Groundwater Protection Initiative (GPI) - Voluntary Special Report for Tritium Discovered On-Site
ML15139A272
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 05/15/2015
From: Pat Navin
Exelon Generation Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NEI 07-07
Download: ML15139A272 (2)


Text

A ExeLon Generation NEI 07-07 May 15, 2015 U.S. Nuclear Regulatory Commission ATLTN: Document Control Desk Washington, DC 20555-0001 Peach Bottom Atomic Power Station (PBAPS), Units 2 and 3 Renewed Facility Operating License Nos. DPR-44 and DPR-56 NRC Docket Nos. 50-277 and 50-278

Subject:

Groundwater Protection Initiative (GPI) - Voluntary Special Report for Tritium Discovered On-Site This voluntary, special report is submitted in accordance with NEI 07-07, Industry Ground Water Protection Initiative - FinalGuidance Document.

On April 17, 2015, a water sample from an on-site groundwater monitoring well was confirmed to contain a level, of tritium in excess of the NEI 07-07 voluntary reporting threshold of 20,000 picocuries per liter. This water sample was collected on April 7, 2015 from just outside of the northeast corner of the Unit 3 Turbine Building. The level of tritium measured was 37,700 picocuries per liter.

A small accumulation of water on the turbine building floor was identified as a possible source and removed. Drainage was improved to prevent future accumulation. Follow-up sampling from the well has shown a declining trend. A sample obtained on May 4, 2015, contained 9,410 picocuries per liter.

The samples were obtained from a well that is for groundwater monitoring only. This event had no impact on any on-site or off-site drinking water wells. It is possible that the water could eventually migrate into the plant's outlet canal. If so, the potential dose to a member of the public would be negligible. This will be calculated as part of the site's annual effluent report.

There are no regulatory commitments contained in this document. If you have any questions or require additional information, please contact Mr. Frank Leone, Chemistry, Environmental and Radwaste Manager at 717-456-3844.

Sincerely, 4-Patrick D. Navin Plant Manager Peach Bottom Atomic Power Station

U.S. Nuclear Regulatory Commission Page 2 May 15, 2015 cc: D. H. Dorman, US NRC, Administrator, Region I S. L. Hansell, US NRC, Senior Resident Inspector R. R. Janati, Commonwealth of Pennsylvania S. Grey, State of Maryland P. Steinhauer, PSE&G, Financial Controls and Co-owner Affairs R. Anderson, NEI (GW Notice@nei-org)

S. Focht, American Nuclear Insurer's CCN: 15-52 IR 2486460