May 7, 2018
SUBJECT:
DIABLO CANYON POWER PLANT, UNITS 1 AND 2 - NRC INDEPENDENT SPENT FUEL STORAGE INSTALLATION SECURITY INSPECTION REPORT 05000275/2018401, 05000323/2018401 AND 07200026/2018401
Dear Mr. Welsch:
March 30, 2018
SUBJECT:
DIABLO CANYON POWER PLANT, UNITS 1 AND 2 - NRC INDEPENDENT SPENT FUEL STORAGE INSTALLATION SECURITY INSPECTION REPORT 05000275/2018401, 05000323/2018401 AND 07200026/2018401
Dear Mr. Welsch:
On March 30, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed a security inspection at your Diablo Canyon Power Plant, Independent Spent Fuel Storage Installation.
The NRC inspector discussed the results of this inspection with Mr. R. Zimkowski, Acting Director of Security, and other members of your staff. The inspector documented the results of this inspection in the enclosed inspection report.
No NRC-identified or self-revealing findings were identified during this inspection.
In accordance with Title 10 of the Code of Federal Regulations (CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding, of the NRC's "Agency Rules of Practice and Procedure," a copy of this letter will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of ADAMS. ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
However, the enclosed report contains Security-Related Information, so the enclosed report will not be made publically available in accordance with 10 CFR 2.390(d)(1). If you choose to provide a response that contains Security-Related Information, please mark your entire response Security-Related Information - Withhold from Public Disclosure Under 10 CFR 2.390 (d)(1) and follow the instructions for withholding in 10 CFR 2.390(b)(1). The NRC is waiving the affidavit requirements for your response in accordance with 10 CFR 2.390(b)(1)(ii).
Sincerely,
/RA/
Jeremy R. Groom, Chief Plant Support Branch 1 Division Reactor Safety
Docket No.72-026 License No. SNM 2511
Enclosure:
NRC Inspection Report 05000275/2018401, 05000323/2018401 AND 07200026/2018401 w/Attachment: Supplemental Information
cc w/enclosure:
Manager, Site Security Diablo Canyon Power Plant Pacific Gas and Electric Company P.O. Box 56 Avila Beach, CA 93424
cc w/o enclosure:
Electronic Distribution for Diablo Canyon
ML18122A049 Entire Report:
ADAMS:
Non-Publicly Available Non-Sensitive Keyword:
SUNSI Review By: JRG Yes No Publicly Available Sensitive _______MD 3.4 A.3
ADAMS ACCESSION NUMBER: ML18123A491 Cover Letter Only:
ADAMS:
Non-Publicly Available Non-Sensitive Keyword:
SUNSI Review By: JRG Yes No Publicly Available Sensitive NRC-002 OFFICE DRS/PSB1 DRS/PSB1 DRP/RBBA DNMS/FCDB DRS/PSB1
NAME RLanfear JGroom MHaire RKellar JGroom
SIGNATURE
/RA/
/RA/
/RA/
/RA by RBrowder Acting For/
/RA/
DATE 4/30/18 4/30/18 05/02/18 05/02/18 05/07/18