and associated elevated temperatures in the Units 1 and 2, 4 kV vital switchgear rooms on August 6 - September 26,

OTHER ACTIVITIES

- TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL 60855.1Operation of an Independent Spent Fuel Storage Installation and 60857 - Review of 10 CFR 72.48 Evaluations The inspectors evaluated the licensees operation of the independent spent fuel storage installation (ISFSI) July 23-27, 2018, on-site at the Diablo Canyon Power Plant (DCPP) and conducted an in-office review of additional documentation, including quality assurance (QA)audit reports, condition reports, and documents related to the licensees maintenance of their ISFSI and related equipment.

The DCPP ISFSI consisted of seven concrete pads, each sized at 7,140 sq. ft. (68 ft. by 105 ft.) for a total area of 49,980 sq. ft. Each pad was designed to hold 20 Holtec International HI-STORM 100SA storage casks securely anchored to steel embedment plates in the concrete. The ISFSI contained 54 (out of 140 total possible) HI-STORM 100SA overpacks loaded with MPC-32 canisters at the time of the routine NRC inspection. DCPP was currently loading canisters in accordance with their site specific SNM-2511 License, Amendment 5, and the Final Safety Analysis Report (FSAR), Revision 7. During the NRC inspection, DCPP was processing the 6th canister out of 9 planned for their seventh dry fuel storage campaign. By the end of the loading campaign, the licensee was expected to have 58 storage casks on its ISFSI pad. The 58th HI-STORM overpack was bolted to the ISFSI pad on August 18, 2018.

The ISFSI activities specifically reviewed during the on-site inspection and the subsequent in-office review included:

(1) Evaluated and observed fuel selection and fuel loading operations associated with dry fuel storage multi-purpose canister (MPC) #55.
(2) Evaluated and observed welding of the canister, non-destructive testing of the welds, pressure testing, forced helium drying, helium backfill, and heavy load movements from the spent fuel pool to the sites vertical cask transporter.
(3) Reviewed the licensee's loading, processing, and heavy load procedures associated with their current dry fuel storage campaign.
(4) Reviewed licensees corrective action program implementation for ISFSI operations since the last routine ISFSI inspection which was completed in September 2016.
(5) Reviewed QA program implementation, including recent QA audits, surveillances, and quality control activities.
(6) Reviewed documentation for compliance with technical specifications (TS) related to operational surveillance activities and FSAR required annual maintenance activities.
(7) Reviewed the licensees radiological monitoring data for the calendar years 2016, 2017, and the first quarter of 2018 to verify compliance with 10 CFR 72.104 requirements.
(8) Reviewed spent fuel documentation for the canisters loaded since the last routine ISFSI inspection to verify the fuel met all TS requirements for storage (canisters 43-55).
(9) Reviewed annual maintenance activities for heavy lifting components which included special lifting devices and the sites cask handling crane.
(10) Reviewed all 10 CFR 72.48 safety evaluations/screenings performed by the licensee for changes made to the ISFSI program since the last routine ISFSI inspection in accordance with NRC Inspection Procedure 60857.
(11) Reviewed changes made to the licensees Updated FSAR from Revision 6 to Revision 7.

There were no findings associated with the NRC ISFSI inspection at DCPP.

INSPECTION RESULTS

Multiple Examples of Scaffolding in Place Greater Than 90 Days Without Required Evaluation Cornerstone Significance Cross-cutting Aspect Inspection Procedure Mitigating Systems

Green NCV 05000275/2018003-01 and 05000323/2018003-01 Closed P.2 - Problem Identification and Resolution

- Evaluation

71111.05Q - Fire Protection

Annual/Quarterly The inspectors identified a Green, non-cited violation of 10 CFR 50, Appendix B, Criterion V, Procedures, because PG&E personnel failed to follow the requirements of AD7.ID5, Scaffold Material Structure. Specifically, 20 instances of scaffold structures installed in the plant were identified that had been in place for greater than 90 days without required 10 CFR 50.59 reviews being completed.

Description:

When used in the plant, the design and installation of temporary scaffold must be controlled to ensure that it does not have an adverse impact on safety-related equipment and equipment used to support the safe shutdown of the plant. PG&E procedures control the installation of temporary scaffold at Diablo Canyon Power Plant, in part, by specifying that a scaffold structure cannot be installed for greater than 90 days without an additional 10 CFR 50.59 review being completed.

PG&E procedure AD7.ID5, Scaffold Material Structure, Revision 14, Step 5.3.1.a states that:

Structures erected per this procedure in support of maintenance activities:

a. Shall not exceed 90 days at power. A LBIE 10 CFR 50.59 screen is required if a structure is to exceed 90 days.

This requirement was implemented in AD7.ID5 in January 2018 as part of a procedure revision. An extent of condition walkdown was conducted by PG&E personnel prior to implementation of the procedure revision to ensure that there were no scaffold structures in the plant erected for greater than 90 days without the required 10 CFR 50.59 review.

While performing routine plant walkdowns on August 8, 2018, the NRC inspectors identified a scaffold structure in place in the Unit 1, residual heat removal system heat exchanger room without the required tags in place. Upon questioning, PG&E personnel determined that the scaffold had been in place for over 9 years and that the procedurally required 10 CFR 50.59 review had not been conducted. PG&E entered the issue into the corrective action program and subsequently conducted an extent of condition walkdown on both Units 1 and 2 to determine if additional scaffold structures existed in the power blocks of either unit that were not in accordance with the requirements of AD7.ID5. Nineteen additional instances of scaffold in place for greater than 90 days without required 50.59 reviews were identified during this walkdown, including scaffold structures in the vicinity of safety-related equipment.

Corrective Actions: PG&E personnel performed an extent of condition walkdown and conducted the required 50.59 reviews on each instance of a scaffold structure in place for greater than 90 days without the required review. Additionally, PG&E removed any structure that was no longer required to be in place. The 50.59 reviews did not identify any structure in place for greater than 90 days that was not acceptable or would have required NRC prior approval.

Corrective Action Reference: Notification 50991907

Performance Assessment:

Performance Deficiency: The inspectors determined that not conducting procedurally required 50.59 reviews on scaffold structures in place for greater than 90 days, including structures in the vicinity of safety-related equipment, was a performance deficiency within PG&Es ability to foresee and correct.

Screening: The performance deficiency was considered to be more than minor because it is associated with the protection against external factors attribute of the Mitigating Systems cornerstone and adversely affected the Mitigating Systems cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, twenty instances of scaffold structures installed in the plant were identified that had been in place for greater than 90 days without required AD7.ID5-directed 50.59 reviews being completed. Additionally, it was similar to example 4.a in IMC 0612, Appendix E, Examples of Minor Issues, which states that the issue of failing to appropriately evaluate scaffold installation as required by procedures is more than minor if the licensee routinely failed to perform required engineering evaluations.

Significance: The issue was evaluated in accordance with IMC 0609, Appendix A, The Significance Determination Process for Findings At-Power, and determined to be of very low safety significance (Green) since it did not involve the loss or degradation of equipment or function specifically designed to mitigate a seismic event.

Cross-cutting Aspect: This finding is related to the cross-cutting area of Problem Identification and Resolution - Evaluation because PG&E did not thoroughly evaluate issues to ensure that resolutions address causes and extent of conditions commensurate with their safety significance [P.2]. Specifically, PG&E personnel did not perform an adequate extent of condition review after revising procedure AD7.ID5, Scaffold Material Structure, resulting in 20 instances of scaffold structures being erected in the plant for greater than 90 days without procedurally required 50.59 evaluations.

Enforcement:

Violation: Title 10 CFR Part 50, Appendix B, Criterion V, Procedures, requires, in part, that activities affecting quality shall be prescribed by documented procedures and shall be accomplished in accordance with those procedures. PG&E procedure AD7.ID5, Scaffold Material Structure, Revision 14, Step 5.3.1.a states, in part, that structures erected per this procedure in support of maintenance activities shall not exceed 90 days at power. A LBIE 10 CFR 50.59 screen is required if a structure is to exceed 90 days.

Contrary to the above, from January 2018 to September 2018, 20 instances of scaffold structures were in place in the plant for greater than 90 days without procedurally required 10 CFR 50.59 screens, including some in the vicinity of safety-related equipment. After the issue was identified by the inspectors, PG&E performed an extent of condition walkdown, performed a 50.59 review on each identified instance of a scaffold structure in place for greater than ninety days without the required review, and removed scaffold structures no longer required to be in place.

Disposition: This violation is being treated as a non-cited violation consistent with Section 2.3.2 of the NRC Enforcement Policy.

4 kV Vital Switchgear Room Ventilation Degraded or Non-Conforming Condition and Associated Compensatory Measure Not Corrected in a Timely Manner Cornerstone Significance/Severity Cross-cutting Aspect Inspection Procedure Mitigating Systems

Green NCV 05000275/2018003-02 and 05000323/2018003-02 Closed H.1 - Human Performance - Resources

71152 - Problem

Identification and Resolution The inspectors identified a Green, non-cited violation of 10 CFR 50, Appendix B, Criterion XVI, Corrective Action, because PG&E personnel failed to promptly correct a degraded or non-conforming condition associated with an open operability condition.

Specifically, PG&E personnel did not promptly correct a degraded condition associated with an open operability determination and corresponding compensatory measure related to Unit 1 and Unit 2, 4 kV vital switchgear ventilation for a period of over 4 years. This time period included two refueling outages for Unit 1 and three refueling outages for Unit 2.

Description:

PG&E procedure OM7.ID12, Operability Determination, Step 5.9.1 states, in part, that, degraded or non-conforming conditions (DUNCs), with regard to the CLB, shall be corrected at the first available opportunity commensurate with the safety significance of the issue (applicable MOW, forced outage, or refueling outage). Provide adequate justification if the condition is not corrected in the next applicable MOW, forced outage, or refueling outage.

NRC Inspection Manual Chapter (IMC) 0326, Operability Determinations & Functionality Assessments for Conditions Adverse to Quality of Safety, Section 07.03 states, in part, that the NRC expects that conditions calling for compensatory measures to restore SSC operability will be more quickly resolved than conditions that do not rely on compensatory measures to restore operability. The reason is that reliance on compensatory measures to restore SSC operability suggests a greater degree of degradation of nonconformance.

In June 2014, PG&E personnel identified a degraded condition associated with the vital 4 kV switchgear and cable spreading rooms for both Unit 1 and Unit 2. Due to the ventilation configuration of the 4 kV switchgear rooms and their vicinity to the operating deck of the main turbines, following a high energy line break in the turbine building, there is a potential for steam to enter the Unit 1 and Unit 2 vital 4 kV switchgear rooms and 4 kV cable spreading rooms. Under certain conditions, the humidity in the rooms could significantly exceed that described in the current licensing basis and challenge the operability of the 4 kV vital switchgear for both units. Upon identification of the issue, PG&E operations entered the applicable technical specification action statements and conducted an immediate and prompt operability determination. As part of the operability determinations, PG&E implemented a compensatory measure to close the fire dampers of the ventilation discharge into each 4 kV vital switchgear room. The compensatory measure eliminated the source of humidity into the 4 kV vital switchgear room during a high energy line break in the turbine building. However, this action also cut off normal ventilation flow to the 4 kV vital switchgear rooms, causing temperatures to be elevated but below procedural and licensing limits required for operability.

PG&E determined that, with this compensatory measure in place, despite the degraded condition, operability of the 4 kV vital switchgear was maintained.

In September 2018, during an inspection of high temperatures observed in the 4 kV vital switchgear rooms and the open compensatory measures associated with the degraded and non-conforming condition, the NRC inspectors identified that the compensatory measure associated with the 4 kV vital switchgear ventilation for Units 1 and 2 had been in place since June 2014 - a period of over 4 years. This interval included two refueling outages for Unit 1 and three refueling outages for Unit 2. Upon further investigation, the NRC inspectors determined that the efforts made by the licensee to either restore full compliance for 4 kV vital switchgear ventilation or change the current licensing basis to reflect the conditions established by the compensatory measure were untimely, contrary to the guidance in PG&E procedure OM7.ID12. Specifically, PG&E personnel delayed the implementation of corrective actions to restore full compliance multiple times due to organizational changes, resource challenges, and funding delays.

Corrective Actions: PG&E is expected to restore full compliance by February 2019.

Compliance is expected to be met by justification of a change to the current licensing basis to incorporate the conditions established by the compensatory measure into the current licensing basis for the station.

Corrective Action Reference: Notification 50998167

Performance Assessment:

Performance Deficiency: The inspectors determined that PG&E personnel failed to promptly correct a degraded or non-conforming condition associated with an open operability condition.

Specifically, PG&E personnel did not promptly correct a degraded condition associated with an open operability determination and corresponding compensatory measure related to Unit 1 and Unit 2, 4 kV vital switchgear ventilation and cable spreading rooms for a period of over 4 years. This time period included two refueling outages for Unit 1 and three refueling outages for Unit 2.

Screening: The performance deficiency was considered to be more than minor because it is associated with the design control attribute of the Mitigating Systems cornerstone and adversely affected the Mitigating Systems cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the failure to promptly correct a degraded or non-confirming condition associated with vital 4 kV switchgear room ventilation allowed for the vital 4 kV switchgear rooms of both units to be continuously exposed to higher temperatures due to a ventilation configuration that deviated from that assumed in the current licensing basis. This condition has existed for a period of over 4 years when corrective actions to restore full compliance could have reasonably been taken in a shorter timeframe.

Significance: The issue was evaluated in accordance with IMC 0609, Appendix A, The Significance Determination Process for Findings At-Power, and determined to be of very low safety significance (Green) since it did not involve a deficiency affecting the design or qualification of a mitigating SSC that resulted in the inoperability or non-functionality of the SSC.

Cross-cutting Aspect: This finding is related to the cross-cutting area of Human Performance

- Resources [H.1] because PG&E leaders did not ensure that personnel, equipment, procedures, and other resources are available and adequate to support nuclear safety.

Specifically, resource and funding delays led to a compensatory measure and degraded condition associated with an operability determination to be in place for a period of over 4 years without restoration of full compliance.

Enforcement:

Violation: Title 10 CFR Part 50, Appendix B, Criterion XVI, Corrective Action, requires, in part, that measures shall be established to assure that conditions adverse to quality, such as failures, malfunctions, deficiencies, deviations, defective material and equipment, and nonconformances are promptly identified and corrected.

Contrary to the above, from June 2014 to present, PG&E personnel failed to promptly correct a condition adverse to quality. Specifically, the licensee failed to correct a degraded or non-conforming condition associated with an open operability determination and corresponding compensatory measure related to Unit 1 and Unit 2, 4 kV vital switchgear ventilation and cable spreading rooms for a period of over 4 years. This time period included two refueling outages for Unit 1 and three refueling outages for Unit 2.

Disposition: This violation is being treated as a non-cited violation consistent with Section 2.3.2 of the NRC Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

On July 12, 2018, and September 27, 2018, the inspectors presented the baseline radiation protection inspection results to Ms. P. Gerfen, Station Director, and other members of the licensee staff.

On July 26, 2018, the inspectors presented the routine ISFSI inspection results to Ms. M. Zawalick, Director, Risk & Compliance, and other members of the licensee staff.

On September 17, 2018, the inspectors presented the annual requalification inspection results to Mr. A. Kadir, Examination Development and Simulator Supervisor.

On October 9, 2018, the inspectors presented the quarterly resident inspector inspection results to Mr. J. Welsch, Vice President Nuclear Generation and Chief Nuclear Officer, and other members of the licensee staff.

The inspectors verified no proprietary information was retained or documented in this report.

DOCUMENTS REVIEWED

71111.01: Adverse Weather Protection

Work Order 64173780

Procedures

Number

Title

Revision

AD7.DC6

On-Line Risk Management

CP M-16

Severe Weather

DCM T-45

Diverse and Flexible Coping Strategies

MA1.ID23

Review of Intake Preparedness for High Debris Loading

Event

OP AP-26

Loss of Offsite Power

OP J-2:VIII

Guidelines for Reliable Transmission Service for DCPP

OP O-28

Intake Management

STP M-70.SWG

Inspection of ECG Swing Type Doors

Drawings

Number

Description

Revision or

Date

438014

Switchyard Topographical Map

2110, Sh. 1

Single Line Diagram 500/230/25/12/4.16kV Systems

DCL-17-064

DCPP Focused Evaluation Report for External Flooding

7/19/2017

ML17328A249

NRC Staff Assessment of Flooding Focused Evaluation

2/18/ 2017

Report VL 18014 2018 DCPP Culvert Inspection

7/19/2018

Other

Number

Description

Revision

DCM No. S-61B

500-kV and 230-kV Systems

71111.04: Equipment Alignment

Notifications

50975649

50947335

50856513

50985428

Notifications

50966459

50996560

Procedures

Number

Title

Revision

OP D-1:II

Auxiliary Feedwater System - Alignment Verification for

Plant Startup

OP J-6B:I

Diesel Generator 1-1 - Make Available

OP J-6B:I-A

Diesel Generator 1-1 - Alignment Checklist

OP J-6B:II-A

Diesel Generator 1-2 - Alignment Checklist

OP J-6C:V

Diesel Fuel Oil Transfer System - Use of Portable FOTP

and DFO Day Tank LCVs

OP O-36

Protected Equipment Postings

STP M-21-VI.1

Pre Outage Diesel Engine Visual Inspections

Drawings

Number

Description

Revision

106721

Sheet 2

106721

Sheet 3

106721

Sheet 4

106721

Sheet 6

106721

Sheet 7

107703

Auxiliary Feedwater System

Other

Number

Description

Revision

DCM S-9

Safety Injection System

DCM S-10

Residual Heat Removal System

71111.05: Fire Protection

Notifications

50993077

50992984

50997282

50997298

50998176

Work Order 64145206

Procedures

Number

Title

Revision

CP M-6

Operations Responder Checklist

OM8.ID4

Control of Flammable and Combustible Materials

OM8.ID8

Equipment Important to NFPA 805 Fire Response

STP M-39D

Routine Surveillance Test of Carbon Dioxide Hose Reel

Drawings

Number

Description

Revision

RA-7

Fire Drawing: Radiological Control Area & H Block Elev 100 8

TB-16

Fire Drawing: Unit 1 and 2 Turbine Building Area 114 foot

elevation

TB-1

Fire Drawing: Unit 1, Turbine Building Buttress Elev. 85 &

104

RA-19/20

Fire Drawing: Unit 2, RCA 140 ft Elev

TB-3/14

Fire Drawing: Unit 1 and 2 Turbine Building Area 85 foot

elevation

RA-9/17

Fire Drawing: Radiological Control Area & H Block Elev 115

Unit 1 and 2

RA-11/13

Fire Pre-plan Unit 1 and Common, RCA 140 ft Elev

71111.06: Flood Protection Measures

Notifications

50988996

50985660

50987318

50883656

50989004

50987245

Work Orders

64149269

64153985

Other

Number

Description

Revision

DCM T-12

Emergency Diesel Generator

71111.11: Licensed Operator Requalification Program and Licensed Operator

Performance

Notification

50995365

Procedures

Number

Title

Revision

JSIM-507

Evaluator Skills

OP1.DC10

Conduct of Operations

TQ2.DC3

Licensed Operator Continuing Training Program

Other

Number

Description

Date

Annual Requalification Results Summary

9/17/2018

71111.12: Maintenance Effectiveness

Notifications

50993567

50993892

50996560

Work Orders

64149269

64153985

Procedures

Number

Title

Revision

CF3.ID9

Design Change Notice

MA1.ID17

Maintenance Rule Monitoring Program

STP M-9I

Diesel Generator Start and Load Tracking

Other

Number

Description

Revision

DCM S-21

Diesel Engine System

DCM S-38A

Plant Protection System

11A

DCM T-4

Fuel Oil Storage

71111.13: Maintenance Risk Assessments and Emergent Work Control

Notifications

50955324

50989814

50990566

50993088

50992492

50998349

50949662

50992967

Procedures

Number

Title

Revision

AD7.DC6

On-Line Maintenance Risk Management

AD7.DC6

On-line Risk Management

AD7.ID14

Assessment of Integrated Risk

AD7.ID14

Assessment of Integrated Risk

AD7.ID17

PRA Significant Component Management

OM7.13

Technical Evaluation

OM7.ID7

Emerging Issue and Event Investigation

OP O-36

Protected Equipment Postings

STP I-1C

Routine Weekly Checks Required By Licensee

118

71111.15: Operability Determinations and Functionality Assessments

Notifications

50986728

50953506

50985428

50987811

50953201

50989078

50558837

50344566

50555151

50992967

50975752

Work Order 64197770

Procedures

Number

Title

Revision

STP M-21A

Main Turbine/Generator Trip Functional Tests

AD1.ID2

Procedure Process Control

STP P-CCP-22

Routine Surveillance Test of Centrifugal Charging Pump 2-2 27

STP M-11B

Station Battery Monitoring

OM7.ID13

Technical Evaluations

AR DG22-2-4

Crankcase Failure Alarm Response

Other

Number

Description

Date

Vendor Record

073719

ALCO Power Crankcase Exhauster Design

9/18/1985

WCAP-16054-P

Probabilistic Analysis of Reduction in Turbine Valve Test

Frequency for Nuclear Plants with Siemens-Westinghouse

BB-05/96 Turbines

71111.18: Plant Modifications

Notifications

50599190

50972297

50856133

Work Orders

68052661

60095763

60093384

Procedures

Number

Title

Revision

CF3.ID9

Design Change Notice

TS3.ID2

Licensing Basis Impact Evaluations

Drawings

Number

Description

Date

DDN 2*1787

Modification to Eliminate High Wind Effect

3/22/2018

Other

Number

Description

Revision

9000033674

Unit 1 Electrical Penetration Protection Calculation

WCAP-15804

Rod Control System Gripper Circuits Fuse Enhancement

Program

71111.19: Post-Maintenance Testing

Notifications

50988182

50973076

50989895

50996099

50990566

50991017

50990713

50972942

50841994

50998087

50998093

50998340

Work Orders

64147203

64153268

64192553

60094511

64126949

64158803

50874024

60113365

64169308

60098911

64160080

Procedures

Number

Title

Revision

MA1.DC54

Conduct of Maintenance

MP E 53.10A

Preventative Maintenance of Limit torque Motor Operators

MP I-21-T92

D/G Lube Oil Low Temperature Alarm Switch Calibration

MP M-23-FAN.4

Preventative Maintenance of Ventilation Fans with Dampers

and Inlet Vanes

STP M-21-RTS.1 Return Diesel Engine to Service Following Outage

Maintenance

STP M-9A2

Diesel Emergency Generator Routine Surveillance Test

Drawings

Number

Description

Revision

2008

Chemical & Control Volume Control System

115

106708

Reactor Coolant Chemical & Volume Control OVID

2

106717

Auxiliary Saltwater Valve Drawing

205

107725

Air system controls

163

Other

Designation

Description

Revision

DC-663278

Buffalo Forge Co. Centrifugal Fan Vendor Manual

71111.22: Surveillance Testing

Notification

50993759

Work Orders

64158289

64170799

64199327

64177878

Procedures

Number

Title

Revision

MP E-50.33A

Westinghouse Type SSV-T One Unit Undervoltage Relay

Maintenance

14A

MP E-50.61

Basler Type BE1-27 Medium Inverse Undervoltage Relay

Maintenance

8A

MP E-50.62

Basler BE1-GPS100 Relay Maintenance Calibration

STP M-21-A.1

Diesel Engine Analysis

STP M-75F

kV Vital Bus F Undervoltage Relay Calibration

STP M-75H

kV Vital Bus H Undervoltage Relay Calibration

STP M-9A1

Diesel Generator 1-1 Routine Surveillance Test

9A

STP V-2D2A

Exercising and Position Verification of Valve 8700A

STP V-3M4A

Exercising RHR Pump 1 Suction Valve 8700A

Drawing

Number

Description

Revision

1077190

Sheet 1

71114.06: Drill Evaluation

Notification

50995365

Procedures

Number

Title

Revision

EP G-4

Assembly and Accountability

OM10.DC1

Emergency Preparedness Drills and Exercises

OP1.DC10

Conduct of Operations

50A

TQ2.ID4

Simulator Setup Checklist

71124.05: Radiation Monitoring Instrumentation

Notifications

50867768

50867890

50911367

50956872

Procedures

Number

Title

Revision

CAP B-50.1

Liquid Scintillation Analyzer Model 2910

CAP B-53:IV

Administration of the Canberra Apex Gamma Spectroscopy

System

MP I-RX01

Initial On-Site Calibration of Portable Radiation Detection

Instruments

RCP D-900

Performance Tests for Radiation Protection Instruments

RCP D-970

Radiation Protection Instrument Calibration Schedule

RCP D-981

Annual Verification of the J.L Shepherd Model 89 Shielded

Calibrator

STP I-119B

Calibration of Fuel Handling Building Area Radiation

Monitors RM-58 & RM-59

STP I-39-R30.B

Containment High Range Area Radiation Monitor

RM-30/RM-31 Calibration

STP I-39-R71.B

Calibration of Main Steam Line Radiation Monitors

RM-71, 72, 73, 74

Audits and Self-Assessments

Number

Description

Date

2018 NRC Inspection Prep by Chemistry - Inspection

Procedure 71124 Attachments 05 and 06

6/15/2018

Assessment of Effluent and EAL-Related Radiation

Monitors

6/26/2018

Audits and Self-Assessments

Number

Description

Date

Radiation Effluent Monitor Formal Self-Assessment

5/23/2018

Installed Radiation Instrument Calibration Records

Radiation

Monitor

Title

Date

RM-3

Oily Water Separator Influent Radiation Monitor

4/17/2017

RM-30

Containment High Range Area Radiation Monitor Unit-1

1/12/2017

RM-30

Containment High Range Area Radiation Monitor Unit-2

4/24/2018

RM-42

Gas Decay Tank #2 Radiation Monitor

9/18/2017

RM-42

Gas Decay Tank #2 Radiation Monitor

9/13/2016

RM-58

Spent Fuel Pool Area Radiation Monitor Unit-1

6/13/2017

RM-58

Spent Fuel Pool Area Radiation Monitor Unit-2

5/18/2018

RM-72

Main Steam Line #2 Radiation Monitor Unit-1

9/9/2016

RM-72

Main Steam Line #2 Radiation Monitor Unit-2

6/28/2017

Portable Radiation Instrument Calibration Records

Number

Title

Date

206530

Thermo Neutron EPD-N2 NK2.5

11/30/2017

206648

Thermo Neutron EPD-N2 NK2.5

11/30/2017

206656

Thermo Neutron EPD-N2 NK2.5

11/28/2017

RP 03.32.045

Radeye G

4/18/2018

RP 03.37.004

Ludlum Neutron Detector

8/2/2017

RP 03.37.003

Ludlum Neutron Detector

6/12/2018

RP 03.45.063

Thermo Scientific R-02AA

5/18/2018

RP 03.45.003

Thermo Scientific R-02AA

3/4/2018

RP 03.45.031

Thermo Scientific R-02AA

5/8/2018

RP 06.13.001

Ludlum Model 3030

11/8/2017

RP 06.13.004

Ludlum Model 3030

11/8/2018

Stationary Radiation Instrument Calibration Records

Number

Title

Date

37.001

AMS-4

7/31/2017

Stationary Radiation Instrument Calibration Records

Number

Title

Date

38.001

AMS-4

8/1/2017

38.005

AMS-4

8/1/2017

38.020

AMS-4

2/21/2017

38.023

AMS-4

8/27/2017

5.12.005

ARGOS-5AB

2/14/2017

5.12.010

ARGOS-5AB

2/14/2017

5.13.010

GEM-5

10/26/2017

5.13.005

GEM-5

2/14/2017

Source Calibration Records

Number

Title

Date

RS-001

Annual Verification of Calibration for the J.L.

Shepherd Model 89 Irradiator (260 Ci Cs-137)

3/7/2017

RS-001

Annual Verification of Calibration for the J.L.

Shepherd Model 89 Irradiator (260 Ci Cs-137)

2/28/2018

RS-002

Annual Verification of Calibration for the J.L.

Shepherd Model 89 Irradiator (400 Ci Cs-137)

3/8/2016

RS-002

Annual Verification of Calibration for the J.L.

Shepherd Model 89 Irradiator (400 Ci Cs-137)

2/27/2018

Miscellaneous Documents

Number

Title

Date

Assessment of Effluent & EAL Related Radiation Monitors

6/25/2018

DCPP ISFSI Neutron TLD Factor Calibration

3/28/2016

DCPP RP Source Control Record

7/11/2018

2-079

Neutron Field Characterization at Diablo Canyon for

Dosimetry Correction Factors

8/19/2013

System 39

Radiation Monitoring System Failures

2/13/2017

71124.06: Radioactive Gaseous and Liquid Effluent Treatment

Notifications

50873232

50863318

50943748

50008864

50688030

50943748

50863318

50869577

Notifications

50903159

50955902

50972944

50870286

50893144

50974501

Procedures

Number

Title

Revision

CAP A-11

Liquid Radwaste Processing System Selection

CAP A-5

Liquid Radwaste Discharge Management

CAP A-6

Gaseous Radwaste Sampling and Analysis for Release

CAP A-6A

Gaseous Radwaste Release Permit

CAP A-6B

Gaseous Radwaste Postrelease Summary

CAP A-8

Off-Site Dose Calculations

CAP B-50:I

Liquid Scintillation Analyzer Model 2910 Operation

CAP B-53:III

Operation of the Canberra APEX Gamma Spectroscopy

System

CAP B-53:IV

Administration of the Canberra APEX Gamma Spectroscopy

System

CAP D-17

Tritium in Airborne Samples

CAP D-19

Correlation of Rad Monitors of Radioactivity

CAP D-23

Preparing Liquid Radwaste Composite Samples

CAP E-19

Routine Plant Vent Radioactive Effluent Sampling

CAP E-19:I

Alternative Plant Vent Radioactive Effluent Sampling

CAP E-2:II

Laundry and Radwaste Storage Building Ventilation Exhaust

Sampling

CAP E-2:X

Sampling Containment Atmosphere During ILRT

CAP E-5:I

Liquid Radwaste and Miscellaneous Discharge Sampling

CAP Q-6

Radiochemical Cross-Check Program

CY2

Radiological Monitoring and Controls Program

7B

CY2.DC1

Radiation Monitoring System High Alarm Setpoint Control

Program

CY2.ID1

Radioactive Effluent Control Program

Miscellaneous Documents

Number

Title

Date

NUPIC QA Audit of GEL Laboratories

11/1/2016

Letter DCL-17-031

2016 Annual Radioactive Effluent Release Report

4/26/2017

Letter DCL-18-028

2017 Annual Radioactive Effluent Release Report

4/24/2018

Audits, Self-Assessments, and Surveillances

Number

Title

Date

2018 NRC Inspection Prep by Chemistry - Inspection

Procedure 71124 Attachments 05 and 06

6/15/2018

Assessment of Effluent and EAL-Related Radiation

Monitors - Chesapeake Nuclear Services

6/25/2018

Radiation Effluent Monitor Formal Self-Assessment

5/23/2018

2770010

2017 Chemistry & Environmental Operation Program Audit

3/1/2017

Effluent Release Permits

Permit Number

Type

Release System

Date

G-2017-0607

Gas

Plant Vent

9/7/2017

G-2018-0198

Gas

Plant Vent

6/4/2018

L-2017-0792

Liquid

Oily Water Separator Effluents

1/5/2017

L-2018-0113

Liquid

Miscellaneous Liquid Release

1/24/2018

L-2018-0232

Liquid

Steam Generator Blowdown

4/12/2018

Radiation Monitor Calibrations

Instrument Number Description

Date

0-RM-18

Liquid Rad Waste Discharge

8/17/2017

0-RM-3

Oily Water Separator Influent

4/17/2017

1-RM-14

PV Noble Gas

4/3/2018

1-RM-14R

PV Noble Gas

4/20/2017

1-RM-24

PV Iodine

4/3/2018

1-RM-24R

PV Iodine

4/20/2017

1-RM-28

PV Particulate

4/3/2018

2-RM-14

PV Noble Gas

2/9/2017

2-RM-24

PV Iodine

2/9/2017

Radiation Monitor Calibrations

Instrument Number Description

Date

2-RM-28

PV Particulate

2/9/2017

Ventilation System Filter Testing Records

Number

Title

Date

U1-STP M-3A

Auxiliary Building Ventilation System

4/2017

U1-STP M-41

Fuel Handling Building Ventilation System

1/2017

U1-STP M-53

Control Room Ventilation System

4/2017

U2-STP M-3A

Auxiliary Building Ventilation System

2/2017

U2-STP M-41

Fuel Handling Building Ventilation System

6/2017

U2-STP M-53

Control Room Ventilation System

4/2017

71124.07: Radiological Environmental Monitoring Program

Notifications

50849290

50869682

50874451

50674452

50881026

50886780

50903443

50912865

50930029

50944102

50947773

50950702

50953420

50966993

50966994

50969114

50974851

50975481

50979527

50988085

50991024

Procedures

Number

Title

Revision

CAP A-8

Off-Site Dose Calculations

CY2

Radiological Monitoring and Controls Program

7B

CY2.ID1

Radioactive Effluent Controls Program

RCP EM-1

Radiological Environmental Biological Sampling

RCP EM-2

Radiological Environmental Air Sampling

RCP EM-3

Use of Environmental Thermoluminescent Dosimeters

RCP EM-5

DCPP REMP and GPI Groundwater Sampling

RCP EM-6

Radiological Environmental Carbon-14 Air Sampling

Procedures

Number

Title

Revision

RCP EM-21

GPI Well Maintenance Plan

RP1.ID11

Environmental Radiological Monitoring Procedure

RP1.ID13

DCPP Ground Water Protection Initiative Program

STP 1-40-

M559.B

Primary Meteorology Wind Direction, wind Speed, and Air

Temperature / DT Cal

Audits and Self-Assessments

Number

Title

Date

2016 Quality Assurance Report for the Radiological

Environmental Monitoring Program (REMP)

3/29/2017

2017 Quality Assurance Report for the Radiological

Environmental Monitoring Program (REMP)

3/9/2018

173180001

2018 Radiation Protection Programs Audit

2/26/2018

SAPH 50956870 NRC Pre-Inspection 71124.07 Radiological Environmental

Monitoring Program (REMP)

6/6/2018

Calibrations and Surveillances

Number

Title

Date

08095

F&J Air Flowmeter - Sampling Station 8S2

8/21/2018

2630

F&J Air Flowmeter - Sampling Station MT1

6/6/2018

WO 64165716

I40M569B Met Facility Equip Cal

9/28/2017

WO 64168464

I40M559B Cal Primary Met Inst Chan (PME)

10/10/2017

WO 64176636

I40M569B Backup Met Facility Equip Cal

1/25/2018

WO 64178127

I40M559B Cal Primary Met Inst Chan (PME)

4/11/2018

Miscellaneous Documents

Number

Title

Revision /

Date

Annual Radiological Environmental Operating Report

2016

Annual Radiological Environmental Operating Report

2017

DCPP Groundwater Protection Initiative SSC Scoping

Priority Index Worksheet

1/11/2018

29627

Diablo Canyon Power Plant Site Conceptual Model (SCM)

Report

7/30/2014

Miscellaneous Documents

Number

Title

Revision /

Date

100555-0

NVLAP On-Site Assessment Report: Mirion Technologies

(GDS), Inc.

1/9/2018

CAP A-8

Current Dose Receptor Information

11/14/2017

DCL-18-028

2017 Annual Radioactive Effluent Release Report

4/24/2018

ECG 40.1

Meteorological Monitoring Instrumentation

GL-QS-B-001

GEL Laboratories, LLC Quality Assurance Plan

IRSI04

I&C Maintenance Qualification Guide

6/24/2017

71124.08: Radioactive Solid Waste Processing, and Radioactive Material Handling,

Storage, and Transportation

Notifications

50871496

50869923

50926292

50930535

Procedures

Number

Title

Revision

CAP A-8

Off-Site Dose Calculations

RCP D-631

Radioactive Material Shipments

RCP RW-1

Collection and Packaging of LLRW

16A

RCP RW-13

Storage and Accountability of LLRW

RCP RW-2

Packaging Radwaste in PIC HICs

RCP RW-20

Spent Resin Sampling

RCP RW-3

Radioactive Waste Nuclide Fractions and Correlation

Factors Determination

RCP RW-4

Solid Radioactive Waste Shipment

RCP RW-5

Receiving, Loading, and Releasing of Transport Vehicle for

Radioactive Waste Shipment

RP2.DC1

Radioactive Waste Classification Program

RP2.DC3

Radwaste Dewatering Process Control Program

Audits and Self-Assessments

Number

Title

Date

50956871

Quick Hit Self-Assessment: NRC IP 71124.08, Radioactive

Solid Waste Processing and Radioactive Material Handling,

Storage, and Transportation

4/10/2018

Radiological Surveys

Number

Title

Date

35503

Old Steam Generator Storage Facility

7/9/2014

219

ISFSI Pads 1 & 2

11/10/2017

2074

Radwaste Building - 115 Elevation

5/31/2018

2151

Radwaste Building - 115 Elevation

6/6/2018

2557

WHSE A RAM Storage Area

7/5/2018

Radiation Monitor Calibrations

Number

Title

Date

64141015

RM-90 - Radwaste Storage Building Truck Bay

3/29/2016

64145736

RM-84 - Solid Radwaste Inspection Station - Contact

7/10/2018

64145830

RM-85 - Solid Radwaste Inspection Station - One Meter

7/3/2018

Radioactive Material and Waste Shipments

Number

Title

Date

RMS-17-064

Dry Active Waste: UN3321, RAM, LSA-II, 7; Class A

6/5/2017

RMS-17-069

BB Equipment: UN2910, RAM, Excepted Package - LQ, 7;

Class A

6/6/2017

RMS-17-089

Dry Active Waste: UN3321, RAM, LSA-II, 7; Class A

7/10/2017

RMS-17-151

Dry Active Waste: UN3321, RAM, LSA-II, 7; Class A

2/4/2017

RMS-18-064

Oil Samples: UN2910, RAM, Excepted Package - LQ, 7

6/7/2018

RMS-18-073

Dirt and Clean Trash: UN2910, RAM, Excepted Package,

LQ, 7; Class A

7/12/2018

RWS-17-001

Mechanical Filters: UN3321, RAM, LSA-II, Fissile-Excepted,

7, RQ; Class AU

2/22/2017

RWS-17-002

Spent Resin: UN2916, RAM - Type B(U) Package, Fissile-

Excepted, 7, RQ; Class B

3/21/2017

RWS-17-003

Spent Resin: UN2916, RAM - Type B(U) Package, Fissile-

Excepted, 7, RQ; Class C

3/29/2017

Radioactive Material and Waste Shipments

Number

Title

Date

RWS-17-004

Spent Resin: UN3321, RAM, LSA-II, 7; Class AU

10/10/2017

Miscellaneous Documents

Number

Title

Revision /

Date

2016 Annual Radioactive Effluent Release Report

4/26/2017

2016 Radioactive Material Shipment Log

2016

2016 Radwaste Correlation Factors Summary

6/13/2017

2016 Radwaste Shipment Log

2016

2017 Annual Radioactive Effluent Release Report

4/24/2018

2017 Radioactive Material Shipment Log

2017

2017 Radwaste Shipment Log

2017

DCPP Units 1&2 FSAR Update: Chapters 11.5 - Solid

Radwaste System

395917001

CFR Part 50/61 Isotope Abundance Report:

Miscellaneous Solids

5/18/2016

71151: Performance Indicator Verification

Procedure

Number

Title

Revision

XI1.ID5.

Collection and Submittal of NRC Performance Indicators

Other

Number

Description

Revision or

Date

DCPP MSPI

Basis

Mitigating System Performance Index Basis Document

MSPI Derivation

Reports

Unit 1 and 2 Diablo Canyon (MSPI MS 08,09,10)

8/2018

Technical

Specification

Logs

Diablo Canyon Power Plant

7/2017 to

6/2018

71152: Problem Identification and Resolution

Notifications

50988369

50988318

50988860

50988376

50636744

50986188

50982633

50987822

50987782

50983750

50998167

50636744

50828884

Procedures

Number

Title

Revision

CF3

Design Control

9B

CF4.ID7

Temporary Alteration

MA1.ID27

Preventative Maintenance Program

OM7.ID12

Operability Determinations

TS3.ID2

Licensing Basis Impact Evaluations

Other

Number

Description

Date

DCL-87-262

Special Report 87-05, High Vital Area Room Temperature

11/3/1987

60855.1: Other Activities - Temporary Instructions, Infrequent and Abnormal

Notifications

DA20904174

DA50896980

DA50946862

DN50694923

DN50847556

DN50874981

DN50879197

DN50881057

DN50896847

DN50903489

DN50936773

DN50946075

DN50946752

DN50955392

DN50968883

DN50974864

DN50975342

DN50978161

DN50986155

Work Orders

68051705

64158932

64132214

64145571

64144618

64137170

64155360

HOI-068878

HOI-068880

Procedures

Number

Title

Revision

MP M-42-DFS.1

FHB Dry Fuel Storage Rigging and Load Handling

OM7.ID1

Problem Identification and Resolution

OP B-8H

Spent Fuel Pool Work Instructions

PEP DF-1

Multi-purpose Canister (MPC) and HI-STORM Preparation

PEP DF-2

Multi-purpose Canister (MPC) Loading

PEP DF-3

Drying, Backfilling, and Sealing the Multi-purpose Canister

(MPC)

6A

PEP DF-4

Multi-purpose Canister Transport

PEP DF-6

Responding to Abnormal Conditions

PEP DF-9

PG&E Liaison Guidance

STP I-1A

Routine Shift checks Required by Licenses

135

TS3.ID2

Licensing Basis Impact Evaluations

Design Basis Documents

Number

Description

Revision

N/A

Diablo Canyon Spent Fuel Storage Installation Final Safety

Analysis Report Update

SNM-2511

License for Independent Storage of Spent Nuclear Fuel and

High-Level Radioactive Waste

Miscellaneous Documents

Number

Description

Revision or

Date

2480003

2017 ISFSI and Fuel Management Audit Report

11/14/2017

69-10430

Applicability Determination (numerous)

69-11510

Radiation and Contamination Survey Form

11/10/2017

GQP 9.2

High Temperature Liquid Penetrant Examination and

Acceptance Standards for Welds, Base Materials, and

Cladding

GQP 9.6

Visual Examination of Welds

N/A

2016 Annual Radiological Environmental Operating Report,

Diablo Canyon Power Plant

4/26/2017

Miscellaneous Documents

Number

Description

Revision or

Date

N/A

2017 Annual Radiological Environmental Operating Report,

Diablo Canyon Power Plant

4/26/2018

PI-CNSTR-OP-

HLTC-H-01

Closure Welding of Holtec MPCs

RE-20160725

Engineering Calculation

RE-20160808

Engineering Calculation

RE-20180104

Engineering Calculation

RE-20180108

Engineering Calculation

Request for Information for

Resident Inspection at

Diablo Canyon Power Plant -

3rd Quarter 2018

Please provide the following documents (use date range of document request unless

otherwise noted):

1. Summary listing of all root and apparent cause evaluations performed on this system

2. Summary listing of all condition reports written on this system, sorted by category type

3. Summary listing of OE screening and dispositioning reviews

4. Summary listing of all corrective maintenance work orders, with description of work,

performed on this system

5. List of all work orders, with description of work, planned within the next 6 months (from

start of applicable quarter).

6. List of maintenance rule functional failure assessments - regardless of the result -

performed on this system for previous two years. Include condition report numbers for

each item on the list

7. Summary list of system design calculations

8. Summary list of fire impairments associated with this system

9. List of completed engineering changes and planned engineering changes (within the

next six months of start of applicable quarter) associated with this system.

10. Schedule of system surveillance and work activities for the planned quarter of interest.

11. Summary listing of temporary and permanent modifications associated with the system

completed within the last two years

2. Summary listing of 50.59 screenings and evaluations related to the system

13. Maintenance rule scoping and basis documents

14. Maintenance rule expert panel meeting minutes for meetings related to system

15. Current UA hours and UR data tracking documents (system health report)

3rd Quarter 2018

System: Emergency Diesel Generator

IMS Upload Date Requested By: June 25, 2018

Date Range of Document Request: July 1, 2016 - Current

The following items are requested for the

Public Radiation Safety Inspection

at Diablo Canyon Nuclear Power Plant

Dates of Inspection: July 9 thru 14, 2018

Integrated Report 2018002

Inspection areas are listed in the attachments below.

Please provide the requested information on or before June 26, 2018.

Please submit this information using the same lettering system as below. For example, all

contacts and phone numbers for Inspection Procedure 71124.01 should be in a file/folder titled

1-A, applicable organization charts in file/folder 1-B, etc.

If information is placed on ims.certrec.com, please ensure the inspection exit date entered is at

least 30 days later than the onsite inspection dates, so the inspectors will have access to the

information while writing the report.

In addition to the corrective action document lists provided for each inspection procedure listed

below, please provide updated lists of corrective action documents at the entrance meeting.

The dates for these lists should range from the end dates of the original lists to the day of the

entrance meeting.

If more than one inspection procedure is to be conducted and the information requests appear

to be redundant, there is no need to provide duplicate copies. Enter a note explaining in which

file the information can be found.

If you have any questions or comments, please contact Louis Carson at (817) 200-1221 or

Louis.Carson@nrc.gov.

PAPERWORK REDUCTION ACT STATEMENT

This letter does not contain new or amended information collection requirements subject

to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information

collection requirements were approved by the Office of Management and Budget,

control number 3150-0011.

5.

Radiation Monitoring Instrumentation (71124.05)

Date of Last Inspection:

August 11, 2016

A.

List of contacts and telephone numbers for the following areas:

1. Effluent monitor calibration

2. Radiation protection instrument calibration

3. Installed instrument calibrations

4. Count room and Laboratory instrument calibrations

B.

Applicable organization charts.

C.

Copies of audits, self-assessments, vendor or NUPIC audits for contractor support and

LERs, performed since the date of the last inspection related to:

1. Area radiation monitors, continuous air monitors, criticality monitors, portable survey

instruments, electronic dosimeters, teledosimetry, personnel contamination monitors,

or whole body counters.

2. Installed radiation monitors.

D.

Procedure index for:

1. Calibration, use, and operation of continuous air monitors, criticality monitors,

portable survey instruments, temporary area radiation monitors, electronic

dosimeters, teledosimetry, personnel contamination monitors, and whole body

counters.

2. Calibration of installed radiation monitors.

E.

Please provide specific procedures related to the following areas noted below.

Additional procedures may be requested by number after the inspector reviews the

procedure index.

1. Calibration of portable ion chambers

2. Whole body counter calibration

3. Laboratory instrumentation quality control

F.

A summary list of corrective action documents (including corporate and sub-tiered

systems) written since the date of the last inspection, related to the following programs:

1. Area radiation monitors, continuous air monitors, criticality monitors, portable survey

instruments, electronic dosimeters, teledosimetry, personnel contamination monitors,

whole body counters

2. Installed radiation monitors

3. Count room radiation instruments

NOTE: The lists should indicate the significance level of each issue and the search

criteria used. Please provide in document formats which are searchable so that

the inspector can perform word searches.

G.

Most recent calibration data for the whole body counters.

H.

Radiation Monitoring System health report for the previous 12 months.

6.

Radioactive Gaseous and Liquid Effluent Treatment (71124.06)

Date of Last Inspection:

August 11, 2016

A.

List of contacts and telephone numbers for the following areas:

1. Radiological effluent control

2. Engineered safety feature air cleaning systems

B.

Applicable organization charts.

C.

Audits, self-assessments, vendor or NUPIC audits of contractor support, and LERs

written since the date of the last inspection, related to:

1. Radioactive effluents

2. Engineered Safety Feature Air cleaning systems

D.

Procedure indexes for the following areas:

1. Radioactive effluents

2. Engineered Safety Feature Air cleaning systems

E.

Please provide specific procedures related to the following areas noted below.

Additional procedures may be requested by number after the inspector reviews the

procedure indexes.

1. Sampling of radioactive effluents

2. Effluent monitor setpoint determination

3. Generating radioactive effluent release permits

4. Laboratory instrumentation quality control

5. In-place testing of HEPA filters and charcoal adsorbers

F.

List of corrective action documents (including corporate and sub-tiered systems) written

since the date of the last inspection, associated with:

1. Radioactive effluents

2. Effluent radiation monitors

3. Engineered Safety Feature Air cleaning systems

NOTE: The lists should indicate the significance level of each issue and the search

criteria used. Please provide in document formats which are searchable so that

the inspector can perform word searches.

G.

Annual Radioactive Effluent Release Reports for calendar years 2016 and 2017, or the

two most recent reports.

H.

Current revision of the Offsite Dose Calculation Manual.

I.

The 2016 and 2017 inter-laboratory comparison results for laboratory quality control

performance of effluent sample analysis, or the two most recent results.

J.

Effluent sampling schedule for the week of the inspection.

K.

New entries into 10 CFR 50.75(g) files since the date of the last inspection.

L.

Operations department (or other responsible dept.) log records for effluent monitors

removed from service or out of service.

M.

Listing or log of liquid and gaseous release permits since the date of the last inspection.

N.

A list of the technical specification-required air cleaning systems with the two most

recent surveillance test dates of in-place filter testing (of HEPA filters and charcoal

adsorbers) and laboratory testing (of charcoal efficiency) and the work order numbers

associated with the surveillances.

O.

System Health Report for radiation monitoring instrumentation. Also, please provide a

specific list of all effluent radiation monitors that were considered inoperable for 7 days

or more since the date of the last inspection. If applicable, please provide the relative

Special Report and condition report(s).

P.

A list of significant changes made to the gaseous and liquid effluent process monitoring

system since the date of the last inspection. If applicable, please provide the

corresponding UFSAR section in which this change was documented.

Q.

A list of any occurrence in which a non-radioactive system was contaminated by a

radioactive system since the date of the last inspection. Please include any relevant

condition report(s).

7.

Radiological Environmental Monitoring Program (71124.07)

Date of Last Inspection:

August 11, 2016

A.

List of contacts and telephone numbers for the following areas:

1. Radiological environmental monitoring

2. Meteorological monitoring

B.

Applicable organization charts

C.

Audits, self-assessments, vendor or NUPIC audits of contractor support, and LERs

written since the date of the last inspection, related to:

1. Radiological environmental monitoring program (including contractor environmental

laboratory audits, if used to perform environmental program functions)

2. Environmental TLD processing facility

3. Meteorological monitoring program

D.

Procedure index for the following areas:

1. Radiological environmental monitoring program

2. Meteorological monitoring program

E.

Please provide specific procedures related to the following areas noted below.

Additional procedures may be requested by number after the inspector reviews the

procedure indexes.

1. Sampling, collection and preparation of environmental samples

2. Sample analysis (if performed onsite)

3. Laboratory instrumentation quality control

F.

A summary list of corrective action documents (including corporate and sub-tiered

systems) written since the date of the last inspection, related to the following programs:

1. Radiological environmental monitoring

2. Meteorological monitoring

NOTE: The lists should indicate the significance level of each issue and the search

criteria used. Please provide in document formats which are searchable so that

the inspector can perform word searches.

G.

Copies of the two most recent calibration packages for the meteorological tower

instruments.

H.

Copies of the 2016 and 2017 Annual Radiological Environmental Operating Reports and

Land Use Census, and current revision of the Offsite Dose Calculation Manual.

I.

Copy of the environmental laboratorys inter-laboratory comparison program results for

2016 and 2017, or the two most recent results, if not included in the annual radiological

environmental operating report.

J.

Data from the environmental laboratory documenting the analytical detection sensitivities

for the various environmental sample media (i.e., air, water, soil, vegetation, and milk).

K.

Quality Assurance audits (e.g., NUPIC) for contracted services.

L.

Current NEI Groundwater Initiative Plan and status.

M.

Technical requirements manual or licensee controlled specifications which list the

meteorological instruments calibration requirements.

N.

If applicable, per NEI 07-07, provide any reports that document any spills/leaks to

groundwater since the date of the last inspection.

8.

Radioactive Solid Waste Processing, and Radioactive Material Handling, Storage,

and Transportation (71124.08)

Date of Last Inspection:

September 29, 2016

A.

List of contacts and telephone numbers for the following areas:

1. Solid Radioactive waste processing

2. Transportation of radioactive material/waste

B.

Applicable organization charts (and list of personnel involved in solid radwaste

processing, transferring, and transportation of radioactive waste/materials)

C.

Copies of audits, department self-assessments, and LERs written since the date of the

last inspection related to:

1. Solid radioactive waste management

2. Radioactive material/waste transportation program

D.

Procedure index for the following areas:

1. Solid radioactive waste management

2. Radioactive material/waste transportation

E.

Please provide specific procedures related to the following areas noted below.

Additional procedures may be requested by number after the inspector reviews the

procedure indexes.

1. Process control program

2. Solid and liquid radioactive waste processing

3. Radioactive material/waste shipping

4. Waste stream sampling and analysis

F.

A summary list of corrective action documents (including corporate and sub-tiered

systems) written since the date of the last inspection, related to:

1. Solid radioactive waste

2. Transportation of radioactive material/waste

NOTE: The lists should indicate the significance level of each issue and the search

criteria used. Please provide in document formats which are searchable so that

the inspector can perform word searches.

G.

Copies of training lesson plans for 49 CFR 172 subpart H, for radwaste processing,

packaging, and shipping.

H.

A summary of radioactive material and radioactive waste shipments made from the date

of the last inspection, to present.

I.

Waste stream sample analysis results and resulting scaling factors for 2016 and 2017,

or the two most recent results.

J.

A listing of onsite radwaste storage facilities. Please include a summary or list of the

items stored in each facility.

ML18304A467

SUNSI Review

By: MSH2

Non-Sensitive

Sensitive

Publicly Available

Non-Publicly Available

Keyword:

NRC-002

OFFICE

SRI:DRP/A

RI:DRP/A

C:DRS/EB1

C:DRS/EB2

C:DRS/OB

C:DNMS/FCDB

NAME

CNewport

JReynoso

TFarnholtz

GWerner

VGaddy

JKatanic

SIGNATURE

CWN

JPR

TRF

GEW

vgg

JFK

DATE

10/22/18

10/23/18

10/22/2018

10/24/2018

10/19/18

10/22/18

OFFICE

C:DRS/PSB2

C:DRS/IPAT

SPE:DRP/A

BC:DRP/A

NAME

HGepford

GMiller

RAlexander

MHaire

SIGNATURE

hjg

GAG for

RDA

MSH

DATE

10/19/18

10/19/18

10/22/18

10/31/18